Sei sulla pagina 1di 3

Portland cement pervious

pavement construction
By Jack Paine

Unique mix design calls for special mixing and placing techniques

hen properly proportioned and within 1 hour from the time mix water mum density as determined by AASHTO
W placed, pervious concrete pave-
ments provide a smooth, durable riding
is introduced.
Pervious pavement can pass 3 to 5 gal-
T-180. The subgrade or subbase must be
permeable so it can accommodate the wa-
surface while retaining an open surface lons of water per minute for each square ter that drains through the pervious pave-
texture that allows water to pass. But be- foot of surface area. Omitting most or all ment. It may even be designed as a port-
cause of its unique characteristics, pervi- the fine aggregate gives the pavement its land cement permeable base (see article
ous concrete requires procedures for sub- porosity. Typically, portland cement per- on page 660).
grade preparation, mixing, transporting, vious pavements use a single-size graded Sandy soil with good drainage re-
and placing that are different from those aggregate and have a void content rang- quires no special treatment. Impervious
for conventional concrete. ing from 15% to 25%. Because fine ag- subbases, such as clay, must have a per-
gregate is omitted, a maximum coarse ag- meable layer at least 4 to 6 inches thick
Applications for gregate size of 38 inch is normally used to installed between it and the pavement.
pervious pavements provide a relatively smooth riding sur- Consult a geotechnical engineer for de-
Stormwater management is the most face. The smaller size coarse aggregate al- sign and construction options when the
common reason for using pervious pave- so makes handling and placing easier. subgrade consists of clay or other im-
ments (Ref. 1). Florida, for example, uses pervious soil layers.
pervious pavements because the state Subgrade preparation The pervious pavement profile should
government restricts the amount of rain- Pervious concrete pavements are be relatively flat. If placed on a steep
water runoff that new building develop- placed over a permeable subgrade or sub- grade, the stormwater flow within the
ments can add to drainage channels. By base compacted to 94%, 2%, of maxi- pavement washes away the subgrade ma-
allowing water penetration, pervious
pavements have less surface runoff. This
decreases peak water flow into storm
sewers and nearby streams and decreases
the area required for stormwater retention
ponds. Pervious pavements also allow op-
timum land use, reducing development
costs. Other applications for pervious
concrete include driveways, pool decks,
tennis courts, and patios.

What is pervious pavement?


Pervious concrete is a discontinuous
mixture of coarse aggregate, portland ce-
ment, and water. The cement content
ranges from 600 to 630 pounds per cubic
yard, coarse aggregate content from 2,000
to 2,500 pounds, and the water-cement ra-
tio from 0.34 to 0.40 (Ref. 2). Laboratory
and field tests show 600 pounds per cubic
yard to be the minimum cement factor.
Because it uses very little mix water, per- Figure 1. Workers use shovels and rakes to spread pervious concrete before
vious concrete has a short initial set time strikeoff by a mechanical screed.
terial. If grades with slopes greater than
1% are required, create impervious barri-
ers perpendicular to the direction of the
drainage. Using a soil filter fabric, for ex-
ample, will hold subgrade soils in place
and reduce soil migration.
Because pervious concrete contains lit-
tle mix water, the subgrade or subbase
must be moist before concrete placement.
A dry subbase or subgrade accelerates set
time, decreasing the contractors time for
placing, compacting, and jointing the
pavement. Also, rapid moisture loss
weakens the aggregate bonding strength
of the mortar paste.

