Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Carry out jobs on following columns as per general guide line given in Appendix A
attachment 2 and specific scope as detailed below.
NHGU
Naphtha
EQUIPMENT NO 133-C-301 SERVICE Deaerator / Surge
drum
PM ORDER NO. NA NO. OF TRAYS NA
Column Dia (mm) 2500 HEIGHT (mm) 6400
NO. OF BEDS 2 BED SIZE 0.8 X 2 M
DEMISTER YES DRAWING 133-ME-2-25-1
NO. OF SIZE( In) 24 X 150 /
2 + 1( Dome)
MANWAYS /RATING(lbs) 32 X 150
Sr. SIZE RATING
LOCATION
No. (inch) (lbs)
1. NAPHTHA I/L TO DEAERATOR 4 150
2. PROCESS GAS,N2, CRU OFF
GAS COMMON LINE TO
DEAERATOR 4 150
3. LP STEAM I/L LINE 2 150
4. C-310 O/L TO P-301 A/B LINE 4 150
1
5. P-301 A/B BALANCING LINE TO
C-301 2 300
6. P-301 A/B ARC LINE TO C-301 2 150
7. PUMP DISCHARGE RV'S LINE
TO C-301 3 150
SPADE LIST
8. COMMON DRAIN LINE TO
CBD/OWS 3 150
9. NAPHTHA FROM V-313 TO C-
301 2 150
10. SAMPLE POINT RSC1471 LINE
FLANGE 2 150
11. COMMON O/L LINE TO F-301
AND RV'S 4 150
12. GAUGE GLASS DRAIN LINE ( 4
NOS. ) 2 150
13. LEVEL SWITCH 402 A/B/C
DRAIN LINE( 3 NOS.) 2 150
14. RPDT-402 DRAIN LINE 3/4" 300
Page 1 of 10
SR NO DESCRIPTION OF WORK
1 Carry out spading as per spade list
2 Erect external scaffolding wherever required.
3 Open all hand holes on column and man ways of surge drum.
4 Unload pal rings from both the beds through hand holes.
5 Open top flange of column.
6 Remove demister. Demister shall be replaced with new one.
7 Remove Naphtha and Gas inlet distributors, clean and check
8 Dismantle the column in three sections by opening intermediate shell flanges and
lower the section on ground floor and clean the individual section.
9 Enter inside the surge drum
10 Carry out internal cleaning of surge drum including surge drum boot.
11 Service all first isolation valves
12 Remove service and fix back all the gauge glasses.
13 Clean all the nozzles.
14 Fix naphtha inlet distributor.
15 Assemble bottom section of the column.
16 Box up hand hole and load the pal ring in bottom bed.
17 Assemble middle section of the column.
18 Box up hand hole and load the new pal ring in top bed.
19 Fix back the gas inlet distributor, demister and box up the end flange third (top most)
section of column.
20 Assemble back the top section of column.
21 Box up surge drum man ways
22 Carry out de-spading
23 Remove external scaffolding except that required for hot bolting of flanges.
Process
EQUIPMENT NO 133-C-302 SERVICE condensate
Stripper
PM ORDER NO. NA NO. OF TRAYS NA
Column Dia (mm) 1000 HEIGHT (mm) 17000
NO. OF BEDS 1 BED VOLUME -
DEMISTER YES DRAWING 133-ME-1-52-1
NO. OF SIZE( In)
1 20 X 600
MANWAYS /RATING(lbs)
2 Sr. SIZE RATING
LOCATION
No. (inch) (lbs)
1. CONDENSATE I/L TO C-302 2 600
2. MORPHOLINE INJECTION LINE 2 600
3. HP STEAM I/L LINE TO C-302 4 600
SPADE LIST 4. C-302 COMMON CONDENSATE 3
O/L LINE TO E-314 A/B/C AND
OWS 600
5. RPDT-659 AND RPDT-661 2 600
6. COMMON STEAM O/L LINE TO 3
MIXING POINT AND RV'S 600
SR NO DESCRIPTION OF WORK
Page 2 of 10
1 Carry out spading as per spade list
2 Erect external scaffolding wherever required.
3 Open top dome cover flange bolts and lower the dome. Open the shell flanges
(manhole 1& 2 ) and remove the shell portion
4 Remove demister from top dome end. Demister shall be replaced with new one.
5 Open bottom man way and enter inside the bottom section of the column.
6 Unload pal rings from both the beds through hand holes. and load new pal rings after
box up of hand holes
7 Provide ladder inside the bottom section for cleaning and inspection.
8 Carry out internal cleaning in bottom section.
9 Service all first isolation valves
10 Remove service and fix back all the gauge glasses.
11 Remove insulation around all the manways, nozzles up to the first flange of nozzle or
250 mm from the column shell for UT gauging / assessing the CUI. Make insulation
pockets at all the platform level on all the four compass direction for UT gauging. The
removed insulation shall be restored back to original shape and contour matching
with the surface and sealing compound shall be applied to avoid water ingress as per
BPCL standard.
12 Open the skirt access and erect scaffolding inside the skit for inspection of bottom
nozzles.
13 Assemble top dome cover of the column and the shell.
14 Remove ladders from the bottom section
15 Box up man ways
16 Carry out de-spading
Remove external scaffolding except that required for hot bolting of flanges.
LOBS
FPU Vacuum
EQUIPMENT NO 132-C-221 SERVICE
Column
PM ORDER NO. NA NO. OF TRAYS NA
Column Dia (mm) 2000 / 6500 HEIGHT (mm) 42245
NO. OF BEDS 6 BED VOLUME
DEMISTER NO DRAWING 132-ME-1-152/11
NO. OF SIZE( In) 24 X 300 /
6+2
MANWAYS /RATING(lbs) 24 X 150
Sr. SIZE RATING
LOCATION
1 No. (inch) (lbs)
1. TRANSFER LINE TO FLASH
34 300
ZONE
2. STRIPPING STEAM 4 300
3. FPU COLUMN START UP VENT 2 150
SPADE LIST
4. FPU COLUMN STEAM OUT
2 300
STEAM SUPPLY
5. OVER FLASH FROM COLUMN 8 300
6. OVER FLASH TO COLUMN 8 300
7. OVER FLASH DRAIN TO CFBD 2 50
8. OVER FLASH DRAIN TO OWS 2 50
Page 3 of 10
9. FPU COLUMN OVER HEAD 30 150
10. FPU O/H TO RELIEF AND PSV'S 6 150
11. VACCUM COLUMN TOP
12 150
SIDECUT DRAW
12. VACCUM COLUMN TOP
6 150
REFLUX
13. VACCUM COLUMN TOP P/B TO
6 150
C OLUMN
14. W 100 N DRAW OFF 8 300
15. W 100 N VAPOR EX C-222 E/S 18 300
16. W 100 N VAPOR EX C-222 W/S 18 300
17. W 100 N P/B TO COLUMN 6 300
18. W 150 N DRAW OFF 10 300
19. W 150 N P/B TO COLUMN 6 300
20. W 150 N P/A TO COLUMN 6 300
21. W 150 N VAPOR EX C-223 E/S 18 300
SR NO DESCRIPTION OF WORK
1 Carry out spading as per spade list
2 Erect external scaffolding wherever required.
3 Open all shell man ways
4 Enter inside the column
5 Erect scaffolding inside the column in bottom dish end area (approximately 3 meter
height)
6 Remove all the distributors located above each bed and below bottom packing, clean
and check. Replace 37 nos spray nozzles each above bed #3 and bed #6.
