Sei sulla pagina 1di 11

POKA YOKE

OR
QUALITY BY MISTAKE PROOFING DESIGN
AND CONSTRUCTION SYSTEMS
Ir is D. Tommelein 1

ABSTRACT
The Japanese concept poka yoke, translated into English as mistake proofing, has
been mentioned at previous IGLC conferences. This notwithstanding, mistake
proofing appears to not have been (nor be) systematically researched or practiced in
the lean construction community. To raise awareness of opportunities provided by
thinking with mistake proofing in mind as a means to build quality into project
delivery, this paper summarizes the philosophy that underlies mistake proofing.
Examples illustrate how mistake proofing applies to the work done within one
specialty trade, how manufacturers and fabricators can design their products so they
cannot be constructed defectively, and how architects and engineers may conceive of
system designs that are less likely to fail during construction or in a products life
cycle. Reader contributions to an online repository of mistake proofing applications in
the architecture-engineering-construction (AEC) industry, posted at
http://p2sl.berkeley.edu/pokayoke/, will be gratefully acknowledged.

KEY WORDS
poka yoke, mistake proofing, jidoka, autonomation, design, engineering, system,
specification, construction, safety, quality, constructability, tolerance management,
life-cycle performance, lean construction

translated as autonomation in
INTRODUCTION AND English, as together they form a pillar
DEFINITION of the Toyota Production System.
Shingo (1986), a master mind of the Autonomation refers to machines
Toyota Production System, introduced built to detect problems and stop by
the concept of poka yoke in themselves, so as to relieve the
Japanese, translated as mistake burden of constantly supervising a
proofing in English, in his book titled machine, and allow [people] to use
Zero Quality Control: Source their talents for more beneficial things
Inspection and the Poka-yoke System. (like adding value) (Liker and Meier
This concept goes hand-in-hand with 2006 p. 177) The purpose of
the concept of jidoka in Japanese, autonomation is the rapid or immediate
address, identification and correction

1
Director, Project Production Systems Laboratory, http://p2sl.berkeley.edu/, and Professor,
Engineering and Project Management Program, Civil and Environmental Engineering Department,
215-A McLaughlin Hall, University of California, Berkeley, CA 94720-1712, Phone +1 510/643-
8678, FAX +1 510/643-8919, tommelein@ce.berkeley.edu

195
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

of mistakes that occur in a process proofing examples. The aim of this


Once the line is stopped, a supervisor effort is to develop a community
or person designated to help correct knowledge base and to spur discussion
problems give immediate attention to around mistake proofing opportunities
the problem the worker or machine has in the architecture-engineering-
discovered. To complete jidoka, not construction (AEC) industry.
only is the defect corrected in the
product where discovered, but the APPLICABILITY OF MISTAKE
process is evaluated and changed to PROOFING IN THE AEC
remove the possibility of making the INDUSTRY
same mistake again. This mistake- Shingos premise of zero quality
proofing of the production line is control is to do it right the first time.
called poka yoke. (Superfactory Bodek stressed this idea in his preface
2008). to Shingos book (1986 p. vii) by
Many online glossaries with lean stating that we should drop the idea
production terms include poka yoke that defects are a normal part of
(e.g., http://www.nummi.com/tps.php) manufacturing. In the AEC industry,
and at least one website has been this thinking is contrary to the reliance
dedicated to this topic of practitioners on inspection and
(http://www.mistakeproofing.com/). punch lists as means to work towards
Books have been written on the an acceptable end product, hopefully
application of mistake proofing in one that is satisfactory and of quality!
specific industries (e.g., Grout 2007 is To eliminate the need for quality
on health care processes). Lean control, the practice of mistake
construction researchers have proofing sets out to prevent errors or
mentioned the concept for many years defects from occurring in the first
at previous IGLC conferences and place.
elsewhere (e.g., Koskela 1992, dos Mistake proofing is particularly
Santos et al. 1998, 1999, dos Santos well suited for the AEC industry with
and Powell 1999, Moser and dos its low-volume and mixed production
Santos 2003, Adbelhamid and Salem systems where statistical quality
2005). This notwithstanding, the control methods cannot be
practice of mistake proofing still implemented due to lack of data and
appears to not be systematically un-timeliness of findings that result
pursued by researchers and from after-the-fact data processing.
practitioners in the lean construction Mistake proofing requires a different
community. To raise awareness of way of thinking about production
opportunities provided by thinking processes and its constituent
with mistake proofing in mind as a operations, but once practitioners have
means to build quality into project learned to recognize mistake proofing
delivery, this paper summarizes the devices, their new mind-set will enable
philosophy underlying mistake them to spot numerous opportunities
proofing, illustrates opportunities for available to mistake proof their
application of this concept in practice workplace. They will find that many
by means of examples, and solicits mistake proofing practices can be
contributions from readers who may implemented at a minimal cost, though
wish to volunteer other mistake

