Sei sulla pagina 1di 5

Overall Weighting Equipment Effectiveness

R. Wudhikarn
College of Arts, Media and Technology, Chiang Mai University, Thailand
(o_un277@hotmail.com)

Abstract This research is designed to improve the an indicator of the process improvement activities within
original Overall Equipment Effectiveness (OEE). The OEE a manufacturing environment [2]. Therefore, several
is the process, in which acquired to specify an equivalent studies [3 - 5] have implemented the OEE and,
weight setting of every single element, even though; each accordingly, major improving outcomes can be
concerning losses are totally different. Hence, the study determined. However, the OEE has some flaws;
proposes a simpler weight setting method, so called the
especially, the weighting of each element is equivalent,
Rank-Order Centroid (ROC), to identify dissimilarity in
weighting each OEE element. The ROC methodology is whilst, their losses are totally different. For example, a
easier to determine the weight than the existing weighted quality rate is composed of qualitative losses but
OEE method, which is based on an analytical hierarchy availability rate associates with the time collapsed.
process. This newly calculating methodology is the Overall Therefore, many studies, including this study, have
Weighting Equipment Effectiveness (OWEE). It is presented attempted to improve this weakness.
and also implemented in a fiber cement roof manufacturer. This study proposes to improve weaknesses of the
The result granted from OWEE, however, is different from OEE by developing an existing calculating methodology.
those of the original OEE and of the existing weighted OEE. The theoretical concept of the OEE measurement is, also,
taking into consideration, thence the problems and the
Keywords Overall equipment effectiveness, Total
development of the OEE are examined and discussed with
preventive maintenance, Rank order centroid,
Normalization, Analytical hierarchy process the regarding literatures. Later, the proposed methodology
is presented, a case study application is, then, analyzed
and, finally, the potential of the new calculating method is
explored. This methodology has aimed to rectify the
I. INTRODUCTION
weight setting of the OEEs elements.
Several business companies are now facing an intense
competitive condition. It has pushed these companies to II. METHODOLOGY
enhance their production availability, performance
efficiency and also product quality, in order to take A. Overall Equipment Effectiveness
advantage over their contenders. The high demand, also,
plays role in stimulating firms to increase their production In 1988, Nakajima [6] proposed the OEE as a tool for
capacity. In order to do so, most of labors are being assessing the success to his proposed TPM philosophy.
replaced by automatic machines. They are believed to According to Nakajima, the OEE is based on three main
have higher reliability, faster production rate, more aspects; each element concerns with different losses (see
precision and contain lower operating cost than human, in Table I).
general. This condition would be possible, if and only if;
these equipments are able to perform with a higher TABLE I
effectiveness and efficiency. These excellent PERFORMANCE ASPECTS OF OEE AND RELATING LOSSES
performances, however, also required an appropriate Performance aspects Relating losses
management system for monitoring its function. Total
1. Availability Rate - Equipment failure/breakdown losses
Preventive Maintenance (TPM) is one of those broadly
applied management systems, as it is employed to - Set-up and adjustment losses

strengthen the manufacturing performance and to achieve 2. Performance Efficiency - Idling and minor stoppage losses
the world-class performance [1]. Still, these management - Reduced speed losses
systems require an appropriate information system to
3. Quality Rate - Defect and rework losses
evaluate their operating performances. The information
gathered from these operating machines is mandatory for - Start-up losses
sustaining the organizations. One of the TPMs
achievements is to enhance the equipment efficiency. The From the Table I, these losses are defined as the six big
calculation is made by using Overall Equipment losses and their definitions are described as follows:
Effectiveness. 1) Equipment failure/breakdown losses: These
The OEE method is based on three main elements of losses are categorized due to time losses (reduced
performance consisting availability, performance productivity), and quantity losses (occurrence of defective
efficiency and qualitative aspect. The OEE is not only products), which are related to sporadic/chronic failures.
defined as an operational measure, but also employed as The sporadic failures happen when the changes occur in