7 Clean all the weld seams of top dish end and top shell course carry out buffing of 6
inches on both sides of weld seams to carry out WFMPI.
8 Carry out internal cleaning including strainer around the vortex breaker. All Structure
packing bed shall be inspected in situ.
9 Remove insulation of top dish end and top shell course, clean and offer to inspection
to check CUI.Remove insulation around all the manways, nozzles up to the first
flange of nozzle or 250 mm from the column shell for UT gauging / assessing the
CUI. Make insulation pockets at all the platform level on all the four compass
direction for UT gauging. The removed insulation shall be restored back to original
shape and contour matching with the surface and sealing compound shall be applied
to avoid water ingress as per BPCL standard.
10 Service all first isolation valves
11 Clean all the nozzles
12 Open skirt access, and Provide scaffolding inside the skirt for inspection of bottom
elbow.
13 Fix back all the distributors, isolation valves.
14 Remove internal scaffolding
15 Box up all shell manways
16 Carry out de-spading
17 Remove external scaffolding except that required for hot bolting of flanges.
Page 4 of 10
PM ORDER NO. NA NO. OF TRAYS NA
Column Dia (mm) 2900 HEIGHT (mm) 7800
NO. OF BEDS 1 BED VOLUME
DEMISTER NO DRAWING 132-ME-1-207/1
NO. OF SIZE( In)
2 24 X 300
MANWAYS /RATING(lbs)
Sr. SIZE RATING
LOCATION
No. (inch) (lbs)
1. C-222 S/C STRIPPER VAPOR
36 300
RETURN
2. S/C STRIPPER VENT TO
2 150
ATMOSPHERE
SPADE LIST 3. W100 N FEED TO C-222 4 300
4. MP STRIPPING STEAM TO C-
1-1/2 300
222
5. STEAM OUT STEAM SUPPLY 2 300
6. STR BOTTOMS TO P-255 A/B 6 300
7. BLT711 DRAIN TO OWS 300
8. P-255A/B MINI CIRCULATION 1 150
SR NO DESCRIPTION OF WORK
1 Carry out spading as per spade list
2 Erect external scaffolding wherever required.
3 Open all shell man ways
4 Enter inside the column
5 Erect scaffolding inside the column in bottom dish end area (approximately 2.5 meter
height)
6 Remove all the distributors located above and below packing bed, clean and check.
7 Carry out internal cleaning including strainer around the vortex breaker. Structure
packing bed shall be inspected in situ.
8 Remove insulation around all the manways, nozzles up to the first flange of nozzle or
250 mm from the column shell for UT gauging / assessing the CUI. Make insulation
pockets at all the platform level on all the four compass direction for UT gauging. The
removed insulation shall be restored back to original shape and contour matching
with the surface and sealing compound shall be applied to avoid water ingress as per
BPCL standard.
9 Service all first isolation valves
10 Remove and service gauge glasses.
11 Clean all the nozzles
12 Open skirt access, and Provide scaffolding inside the skirt for inspection of bottom
elbow.
13 Fix back all the distributors, isolation valves, gauge glasses.
14 Remove internal scaffolding
15 Box up all shell man ways
16 Carry out de-spading
17 Remove external scaffolding except that required for hot bolting of flanges.
Page 5 of 10
Waxy 150N side
EQUIPMENT NO 132-C-223 SERVICE
cut striper
PM ORDER NO. NA NO. OF TRAYS NA
Column Dia (mm) 3700 HEIGHT (mm) 8100
NO. OF BEDS 1 BED VOLUME
DEMISTER NO DRAWING 132-ME-1-208/1
NO. OF SIZE( In)
2 24 X 300
MANWAYS /RATING(lbs)
Sr. SIZE RATING
LOCATION
3 No. (inch) (lbs)
1. C-223 S/C STRIPPER VAPOR
42 300
RETURN
2. S/C STRIPPER VENT TO
2 150
ATMOSPHERE
SPADE LIST
3. W150 N FEED TO C-223 8 300
4. MP STRIPPING STEAM TO C-
2 300
223
5. STEAM OUT STEAM SUPPLY 2 300
6. STR BOTTOMS TO P-257 A/B 6 300
7. BLT712 DRAIN TO OWS 3/4 150
SR NO DESCRIPTION OF WORK
1 Carry out spading as per spade list
2 Erect external scaffolding wherever required.
3 Open all shell man ways
4 Enter inside the column
5 Erect scaffolding inside the column in bottom dish end area (approximately 2.5 meter
height)
6 Remove the distributor located below packing bed, clean and check.
7 Carry out internal cleaning including strainer around the vortex breaker. Structure
packing bed shall be inspected in situ.
8 Remove insulation around all the manways, nozzles up to the first flange of nozzle or
250 mm from the column shell for UT gauging / assessing the CUI. Make insulation
pockets at all the platform level on all the four compass direction for UT gauging. The
removed insulation shall be restored back to original shape and contour matching
with the surface and sealing compound shall be applied to avoid water ingress as per
BPCL standard.
9 Service all first isolation valves
10 Remove and service gauge glasses.
11 Clean all the nozzles
12 Open skirt access, and Provide scaffolding inside the skirt for inspection of bottom
elbow.
13 Fix back all the distributors, isolation valves, gauge glasses.
14 Remove internal scaffolding
15 Box up all shell man ways
16 Carry out de-spading
17 Remove external scaffolding except that required for hot bolting of flanges.
Page 6 of 10
DW product
EQUIPMENT NO 132-C-224 SERVICE
stripper
PM ORDER NO. NA NO. OF TRAYS 10
Column Dia (mm) 1000 / 2000 HEIGHT (mm) 11650
NO. OF BEDS NA BED VOLUME NA
DEMISTER NO DRAWING 132-ME-1-209-1
NO. OF SIZE( In) 24 X 300 /
1+1
MANWAYS /RATING(lbs) 18 X 300
Sr. SIZE RATING
LOCATION
No. (inch) (lbs)
4 1. FEED INLET 4 300
2. MP STRIPPING STEAM 3 300
3. STRIPPER O/H VAPOR 4 300
4. STEAM OUT STEAM INLET 1-1/2 300
5. STRIPPER LIQUID O/L 4 300
SPADE LIST
6. STRIPPER LIQUID O/L DRAIN
2 150
TO OWS
7. STRIPPER O/H TO RELIEF AND
4 300
PSV'S
8. STRIPPER VENT TO
1 150
ATMOSPHERE
9. BLT725 DRAIN TO OWS 3/5 150
SR NO DESCRIPTION OF WORK
1 Carry out spading as per spade list
2 Erect external scaffolding wherever required.
3 Open all shell man ways
4 Enter inside the column
5 Erect scaffolding inside the column in bottom dish end area (approximately 5 meter
height)
6 Remove the distributor located above tray no. 1 and below tray no 10, clean and
check.
