Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Sl.
Particular Detail
No.
R-APDRP is a Govt. of India initiative to renovate and modernize
the electricity power distribution system of urban India in order to
1. Introduction
reduce the AT&C losses and improve the quality of power supply
to the consumer.
Details of the works involved
Supply, transit storage, erection, testing, commissioning of all
major and minor equipments:
1. 33 kV sub-station
New 33/11 kV Sub Stations.
Augmentation of capacity by replacing the old or by
providing additional power transformer at existing 33/11
kV Sub Stations.
R & M of existing 33/11KV substations.
Installation of Capacitor Banks at 33/11 KV Sub Stations.
2. 33kV Line
New overhead lines and underground cables.
Bifurcation and Reconductoring of existing lines.
3. 11/0.433 kV sub-station
New 11 kV Sub Stations.
Augmentation of existing transformers.
R & M of existing 11 KV sub stations.
5. LT Line
New lines from distribution transformers.
Extension of existing lines.
Reconductoring and strengthening of existing lines.
7. Capacitor Banks
Installation of capacitor banks.
All the works indicated above are to be carried out complete in all
3. Execution
respect on Turnkey basis within the specified time.
4. Bill of Quantity 1. The quantity of material required for these works has been
(BOQ) described separately in the Bill of Quantity (BOQ) annexed
with this tender document.
Page | 1
Sl.
Particular Detail
No.
Page | 2
Sl.
Particular Detail
No.
channels and all other unforeseen items whose prices are
not indicated in the price schedule.
Title IS No.
1. Cement IS 269
2. Steel IS 6003/1970
3. Fasteners IS 6639/1972
4. Concrete mix IS 1343
5. RCC IS 456
6. Cable laying and jointing IS 1255
The contractor shall have to follow the procedures laid down with
this tender specification or any other procedure intimated later on.
Page | 3
Sl.
Particular Detail
No.
like steel tape, vernier calipers, screw gauge, tong tester, earth
resistance tester, 2.5 KV meggar etc.
12. Men, Material & T&P 1. The contractor shall himself arrange all men & material, all
constructional T & P and any other material required for
successful and speedy execution of the job within the
prescribed time
Page | 4
Sl.
Particular Detail
No.
2. All tools, welding equipment, crane, scaffolding, rigging
materials, ladders, consumables, hardware etc. required for
installation shall be arranged by the contractor.
15. Erection, Testing and 1. All the works covered under the scope of the tender shall be
Commissioning done in accordance with the norms defined in urban
construction manual of UPPCL, unless the same is not
specifically defined in the specification or with the provisions
of Indian Electricity Rules/Acts/Other Government
Rules/Regulations as prevalent at the time of execution of
the job/work.
Page | 5
Sl.
Particular Detail
No.
Page | 6
Sl.
Particular Detail
No.
possible that some of the specified work may not be carried
out due to space/land/ other technical constraints etc. In
such case the concerned MD of DISCOM], if required, may
divert this work at some other site or cancel the left over
portions of work.
Schedule of work This PERT chart shall include all the activities such as
17. completion/ PERT design, engineering, submission and approval of drawings
Chart/Bar Chart approval of vendors/suppliers, procurement, manufacturing,
erection, testing and commissioning plan.
Page | 7
Sl.
Particular Detail
No.
18. 33kV Sub-station New 33/11kV Sub-station
Drawings and Layout The drawing of earth mat, earthing system, the transformer
18.2 Plan plinths, the foundations of all equipments & their support structure
are to be approved by CEO and the construction work shall be
taken up by the contractor accordingly.
18.4 Earthing 1. Designing the earth mat of the switchyard including diameter
Switchyard of the MS Rod, spacing of the rods etc so that the specified
value of the ground resistance (as per ISS/EEE) in no case
exceeds 1 ohm.
3. The earth mat & earthing work shall include laying mesh,
fabrication and driving of 2500 mm. long 32 mm diameter
earth electrodes, connecting the same to the earth mat points
of all the equipments installed in the outdoor as well as indoor
and the fencing. All the jointing shall be done by electric arc
welding.
4. The earth mat mesh made of M.S. Bar shall be laid crisscross
as per standard practice of RESSPO applicable to the
particular site and as per directives of representative of
Page | 8
Sl.