978-1-4244-8503-1/10/$26.00 2010 IEEE 23


Proceedings of the 2010 IEEE IEEM

some conditions (jigs/tools, work method, and a ratio between the actual operating time and the loading
equipments state). These require a mean of measurement time.
to revert them back to their original conditions. The
chronic failures occur when there are some hidden defects (2)
in the operating equipments. They are uncorrectable, even
if various countermeasures are exploited. The net operating time is the time durable, in which the
2) Set-up and adjustment losses: These represent the equipments are processing at a standard production rate.
time losses in between the endings of the production and To calculate the net operating time, the performance time
the time losses due to adjusting of equipments to meet the losses are subtracted from the operating time. The
requirement of a new item production. A setting up means performance time losses consist of normal production
a series of operations from the removal of jigs and losses (production rate reduction due to start-up,
fixtures to the end of production, clearing up and shutdown, and changeover) and abnormal production
cleaning, until the preparation of jigs2tools and the losses (production rate reductions due to abnormalities).
necessary metal fixtures for the next product, plus their On the other hand, the net operating time is the processed
attachment, adjustment, trial processing, readjustment, amount multiplied with the actual cycle time. Where the
measurement, production, and ,finally, the ability to processed amount refers to the number of items processed
produce excellent products. per time period (day, month or etc.), and the operating.
These first two losses are considered as the time
losses, which are significant for calculating the
availability rate of the equipment. (3)
3) Idling and minor stoppage losses: These losses
take place when the production is interrupted by a The defect amount represents the number of items
temporarily malfunction or when a machine is idling. For rejected due to quality defects, and requires a rework or,
instance, the idling and minor stoppages caused by the otherwise, would become scrapped.
malfunctioning of conveyors and blockages of material in Combining (1) to (3), the OEE for the given
a pipe. equipment operation is computed using:
4) Reduced speed losses: These losses are according
to the delay in equipment speed. To specify; (i) the actual OEE = A x P x Q (4)
speed is slower than the design speed; (ii) the design
speed is slower than the present technological standards As presented, the OEE depends on the availability rate,
or the desirable condition. the performance efficiency and the quality rate. Therefore,
These third and fourth losses are the speed losses, the OEE is in direct proportion to all these three elements.
which determine the performance efficiency of the Rising in the availability rate reduces buffer inventories
equipment. needed to protect a downstream production from breaking
5) Defect and rework losses: These include the down and, at the same time, increases its effective
volume and time losses due to defect and rework (disposal capacity. The reduced buffer inventories lead to a
defects), financial losses due to a product downgrading, decreasing in lead times, since the jobs are not waiting as
and repairing time losses for defective products. long as in the queues. This capability of shortening the
6) Start-up losses: Start-up losses are time and lead-times improves the firms competitive position; in
volume losses. For instance, (i) Start-up after periodic terms of delivery and flexibility, since it is easier to
repair; (ii) Start-up after suspension (long-time stoppage); deliver multiple products or variations of products in a
(iii) Start-up after holidays and (iv) Start-up after breaks shorter lead time. The reduction needed for the buffer
These last two losses are regarded as the quality inventory minimizes the inventory costs directly and,
losses. They affect the quality rate of the equipment later, results in increasing of the effective capacity. This
directly. allows more throughputs and lowers the cost per unit. An
Normally, the OEE is calculated using these six big escalating in the performance efficiency, also, lowers the
losses. These losses are the functions of Availability Rate needs for the buffer inventories, together with enhances
(A), Performance Efficiency (P) and Quality Rate (Q) the effective capacity. This reinforces the benefits gained
which can be determined as in the following equation: from an increasing in equipment availability. An
upgrading in the rate of quality products can be implied
that there is less scrap and rework, which is not only
(1)
reduces the costs, but also yields a higher rate of quality
[7, 8].
, where the loading time is the planned time available per Although the OEE seems to be a complete
time period (day, month, etc.) for production operations, performance measurement indicator, still, it requires a
and the operating time is calculated from the loading time proper modification. For instance, an existing research
subtracted by the time of equipment failures, set-up and had showed the difference in element weights of the OEE
adjustment requirements, exchange of dies and other [9]. The conclusion of this study was; the traditional
fixtures and etc. The availability, in this case, is defined as means of evaluating the maintenance management