7 Open all tray man ways.
8 Carry out internal cleaning including strainer around the vortex breaker.
9 Remove insulation around all the manways, nozzles up to the first flange of nozzle or
250 mm from the column shell for UT gauging / assessing the CUI. Make insulation
pockets at all the platform level on all the four compass direction for UT gauging. The
removed insulation shall be restored back to original shape and contour matching
with the surface and sealing compound shall be applied to avoid water ingress as per
BPCL standard.
10 Service all first isolation valves
11 Remove and service gauge glasses.
12 Clean all the nozzles
13 Replace missing tray valves. (Total SS Valves: AC 5U (LIGHT) 90 nos. Material:
SA 240 Tp 410s, 1.62 mm thk. & AC 5U (HEAVY) 90 nos., Material: SA 240 Tp
410s, 2.0 mm thk. )
14 Open skirt access, and Provide scaffolding inside the skirt for inspection of bottom
elbow.
15 Fix back all the distributors, isolation valves, gauge glasses.
16 Box up tray man ways
Page 7 of 10
17 Remove internal scaffolding
18 Box up all shell man ways
19 Carry out de-spading
20 Remove external scaffolding except that required for hot bolting of flanges.
DW Vacuum
EQUIPMENT NO 132-C-225 SERVICE
Column
PM ORDER NO. NA NO. OF TRAYS NA
Column Dia (mm) 2200 / 3100 HEIGHT (mm) 29630
NO. OF BEDS 4 BED VOLUME
DEMISTER NA DRAWING 132-ME-1-151/10
NO. OF SIZE( In) 24 X 300 /
4+3
MANWAYS /RATING(lbs) 24 X 150
Sr. SIZE RATING
LOCATION
No. (inch) (lbs)
1. TRANSFER LINE TO FLASH
18 300
ZONE
2. STRIPPING STEAM 6 300
3. DW COLUMN START UP VENT 2 150
4. DW COLUMN STEAM OUT
2 300
STEAM SUPPLY
5. OVER FLASH FROM COLUMN 8 300
6. OVER FLASH TO COLUMN 8 300
5 7. OVER FLASH DRAIN TO CFBD 2 150
8. OVER FLASH DRAIN TO OWS 2 150
9. DW COLUMN OVER HEAD 18 150
10. DW O/H TO RELIEF AND PSV'S 8 300
11. P-265 A/B MIN CIRCULATION
SPADE LIST 4 300
TO C-221
12. P-265 A/B START UP VENT 2 150
13. BYPRODUCT DRAW OFF 8 150
14. BYPRODUCT REFLUX 6 150
15. BYPRODUCT P/B 4 150
16. LT LUBE S/C STRIPPER VAPOR 8 150
17. LT LUBE DRAW OFF 4 150
18. LT LUBE P/B 3 150
19. C-225 BOTTOMS 6 300
20. C-225 BOTTOMS DRAIN TO
2 150
CFBD
21. C-225 BOTTOMS DRAIN TO
2 150
OWS
22. BLT727 DRAIN TO OWS 150
23. BLT726 DRAIN TO OWS 3/4 150
SR NO DESCRIPTION OF WORK
1 Carry out spading as per spade list
2 Erect external scaffolding wherever required.
3 Open all shell man ways
Page 8 of 10
4 Enter inside the column
5 Erect scaffolding inside the column in bottom dish end area (approximately 3 meter
height)
6 Remove the distributor located above each packing bed and below bottom packing
bed, clean and check. Replace 07 nos spray nozzles above bed #6.
7 Carry out internal cleaning including strainer around the vortex breaker. Structure
packing bed shall be inspected in situ.
8 Remove insulation from top dish end upto bed no 3 outlet for checking CUI.Remove
insulation around all the manways, nozzles up to the first flange of nozzle or 250 mm
from the column shell for UT gauging / assessing the CUI. Make insulation pockets at
all the platform level on all the four compass direction for UT gauging. The removed
insulation shall be restored back to original shape and contour matching with the
surface and sealing compound shall be applied to avoid water ingress as per BPCL
standard.
9 Service all first isolation valves
10 Clean all the nozzles
11 Open skirt access, and Provide scaffolding inside the skirt for inspection of bottom
elbow.
12 Fix back all the distributors, isolation valves, gauge glasses.
13 Remove internal scaffolding
14 Box up all shell midways
15 Carry out de-spading
16 Remove external scaffolding except that required for hot bolting of flanges.
Page 9 of 10
3 Open column top cover and hand holes
4 Remove the distributor located above and below Packing bed, clean and check.
Carry out replacement of total packing along with bed limiter.
5 Remove insulation around all the manways, nozzles up to the first flange of nozzle or
250 mm from the column shell for UT gauging / assessing the CUI. Make insulation
pockets at all the platform level on all the four compass direction for UT gauging. The
removed insulation shall be restored back to original shape and contour matching
with the surface and sealing compound shall be applied to avoid water ingress as per
BPCL standard.
6 Service all first isolation valves
7 Remove and service gauge glasses.
8 Clean all the nozzles
9 Provide external scaffolding outside the skirt for inspection of bottom elbow.
10 Fix back all the distributors, isolation valves, gauge glasses.
11 Box up top cover.
12 Box up all shell hand holes.
13 Carry out de-spading
14 Remove external scaffolding except that required for hot bolting of flanges.
Page 10 of 10
ATTACHMENT 11 SECTION B
NHGU
Carry out jobs on following heaters as per general guide line given in Appendix A
attachment 3 and specific scope as detailed below.
Page 1 of 11
COLD COLLECTOR
1 Open the cold collector man ways. Opening of man way shall require breaking of
the refractory sleeve at the man way.
2 Take entry inside the cold collector, clean and offer for inspection.
3 Carry out internal refractory repair of approx 5 m2 as per drawing no 133-CE-3-
111.
4 Carry out external shot blasting and painting of cold collector using Thermo
indicative paint as per BPCL AES 5430 System 27.
5 On completion of internal inspection, make the refractory sleeve at man ways and
box up man ways.
STACK
1 Open the access door and offer the stack for internal inspection. Provide
necessary Bosun chair arrangement.