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


196
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

some do require investment in new and-by itself yields advantages,


product development. practitioners will reap the greatest
Mistake proofing could be thought benefits from mistake proofing when
of as a practice that is part of pursuing applying it in concert with other lean
constructability, that is, changing a practices.
design so that it could be built better Shingo (1986 p. 135) thought that
(e.g., more easily, cost effectively, explaining poka-yoke methods by
safely, so it will last longer, etc.), but it means of examples would be
differs from constructability in two extremely effective when it came to
regards. First, the goal of mistake actually adopting the poka-yoke
proofing is to improve production system and he goes on to present
system performance by eliminating numerous examples (ibid pp. 139-
waste, e.g., avoiding product and 261). Likewise, this paper includes a
process defects, reducing variation, selection from nearly hundred AEC
and not tolerating poor quality. examples I have collected to date, to
Second, efforts at mistake proofing do show the broad applicability of
not necessarily coincide with the mistake proofing in various phases of
timing of constructability review in a project delivery. Tommelein and Grout
projects delivery process. Simply put, (2008) describe and analyse many
pursuing constructability sometimes more examples and offer more detail
means cutting costs after a design than is presented here. Examples in
already has been substantially this work are not intended to be
developed but exceeds budget. In endorsements of the products they
contrast, examples in this paper refer to.
illustrate that mistake proofing is a
practice for all project participants MISTAKE PROOFING IN
(designers, manufacturers, fabricators, DESIGN, CONSTRUCTION, OR
builders, and others) to pursue in their MAINTENANCE
day-to-day work and throughout Mistake proofing applies to work done
project delivery. by a single specialist or by several
The purpose of this paper is to specialists. In example 1 (Figures 1
raise awareness of how mistake and 2), specialists in design and in
proofing practices support lean construction have color coded
implementation, specifically on distinctions that matter for their
products and processes in the AEC specific work and phase of a project so
industry. Mistake proofing practices as to avoid mix-ups. In examples 2, 3,
contribute to improving a systems and 4 (Figures 3, 4, 5,and 6), work has
performance, for example, by reducing been productized. Manufacturers
the time it takes to perform a task have made devices to address a
while also narrowing the variation of specific need and thereby reduced the
that tasks duration, by making sure amount of work, and simplified the
hand-offs from one task to the next are nature of the work required of field
sound (not defective), and by reducing personnel. In example 4 (Figures 5 and
variation in products and process 6), a component is added to the system
outcomes. Though the focus in this in order to fail safe maintenance work.
paper is on mistake proofing and These devices literally or figuratively
though application of this concept in- turn work into plug-and-play.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


197
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

Figure 1: Color coding of design drawing shows Figure 2: Color coding shows locations for sheet
different wall types for drywall cost estimate metal straps and pipe hangers on metal decking

(Source: DPR, Inc., Camino Medical Project) (Source: John Mack, Southland Industries, Inc.,
presentation at 2007 Annual Conference of the Lean
Construction Institute, San Francisco, CA)
hose that solves a typical fit-up
E XAMPLE 1: C OLOUR C ODING TO
problem. At one end, the toilet bowl
I MPROVE I DENTIFICATION
(commode) is seated on waste-water
Figure 1 shows colour codes a pipe located in the floor, and the water
construction estimator has assigned to tank rests on and connects to that base
distinguish various wall types. This of the fixture. At the other end, the
helps in clarifying and categorizing the water supply pipe runs in the wall and
design requirements specified by the stubs out of it, ending with a valve.
architects, in performing a quantity The challenge is to connect the pipe at
take off and preparing a cost estimate, this valve to the entry into the water
and in planning the work. Figure 2 tank, recognizing that all construction
shows colour codes being used on site, work that precedes this connection step
to highlight which metal-decking is subject to dimensional variation
inserts belong to which trade. This (tolerances), that is, things do not get
helps, among other things, in making it physically located exactly where
easy to assess whether or not all inserts drawings or computer models showed
are in place prior to casting the them to be. Rather than requiring
concrete slab on this decking. These bending of more rigid tubing or pipe
two examples illustrate mistake and cutting it to size, a flexible hose of
proofing approaches that help reduce approximate (standard) size suits this
the likelihood of occurrencethough purpose without requiring accurate
not 100% preventionof mistakes. measurement.
E XAMPLE 2: F LEXIBLE C ONNECTION Mistake proofing devices to
TO ACCOMMODATE DIMENSIONAL accommodate the manifestation of
VARIATION uncertainty in physical geometry
(dimensions and location), and
Figure 3 shows plumbing where the accumulation of that uncertainty as
mistake proofing device is a flexible work progresses, similarly exist in

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


198
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

other specialties. Another example is connect rigid sheet-metal duct in


that mechanical contractors who build plenum spaces to diffusers in modular
HVAC systems rely on flexible duct to ceiling-tile grids.

