Sei sulla pagina 1di 5

Conclusions Users in both the gold and coal industries have

specified that the path outlined will be followed in all


The simulator described has been developed and future projects with retrofit systems being developed
tested on a number of plants in the minerals industry. for existing plants.
To date the system has been connected to control A major development now taking place is the use of
systems with PLCs supplied by various well known the model base developed as a CAD productivity tool
suppliers. for on-lineprocess optimization and control. W

Kidston gold mines startup


D.A. Knight and V.G. Medinrt

-
Abstract Kidston's 14 000 t/d mine and mill com- forecasting metal prices and estimating capital and
plex in Queensland, Australia, started operation in operating costs. An inaccurate study can either kill a
January 1985. During its first 18 months of operation, project or, if the project goes ahead, result in a highly
the mine produced over 7000 kg (885,000 ox) of gold, unprofitable mine. No amount of shortcuts can bring a
making it the largest gold producer in Australia. This low budget back into line and still produce a good
paper describes the planning, logistics, flowsheet, and operation.
process for the Kidston project, and some of the In preparing a feasibility study, the obvious first
problems encountered during startup and the step is to find and evaluate an ore body, with a
measures taken to correct these problems. comprehensive exploration and metallurgical test
program. As the studies progress, design criteria must
Introduction be set and sources of Dower. water, and labor must be
established. ~ r a n s ~ o k a tand
i o ~communication links
The Kidston Gold Mine (KGM) is located about must be investigated. When the final feasibility study
280 km west of Townsville in the state of Queensland has been completed and approval is given for con-
in northeastern Australia, and is accessible by either struction, a consulting engineering firm must be
land or air. The Kidston ore deposit consists of two selected to carry out the detailed design. Finally, a
adjacent ore bodies known as Wise's Hill and Mack's construction management group must be organized to
Knob - North Knob. Gold mineralization occurs in the take the project from the drawing board to an operat-
margins of an oval breccia pipe. Gold occurs mainly ing plant. The management group will select the
as fine native gold and is disseminated within the construction contractors and manage the project.
breccias and fine veinlets. Total ore reserve a t the The startup is the culmination of years of planning;
start of operation was 44.2 Mt averaging 1.79 g/t gold engineering studies; purchasing; expediting; and
and 2.22g/t silver. civil, electrical, and mechanical construction activities.
The mine operation started in January 1985, almost The final feasibility study for the Kidston Gold Mines
three months ahead of schedule. This early startup Project was completed in March 1984,after four years
resulted in some savings in construction cost, and as a of investigation and studies. Although final approval
result the project was about A$6 000 000 under budget. had not been given, the engineering design was con-
Designed to treat an average of 14 000 t/d during its tracted to Kilborn Engineering of Vancouver, BC,
first year of operation, the milling rate has climbed Canada, in October 1983,and preliminary layouts and
steadily, from 8500 t/d during startup, to the current equipment specifications were undertaken. The speci-
level of 15 000 t/d. Except for the countercurrent fications for the long delivery items, i.e., crushers,
cyclone washing, the Kidston process plant is typical mills, and large electric motors, were sent out in late
of most conventional carbon-in-pulp ((;?P) plants. 1983. The final "go ahead" on the project was given in
Although cyclone washing has been used for many early January 1984 as the feasibility study was being
years in the uranium industry, Placer Development finalized. The mills, crushers, and large motors were
Ltd. was the first to apply the process in the gold ordered immediately and all other equipment specifi-
industry, when the Golden Sunlight Mine near cations were sent out. The result was a deluge of
Whitehall, MT,was developed. quotations arriving all a t once, and this was followed
The startup included most of the usual problems, but by an "echo" in September and October 1904, when
during the first two months two unusual events most of the equipment arrived on site. A construction
occurred. The first was a two week shutdown as a camp was established on site in early l W , and the
result of the SAG (semiautogenous) mill motor failure, first concrete was poured in April 1984. The project
and the second was a 12 day shutdown as a result of a particulars are summarized in Table 1.
strike by the Queensland Electric Commission
employees.
D.A. Knight and V.G. Medlna are general mill superintendent
Feasibility study and planning and project metallurgist, respectively, for Placer Development
Ltd., Vancouver, BC, Canada. SME preprint 86-506, SME-AIME
A successful mine startup depends on the quality of Annual Meeting, New Orleans, LA, March 1986. MMP paper
the feasibility study. It cannot be overemphasized that 86-614. Manuscript January 1986. Discussion of this paper
this study should be reasonably accurate, both in must be submitted, in duplicate, prior to April 30, 1986.