Mixing and transporting


The unique properties of a pervious
concrete mix require special mixing and
handling techniques.
Batching. To produce a mix of proper Figure 2. A full-width roller compacts pervious concrete to the height of the
consistency, measure the aggregate mois- forms. Rolling should be completed within 20 minutes after strikeoff.
ture content and adjust the mix water ac-
cordingly. The quantity of mix water
mixer blades. To provide uniform mixing, the forms. After workers place and
should produce a cement paste that dis-
closely inspect the blades and clean when screed the concrete, they remove the
plays a wet-metallic sheen. Too much wa-
required. To minimize buildup, some pro- tack strip before full-width rolling of the
ter will wash the paste from the aggregate
ducers use a ready mix truck for only two pavement for compaction. This 12-inch
and too little will prevent the paste from
loads of pervious concrete, then use the increase in form height offsets the de-
bonding to the aggregate particles.
truck to haul other concrete types. Adding crease in pavement thickness due to
To check consistency, squeeze a hand-
coarse aggregate and a retarding admix- compaction. The increase of the form
ful of the concrete into a ball, then release
ture in the wash water will help clean the height is usually 12 inch, but can be as
it. If the consistency is right, the concrete
mixer drum if buildup occurs. much as 34 inch depending on the con-
will not crumble or turn into a highly
sistency of the mix and the depth of the
plastic mass without air voids.
Placing methods pavement being placed.
When loading materials into the truck,
Spreading. Use square-end shovels,
choose a charging sequence that mini- Many different methods have been come-alongs, rakes, or asphalt lutes to
mizes undesirable balling. Visually in- used successfully to place pervious con- spread the pervious mixture before strike-
spect the batch to check for balling and crete pavements, but those described here off (Figure 1). Segregation is not a prob-
for the correct mix consistency. are the most common. Placing methods lem with pervious concrete. Place and
Transportation. When transporting vary according to the size and configura- distribute the concrete as evenly as possi-
concrete in the ready mix truck, the mixer tion of the project. Manual methods are ble, then begin the strikeoff operation.
drum should rotate at the lowest agitating used for small commercial parking areas Strikeoff. A vibrating mechanical
speed. Use a water reducer that retards set and slipform pavers for larger areas. screed set at low vibration is the most
when anticipating long haul times. Be- Contractors with limited experience widely used strikeoff method. Some con-
cause of its fast set time, the mix should placing pervious concrete pavements tractors have devised a height-adjusting
be discharged from the truck within 90 should place a trial strip before attempting device on the vibrating screed to allow for
minutes after introducing the mix water to place large areas. the 12- to 34-inch additional thickness
with a retarding admixture. Placing sequence. Typically, contrac- needed for compaction. This eliminates
Discharging. Because pervious pave- tors place alternate 10- to 15-foot-wide the need for the tack strip on the forms.
ment mixes exhibit a slump near zero, strips of pervious concrete, then place Dont use high-frequency vibrating
discharging the concrete from the truck pervious concrete sections between the screeds. They can over-compact the con-
can be difficult. For easier discharge, use strips. Contractors experienced in pervi- crete, reducing the void structure and wa-
ready mix trucks with wide discharge ous concrete placement sometimes place ter permeability. Also, high-frequency vi-
openings and elevate the front wheels of wider strips. brating screeds can drive the paste from
rear-discharge trucks. Forming. The side forms are the the coarse aggregate in the top of the
Cleanup. Pervious mixes exhibit a same as conventional forms, except a 12- pavement so the paste fills the lower por-
strong bond causing rapid buildup on inch wood strip is tacked on the top of tion of the pavement. This reduces per-
meability and creates a weak top surface. Joints other unique set of challenges. Standard
Over-compaction, however, is rarely a Jointing requirements for pervious ASTM concrete sampling and testing
problem because most vibrating screeds concrete pavements are different from methods and acceptance criteria for
dont have the force necessary to ade- requirements for normal concrete pave- slump, cylinders, and beams arent suit-
quately compact the pervious mix. ments. Because pervious concrete has able for pervious concrete pavement. The
Work fast. Many projects require a less than one-third the shrinkage charac- ASTM test methods arent recommended
30-minute material haul time, which teristics of normal concrete, transverse because of the consistency of the mix and