Particular Detail
No.
respective DISCOM.
5. The earth mat mesh should at least be 0.75 Mtr. below the
make up ground plinth level of switchyard. The earth
electrodes shall have to be fabricated and driven into the
ground upto its full length in the manner that its top, is at least
750 mm below the make up ground / plinth level. These
electrodes shall be properly jointed with earth mat mesh by
way of electric arc welding.
11. The fencing shall also be connected with the main earth mat
mesh by means of M.S. / G.I. strips at an interval of 10 Mtrs.
(Approx.). After making joints / welding, each joint shall be
protected by coating the weld with molten bitumen.
18.5 Switchyard Structure 1. All the switchyard structures shall have to be fabricated as
per RESSPO manual of drawing or firms drawing approved
by respective DISCOM.
Page | 9
Sl.
Particular Detail
No.
If required, modification in the structure to match with the
related equipment and ground level shall have to be carried
out by the contractor.
Page | 10
Sl.
Particular Detail
No.
9. Clamps shall be corona free and shall carry an overload of at
least 20% over the rated current of 250 A.
The battery and battery charger along with D.C. and A.C.
distribution board are to be erected in the sub-station control
Battery & Battery room and are to be tested and commissioned.
18.9
Charger
All A.C. and D.C. wiring for the same is to be done by the
contractor.
Page | 11
Sl.
Particular Detail
No.
18.16 Lighting
The control room and the switchyard are to be illuminated
adequately to have clear visibility at every point.
1. The switchyard and control room lighting shall be governed
by detailed technical specification given in the tender
document.
Page | 12
Sl.
Particular Detail
No.
so located that sufficient illumination is available in and
around C&R panels.
6. The concerned CEO has discretion to divert some of the
lighting fixtures to other substation site if so required. The
contractor shall execute the work accordingly.
All the equipments in the yard and control room, including oil
filled equipments, are to be protected by portable fire
extinguishers. These fire extinguishers are to be put at
appropriate locations in and around control room and
switchyard at specified locations. The quantities of portable
CO2 and DCP type fire extinguisher to be installed at one
substation shall be governed by detailed technical specification
18.18 Fire Fighting System
given in the tender document. The payment for the same shall
be made as per price schedule. The contractor must quote the
refilling charges of the extinguisher in the schedule of spares
annexed in the tender documents.
Page | 13
Sl.
Particular Detail
No.
19. 33kV Sub-station R&M Of Existing 33/11 kV Sub Station
1. Design of substation and R&M of associated electrical &
mechanical auxiliary systems includes preparation /
modification of single line diagrams and electrical layouts,
erection key diagrams, electrical and physical clearance
diagrams, design calculations for Earth mat and Direct Stroke
Lighting Protection (DSLP), Bus Bar, control and protection
schematics, wiring and termination schedules, civil designs
and drawings of foundation, repairing and maintenance of
cable trenches and galleries etc., fire fighting, indoor and
outdoor lighting/illumination and other relevant drawings and
documents required for engineering of all facilities.
Page | 14
Sl.
Particular Detail
No.
20. 33kV Sub-station Capacity Augmentation of 33/11 kV Sub-stations
1. By replacing existing transformer with higher capacity
transformer.
Supply and proper laying the power cables from control room
to the transformer (if they are non-existent or damaged) either
20.3 Power Cable through existing cable trenches or the trenches to be
constructed by the contractor.
Page | 15
Sl.
Particular Detail
No.
distribution board including supply of cables & connectors etc.
2. Alignment of the existing bus bars and the proposed I/C and
O/G modules of the new Circuit Breakers must match the
existing bus bar and switchgears.
Page | 16
Sl.
Particular Detail
No.
2. Calculation of the number and type of fire extinguishers
required for covering fire hazard of control room, switch yard,
oil filled equipments and cable trenches shall be approved by
CEO.
Page | 17
Sl.
Particular Detail
No.
3. On checking of the earth pit resistance of the transformer,
LAs and PTs., in case the pipe type earthing resistance
comes out to be more than 4 ohm, a new pipe type earthing
of the above mentioned equipments and its connection to
station ground mat has to be done.