24
Proceedings of the 2010 IEEE IEEM

systems could not yield higher capital productivity. reasonable than the original OEE, as its loss in each
Factors relating to the OEE are not equally important in element is different. Though, the weight setting should
these aspects; however, the different in weights should be not be equivalent. Applying of the analytical hierarchy
taken into account. Furthermore, there is another research process with the simple weight setting is considered to be
[10] engaged with the calculating method, which more complicated for the decision makers; hence, this
proposed; how to calculate an increasing in profits or a research proposes another alternation of the simplifying
decreasing in costs from an increasing percentage of the appropriate weighting method.
OEE. Hence, all the outcomes are presented in term of the
monetary unit allowing easier ranking of the problem C. Rank-order centroid (ROC)
priorities. These studies have put efforts on improving the
OEEs weaknesses to prevent a wrong decision making. The Rank-order centroid (ROC) is proposed by Edwards
They are, however, inappropriately developed, thus, a and Barron [12]. This technique transforms the swing
new indicator has been proposed [11]. This modified ranks into the swing weights. Moreover, the ROC weights
method is called an overall equipment cost loss define the best alternative 75 up to 90% of the time based
indicator. These last two mentioned methods, upon a set of the true swing weights elicited some other
nevertheless, require the operating information way accurately. The calculating formula of the ROC is
accompanied with the financial information, which put defined as in (6)
these indicators into a complicated shop floor. As a
conclusion, the OEE or the weighted OEE is more (6)
suitable for the operational process.

B. Weighting of the OEE Where is the rank of the th objective, is the total
number of the objectives, and is the normalized
The traditional OEE specifies the weighting of each approximate ratio scale weight of the ith objective.
element equivalently. This designation, still, is The ROC method is, also, applied in this research and
inappropriate. These elementary losses are totally the weighting factors for each element are determined by
different, as the availability rate is regarded to the time interviewing a top manager who has a total authority of
losses, the performance efficiency concerns with the the company management.
speed losses and the quality rate is defined as the quality
losses. So Raouf [9] had proposed a modified OEE. This D. Normalization
methodology assigns weights to all the elements using the
analytical hierarchy process. Assuming that has a In general, normalization refers to the comparison of
weight of , has a weight of and has a weight of the overall size of category indicators with the reference
, where 0 1 and 1. In this case, the information [13]. Its main purpose is to resolve the issue
weighted OEE can be calculated as of the unit differences. As a result, the normalization aims
at obtaining a set of comparable scales, which allow inter-
(5) attribute as well as intra-attribute comparisons [14]. As
mentioned, the units and ranges of the time losses, the
The numerical example between the original OEE and the speed losses and the quality losses are different and, in
weighted OEE are represented in Table II. order to make a comparison, these dissimilarities should
be extinguished. The calculating formulas of , and
TABLE II are the ones taking responsible for that, or, to say, to
NUMERICAL EXAMPLE OF OEE AND WEIGHTED OEE change into a normalized form. These comparative values
are used in accompanied with the correlative weight for
Original Weighted
calculating a summarization of the overall equipment
M/C A P Q performance.
OEE OEE

No.1 89.0% 81.4% 98.0% 71.0% 90.9%

No.2 91.2% 79.7% 98.1% 71.3% 90.8% III. PROPOSED METHODOLOGY


Weight 0.20 0.30 0.50 - -
As stated prior, this research main goal is to find the way
to improve the OEE method. To do so, the newly
The Table II depicts a different weight setting for each calculating method combined the traditional OEE
single element. However, the first problematic machine approach with the weighted OEE approaches is proposed.
exhibited a contradiction between the original OEE First, the OEE elements are still computed as in the
contrasts and the modified OEE, since, the weighted OEE original calculation, following (1), (2) and (3)
specified the highest vital at the quality rate element. This for , and respectively. Then, the weight of each
method, on the other hand, has proved to be more element is specified by using the ROC method as

25
Proceedings of the 2010 IEEE IEEM

illustrated in (6). Afterward, the overall weighting The weighting and the OEEs element data from the Table
equipment effectiveness (OWEE) is calculated utilized III and the Table IV were, then, employed to calculate the
the following formula. traditional OEE and the OWEE. Moreover, Raoufs OEE
was also exploited as a comparison mean for both
OWEE (7) methods. The outcomes are exhibited in Table V.