MINERALS AND METALLURGICAL PROCESSING FEBRUARY 1986 45


Table 1 - Kidston Gold Mine at a Glance water to the mill gradually reached a crisis point on
the weekend of February 8,when it was necessary to
Ownership Placer Development Ltd. (70%) shut down the mill for 36 hours because of lack of
Australian (30%) water. The shutdown would have come sooner had the
Operator K~dstonGold Mines Ltd mill ponds and leach tanks not been filled in December
Consultants 1984,before the mill startup. Because supply of water
Mill Flowsheet Placer Development Lld.
Plant Design Kilborn Engineering (BC) Ltd.
to the operation was such a major problem during the
Electrical Design M.A. Thomas Lid. first weeks, a disproportionate amount of the plant
Construction Management Placer Development Lld. maintenance crew's time was spent in maintaining the
Total Capital Expenditure A$137 000 000 water supply.
Budget A$143 000000
Ore Reserve : Tonnage 44.20 M I
: Grade 1.79 glt Au
2.20 glt Ag
Logistics and labor
Overall Strip Ratio 1.46.1
Design Capacity 1 4 000 tld (Oxide Ore)
The mine is located 240 km inland from Cairns and
7 500 tld (Fresh Ore) 280 km from Townsville. Therefore, overland, air, and
Annual Producl~on : Initial 6 870 kqla (220 000 ozia) telephone communications were important considera-
: Average 4 500 kgla (145 000 ozla) tions. Equipment purchased overseas and in southern
Number of Employees 160 Australia had to come through Townsville, since this
city is the nearest point serviced by railroad with
deep-sea docks to handle heavy lifts. Fortunately for
the project, there were only a few short labor strikes
Power and water on the docks, and none resulted in critical delays in
the project.
The critical path studies of the Kidston project Roads to the site were basically in place, but as they
showed that the two major areas of concern were the got further from civilization and closer to the mine,
supply of power and water. A decision was made to they required upgrading. Approximately A$1500 000
buy power from the Queensland Electric Commission. was spent on the roads to ensure that trucks and
The nearest substation was a t Ross River, 296 km from freight could get through to the mine during the rainy
the mine. Initial talks with the state government season. The money was well spent, and there were no
suggested that it would take one year to survey and critical delays during construction and startup a s a
two years to build the 132 000 V line and that the work result of shortages of equipment or supplies. Tele-
would be done by the Queensland Electric Commis- phone, telex, and facsimile communications were
sion. It was obvious that this timing would delay the established and proved adequate for the project.
project startup by many months. An accord was One of the major considerations in a project of this
reached that allowed the power line to be built by KGM type is labor. Consideration was given to building a
using a private contractor on behalf of the Queensland townsite a t the mine. However, the site is basically
Electric Commission, with completion in November remote, with no facilities such a s schools and hospitals
1984,many months ahead of the preliminary schedule within 100 km. The decision was made to establish a
but just in time for the plant startup. fly-in fly-out camp, with the mill crew.working seven
The Kidston Mine is located in a semi-arid region of 12 hour shifts followed by seven days off. The crews
Australia, and there are no lakes or rivers near the are flown in and out from Cairns and Atherton.
mine with adequate year-round flows to supply the Problems did develop when two shift bosses were
mill requirement. Studies showed that adequate water stranded by a flood and could not reach the plane, and
could be stored by building a dam on the Copperfield on occasion when the weather was so bad that crews
River, 23 km from the mill site. The dam building could not fly in and out on schedule. These delays
became a n important milestone in the project, as the caused some disruptions in the startup, but overall the
rainy season is from December to April, and like most system is working well.
desert areas the rain may fall a t any time during this In a startup, it cannot be overemphasized that every
period or even not a t all. To expedite construction it shift must have a t least one experienced shift boss and
was decided to build a roller compacted concrete one or two experienced operators with adequate
(RCC) dam, patterned after a dam constructed a t supervisors on hand to assist in training the "green"
Willow Creek, OR. As the Copperfield River Dam was operators and staff. One of the problems that has
only the second dam of this type constructed in the developed with the resurgence of gold mining is a
world, our engineers studied the US dam carefully. serious shortage of people with gold cyanidation
They employed Gutteridge, Hoskins, and Davie, an circuit operating experience. Fortunately, a t Kidston
Australian consulting firm, and Ernie Shrader, an some experienced people were available, but not a s
American consultant who worked on the original dam many a s desired. Startup and metallurgical assistance
for the US Corps of Engineers, to assist in design and was obtained by borrowing personnel from the Golden
construction. The RCC design resulted in a dam of a Sunlight Mine and Kilborn Engineering. A school
low volume, compared to a conventional earth-fill was run for operators, but it is always difficult to
dam. It became a high productivity project that was teach inexperienced mill people what to do in a crisis.
both economic and fast to build. Before startup, the assay and laboratory facilities
The contractors completed the dam by October 1984, should be fully staffed and operating well. Usually the
a s scheduled in preparation for the anticipated rains. mine will require assays for several weeks before the
Unfortunately, while some rain came in late Decem- mill, and every effort should be made to ensure that
ber 1984,January 1985 was the driest in 80 years, and it the assay office can provide this service and thus be
was not until March that the water level reached the ready for the mill startup. Unrealiable results can
pipe intakes. As water was required from December make the mill operation extremely difficult, and total
on, diesel powered pumps were required to lift the confusion can result if the deficiencies are not
water from behind the dam into the pipe inlets. The corrected. At Kidston an excellent assay staff was
task of keeping the pumps operating and supplying hired and they were well prepared for the startup.