Figure 3: Flexible hose (Source: Picture Figure 4: Connect plug and wiring of light fixtures (Source:
by Iris D. Tommelein, Boston, MA, Finelite (2001) product literature)
2007)
ballast, which is a component in a light
EXAMPLE 3: PLUGS TO ENSURE
fixture used to stabilize the current
CORRECT CONNECTIONS DURING
flow. All wires related to the ballast
ASSEMBLY
fits into the fixture and wiring can be
Figure 4 shows a connect plug that done off site. Until recently, all this
ensures the correct wiring of electrical wiring was continuous; new code
light fixtures and that, furthermore, requires the use of the plug as
greatly simplifies the work otherwise described. The challenge is that
required of a skilled field electrician maintenance personnel, who must
(Finelite 2001, 2008, Tsao and disconnect the ballast from the
Tommelein 2001). The challenge is electrical circuit prior to working on it,
that custom-wiring of light fixtures on at times would not disconnect all
site requires meticulous attention wiring properly and thus risk
(avoid cross-wiring) and work electrocuting themselves. The mistake
overhead. The plugs for each fixture proofing device is a brightly colored
are wired off-site in a shop plug that is easy to unplug and plug
environment, leaving only final back in (Figure 5). A sticker (Figure 6)
assembly to be done on site. The plug on the outside of the light fixture but
allows for only one way in which to out of sight for people occupying the
connect adjacent fixtures together. A room informs maintenance personnel
minimal investment in plugs and shop that this feature is present in that
assembly thus result in a safer, less fixture. A minimal investment in plugs
error-prone, and faster process overall. wired during off-site assembly of the
EXAMPLE 4: PLUGS TO ENSURE fixture thus results in a safer, less
CORRECT MAINTENANCE error-prone fixture maintenance
process.
Figure 5 shows a connect plug
installed in the power supply to a

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


199
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

Figure 5: Wiring plug for ballast inside light fixture (Source: Picture Figure 6: Instruction label on
by Iris D. Tommelein taken at Finelite, Union City, CA, 2008) outside of fixture (Source:
Picture by Iris D. Tommelein
taken at Finelite, Union City,
CA, 2008)
was not always of consistent and
MISTAKE PROOFING A adequate thickness. Either the panels
PRODUCT DESIGN FOR had not been tightened sufficiently
CONSTRUCTABILITY AND (uneven thickness), so the sealant left
LIFE-CYCLE PERFORMANCE gaps through which water could
Mistake proofing can be done in penetrate, or the panels had been
design. The following examples tightened too much (minimum
illustrate how a product was designed thickness not met), so the sealant had
and engineered for constructability been squeezed out, leaving too little
while targeting life-cycle performance. material to be effective. This sealant is
a mistake proofing device that curbs
EXAMPLE 5: SEALANT TO ALLOW variation in the system.
LIMITED COMPRESSION To mistake proof the tightening
Figure 7 shows the cross-section of a process, the manufacturer co-
metal roof, where two roof panels are developed with their supplier a new
joined. The challenge is to make a sealant product, in which tiny but hard
seam that is watertight. This is cubes are embedded and more-or-less
particularly important to the evenly distributed. The dimension of
manufacturer of these roofing products these cubes is commensurate with the
who guarantees long-term performance optimal thickness of the sealant
(e.g., 20 years if not more) of their application. As a result, contractors
installed products and wants to need no longer worry about overly
maintain their brand-name reputation. tightening their fasteners: the
This manufacturer studied the minimum thickness of the sealant is
performance of installed roofs and guaranteed.
found that the sealant between panels