, where; is the weight of the availability rate element, TABLE V


is the weight of the performance efficiency element NUMERICAL RESULTS FROM THREE METHODS
and is the weight of the quality rate element.
The OWEE can be simply applied to any company Machine Original OEE Raoufs OEE OWEE
already implementing the OEE. Anyway, firstly, the ST1 74.29% 95.14% 93.85%
weight must be identified by an authorized person. ST4 73.80% 94.57% 93.32%

ST5 73.82% 94.02% 92.89%

IV. OWEE MODEL APPLICATION CC3 75.75% 94.97% 93.81%

CC4 76.91% 94.62% 93.65%


In this section, the application of the OWEE model CC5 77.17% 95.08% 94.01%
previously discussed is exemplified through a case study.
In this newly improved calculation method, the
production data such as the processed products, the good
products, the loading time, the operating time, and etc. are V. DISCUSSION
collected, as the weight setting is mandatory. In this case
study, a managing director was interviewed for From the Table V, the results from those three
prioritizing the availability rate, the performance different methods have been calculated and the outcomes
efficiency and the quality rate element. The outcome of are presented in percentage. The machine ST4 shows the
the order of magnitude is demonstrated in the quality rate, lowest traditional OEE, even though; for the other
the performance efficiency and the availability rate remaining methods, the machine ST5 comprised a lower
respectively. Then, the prioritized orders were applied for score. This irrelevant outcome, however, is expected, as
calculating weight by using the ROC method resulting in the OEE normally identifies an equivalent weight in each
Table III. single element, on the other hand, both of the modified
methods do not. Therefore, the original OEE possibly
TABLE III gives a different result from other weighting methods.
WEIGHT SETTING BY ROC METHOD Later, the problematic machine can be ranked by
alternatively using the original OEE, the Raoufs OEE
and the OWEE. The results are displayed in Table VI.
Element Ranking Numerical calculation Weight

A 3 13 3 0.11 TABLE VI
MACHINE PRIORITY BY ALTERNATIVE METHODS
P 2 12 13 3 0.28

Q 1 1 12 13 3 0.61 *Ranking by
Machine
Original OEE Raoufs OEE OWEE

The OEE element data of the selected company, a fiber ST1 3 6 5


cement roof manufacturer, between June and December ST4 1 2 2
2009 are depicted as illustrated in Table IV. ST5 2 1 1

CC3 4 4 4
TABLE IV
OVERALL EQUIPMENT EFFECTIVENESS OF MACHINES CC4 6 3 3

CC5 5 5 6
Machine A P Q * Less number means high priority to improve

ST1 88.98% 84.21% 99.15%


From the Table VI, the problematic machines ranked by
ST4 91.58% 81.27% 99.16% the OWEE method are almost similar to the Raoufs OEE.
ST5 92.41% 81.26% 98.31% The OWEEs outcome is mostly dissimilar from the
OEEs, yet, only in the fourth order. Anyway, it shows
CC3 92.03% 83.12% 99.03%
slightly differences from those of Raoufs OEE in the fifth
CC4 93.19% 84.14% 98.09% and the sixth order. From the newly proposed method, the
CC5 93.52% 83.36% 98.99%
machine ST5 is the first improved machine relating to the
Raoufs OEE. This similarity is the result of the and the