46 FEBRUARY 1986 MINERALS AND METALLURGICAL PROCESSING


Flowsheet description Leaching circuit
A simplified flowsheet is given in Fig. 1 and a brief An agitated surge tank was provided to smooth out
process description follows. fluctuations in milling rates, a characteristic inherent
in a SAG mill-ball circuit. The slurry from the grinding
circuit, a t 40% to SOY0 solids, flows by gravity to the
R U N OF M I N E O R E
surge agitator and is pumped to the leach circuit at a
constant rate. A magnetic flowmeter in the pump
discharge line controls the speed of the pump to ensure
constant flow. A distributor box ahead of the two

!
parallel lines of the leach circuit splits the feed

b"m"ac

STOCKPILE
" " C u,F
THICKENING
STAG;
C A R B O N COLUMNS
1 equally to two lines of five agitated leach tanks. Total
retention time in this circuit is 24 hours a t 16 000 t/d.
The surge tank dimension is 14.5 m diameter x 11 m,
while the 10 leach tanks are 14.5 m diameter x 16.6 m.
Each tank is equipped with a 75 kW agitator.
1 SAG-BM
GRINDING / I TRASH SCREENS
BARREN
SOLUTION

Gold recovery circuit


LOADED CARBON
LEACHING
( 2 4 h l
6 STAGE CIP
The gold recovery circuit includes countercurrent
cyclone washing thickening, gold adsorption on carbon
in the CIP circuit and carbon columns. carbon
I
I
4 STAGE CYCLONE
WASH CIRCUIT