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


200
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

Figure 7: Sealant and return leg to guarantee roof performance (Source: Butler manufacturing product
literature)
must slope slightly to allow water to
EXAMPLE 6: OVERLAPPING
run to a drain for ease of cleaning the
MATERIAL TO ACCOMMODATE
floor.
DIMENSIONAL VARIATION
To complicate the situation, design
Figure 7 also shows a sealant pocket drawings showing the layout plan view
and a return leg on each overlapping of a restroom may not accurately
panel made by this manufacturer to reflect the slope of the floor towards
further ensure that the joined roof the drain (Figure 8). A builder may
panels would be water tight. have to pull information together from
different drawings and sections in the
MISTAKE PROOFING THE specifications in order to develop a
DESIGN OF A SYSTEM clearer 3-dimensional picture of the
The last example illustrates how situation (Figure 9). Because of this
designers may use mistake proofing as slope, when the designer selects sinks
a means to accommodate a variety of with an apron to hide plumbing behind
competing requirements from users it, the clearance between the bottom of
while recognizing that dimensional it and the floor will vary in the room.
variation will occur during As a result, some clearances as shown
construction, and mistakes could occur in the design may meet the ADA
as well. Consider designing and requirements whereas others in the
constructing a restroom facility with same room will not. Add to that the
sinks (wash basins). The challenge effect of tolerances that will manifest
with such facilities is that (in no themselves during construction and it
specific order of value): (1) the becomes less likely that clearances will
plumbing must be functional (i.e., the suffice (Figure 10). It is no wonder
sink drains into a pipe with a water then that quite a few facilities get built
lock); (2) designers and users may but fail to meet ADA requirements,
want sinks to be aesthetically pleasing; and following inspection thus require
(3) the sink height must be convenient rework prior to commissioning.
for hand washing; (4) in the United Practitioners are aware of these
States, public restroom facilities must challenges (conflicting values) and
meet American with Disabilities Act have developed various solutions in
(ADA) requirements (this act basically response. Figure 11 shows a bare
states that people with disabilities just sink with ugly plumbing underneath
like everyone else must be able to use of it. Figure 12 shows an
such public facilities); and (5) the floor architecturally more pleasing solution,

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


201
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

however, this one would not meet


ADA requirements.

Figure 8: Sketch with Plan View of Sink Layout

Figure 10: Sketch with Side View of Sink, Drain,


and Exaggerated Sloping Floor
Figure 9: Sketch with Plan View of Sink Layout
with Sloping Floor and Drain

Figure 11: Bare Sink in San Francisco Airport, Figure 12: Dressed-up Sink in Mich. State Univ.
California ( 2006 Iris D. Tommelein) Conf. Center, East Lansing, Michigan ( 2007
Iris D. Tommelein)
a solution that acknowledges the
Figure 13 shows another way of
challenge. Here, the apron is cut back
covering up the plumbing, but it is
to ensure sufficient clearance, at least
unclear if this solution would meet
in a few locations.
ADA requirements. Figure 14 presents

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


202
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

Figure 13: Sink with Covered Apron in Brussels Zaventem Airport, Belgium ( 2007 Iris D. Tommelein)

where it was designed to be (in height


EXAMPLE 7: HINGED CONNECTION
or in horizontal position relative to the
TO ALLEVIATE IMPACT OF
drain), the floor not sloping exactly as
TOLERANCE ACCUMULATION
shown in the design, the apron not
Finally, figure 15 shows a solution being perfectly horizontal, etc. The
designed with mistake proofing in hinged section is clearly marked with a
mind. Here, a section of the apron is handicapped sign to help restroom
cut and attached from the top using a users and to point out to inspectors that
hinge, so that it can turn up when the ADA requirements have been met.
need arises. This need may stem from
the drain not being located exactly

Figure 14: Sink with Cut-out Apron in San Francisco Figure 15: Sink with Adjustable Apron at Oakland
Airport, California ( 2007 Iris D. Tommelein) Airport, California ( 2004 Iris D. Tommelein)
Unlike other mistake proofing devices,
The example in figure 15 like that in
figure 3, showed the use of a mistake these do not in-and-by themselves
prevent or reduce the occurrence of
proofing device (flexible hose or duct,
and hinged apron) to buffer or variation in the system.
alleviate the impact of variation.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