Bus-bars,
20.13 Connectors and As given at 18.7 above
clamps
Page | 18
GENERAL SPECIFICATION FOR CONSTRUCTION OF
33Kv/11Kv/COMPOSITE/LT LINES)
Sl.
Particular Detail
No.
1. Before taking up the line construction work the contractor
shall verify the proposed line route by jointly surveying with
the representative of the concerned CEO.
At all important road crossing the poles shall be fitted with Disc
type insulator but the ground clearance at the roads under
maximum temperature and in still air shall be such that even with
4. Road Crossing conductor broken in adjacent span, ground clearance of the
conductor from the road surface will be as per IE rules1956 as
amended from time to time and proper cradle guarding to be
provided across the road.
5. Railway Crossing
At the time of route survey, the railway crossings shall be
finalized as per the regulation laid down by the Railway
Authorities. The following are the important features of the
prevailing regulations (revised in 1987):
Page | 19
Sl.
Particular Detail
No.
cabin location in an electrified area.
Page | 20
Sl.
Particular Detail
No.
11. Earthing 1. Each and every pole of the new 33/11 kV line and every third
pole of LT line shall be properly earthed by the contractor by
constructing electrode type earthing using 5 mm GI wire and
Page | 21
Sl.
Particular Detail
No.
2500mmx20 mm dia MS earthing rod.
2. The cost of the same shall be included in the price quoted for
poles/supports as per standard practice of UPPCL. Detailed
drawing no. DD&SO-27 are enclosed.
Page | 22
Sl.
Particular Detail
No.
16. Jointing 1. When approaching the end of a drum length, at least three
coils shall be left in place when the stringing operations are
stopped. These coils are to be removed carefully, and if
another length is required to be run out, a proper joint shall be
made.
4. All the joints shall be made at least 30 meters away from the
pole.
No joints or splices shall be made in spans crossing over
main roads, railways and small river spans. Not more than
one joint per conductor per span shall be allowed. The
compression type fittings shall be of the self-centering type,
care shall be taken to mark the conductor to indicate when
the fitting is centered properly.
Page | 23
Sl.
Particular Detail
No.
2. The sag will be checked in the first and the last section span
for section upto eight spans, and in one additional
intermediate span for section with more than eight spans. The
Tensioning And
17. sag also be checked when the conductors have been drawn
Sagging Operations
up and transfered from running block to the insulator clamps.
Page | 24
Sl.
Particular Detail
No.
lines/telecommunication line (as Cradle guarding)
21. Final Checking, Testing After completion of the works, final checking of the line shall be
and Commissioning carried out by the contractor to ensure that all foundation works,
pole erection and stringing have been done strictly according to
the specifications and as approved by the concerned
CEO/SE(D), EUDC-EDC.
Page | 25
Sl.
Particular Detail
No.
contractor through provision of his own equipment, labour etc,
to the satisfaction of the Owner;
h. All poles are properly grouted.
i. The line is tested satisfactorily for commissioning purpose.
Page | 26
Sl.
Particular Detail
No.
33kV:
11kV:
11kV line shall normally be constructed on 11 mtr. long steel
poles (410- SP-55) or 9/8.5 mtr. long PCC pole
3. The stay sets shall comprise GI stay rod, GI anchor plate, stay
2. Stay Sets wire, turn buckles, break insulators and stay clamps.
6. G.S.S. wires shall comply for solid wire (as per I.S.)
1. The wire shall be drawn from mild steel rods. The general
requirement relating to G.I. wire shall be laid down in latest
version.
4. Stay Rod
G.I. stay rod of size 1800 x 20 mm with stay wire 7/4 mm should
Page | 27
Sl.
Particular Detail
No.
be provided on 33 KV line supports whereas GI stay rod at size
1800 x 16 mm with stay wire 7/3.15 mm should be provided on
11 KV/LT. line supports. All G.I material should conform to IS:
226 with latest amendments.
5. Turn Buckle 3. One eye bolt made of 22 mm dia G.I. rod with 40 mm inner
dia. eye to eye threaded upto 300 mm length from the other
side.
4. Two nos. GI nuts suitable for the threaded portion of eye bolt
material specification IS-226/77 (tested quality).
Weasel, Rabbit
65x65x6 mm M.S. 100x50X6mm, MS.