2 Carry out Castable refractory repairs of approx 5 m2.
PRE REFORMER COIL 133-E-301& 302
1 Replacement of both the exchanger shall be carried out by other agency.
AIR PRE HEATER (133-AP-301 /302 / 303)
1 Open man ways of the duct and erect scaffolding inside the duct to access all
coils. Provide scaffolding / ladder arrangement wherever required.
2 Clean all tubes externally free of scales by water washing and blowing with High
pressure air jet and offer for inspection.
3 Remove insulation of the following permanently. After repairs, carryout scrap
cleaning and painting as per company specification.
a) APH 301,
4 Fabricate and carry out the replacement of duct from FD301A/B discharge damper
immediate flange to elbow flange near APH301 as existing (Drg no 133-ME-4-63)
Fabricate and carryout entire replacement of APH 302 BYPASS duct as existing
(133-ME-4-66)
5 Carry out cutting of the finned tubes of APH 301 from inside the duct and spade
inlet and outlet flanges (steam side) of APH 301 (Refer Drg no 133-ME-4-16-2 for
APH 301)
6 Remove insulation of the duct between APH303 and reformer and check for
repairs. After repairs, carryout scrap cleaning, painting and insulation as per
company specification.
DAMPERS
1 Carry out servicing of all the following multi louver dampers.
Page 2 of 11
3) ID fan suction dampers: 4 nos.
4) ID fan discharge dampers: 2 nos.
5) APH 302 by pass damper: 1 no.
6) Combustion air to burner duct dampers: 16 nos.
2 Remove both the multi louver ID discharge dampers and guillotines of ID301A/B.
The position of guillotines and ID discharge dampers shall be swapped. The
necessary modification shall be carried out. as per MOC-NHGU-11-1194 &
Drawing no 133-CE-3-30,Rev.E).
Also replace the adjoining fabric bellow of discharge of both ID fan, if required.
3 Carry out servicing of all air damper assemblies of 133-F-301 burners.
(Each burner has small air damper to control combustion air flow.)
AIR / FLUE GAS DUCTING
1 Open man way covers, clean and offer for internal inspection.
2 Open all access doors and provide necessary ladder/ scaffolding/ hand lamps for
internal inspection.
3 Carry out insulation removal at select location for carrying out CUI assessment..
4 Based on the observations, patch work may be recommended using 3 mm thk
Alloy steel. Payment for patch plating shall be made as per applicable SOR.
5 133-FD-301A/B FD fan discharge duct is patched at 4-5 locations. Carry out
replacement of the same (Approx. 4m X 2m) area using 5mm thk IS 2062 Gr A
plate.
6 133-AP-302 combustion air pre-heater II bypass duct to be delagged completely
and offer for inspection. Same duct is already having leaks at 2 locations on west
of stack. Carry out replacement/patch work for Approx. 6m X 2m area using 5mm
thk IS 2062 Gr A plate.
7 Scrap clean and paint the FD suction duct and suction stack internally with 2
coats of CTE. Scrap clean and paint the FD discharge duct up to steam air heater
internally with 2 coats of zinc dust graphite.
8 Carry out replacement of the FD fan suction silencer baffles as per Annexure I
9 All diverter plates wherever found damaged shall be repaired and fitted back.
REFRACTORY / INSULATION WORK
1 Carry out replacement of approx. 15 m2 ceramic fiber modules, blankets, clips and
SS foils of side walls & roof in both cells of radiation section as per drawing no.
133-CE-3-11 (roof) & 133-CE-3-5 (side walls).
2 Carry out replacement of approx. 5 m2 ceramic fiber modules, blankets, clips and
SS foils of floor as per drawing no. 133-CE-3-12.
3 Carry out replacement of approx. 5 m2 ceramic fiber modules, blankets, clips and
SS foils of taper duct as per drawing no. 133-CE-3-27.
4 Carry out replacement of Castable for an area of 5 m2 as per drawing no. 133-CE-
3-109 for convection section
5 Carry out replacement of Castable for an area of 10 m2 as per drawing no. 133-
CE-3-113 for Flue gas duct section and APH.
6 Fill/pack ceramic blanket/ pumpable ceramic fiber in the expansion joints/gaps in
ceramic modules
7 Carry out replacement of Clamp nuts and ceramic caps at approx. 400 locations
GUILLOTINE DAMPERS
1 Carry out servicing of all the guillotine dampers and offer dampers for inspection.
2 Carry out replacement of the sealing strips of the guillotines as per inspection
finding during shutdown. The payment for replacement of the sealing strips of
Page 3 of 11
the guillotines shall be made as per applicable SOR
MISC JOBS
1 Renew complete 2 nos. leaky fuel Naphtha lines along with their jacket
piping (1B and 2A) of Reformer as their jackets are leaking. Offer hydro test
of both jacket and inner pipe of entire fuel circuit from Naphtha fuel
vaporizer 133-E-312 to 133-V-304 and 16 nos naphtha jacketed lines going
to burners.
2 Fabricate and carry out replacement of approximately 35 nos. of steam trap
assemblies of 133-F-301 jacketed piping fuel gas lines.
Page 4 of 11
23. B SIDE THIRD AND FOURTH ROW OFF GAS MAIN NAPHTHA
12 150
BLOCK VALVE
24. B SIDE FIFTH ROW BURNER MAIN OFF GAS BLOCK VALVE 8 150
25. C SIDE FIRST ROW BURNER MAIN OFF GAS BLOCK VALVE 6 150
26. C SIDE SECOND ROW BURNER MAIN OFF GAS BLOCK
8 150
VALVE
27. C SIDE THIRD AND FOURTH ROW BURNER MAIN OFF GAS
12 150
BLOCK VALVE
28. C SIDE FIFTH ROW BURNER MAIN OFF GAS BLOCK VALVE 8 150
29. D SIDE FIRST ROW BURNER MAIN OFF GAS BLOCK VALVE 6 150
30. D SIDE SECOND ROW BURNER MAIN OFF GAS BLOCK
8 150
VALVE
31. D SIDE THIRD AND FOURTH ROW BURNER MAIN OFF GAS
12 150
BLOCK VALVE
32. D SIDE FIFTH ROW BURNER MAIN OFF GAS BLOCK VALVE 8 150
33. R 303 O/L LINE TO BE SPADED 16 900
34. EJECTOR I/L PROCESS GAS FLANGE TO BE SPADED 10 900
35. EW 301 O/L LINE FLANGE 18 300
36. EW 301 RISERS TO V 301 12 600
37. EW 301 DOWNCOMERS TO V 301 12 600
38. EW 301 BLOWDOWN LINE 2 150
39. EW 301 Steam Inlet valve upsteam Flange 1.5 150
40. STEAM JACKETING TO REFORMER AREA 2 600
41. R 303 RPDT 564 I/L BLOCK VALVE D/S FLANGE LINE TO BE
3/4 150
SPADED
LOBS
Carry out jobs on following heaters as per general guide line given in Appendix A
attachment 3 and specific scope as detailed below.