I I
SAIYETV SCREENS

I
LOADED CARBON
desorption, electrowinning by the Zadra process, and
smelting and refining of the loaded cathodes.
(-)
The discharge from the final leach agitators feeds
UIF
two four-stage countercurrent cyclone wash circuits
using 0.66 m cyclones. Wash water is added to the last
stage. At a wash ratio of 4 : l and cyclone underflow
DISPOSAL
ACID WASHING
DESORPTION
densities of 70% to 75% solids, the washing efficiency
is 99.8%.
The first stage cyclone overflow, at 18% solids, is
ELECTROWINNING
thickened to about 40% solids in two 13.7 m diameter
REACTIYATION high capacity thickeners. The thickeners are equipped
with bed level sensors, variable speed underflow
pumps, and density gauges for automatic control, to
I CARBON
H O L D N G TANKS ( ( REFINNG I maintain a constant underflow density and clear
overflow. The underflow is pumped to the CIP circuit
+
T O C I P AND Au
+
- A0
and the overflow is pumped to the carbon columns.
CARBON COLUMNS DORE The underflow of the last stage cyclones together
with the CIP tailing constitute the final plant tailing
Fig. 1 - Kidston mill flowsheet which is pumped to the tailing pond.
The CIP circuit has six 9 m diameter x 9.25 m
agitated tanks, each of which has 24 equalized pressure
Crushing and grinding air cleaned internal launder screens, 0.84 m x 0.45 m,
of which 0.3 m is submerged. The screens retain
The run-of-mine ore is crushed to -175 mm in a carbon within the tank while allowing slurry to
1.07 m x 1.65 m (42 in. x 65 in.) gyratory crusher and advance through the six stages. Carbon is advanced
conveyed to the 25 000 t (live) coarse ore stockpile. countercurrently between stages by vertical recessed
The crusher is equipped with a rock grapple to remove impeller pumps. Carbon concentration in each tank is
oversize boulders. maintained at about 15 to 20 g/L. Total pulp retention
Ore is withdrawn from the coarse ore stockpile by time is six hours. Carbon is loaded to 3000 g/t Au.
four 1.07 m x 2.4 m vibrating feeders, with two The carbon columns which treat the clear thickener
operating and two on standby. The feeders discharge overflow are in two lines of five 3.2 m diameter x 5.0 m
directly onto the SAG mill feed conveyor. tanks. Carbon is forwarded countercurrently by water
The grinding circuit consists of a SAG mill, 8.5 m jet eductors. Total retention time in this circuit is 30
diameter x 3.65 m (28 ft x 12 ft), driven by a 4100 kW minutes. Carbon is loaded to 4000 g/t Au.
variable speed motor, and a ball mill, 5.0 m x 8.34 m Both the CIP and carbon column circuits are pro-
(16.5 ft x 27.5 ft) driven by a 3730 kW synchronous vided with trash screens to keep wood chips and other
motor. trash materials out of the circuits, and safety screens
The SAG mill, in closed circuit with two 1.83 m x to recover any carbon that manages to go through the
6.71 m stationary screens produces grinds ranging launder screens or overflows the carbon columns.
from Kgo of 500 to 1000 pm depending on the type of ore Seven 1.5 m x 3.0 m high frequency screens are used
treated (present average is about 780 pm). The SAG in the two circuits.
mill product is reground in the ball mill to produce a Loaded carbon from both CIP and carbon column
final grind of about K80 of 210 pm (present average is circuits is pumped to the 1.5 m x 3.0 m loaded carbon
about 240 pm). The ball mill is in closed circuit with screen in the refinery building. The screen discharges
six 0.66 m diameter cyclones. into a measuring tank. From this tank, the loaded
This circuit processes ore a t rates varying from 475 carbon is educted to one of three 1.83 m x 7.5 m ( 9 t
to 660 t/h, depending on the hardness of the ore. During capacity) desorption vessels and pressure stripped for
October 1985, the mill averaged 630 t/h, with 96% 12 to 14 hours. Hot aqueous solution containing 3%
operating time. sodium hydroxide is pumped up through the carbon in
MINERALS AND METALLURGICAL PROCESSING FEBRUARY 1986 47
the desorption vessel a t a rate of about 30 m3/h. Initially, the startup tonnage apparently could not be
Temperature and pressure in the vessel are main- pushed over 300 t/h, compared to the design rate of
tained a t 120C and 350 kPa, respectively. Three 600 t/h, so sample belt cuts were made. It was found
circulating hot oil heaters, each rated a t 60 kW, that the weigh scale calibration was off by a factor of
provide the required heat for this operation. two. Recalibration solved the problem.
Gold and silver are recovered from the pregnant An error in design soon became apparent when the
strip solution by electrowinning. Two 152 cm x 91.5 cm trommel screen could not handle the tonnage of
x 91.5 cm electrowinning cells are in closed circuit rejects. Larger holes were cut in the screen and the
with each desorption vessel. Spent electrolyte is problem was solved. The trommel screen openings
recycled to the desorption vessel until the strip cycle were only marginally larger than the openings in the
is completed. grates. They should have been three or four times a s
After stripping, one third of the loaded steel wool big to handle tramp oversize.
cathodes is removed from the first cell, dried, fluxed, For many years Placer Development has used fluid
and smelted in a 250 kg induction furnace. The drives for variable speed control on pumps. At Kidston
cathodes of the second cell a r e transferred to the first, Gold Mines, the variable frequency system was used