leaves the contractor only 30 minutes to contraction joints are spaced 45 to 60 the rodding procedures required when
discharge, spread, strike off, compact, and feet apart. The joint depth should be one- conducting the tests. Flexural and com-
cure the pavement. To minimize prob- fourth the pavement depth. Cut trans- pressive strength test results will vary
lems related to the early set time, use re- verse joints immediately following com- greatly depending on the degree of com-
tarding admixtures and water reducing re- paction using a rolling joint tool. Or paction of the sample.
tarders to extend the initial set time by 1 install the joint later using conventional Present acceptance criteria for pervi-
hour or more. The extended set time al- sawing methods. ous concrete mixes are based on the field
lows the contractor to place and compact Dont delay when sawcutting joints. unit weight. The unit weight of cores tak-
the concrete properly. Because of the large area of exposed per- en from the pavement and the delivered
vious pavement, the material loses water plastic mixture should be within 5
Compaction faster than conventional concrete. Though pounds per cubic foot of the design unit
Immediately following vibrating it shrinks less than conventional concrete, weight. A 0.25-cubic-foot sample of the
screed strikeoff, use a full width heavy- it can shrink faster. About 50% to 80% of plastic pervious mix is recommended for
steel pipe roller to compact the pervious the total drying shrinkage can occur with- uniform results. Because pervious con-
concrete mix to the height of the forms in 10 days after placement. crete is different in consistency and be-
(Figure 2). Depending on the consistency Performance of pervious concrete havior from conventional concrete, new
of the mix and the ambient temperatures, pavements to date has shown no need to or modified testing methods need to be
more than one pass of the steel roller may use reinforcement or expansion joints. developed to accurately predict pavement
be needed. A roller that applies 5 to 10 psi performance.
is adequate. Clean and oil the roller before Curing
use to prevent surface aggregate from ad- Curing a pervious concrete pavement References
hering to it. requires more attention than curing nor- 1. J. E. Paine, Stormwater Design
Experience has shown that the longitu- mal concrete. Because the forms can be Guide Portland Cement Pervious
dinal construction joints of the fill-in Pavement, Florida Concrete & Prod-
removed earlier than in conventional con- ucts Association, February 1990.
pavement strips are susceptible to joint crete paving operations, pervious pave-
raveling. Additional compaction is need- ment edges may lose more moisture. Re- 2. J. E. Paine, Pervious Pavement
ed along this joint to prevent dislodging Manual, Florida Concrete & Products
member, there are 20% voids in the
of the surface aggregate. Association, 1988.
pavement, so air and water can move lat-
Pavement rolling should be completed erally and vertically within the pavement Acknowledgment
within 20 minutes after strikeoff. Due to structure. Surface durability can be re- Segments of this article were con-
the concretes open texture, moisture loss duced by more than 60% if surfaces are tributed by Richard O. Albright, a con-
is rapid and initial set is fast. Delayed sulting engineer based in Carmel, Ind.
improperly protected during the initial
rolling can be detrimental to the pave- curing period of 5 to 7 days.
ment surface. If the concrete has set, the Jack Paine is the engineering manager,
The most common method of curing a
roller wont compact it to the desired quality assurance & pavement design
pervious pavement is to cover the sur-
grade. Also, delayed rolling causes sur- construction, for Tarmac Florida Inc.,
face and edges with a minimum 6-mil
face fracturing of the coarse aggregate Maitland, Fla.
polyethylene sheeting. Membrane-form-
from the mortar paste and increases the ing curing compounds dont work well
potential for future raveling. because they dont cover exposed sur-
Finishing not required. Typically, no faces in the voids. Place the sheeting im-
finishing operations are required, either mediately following compactive rolling.
before or after compaction. In fact, nor- Secure it in place with reinforcing bars
mal bull floating or troweling is not rec- or lumber carefully laid on the pavement
ommended because these operations may surface. Avoid using dirt to hold down
seal off the pavement surface and de- the sheeting since it is difficult to remove
crease water penetration. Correct any sur- without contaminating the pervious
face defects immediately by hand-tamp- pavement.
ing rather than by normal floating. A
rolling edger with a small radius effec- Testing PUBLICATION #C920655
tively reduces edge raveling. Testing pervious concrete mixtures for Copyright 1992, The Aberdeen Group
consistency and acceptance presents an- All rights reserved

Potrebbero piacerti anche