Page 5 of 11
3 Carry out external cleaning of tubes. Use SS wire brush for cleaning & spot
making.
4 Make around 700 nos. 2 diameter spot on tubes and all U bends for UT gauging.
5 Clean all the weld joints of tubes size 8 / 6 / 4 for fluorescent DP testing.
6 Clean 8 nos. thermocouple weld joint and offer for DP testing
7 Open all the temperature indicator flanges at inlet end of each stream for
assessing internal condition of the tubes
CONVECTION
1 Open convection coil panels
2 Clean the entire convection coil bend, make approximately 250 nos. 2 diameter
spot on bends and on first row of plain tubes. Use SS wire brush for cleaning &
spot making.
3 Provide scaffolding for accessing bottom row of convection coil.
4 Provide scaffolding in the bridge section of the convection bank and breech
section below stack.
5 Clean all the welds of 3 dia U bends in convection section and offer for DP test.
6 Clean 4 nos. thermocouple weld joint and offer for DP testing
7 Open all the temperature indicator flanges at inlet end of each stream for
assessing internal condition of the tubes
8 Carry water washing of all the tubes in convection section. (Dry Ice blasting?). The
tubes of convection zones shall be thoroughly water washed; in order to clean
them externally free of deposits (ensure that chloride is less than 50 ppm).
Suitable arrangement shall be made for draining water so that the refractory inside
the heater does not get affected
9 Carry out replacement /repairs to approx 12 m2 header box plate.
HYDRO TESTING
1 Carry out hydro testing of all the 4 passes using DM water at 34.5 Kg / cm2.
CROSS OVER PIPING
1 Offer the entire cross over piping for inspection.
2 Open insulation pockets at all elbow locations and few straight sections of all 4
crossover pipe lines connecting convection outlet to radiation inlet. Provide
necessary scaffolding for thickness measurement at these locations.
STACK
1 Open the access door and offer the stack for internal inspection. Provide
necessary Bosun chair arrangement//scaffolding.
2 Carry out insulating castable refractory repairs of approx 5 m2 as per drawing no
132-CE-3-247
DAMPERS
1 Carry out servicing of all the dampers , louvers & Pee hole doors.
APH AND AIR / FLUE GAS DUCTING
1 Open man way / access door covers of APH modules, Cold air ducts, hot air
ducts and flue gas ducts. Clean the ducts internally and APH tubes (internally /
externally) free of all deposits and offer for inspection.
2 Provide necessary ladder/ scaffolding/ hand lamps for internal inspection.
3 Take necessary precautions while erecting scaffolding below Glass APH module
and while cleaning the glass tubes.
4 Based on inspection findings, carry out renewal of 100 nos damaged glass tubes
size 32 mm OD x 2.0 mm thk. Borosilicate glass tubes. Removal of insulation,
cutting of duct , rewelding of duct plates and fixing back insulation for carrying out
replacement of glass tubes shall be in Contractors scope.
Page 6 of 11
5 Carry out water wash cleaning of the Glass and the Cast air pre heater modules.
6 Scrap clean and paint the FD suction duct and suction stack internally with 2
coats of CTE. Scrap clean and paint the FD discharge duct and GAPH bypass
duct up to GAPH module internally with 2 coats of zinc dust graphite.
7 Carry out insulation removal of flue / air duct for inspection
8 Carry out patch plating of the duct using 6 to 8 mm thick SA 515 / 516 Gr 60 / 70
plates. The payment for patch plating shall be made as per applicable SOR.
REFRACTORY / INSULATION WORK
1 Carry out replacement of 8 nos. burner muffle blocks. For remaining 8 nos burner
muffle block carry out repairs. Offer all the cup throats for inspection of internal
lining and carry out refractory repair if any.
2 Carry out repairs of refractory wall and roof ceramic modules (approx area 15
m2) as per drawing no. 132-CE-3-253 & 132-CE-3-254.
3 Carry out repair of insulating Castable (approx. 5 m2) along with anchors of
furnace floor as per drawing no. 132-CE-3-243.
4 Carry out touch up / minor refractory repairs of peep holes and area around it in
standard manner.
5 Carry out insulating Castable repair (approx. 10 m2) along with anchors of
convection section as per drawing no. 132-CE-3-246-2.
6 Carry out insulating Castable repair (approx. 10 m2) along with anchors of header
box covers as per drawing no. 132-CE-3-246-2.
7 Carry out replacement/repair of Ceramic fiber modules (approx. 5 m2) along with
anchors of ID flue gas ducts as per drawing no. 132-CE-3-251.
8 Carry out insulating Castable repair (approx. 10 m2) along with anchors of APH
section as per drawing no. 132-CE-3-255-2
9 Pack ceramic insulation material in the expansion joint gaps.
GUILLOTINE
1 Carry out servicing of all the guillotine dampers and offer dampers for inspection.
2 Carry out replacement of the sealing strips of the other guillotines as per
inspection finding during shutdown. The payment for replacement of the sealing
strips of the guillotines shall be made as per applicable SOR.
Size Rating
Sr no. Location
( In) (Lbs)
1. PASS 1 FURNACE INLET 3 300
2. PASS 2 FURNACE INLET 3 300
3. PASS 3 FURNACE INLET 3 300
4. PASS 4 FURNACE INLET 3 300
5. PASS 1 FURNACE OUTLET 8 300
6. PASS 2 FURNACE OUTLET 8 300
7. PASS 3 FURNACE OUTLET 8 300
8. PASS 4 FURNACE OUTLET 8 300
9. PASS 1 FURNACE OUTLET TO CFBD 2 150
10. PASS 2 FURNACE OUTLET TO CFBD 2 150
11. PASS 3 FURNACE OUTLET TO CFBD 2 150
12. PASS 4 FURNACE OUTLET TO CFBD 2 150
Page 7 of 11
13. ATOMIZING STEAM 2 300
14. FO SUPPLY 2 300
15. FO RETURN 2 300
16. MAIN FG SUPPLY 4 150
17. PILOTS FG SUPPLY 2 150
18. OFF GAS EX FPU COLUMN 8 150
19. OFF GAS EX FPU COLUMN 8 150
20. OFF GAS EX DW COLUMN 6 150
21. OFF GAS EX DW COLUMN 6 150
22. STEAM TO SOOT BLOWER 3 300
23. SNUFFING STEAM TO FIRE BOX 8 150
Page 8 of 11
STACK
1 Open the access door and offer the stack for internal inspection. Provide
necessary Bosun chair arrangement/scaffolding
2 Carry out insulating castable refractory repairs of approx 5 m2 as per drawing no
132-CE-3-272
DAMPERS
1 Carry out servicing of all the dampers , louvers & Pee hole doors.
REFRACTORY / INSULATION WORK
1 Offer all the 16 nos. cup throats for inspection and carry out refractory repair if
any. Carry out repair of all the muffle blocks. Carry out replacement of 8 nos.
burner muffle blocks. For remaining 8 nos burner muffle block carry out repairs.
