Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Oleh :
Laveda Nidya Irianti 3116203020
Akhbar Ariefianto Suprapto 3116203022
Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis use numerically analyzing
the probability and impact of each risk and analyzing the
extent of overall project risk
Quantitative Risk Analysis is an attempt to determine how
much risk the project has and where, so we can spend our
limited time and effort to decrease the risk on the project
The Perform Quantitative Risk Analysis process can be
thought of as an attempt to make more informed decisions
about the amount of risk on the project than is possible with
qualitative risk analysis
Objectives of the Perform Quantitative Risk
Analysis process
Decide which risk warrant a response
Evaluate the probability and impact of each risk
Determine the level of risk the project currently has and
whether that level of risk is acceptable for the expected gain
from the product of the project
Determine how much the project will cost and how long it will
take if no further risk management actions are taken to
decrease project risk
Determine which risks require response planning
Determine the probability of achieving cost or schedule
objectives for the project
Input
Question : What is the expected monetary value of the cost and time of these risks?
Assuming that these are the only risk on the project :
a. What is the best case?
b. If without a risk analysis?
c. What is the expected monetary value of the project?
d. What is the worst case?
Expected Monetary Value of Cost
Expected Monetary Value of Cost
Expected Monetary
Risk Calculation
Value of the Cost
A 0.05 times $ 75,000 $ 3,750
B 0.15 times $ 30,000 $ 4,500
C 0.75 times $ 3,000 $ 2,250
D 0.05 times $ 2,500 ($ 125)
E 0.15 times $ 8,000 $ 1,200
Total $ 2,575
Question Calculation Answer
Best case $400,000 - $ 30,000 - $ 2,500 $ 367,500
Sponsor's or customer's expectations $ 400,000
Expected monetary value $400,000 + $ 2,575 $ 402,575
Worst case $400,000 + $ 75,000 + $ 3,000 + $ 8,000 $ 486,000
Expected Monetary Value of Time
Expected Monetary Value of Time
Expected Monetary
Risk Calculation
Value of the Time
A 0.05 times 14 days 0.7
B 0.15 times 28 days (4)
C 0.75 times 56 days 42
D 0.05 times 14 days (0.7)
E 0.15 times 21 days 3.15
Total 40.95 days
Question Calculation Answer
Best case 224 - 28 - 14 182 days
Sponsor's or customer's expectations 224 days
Expected monetary value 224 + 40.95 264.95 days
Worst case 224 + 14 + 56 + 21 315 days
Monte Carlo Simulation
Computerized method of estimating that simulates the project to
determine time or cost estimates based on probability
distribution
Advantages Disadvantages
Helps to determine to overall risk of Only evaluate overall (not detailed)
meeting require project time or cost project risk, time, and cost
necessary to manage the project
Determine the most realistic length
of time the project will take Requires the purpose of Monte
Indicates what activity make have Carlo software
the highest probability of becoming
critical activities
Allowing better management and
oversite
Monte Carlo Simulation
Monte Carlo Simulation
Monte Carlo Simulation
Decision Tree
A model of a situation used to see the potential impact of
decision by taking into account associated risks, probabilities, and
impacts
Output
Updates to the risks register. It is updated to add the results of this
process, including the following information
Risk Register Updates
Prioritized list of quantified risks
Amount of contingency time and cost reserves needed
Possible realistic and achievable completion dates and project
costs, with confidence levels, versus the time and cost objectives
for the project
The quantified probability of meeting project objectives
Trends