and new cathodes installed on the second cell. Three on electric motors of less than 150 kW. These drives
sets of cathodes are pulled each week. Each set is can be changed very quickly and furthermore to lower
"triple loaded" (three strips/set). speeds without stalling. On occasion, this resulted in
The gold buttons produced from smelting are re- subcritical flow velocities. The problem was solved by
melted in a 75 kg induction furnace and poured into installing a low speed limit on the controller to ensure
32 kg (1000oz) bars. The bars typically assay 65% Au, that the slurry velocity in the line was kept high
30% Ag, and 5% impurities. enough to avoid sanding.
The stripped carbon is acid washed with dilute The SAG mill is equipped with a variable speed DC
hydrochloric acid, to remove calcium carbonate, motor. The ability to vary the speed during startup
reactivated a t 750 O C in two 225 kg/h vertical furnaces, was a great aid and with the problems associated with
and returned to the CIP and carbon column circuits. virtually no feed rate control. The mill could have had
The acid reactor is 2.5 m diameter x 4.0 m, and can considerable liner damage during the early days if it
hold 10 t of carbon. A dilute solution of hydrochloric had not been for the variable speed drive.
acid at pH 1.4 is continuously circulated through the A major accident occurred in the early morning of
carbon in the reactor for about eight to 10 hours. This January 7, when a 12.5 m m bolt came loose from the
treatment removes calcium carbonate scale and ring bus within the DC motor and fell into the motor air
metal cyanide complexes that are adsorbed in the gap. The windings shorted, and after about one and a
carbon, restoring carbon activity to the 60% level. The half turns, the motor "locked up" and the mill stopped.
thermal reactivation that follows restores carbon Fortunately, the pinion was not doweled in and it
activity to 96% of the original level. jumped back, bending the 38 mm jacking bolts. There
After acid washing, the spent liquor is drained and was no damage to the pinion and the ring gear. The
pumped to a storage tank for reuse in the succeeding motor armature was badly damaged, but a full set of
acid washing operation. The carbon is washed with spare coils was available. The armature and the upper
caustic solution to neutralize the remaining acid and magnet frame were sent to the Evens Deakins Shop in
educted to the carbon storage tank from where it is Brisbane, 1550 km away. The repair job was carried
educted back to the CIP and carbon columns or to the out very quickly and 14 days later the motor was back
reactivation furnace feed tank. in service.
On the Kidston project, like many others, by the
time the piping was being specified and designed,
everybody's mind was on other things. As a result,
Plant startup many of the small bore pump intakes were about four
times as long a s they should have been and their pump
Ore supply to the mill at Kidston was not a problem. bases were below the maximum water level in some of
From the first day on, the mine supplied sufficient ore the sumps. The grinding sump was particularly bad,
to the mill. with some oil return pumps set low enough that they
The first ore was put through the crusher in Decem- got sand in the motors. These problems were fairly
ber 1984. To save on concrete and construction costs, easy to correct, but troublesome a t the time.
the design of the crusher did not include a large surge The surge tank ahead of the leach tanks was, with its
pocket or an apron feeder for the first conveyor. The variable speed pumps, a good aid to circuit control.
conveyor was designed to handle 2200 t/h, i.e., the However, several mistakes were made in leach
maximum surge loading expected from the crusher agitator design. This points out the need for mill
when a truck dumps. Initially the ore was very dry and designers to get more information from the agitator
fine, resulting in overloading of the conveyor. The suppliers. First, the agitator upcomers were too big in
chute opening was reduced, and loading became cross-sectional area and extended too far down into the
satisfactory. tanks. Second, the four air headers in each tank
Construction was completed to the point where the extended down too low into the tank,and some became
grinding and leaching circuits could be started up on blocked immediately. Third, the gradient between the
Jan. 5, 1985. Several problems surfaced when the ore tanks was not sufficient to give a free flow of the slurry
started through the mill. The ore was difficult to get from tank to tank. The use of air in the upcomers
started through the feeders from a full stockpile, and helped the flow problems, and revisions to the air
the speed control on the feeders did not work a t all. The system have gradually been carried out to eliminate
feeders were dug out and once they were moving aeration difficulties.
regularly, they were operable. It was only possible to Initially, efforts were made to run a t a low pH, 9.5,
adjust the feed rate by switching feeders, each of but clarity could not be achieved in the high capacity
which gave a different flow rate. After several weeks thickener overflows. The low pH resulted in a heavy
of frustration, new controls were purchased, and the carryover of slimes to the carbon columns and the
operation is now satisfactory. reclaim water system. When operated a t pH 10.5, the