2 Carry out repair/replacement of refractory wall and roof ceramic modules during
shutdown (approx area 15 m2) as per drawing no. 132-CE-3-274-1 & 132-CE-3-
274-2.
3 Carry out repair of insulating Castable (approx. 5 m2) along with anchors of
furnace floor as per drawing no. 132-CE-3-265
4 Carry out touch up / minor refractory repairs of peep holes and area around it in
standard manner.
5 Carry out insulating Castable repair (approx. 10 m2) along with anchors of
convection section as per drawing no. 132-CE-3-266-1.
6 Carryout insulating Castable repair (approx. 10 m2) along with anchors of header
box covers as per drawing no. 132-CE-3-266-2.
7 Pack ceramic insulation material in the expansion joint gaps.
Size Rating
Sr no. Location
( In) (Lbs)
1. PROCESS INLET 8 1500 RTJ
2. PROCESS OUTLET 8 1500 RTJ
3. PROCESS O/L DRAIN TO CFBD 2 150
4. MAIN FG SUPPLY 2 150
5. PILOTS FG SUPPLY 1 150
Page 9 of 11
5 Clean 4 nos. thermocouple weld joint and offer for DP testing
6 Open all the temperature indicator flanges at inlet end of each stream for
assessing internal condition of the tubes
CONVECTION
1 Open convection coil panels
2 Clean the entire convection coil bend, make approximately 150 nos. 2 diameter
spot on bends and on first row of plain tubes.
3 Provide scaffolding for accessing bottom row of convection coil.
4 Provide scaffolding in the bridge section of the convection bank.
5 Clean all the welds of 3 / 4 dia U bends in convection section and offer for DP
test.
6 Clean and offer 2 nos. thermocouple weld joint of the coils for DP test.
7 Open all the temperature indicator flanges at inlet end of each stream for
assessing internal condition of the tubes
8 Clean and offer Economizer and steam super heater coil in convection section for
inspection.
9 Carry water washing of all the tubes in convection section.
CROSS OVER PIPING
1 Offer all cross over piping for inspection.
2 Open insulation pockets at all elbow locations and few straight sections of both the
crossover pipe lines connecting convection outlet to radiation inlet.
HYDRO TESTING
1 Carry out hydro testing of all the passes at 11.5 Kg / cm2.
2 Carry out hydrostatic test of Economizer & steam super heater coil at 56.4
Kg/cm2 and 40.3 Kg/cm2 respectively for BPCL Inspection and at 31.5 kg/cm2g
along with other equipment of LOBS Waste heat boiler MR-13892 to GBI.
STACK
1 Open the access door and offer the stack for internal inspection. Provide
necessary Bosun chair arrangement//scaffolding.
3 Carry out insulating castable refractory repairs of approx 5 m2 as per drawing no
132-CE-3-264.
DAMPERS
1 Carry out servicing of all the dampers, louvers & Pee hole doors.
REFRACTORY / INSULATION WORK
1 Offer all the 4 nos. cup throats for inspection and carry out refractory repair if any.
Carry out renewal of 2 nos muffle block and repair remaining muffle blocks.
2 Carry out repair/replacement of refractory wall and roof ceramic modules during
shutdown (approx area 15 m2) as per drawing no. 132-CE-3-264
3 Carry out repair of insulating Castable (approx. 5 m2) along with anchors of
furnace floor as per drawing no. 132-CE-3-257
4 Carry out touch up / minor refractory repairs of peep holes and area around it in
standard manner.
5 Carry out insulating Castable repair (approx. 10 m2) along with anchors of
convection section as per drawing no. 132-CE-3-258-1& 2.
6 Carry out insulating Castable repair (approx. 10 m2) along with anchors of header
box covers as per drawing no. 132-CE-3-258-1 & 2.
7 Pack ceramic insulation material in the expansion joint gaps.
Page 10 of 11
Spade List for 132-F-206
Size Rating
Sr no. Location
( In) (Lbs)
1. PASS 1 FURNACE INLET 3 300
2. PASS 2 FURNACE INLET 3 300
3. PASS 1 FURNACE OUTLET 8 300
4. PASS 2 FURNACE OUTLET 8 300
5. MAIN FG SUPPLY 2 150
6. PILOTS FG SUPPLY 1 150
7. PROCESS O/L DRAIN TO CFBD 2 150
8. PROCESS O/L DRAIN TO CFBD 2 150
9. SNUFFING STEAM TO FIRE BOX 4 150
ANNEXURE I
Procedure and scope of work for replacement of 133-F-301 FD fan suction silencer
baffles.
3. Make necessary rigging arrangement and remove the silencer piece (i.e. Section
between connecting piece for stack and transition piece as per BPCL drawing no.
133-CE-3-29).
4. If any connected duct / structure required to be removed for completion of the job,
then removal and restoration of the same is included in your scope.
5. Carry out replacement of all the baffles (part no. 17.1) inside the silencer. New
baffles shall be provided by BPCL.
a. Remove the stopper of any one side of the baffle by gas cutting. Stopper
is nothing but the small piece of angle welded to silencer housing.
b. Remove the baffle.
c. Insert the new baffle.
d. Weld the stopper as earlier.
e. Repeat the above steps to replace the other baffles.
7. On completion of the baffle assembly, the silencer assembly shall be fitted back.
9. Old baffles metal part after removal of the insulation shall be disposed in scrap
yard.
Page 11 of 11
WORK PACKAGE FOR PACKAGE NO. 3
Part A: For the following exchangers carry out the entire jobs as
per general scope of work detailed in Appendix A attachment 4
including opening and pulling out of exchanger bundle and
specific job as detailed against individual exchangers.
General RFET & ECT requirement for this package is given in the
inspection scope under section-Q
NHGU
Note: For the entire data sheet, the unit of measurement shall be , tube
length in mm, Pressure in kg/cm2, weight in Kg. The no of tubes
mentioned are for each bundle.