203
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

SUMMARY research, broadening theoretical


This paper described the concept of understanding and use of this lean
mistake proofing and illustrated how it concept in the AEC industry, we
applies to the AEC industry by would appreciate receiving your
drawing on examples from current examples of and thoughts on mistake-
practice. These examples showed not proofing practices. Please email
only that but also how mistake pictures of examples with a description
proofing applies to various project to tommelein@ce.berkeley.edu. We
delivery phases in this industry. The will gratefully acknowledge all
examples illustrated that mistake contributors and add selected
proofing can be practiced within a submissions to those already posted at
specialty (e.g., plumbing, electrical, or http://p2sl.berkeley.edu/pokayoke/.
mechanical work), it can be practiced This website has been set up to grow
by designers, manufacturers, or into a community knowledge base to
fabricators to benefit a product as it is promote lean thinking.
being constructed or throughout its
ACKNOWLEDGEMENTS
lifecycle performance, or it can be
practiced by designers to benefit a Research on tolerance management
system (e.g., assembly of multiple conducted with my PhD student Colin
components by multiple trade Milberg and discussions with Dr. John
specialists). Grout about mistake-proofing practices
AEC industry researchers and in other industries have spurred me to
practitioners are not taking advantage document practices and opportunities
to the extent they could of to mistake-proof processes in the AEC
opportunities to mistake proof their industry. The research on tolerance
processes and products. This paper management was funded by grant
was written to help people see where CMS-0116877 from the National
opportunities may exist for mistake Science Foundation. Research for this
proofing, to help them gauge what paper was in part supported by gifts
value may stem from it, and to sharpen made to the Project Production
everyones thinking about Systems Laboratory
opportunities to mistake proof AEC (http://p2sl.berkeley.edu/). All support
products and processes. is gratefully acknowledged. Any
Mistake proofing is an active area opinions, findings, conclusions, or
of research that falls under the Built-in recommendations expressed in this
Quality Initiative of the Project paper are those of the author and do
Production Systems Laboratory (P2SL) not necessarily reflect the views of the
at the University of California at National Science Foundation or
Berkeley, California. In pursuit of this contributors to the Project Production
Systems Laboratory.

REFERENCES
Abdelhamid, T. and Salem, S. (2005) Lean construction: a new paradigm for managing
construction projects. Intl. Workshop on Innovations in Materials and Design of
Civil Infrastructure, 28-29 December, Cairo, Egypt, 25 pp.
Bodek, N. (1986). Page vii of Publishers Preface to Shingo (1986).

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


204
Poka Yoke or Quality by Mistake Proofing Design and Construction Systems

Iris D. Tommelein

dos Santos, A. and Powell, J. (1999). Potential of poka-yoke devices to reduce


variability in construction. Proc. 7th Ann. Conf. Intl. Group for Lean Constr.,
Berkeley, CA, pp. 51-62.
dos Santos, A., Powell, J., and Formoso, C.T. (1999). Evaluation of Current Use of
Production Management Principles in Construction Practice. Proc. 7th Ann. Conf.
Intl. Group Lean Constr., Berkeley, CA, pp. 73-84.
dos Santos, A., Powell, J., Sharp, J., and Formoso, C.T. (1998). Principle of
transparency applied in construction. Proc. 6th Ann. Conf. Intl. Group for Lean
Construction, Guaruja, Brazil.
Finelite (2001). The Affordable Alternative Contractor Guide. Finelite Inc., Union City,
CA, http://www.finelite.com/, 20 pp.
Finelite (2008). Estimator and Contractor Guide. Available online at
http://www.finelite.com/contractor/ContractorGd_m.pdf visited 22 April.
Grout, J. (2007). Mistake Proofing the Design of Health Care Processes. AHRQ,
available online at http://www.ahrq.gov/qual/mistakeproof/mistakeproofing.pdf
Koskela, L. (1992). Application of the new production philosophy to construction.
Technical Report 72, CIFE, Stanford University, Stanford, CA.
Liker, J.K. and Meier, D. (2006). The Toyota Way Fieldbook. McGraw-Hill, 475 pp.
Moser, L. and dos Santos, A. (2003). Exploring the role of visual controls on mobile cell
manufacturing: A case study on drywall technology. Proc. 11th Ann. Conf. Intl.
Group for Lean Construction, Blacksburg, VA.
Shingo, S. (1986). Zero Quality Control: Source Inspection and the Poka-yoke System.
Productivity Press, Cambridge, Mass.
Superfactory (2008). Website http://www.superfactory.com/topics/jidoka.htm visited on
May 5th.
Tommelein, I.D. and Grout, J. (2008). Mistake Proofing Architecture, Engineering, and
Construction Processes. Project Production Systems Laboratory (P2SL), U.C.
Berkeley, CA, forthcoming.
Tsao, C.C.Y. and Tommelein, I.D. (2001). Integrated Product-Process Development by
a Light Fixture Manufacturer. Proc. 9th Ann. Conf. Intl. Group for Lean Constr., 6-8
August, Singapore.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


205

Potrebbero piacerti anche