11 KV LINES AND
Angle Iron (5.8Kg/M) channel (7.9Kg/M)
11kV & L.T. COMPOSIT
V- type cross arm, cross arm,
MAINS
Raccoon, Dog 125x65mm, M.S.
11 KV LINES AND 11kV 100x50x6 mm, M.S. channel (10.7 Kg/M)
Page | 28
Sl.
Particular Detail
No.
channel (7.9 Kg/M)
& L.T. COMPOSIT
V- type cross Cross arm
MAINS
arm
Section:
150x75 mm. M.S. channel (14.4
125x65 mm M.s.
Kg/M) cross arm
Panther channel (10.7xKg/M)
Terminal :
33KV LINES 33 KV V- type cross
150x75 mm, M.S. Channel
arm,
(14.4Kg/M)
cross arm
13. Danger Boards 1. The danger Board shall be provided as per SMC material.
Page | 29
Sl.
Particular Detail
No.
Drawing of Danger Board of 33 KV line shall be as of 11 KV line
Danger Board except displaying 33,000 volts in place of 11000
volts.
The thickness of plate for danger Boards shall be of 2 mm
(14SWG). The danger boards shall be as per IS: 2551 and duly
enameled and fixed with proper clamping arrangement.
Page | 30
Sl.
Particular Detail
No.
activities of the price schedule itself and no separate payment
shall be allowed on this head.
9. The unit rates quoted shall include minor details which may not
have been included in these documents but are executed for
satisfactory completion of the various works.
Page | 31
Sl.
Particular Detail
No.
In each town, there are number of new distribution transformers
(11/0.4KV) sub-stations required to be constructed
(25/63/100/250/400 KVA). The scope includes design,
engineering, fabrication of the structure and placing of new
Distribution Transformer and its accessories on it. This shall
include supply and erection of the following items: -
5. Contractor shall carry out BDV and DGA of the oil and submit
1.3 Oil Test
the results to the owner.
1.5 DO Fuse Set 7. Drop out fuse on 11KV side give protection to the DT even
during dead short circuit condition at 11 KV side.
1.6 11kV LA
Page | 32
Sl.
Particular Detail
No.
8. 11KV LAs shall be pole mounted and its neutral points be
earthed through G.I. strip to the pipe in pipe earthing of DT
body, LT distribution board, fencing etc.
11. All the LT cable shall be properly lugged at both the ends. For
1.9 Termination Kit
HT cable, the contractor shall supply 11KV heat shrink type
termination Kits of standard make.
This distribution box shall have TPN bus bar of 500 or 800
amps capacity. The single core cables emanating from
Distribution Transformers LT side shall be connected to bus
bars and outgoing feeders shall be taken out by Single Core
LT XLPE insulated cable through Kit Kat Rewireable type fuse
units. The size of bus bar and nos. of outgoing feeders shall
depend on capacity of transformer.
For 400 & 250 KVA Transformers, bus bar of 800 amps shall
be used and no. of outgoing feeder per distribution box shall
be three with 300 amps fuse unit on each outgoing feeder.
For 160 & 100 KVA Transformers, bus bar of 500 amps shall
be used and no. of outgoing feeders shall be two with 200
amps fuse unit on each outgoing feeder.
Page | 33
Sl.
Particular Detail
No.
For 63 KVA Transformers, bus bar of 300 amps shall be used
and no. of outgoing feeders shall be two with 100 amps fuse
unit on each outgoing feeder.
Page | 34
Sl.
Particular Detail
No.
The fencing is constructed utilizing vertical post duly grouted /
fitted in ground/on floor. Horizontal rails fitted to the vertical posts,
pickets (if required) fitted to rails and gate to facilitate entry and
exit within the covered area.
Page | 35
Sl.
Particular Detail
No.