Page 1 of 26
SHELL AND TUBE DETAILS
TUBE OD 25 MM TUBE LENGTH 8000
TUBE THICK 2 MM TUBE MAT SB163 UNS4400
NO OF TUBES 392 BUNDLE WEIGHT 10700
SHELL ID 0.775 meter AREA 243
SHELL HYD 37.1 TUBE HYD 24.7
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL INLET 12-300# 2
SHELL OUTLET 12-300# 2
TUBE INLET 8-150# 1
TUBE OUTLET 8-150# 1
801 LHS GSKT,CAF,810x836x2,PN:801 LHS,W/P 1 85.31.10.810.5
803 RHS GSKT,CAF,803x829x2,PN:801 RHS,W/P 1 85.31.10.803.5
INSERT PTFE 392 43.53.98.332.5
DRG NO 133-ME-3-40
SR NO DESCRIPTION OF WORK
1 Carry out ECT of 100% of the tubes. Carry out replacement of 25% of
tubes of both coolers at site (including seal welding)
2 Carry out internal CTE painting of wet part of the exchanger
component on cooling water side including both tube sheets as per
BPCL painting specification AES 5430
3 Offer shell test at 37.10 kg/cm2.
4 Offer tube test at 24.7 kg/cm2
5 Open insulation for CUI including insulation rings and UT gauging
Page 2 of 26
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL INLET 2-150# 1
SHELL OUTLET 6-150# 1
TUBE INLET 3-600# 1
TUBE OUTLET 3-600# 1
802 GSKT,IJA,393x413x3,PN:802,W/P 1 85.37.05.322.5
803 GSKT,IJA,393X413X3,PN:803,W/OP 85.37.05.314.5
INSERT NA -- NA
DRG NO 133-ME-3-64
SR NO DESCRIPTION OF WORK
1 Carry out RFET of 20% of tubes.
2 Offer shell test at 7.8 kg/cm2.
3 Offer tube test at 65 kg/cm2
4 Open insulation for CUI including insulation rings and UT gauging
Page 3 of 26
TUBE INLET 2-600# 1
TUBE OUTLET 2-600# 1
VENT 2-600# 1
DRAIN 2-600# 1
802 GSKT,SS304SSPWND,309X255X4.5,PN:802,W/OP 1 85.41.12.301.5
INSERT NA -- NA
DRG NO 133-ME-3-76
SR NO DESCRIPTION OF WORK
1 Carry out ECT of 20% of the tubes
2 Carry out repairs to leaky channel box
3 Offer shell test at 66.30 kg/cm2.
4 Offer tube test at 68.90 kg/cm2
5 Open insulation for CUI excluding insulation rings and UT gauging
Page 4 of 26
SHELL 13.7 TUBE HYD 9.1
HYD
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL 8-150# 2
INLET
SHELL 10-150# 1
OUTLET
TUBE 4-150# 1
INLET
TUBE 4-150# 1
OUTLET
VENT 2-150# 1
DRAIN 2-150# 1
801 GSKT,CAF,590x610x2,PN:801 RHS,W/P 1 85.31.10.588.5
801 GSKT,CAF,590x610x2,PN:801 LHS,W/P 1 85.31.10.589.5
INSERT PTFE 170 43.53.98.332.5
DRG NO 133-ME-3-95
SR NO DESCRIPTION OF WORK
1 Carry out replacement of 100% of tubes at site.
2 Carry out internal CTE painting of wet part of the exchanger component
on cooling water side including both tube sheets as per BPCL painting
specification AES 5430
3 Offer shell test at 13.70 kg/cm2.
4 Offer tube test at 9.10 kg/cm2
5 Open insulation for CUI including insulation rings and UT gauging
Page 5 of 26
SHELL HYD 10.5 TUBE HYD 10.5
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL INLET 1.5-150# 1
SHELL OUTLET 1.5-150# 1
TUBE INLET -- 1
TUBE OUTLET -- 1
802 GSKT,CAF,126.5x145x2,PN:802,W/OP 1 85.31.10.126.5
INSERT NA -- NA
SR NO DESCRIPTION OF WORK
1 Carry out internal CTE painting of wet part of the exchanger
component on cooling water side including both tube sheets as per
BPCL painting specification AE-DEP-C03.
2 Offer shell test at 10.50 kg/cm2.
3 Offer tube test at 10.50 kg/cm2
Page 6 of 26
SHELL INLET 4-600# 1
SHELL OUTLET 4-600# 1
TUBE INLET 3-300# 1
TUBE OUTLET 3-300# 1
GASKET
Page 7 of 26
TUBE INLET 2-300# 1
TUBE OUTLET 2-300# 1
GASKET
805 GSKT,SW,270X298X4.5,PN:805,W/P 1 85.41.33.123.5
802 GSKT,SW,304X358X4.5,PN:802,W/OP 1 85.41.33.200.5
804 GSKT,SW,393X447X4.5,PN:804,W/OP 1 85.41.33.276.5
INSERT PTFE 31 43.53.98.332.5
GASKET MAT NA
DRG NO 133-ME-3-115
SR NO DESCRIPTION OF WORK
1 Carry out Glass flake coating (800-1000 microns thick) of both the Tube
sheets on cooling water side.
2 Offer shell test at 56.90 kg/cm2.
3 Offer tube test at 38.50 kg/cm2
Page 8 of 26
TAG NO 133-EA-302A/B TYPE AFC
SERVICE PROCESS GAS AIR COOLER(AFC) LOCATION HGU
SHELL AND TUBE DETAILS
TUBE OD 32MM TUBE LENGTH 6500MM
TUBE THICK 2MM TUBE MAT SA 213 TP 304L +
SB209
NO OF TUBES 230 BUNDLE WEIGHT ~6000
SHELL ID NA AREA 3187
SHELL HYD NA TUBE HYD 37.05
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
TUBE INLET 8-300# 2
TUBE OUTLET 8-300# 2
VENT 2-300# 1
DRAIN 2-300# 1
GASKET PLUG GSKT,SS316L,43X48X2,PLUG GSKT,W/OP 85.41.11.043.5
PLUG SA182F304L 76.99.99.510.8
INSERT NA -- NA
GASKET MAT SS316L SPWD WITH GRAFITE FILLER
DRG NO 133-ME-3-137
SR NO DESCRIPTION OF WORK
1 Carry out external cleaning of the air fin cooler using foam method.
2 Carry out opening of 20% plugs and carry out ECT for these tubes
3 Carry out tube test at 37.10 kg/cm2
LOBS
Page 9 of 26
TAG NO 132-E-258 TYPE AEM
SERVICE DW VACUUM BOTTOMS COOLER LOCATION LOBS
SHELL AND TUBE DETAILS
TUBE OD 25MM TUBE LENGTH 6000MM
TUBE THICK 2MM TUBE MAT SB-338 (SEAM LESS)
GRD2
NO OF TUBES 228 BUNDLE WEIGHT 3750
SHELL ID 0.6 meter AREA 105
SHELL HYD 24.1 TUBE HYD 31.2
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL INLET 4-300# 1
SHELL OUTLET 4-300# 1
TUBE INLET 6-150# 1
TUBE OUTLET 6-150# 1
DRAIN 1
2-150#
VENT 1
2-150#
PG Connection 1
-300#
801 GSKT,MONEL,602X628X3 MM
THK,PN:801/2,W/P 1 85.43.96.602.5
802 GSKT,MONEL,602X628X3 MM
THK,PN:801/2,W/P 1 85.43.96.602.5
804 1
GSKT,MONEL,602X628X3 MM THK,PN:804 ,W/P 85.43.96.603.5
INSERT NR - --
DRG NO. 132-ME-3-84
SR NO DESCRIPTION OF WORK
1 Carry out internal CTE painting of wet part of the exchanger
component on cooling water side including both tube sheets as per
BPCL painting specification AES 5430.