48 FEBRUARY 1986 MINERALS AND METALLURGICAL PROCESSING


thickener overflows were clear. Considering the size and complexity of the Kidston
The carbon columns usually are all made the same cyanidation plant, with its SAG mill-ball mill grinding
height and stepped. The Kidston columns are on a circuit and cyclone washing circuit, the startup was
common base and each column has a different height very good. After all the minor problems were correct-
to give the required gravity flow. The design did not ed, the mill has not only attained designed capacity but
present any operating problems. The eductors were has consistently exceeded it. Recently, 18 625 t were
initially drawing from the outside edge of the columns, treated in a 24 hour period, exceeding the design rate
but because the activity was low, the intakes were by more than 2000 t. Recoveries have steadily im-
moved to the center of the tanks. proved since startup and are now averaging close to
The screens for the carbon-in-pulp tanks were the predicted figures. The milling rate, expressed as a
designed as balanced head-equalized pressure, air percentage of designed capacity, and the operating
cleaned (EPAC) screens, with the screens installed time for each month of 1985 is shown in Fig. 2. The
vertically. To improve the operation, the operators mill performance for the second half of 1986 is
now tilt the screens a t an angle to give better air summarized in Table 2.
sweeping action on the screens. An experimental
rotary screen was tried initially, and while the
operation was good, like many prototypes, it suffered
some mechanical problems. The rotary screen
appears to have a great advantage over the EPAC
screens, in that the power to drive the rotary screens is
very much less than the power required for com-
pressed air for cleaning the screens.
The recessed impeller pumps used for forwarding
carbon in the CIP tanks and for several other carbon
transfer applications worked well.
The carbon strip circuit, while it had some opera-
tional problems, worked well. Plate and frame heat A ACTUAL Vs PREDlCTED MILL RATE 1
exchangers were used by the Placer group for the first
time on the Kidston project and, unfortunately, the 20 - OPERATING TIME

wrong gaskets were selected. The initial gaskets are


completely unsuitable for a strip circuit where the 0 1 ' 1 ' 1 ' 1 ' l '
gaskets are alternately wet and dry. When the 0 2 4 6 8 10 12
gaskets were changed to EPDM, there were no MONTHS AFTER STARTUP
further problems. The circulating hot oil heating
system worked very well. It takes about two hours to Fig. 2 - Kidston startup p e r f o r m a n c e
bring the strip vessel up to temperature and tempera-
ture control was very accurate. At present, the system
is handling 45,lO t batches of carbon per month. Table 2 - Average Mill Performance, July to December 1985
The electrowinning and refining circuits presented
only minor problems. The Inductotherm melting Actual

furnaces developed high temperatures in the cooling Milling Rate, tld Oxide Ore -
Transition -
water. Investigation showed that a partially blocked Fresh -
pipe line in the heat exchangers was restricting the Year One 13 130
flow. When this was cleared, the problem was Primary Grind, K80, pm 240
Mill Head, glt Au 2.14
eliminated. Leached Residue, glt Au 0.31
The vertical carbon reactivation furnace was a Gold Recoverv. % 86.2
Production, ksmonth, Au 752
major problem. The unit suffered from poor fire box Reagent Consumption, kglt
design and poor construction of the internals. The Sodium Cyanide 0.62
operators ordered a second furnace, and by May 1985, Lime
Flocculant
2.45
0.035
when the unit was installed, the original furnace Grinding Ball consumption, kglt
needed a complete overhaul. In a recent monthly SAG Mill 0.31
report, it was noted that both furnaces had been out of Ball Mill 0.40
Total 0.71
service for the whole month to make design
Power Consumption, kWhlt
modifications. SAG Mill 5.07
The reagent mixing systems for the 0.9 t bags of Ball Mill 5.66
sodium cyanide and the 25 kg bags of dry flocculant
worked well. The plastic piping in the distribution
system had many leaks initially, but these were In the first 12 months of operation, the Kidston Mine
gradually repaired. The lime slaking system was a has produced over 7000 kg (225,000 oz) of gold and
disappointment. It appears that a North American 3500 kg (112,500 oz) of silver, ranking it the biggest in
style slaker is not suitable on the type of lime available Australia. The total operating cost of about US $12010~
in most of Australia. For a future project, Placer makes it one of the lowest cost, low grade gold mines
Development would not consider anything but a ball in the world.
mill-classifierfor slaking poor quality lime.
The mill was just starting to operate smoothly when Acknowledgments
the Queensland Electric Commission negotiations with
their employees broke down and a state wide electric The authors thank the management of Placer
power shut down occurred on Feb. 12,1985. KGM was Development Ltd. and Kidston Gold Mines Ltd. for
originally allowed 10% of its power load, but this was permission to present this paper. We acknowledge the
soon dropped to 5%. At these levels, the mine was dedicated efforts of the mill operating crew and staff
unable to operate and was shut down from February 12 in bringing the Kidston mill up to design quickly
until February 23, when operations were resumed. and efficiently.
MINERALS AND METALLURGICAL PROCESSING FEBRUARY 1986 49

Potrebbero piacerti anche