In the town under the scope of this tender, there are number of
existing distribution transformer Sub Stations (11/0.4 KV) with
ratings varying from 25 KVA to 1000 KVA scattered all over the
town. Lot of its components are either missing or have become
faulty over the years. The scope of the contractor shall be to carry
out reconditioning of existing Distribution Transformers and
renovation and modernization (R & M) work of all DTs Sub
Station of 25 KVA and above ratings including supply of spares,
erection, testing and commissioning. In addition to this metering
system on DT sub stations (where metering system is not
installed) are also required to be installed. (LT TVM, LT CTs &
Cubicles either to be mounted on double pole structure or to be
placed in the LT distribution box without TVM cubicle). All the old
Distribution Transformers shall be made completely self
protective. For self protection the Microprocessor based MCCB
shall be mounted outside the transformer tank in a closed box
and it is essentially required to meet the compatibility with
Overloading conditions of the transformer. The Internal Circuit
Breaker or Microprocessor based MCCB must meet the
overloading condition of transformer as per IS 6600. The
reconditioned transformers shall be guaranteed for three years
from the date of commission.
- 11 KV TPMO
- 11 KV Drop Out fuse set
- 11 KV LA set
- LT distribution box, MCCBs, neutral link etc.
- Topping up of transformer oil after arresting oil leakages
including maintenance of DTs.
- Pipe type earthing.
- Cable lugs
- Plinth for transformers.
- LT cables (3.5 core) 240 & 400 Sq. mm XLPE
- LT XLPE cable single core 50, 70, 240, 400, 630, 1000 Sq.
mm.
- Heavy duty SFU for capacitor bank.
- Capacitor bank (LT).
- Fencing of sub stations
- Painting of transformer and structure.
- Replacement of faulty insulator and bushing, if any.
- Supply of new DTs in case of increasing capacity.
1.2 Repair of DT
vii) During the course of work, if any internal fault develops in
the running DT, the contractor shall either repair the same at
site or shall transport them to the workshop and repair it. Its
Page | 36
Sl.
Particular Detail
No.
handling and supply of spares etc shall be to contractor's
account.
Contractor will ensure continuity of supply with the help of
trolley mounted DT
xi) 11KV LAs shall be pole mounted and its neutral points be
earthed through G.I. strip to the pipe in pipe earthing of DT
1.6 11kV LA
body, LT distribution board, fencing etc.
This distribution box shall have TPN bus bar of 500 or 800
amps capacity. The single core cables emanating from
Distribution Transformers LT side shall be connected to bus
bars and outgoing feeders shall be taken out by Single Core
LT XLPE insulated cable through Kit Kat Rewireable type fuse
units. The size of bus bar and nos. of outgoing feeders shall
depend on capacity of transformer.
L.T. Distribution Box
1.7 (Made of SMC or
For 400 & 250 KVA Transformers, bus bar of 800 amps shall
CRCA MS Sheet)
be used and no. of outgoing feeder per distribution box shall
be three with 300 amps fuse unit on each outgoing feeder.
For 160 & 100 KVA Transformers, bus bar of 500 amps shall
be used and no. of outgoing feeders shall be two with 200
amps fuse unit on each outgoing feeder.
2.0 Plinth xv) Contractor shall carry out modifications, repair (in case
necessary) in the plinth if the DT is plinth mounted or the
bolting arrangement of the transformer body with the support
Page | 37
Sl.
Particular Detail
No.
structure, in case DT is pole mounted.
Page | 38
GENERAL SPECIFICATION FOR LAYING OF AERIAL BUNCHED CABLES
Sl.
Particular Detail
No.
Aerial Bunched Cable shall be laid over-head with bare messenger
wire duly suspended with the help of special clamps and hooks as per
drawing enclosed. The clamps shall be supported on LT Poles. The
Aerial Bunched maximum Sag various spans shall be as follows:
Cables on New
Supports Span Sag
60 M 1.409 M
50 M 1.025 M
40 M 0.702 M
30 M 0.423 M
20 M 0.222 M
Page | 39
Sl.
Particular Detail
No.
De-energizing of L.T. system or 11 KV of the site as decided by
Engineer in charge before taking up the work. It shall be the sole
De-energizing of
3. responsibility of the contractor to ensure that the line is de-energized
system
and safe in all respect before start of the work.
7. Installation of 1. The distribution box (SMC or Deep drawn CRCA MS Sheet)) shall
Distribution Box be suitable for mounting/fixing on round poles & rails. Number of
and Release such distribution boxes to be mounted on one pole shall depend
Service on the number of service connections to be given from the pole
Connection and it may be two to three in numbers. 4 nos. 35 mm 2.
