Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
S h d li
Scheduling
Construction Management
Project
j p planningg
iis a ffundamental
d t l and
d challenging
h ll i activity
ti it iin
the management and execution of
construction
t ti projects.
j t
It involves:
the choice of technology,
the definition of work tasks,
the estimation of the required resources and
durations for individual tasks, and
the identification of any interactions among the
different work tasks
Construction planning
p g
a planner:
l
begins with a result (i.e. a facility design)
must synthesize the steps required to yield this result
result.
Essential aspects of construction planning include
the generation of required activities,
activities
analysis of the implications of these activities, and
choice among the various alternative means of performing
activities.
a useful approach
iis tto simulate
i l t ththe construction
t ti process either
ith iin th
the
imagination of the planner or with a formal computer based
simulation technique
Alternative Emphases
p in Construction
Planning
Aspects
p contribute
b the b
breakdown
d w of the p
project
j
Methods used to place the work
skills needed for the work
crafts involved
critical resources (cranes,crews,etc)
administrative actions that require time (obtaining
permits,inspections,etc)
deliveries or approvals that must be considered
(approval of shop drawing,delivery of piles,etc.)
special activities (cure concrete
concrete,etc.)
etc )
Illustrative Hierarchical Activityy
Divisions for a Roadway Project
Definingg Precedence Relationships
p
Among Activities
Once workk activities
O ti iti have
h b
been d
defined,
fi d ththe
relationships among the activities can be
specified.
ifi d
Precedence relations between activities
signify that the activities must take place in a
particular sequence.
Numerous natural sequences exist for
construction activities due to requirements for
structural integrity, regulations, and other
technical requirements
Illustrative Set of Four Activities with
Precedences
Types
yp of project
p j planning
p g
Bar chart
Linear scheduling
g method
Network planning
Bar chart
Gantt chart
Representation of a project activity as a time-
scaled bar whose length represents the
planned
l ddduration
ti off th
the activity
ti it
Easy to make, read and effective for
communicating in field
Project
j information illustration is limited,,
where :
Interdependency
p y between activities are not shown
Critical activities are not shown
Example
p of Bar ((Gantt)) Chart
Bar chart
Planned duration
Project
work item
50% complete
Project
work item
Percent complete
0 25 50 75 100 scale
LINEAR SCHEDULING METHOD
Units of
production
100
80 Planned rate
of progress
60
40
Actual rate of
progress
20
Project
month
5 10 15 20 25
Network planning
p g
Activity :
Needs duration ((time)) to finish an activity
y
Length or slope of arrow have no means, but the
head of arrow shows the sequence
q of activity
y
Start from a node and end to another node
Example : Excavating
Excavating, Concrete Curing
Curing, etc
Terms in Arrow Diagram
g
Event
Start or end of activity
Has no duration
Example : start of excavation, finish of excavation,
etc
Milestone : Event that has important
meaning, that can be a controlling target.
Terms in Arrow Diagram
g
Dummy activity : Activity has no time and
resources. Needs to help in linking activity
logic.
Critical Path :
A path of network that has the longest total activity
duration.
Total Float (TF) = 0
Critical Path duration = Project Duration
N d extra
Needs t control
t l iin th
these activities
ti iti
Arrow diagram
g
i - event i
j - event j
TiE - early time of event i
i TjE - early time of event j
TiL - late time of event i TjL - late time of event j
Activity A precedes B
Activity C precedes B
A B
Activity
A ti it C precedes
d D
no relations between A & D
C D
A B A B
C D
C D
Arrow diagram
g ((example)
p )
A ti it
Activity Titl
Title Duration
D ti Preceding
P di
(days) Activities
A Mobilize 10 -
B Obtain permits 15 -
C Site works 8 A
D Exterior utilities 12 A
E Excavate catch basin 2 B,C
F Excavate footers 5 B,C
G Excavate foundation peers 6 B,C
H Pour footers 8 D,E,F,G
I Erect building frame 10 H
Arrow diagram
g ((example)
p )
D
12
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 5
15
G
5
6
Analyze
y project
p j network to:
D
12
0 10 18 24 32 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 18 5
15
G
5
6
18
Backward-pass
p algorithm
g
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 18 19 5
15
G
5
6
18 18
FLOAT
2 2
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
0 0 0 0 4 4 0 0 0 0
4 F
B 18 19 5 1 1
15
3 3 G
5 N t
Note:
6
18 18 0 0 FF TF
Critical path
p
2 2
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
0 0 0 0 4 4 0 0 0 0
4 F
B 18 19 5 1 1
15
3 3 G
5 Note:
6
18 18 0 0 Critical activity
PRECEDENCE DIAGRAM
Network diagram that use node to describe activity
Possible for multiple logic relationship,
relationship such as :
Finish to start (FS) = a start of an activity depends on
finish of the precedence
Start to start (SS) = a start of an activity depends on
B C
4 6
EST A EFT F
LST 2 LFT 8
D E
5 2
Precedence diagram
g
TF = 0 TF = 0
2 B 6 6 C 12
2 4 6 6 6 12
TF = 0 FF = 0 FF = 0 TF = 0
0 A 2 12 F 20
0 2 2 12 8 20
FF = 0 FF = 0
TF = 3 TF = 3
2 D 7 7 E 9
5 5 10 10 2 12
FF = 0 FF = 0
Precedence diagram
g
TF = 0 TF = 0
2 B 6 6 C 12
2 4 6 6 6 12
TF = 0 FF = 0 FF = 0 TF = 0
0 A 2 12 F 20
0 2 2 12 8 20
FF = 0 FF = 0
TF = 3 TF = 3
2 D 7 7 E 9
5 5 10 10 2 12
FF = 0 FF = 0
P.E.R.T
Program Evaluation
E al ation Re
Review
ie
Technique
Tec que (PERT)
(P T)
PERT:
developed by U.S. Navy Polaris Program for the
Polaris Fleet Ballistic Missile in 1957
Using probabilistic approach in determining
duration
Probabilityy in PERT
Optimistic duration: o
Most likelyy duration: m
Pessimistic duration: p
o + 4m + p
te =
6
Probabilityy in PERT
Optimistic
O ti i ti dduration:
ti Pessimistic duration
te < most likely time te > most likely time
Example: Example:
o=4 o=4
m=6 m=5
p=7 p = 18
te = (4 + 24 + 7) / 6 te = ((4 + 20
0 + 18)
8) / 6
=7 > 6
= 5.8 < 6
Variance ((te)
is a measure of difference
described uncertaintyy associated with the
time-estimating
the larger the variance
variance, the bigger the
uncertainty
te = [(p - o) / 6]2
Variance ((te)
A: A1:
o=4 o = 4
m=6 m = 5.5
p=8 p = 10
4 + 24 + 8 4 + 22 + 10
te(A) = =6 te(A1) = =6
6 6
2
TE = v te2 = v
p-o
6
Example
p
A B C D
1 2 3 4 5
o =4 o =3 o =2 o =4
m=6 m=8 m=4 m=5
p =8 p =9 p =7 p =6
8-4 2
te = 6
2 te2 = 12 te2 = 0.8332 te2 = 0.3332
2 2
= 3
TE = v te2
P j t duration
Project d ti range is
i from
f 21.0
21 0 to
t 24.0
24 0
Use of standard normal distribution table
Schedule duration = TS
Expected project duration = TE
Use of standard normal distribution table
Example:
from previous example what is the probability of
finishing the project at TS = 21.5
TS - TE 21.5 - 22.5
Z= = = -0.67
TE