26
Proceedings of the 2010 IEEE IEEM

elements, which contain the lowest performance. The [4] M. Lesshammar, Evaluation and improvement of
, however, is the highest weight element, due to its manufacturing performance measurement systems the
lowest score. For the differences between the OWEE and role of OEE, International Journal of Operations and
Production Management, vol. 19, no. 1, pp. 55-78, (1999).
the original OEE, the ST4 is identified as the first
[5] R. Wudhikarn and W. Manopiniwes, Autonomous
problematic machine for the OEE traditional method. As maintenance using total productive maintenance approach:
the OWEE identified the highest weight setting on the , A case study of synthetic wood plank factory, Technology
then the overall result mostly depends on this element. Innovation & Industrial Management Conference,
As for the flaws of this study, this numerical case TIIM2010, Pattaya, Thailand, in press.
study contains only a few sets of machines and, plus, the [6] S. Nakajima, Introduction to TPM, Productivity Press,
performance results are also nearly similar. For a better Cambridge, MA., 1988.
alternative of the further developed study; it is suggested [7] M. Lesshammar, Evaluation and improvement of
to have more machines and also a vast variation in manufacturing performance measurement systems the
role of OEE, International Journal of Operations and
capability. Still, at this moment, there is no completely
Production Management, vol. 19, no. 1, pp. 55-78, (1999).
optimal method for every circumstance. The methodology [8] L.D. Frendall, J.W. Patterson and W.J. Kneedy,
is highly depending on, which is the most appropriated Maintenance modeling its strategic impact, Journal of
mean to specify a problem. Finally and importantly, Managerial Issues, vol. 9, no. 4, pp. 440-448, 1997.
everything is depending on the decision maker, solely. [9] A. Raouf, Improving capital productivity through
maintenance, International Journal of Operations and
Production Management, vol. 14, no. 7, pp. 4452, 1994.
VI. CONCLUSION [10] O. Kwon and H. Lee, Calculation methodology for
contributive managerial effect by OEE as a result of TPM
activities, Journal of Quality in Maintenance Engineering,
The performance measurement for operating a
vol. 10, no. 4, pp.263-272, 2004.
machine, together with an appropriate decision from an [11] R. Wudhikarn, C. Smithikul and W. Manopiniwes,
authorized manager, is crucial for sustaining a business Developing overall equipment cost loss indicator, in
organization. Therefore, it is mandatory to establish a Proc. 6th Conf. of Digital Enterprise Technology,
proper mean of measurement. In addition, accuracy in the DET2009, Hong Kong, Hong Kong, pp. 557-567.
performance measurement is essential to improve and is [12] F.H. Barron and B.E. Barrett, Decision quality using
the key to success in a business goal. One of the most ranked attribute weights, Management Science, vol. 42,
important and widely used metrics of performance in the no. 11, pp. 15151523, 1996.
manufacturing is the OEE, especially, for firms already [13] J. Guine, Handbook in Life Cycle Assessment,
Operational Guide to the ISO Standars, Kluwer Academic,
applying the TPM.
Dordrecht, 2002.
The original OEE method does not appropriately [14] C.L. Hwang and K. Yoon, Multiple attribute decision
prioritize the problematic equipments. It specifies an making: Methods and applications: a state-of-the-art
equivalent weight in each element, then, the weighted survey, Springer-Verlag, Berlin and New York, 1981.
OEE method is presented and the analytical hierarchy
process has been applied for setting the weight. This
methodology is, however, complicated for a decision
maker, especially, those who have not priory became
accustomed to this method. To avoid these conflicts, this
research has proposed a simpler mean of weighting
method and, at the same time, provides a summarized
calculation, known as the OWEE. Finally, the
implemented case study is also discussed. It is proved that
the prioritized problematic machine demonstrates
differences from the original OEE and the Raoufs OEE.

REFERENCES

[1] K.E. McKone, R.G. Schroeder and K.O. Cua, The impact
of total productive maintenance practices on manufacturing
performance, Journal of Operations Management, vol. 19,
no. 1, pp. 3958, 2001.
[2] B. Dal, P. Tugwell and R. Greatbanks, Overall equipment
effectiveness as a measure of operational improvement,
International Journal of Operations & Production
Management, vol. 20, no. 12, pp. 14881520, 2000.
[3] D. Kotze, Consistency, accuracy lead to maximum OEE
benefits, TPM Newsletter, vol. 4, no. 2, 1993.

27

Potrebbero piacerti anche