Aluminium multi strand cable shall be used to connect the
incoming bus bars of the distribution box to the main Aerial
Bunched conductor by using suitable L.T. insulation piercing
connectors.
The number of outgoing cable provisions shall be of
approximately 10-15 service cable connections from each
distribution box.
Page | 40
Sl.
Particular Detail
No.
decision of the Engineer in-charge.
The scope covers supply, erection, grouting & plinthing of LT poles at
Supply and
some places wherever required along with its civil work. This includes
8. erection of new
erection of adequate number of stays with its nuzzling and grouting.
poles
The pole earthing shall be done through 20 mm dia 2500 mm long
9 Earthing of poles earthing rod and 6 SWG G.I. wire.
The damaged and rusted poles which are repairable shall be identified
by Engineer In-charge. The contractor shall repair these poles at site
by welding of M.S. Angle 50x50x6 mm 0.70 mm long 4 nos. to
strengthen the bottom of rotten poles. The contractor shall construct
Repair of
10. adequate size plinth for such poles by concreting in the ratio of 1:3:6
damaged poles
of cement, sand & brick ballast and curing the same. The contractor
shall have to arrange welding set and other necessary materials
including M.S. Angle etc. for this work.
Page | 41
GENERAL SPECIFICATION FOR LAYING OF 11 KV & 33 KV XLPE CABLE
Sl.
Particular Detail
No.
1. The scope shall cover complete installation of all equipment
and accessories covered under this contract.
S.
Item For 33 kv For 11 kv
No.
1. Depth of trench 1050 mm 900 mm
500 mm (For
2. Width of trench 750 mm
single cable)
450x600x50mm
450x600 (For 3x185sq mm
3. Size of stone slab
x50 mm or above size
cable)
No. of stone slab
4. 1.67 1.67
per meter
No. fo bricks 9x2 for 3x185
5. 9x2
per meter mm2 or above
Local sand 0.563 cubic 0.375
6.
per meter meter cubic meter
Page | 42
Sl.
Particular Detail
No.
D.C voltage to which
cable shall withstand
for 5 minutes after
completion of
7. laying/jointing/terminati 60 KV 18 KV
on (in kms) between
any conductor and
metallic
sheath/screen/armour.
As per
specification
8. (HDD method)
given in Vol. II
part A
Clearances- The
desired minimum
Clearance not
Clearances are as Clearance not
necessary,
follows. necessary,
however larger
a) Power cable to however larger the
the clearance
power cable clearance better
9. better would be
b) Power cable to would be current
current carrying
control cable carrying capacity.
capacity.
c) Power cable to 0.2 meter
0.2 meter
communication cable 0.3 meter
0.3 meter
d) Power cable to 0.3 meter
0.3 meter
water line
Note:-
High voltage test to be conducted by contractor.
The trenchless technology shall be used with HDPE casing
for the portion of the cable route such as road, railway, nullah
crossing and without HDPE casing for major portion of the
cable route. The outer diameter of the HDPE pipe shall be
suitable for insertion in an 8 diameter horizontally drilled
bore. The HDPE pipe shall be of PE 80 grade with pressure
rating PN4 conforming to IS 4984/1995 and shall have wall
thickness of 6.20 to 7.10 mm. The HDPE pipes shall be
joined by using Butt welding and a 7/20 G.I wire shall be
3. Cable Laying
provided along the entire length of each pipe duct .
The Depth of horizontal drilling shall be between 2 to 3
meters or as required. The drilling shall be with a Directional
drilling unit equipped with automated pipe handling system
and all necessary accessories.
Note:-
In case of any damage of material/ equipment of 3rd party, all
charges would be borne by the contractor
4 Cable Trench 1. The trenches for the cable laying shall be done as per
standard practice The trenches shall be dug in such a manner
so that soil etc once excavated does not fall back in the
trench.
The cables (a) entry and exit in pipes etc should be according
to relevant ISS.
Page | 43
Sl.
Particular Detail
No.
2. When more than one cable shall be laid in the same trench, a
horizontal inter axial spacing for 0.25 to 0.40 meters for 33 KV
and 0.15 to 0.25 meter for 11 KV in order to reduce the effect
of mutual heating effect and also to ensure the fault occurring
on one cable shall not damage to other cable.
Page | 44