2 Open insulation for CUI including insulation rings and UT gauging.
3 Carry out shell test at 24.10 kg/cm2
4 Carry out tube test at 31.20 kg/cm2
Page 10 of 26
DRG NO. 132-ME-3-85
SR NO DESCRIPTION OF WORK
1 Carry out internal CTE painting of wet part of the exchanger
component on cooling water side including both tube sheets as per
BPCL painting specification AES 5430.
2 Open insulation for CUI including insulation rings and UT gauging.
3 Carry out shell test at 20 kg/cm2
4 Carry out tube test at 26 kg/cm2
Page 11 of 26
801 1
GSKT,INC,1162x1188x3MM THK,PN:801/2, W/P 85.43.59.116.5
802 1
GSKT,INC,1162x1188x3MM THK,PN:801/2, W/P 85.43.59.116.5
803 1
GSKT,IRON,1162X1188X3MM THK,PN:803, W/OP 85.38.12.116.5
804 1
GSKT,IRON,1247X1273X3MM THK,PN:804, W/OP 85.38.12.124.5
805 1
GSKT,INC,1116x1142x3MM THK,PN:805, W/OP 85.43.59.111.5
INSERT PTFE 838 43.53.98.332.5
DRG NO. 132-ME-3-73
GASKET SS 304 SW GRAPHITE FILLED
SR NO DESCRIPTION OF WORK
1 Remove channel box, channel cover, float head cover and channel
cover and sent to machine shop for repair.
2 Carry out Glass flake coating (800-1000 microns thick) of both the Tube
sheets on cooling water side.
3 Carry out shell test at 9.10 kg/cm2
4 Carry out tube test at 7.10 kg/cm2
5 Carry out ECT for 100% tubes
6 Open insulation for CUI excluding insulation rings and UT gauging.
Page 12 of 26
TAG NO 132-E-271 C TYPE AES H
SERVICE AFTER CONDENSER LOCATION LOBS
SHELL AND TUBE DETAILS
TUBE OD 25MM TUBE LENGTH 6000MM
TUBE THICK 2MM TUBE MAT SA-789 M UNS N-
32750
NO OF TUBES 838 BUNDLE WEIGHT 3700/100 WT.UNIT
/BUNDLE
SHELL ID 0.45 meter AREA 376.3
SHELL HYD 9.1 TUBE HYD 7.1
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL INLET 6-150# 1
SHELL OUTLET 4-150# 1
TUBE INLET 10-150# 1
TUBE OUTLET 10-150# 1
801 1
GSKT,INC,462X488X3 MM THK,PN:801/2,W/P 85.43.59.462.5
802 1
GSKT,INC,462X488X3 MM THK,PN:801/2,W/P 85.43.59.462.5
803 1
GSKT,IRON,462X488X3 MM THK,PN:803, W/OP 85.38.12.462.5
804 1
GSKT,IRON,552X578X3 MM THK,PN:804, W/OP 85.38.12.552.5
805 1
GSKT,INC,421x447x3 MM THK,PN:805, W/OP 85.43.59.421.5
INSERT PTFE 838 43.53.98.332.5
DRG NO. 132-ME-3-69
GASKET SS 316 SW GRAPHITE FILLED
SR NO DESCRIPTION OF WORK
1 Remove channel box, channel cover, float head cover and channel
cover and sent to machine shop for repair.
2 Carry out Glass flake coating (800-1000 microns thick) of both the Tube
sheets on cooling water side.
3 Send the bundle to BPCL shop for re-tubing
4 Carry out shell test at 9.10 kg/cm2
5 Carry out tube test at 7.10 kg/cm2
6 Carry out ECT for 100% tubes
7 Open insulation for CUI excluding insulation rings and UT gauging.
Page 13 of 26
803 1
GSKT,IRON,689X717X3 MM THK,PN:803, W/OP 85.38.12.689.5
804 1
GSKT,IRON,777X803X3 MM THK,PN:804, W/OP 85.38.12.777.5
805 1
GSKT,INC,646X672X3 MM THK,PN:805, W/OP 85.43.59.646.5
INSERT PTFE 280 43.53.98.332.5
DRG NO. 132-ME-3-70
GASKET SS 304 SW GRAPHITE FILLED
SR NO DESCRIPTION OF WORK
1 Remove channel box, channel cover, float head cover and channel
cover and sent to machine shop for repair.
2 Carry out Glass flake coating (800-1000 microns thick) of both the Tube
sheets on cooling water side.
3 Carry out shell test at 9.10 kg/cm2
4 Carry out tube test at 7.10 kg/cm2
5 Open insulation for CUI and UT gauging. Carryout removal of insulation
support rings of shell for inspection and carryout insulation in
standard manner after inspection.
6 Carry out ECT for 100% tubes
Page 14 of 26
standard manner after inspection.
7 Carry out ECT for 100% tubes
Page 15 of 26
VENT 2-300# 1
DRAIN 2-300# 1
GASKET MAT SS 304 SPWD WITH FLEXIBLE GRAPHITE FILLER
GASKET PLUG
GASKET,PLUG,SOFT IRON,30X35X2 MM, W/OP 85.37.27.010.5
PLUG SA105 76.99.99.502.8
INSERT NA -- NA
DRG NO. 132-ME-3-23
SR NO DESCRIPTION OF WORK
1 Carry out external cleaning of the air fin cooler using foam method.
2 Carry out opening of 20% plugs and carry out for RFET for the tubes.
3 Carry out tube test at 25.35 kg/cm2
Part B: For the following exchanges there is no requirement for opening of the
exchanger & removal of tube bundles. Scope shall include only following activities,
Page 16 of 26
NHGU:
TAG NO 133-E-305 A/B TYPE BHU(H)
SERVICE 1ST BFW PREHEATER LOCATION HGU
SHELL AND TUBE DETAILS
TUBE OD 20 MM TUBE LENGTH U-TUBE
TUBE THICK 2.3 MM TUBE MAT SA 213M T12
NO OF TUBES 368 BUNDLE WEIGHT 4450
SHELL ID 0.775 meter AREA 136
SHELL HYD 37.10 TUBE HYD 104
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL INLET 14-300# 2
SHELL OUTLET 14-300# 2
TUBE INLET 4-600# 1
TUBE OUTLET 4-600# 1
VENT 2-300# 1
DRAIN 2-300# 1
802 1
GSKT,SS410SSPWND,841X775X4.5,PN:802,W/P 85.41.12.833.5
803 GSKT,SS410SSPWND,841X775X4.5,PN:803,W/OP 1 85.41.12.834.5
INSERT NA -- NA
DRG NO 133-ME-3-16
SR NO DESCRIPTION OF WORK
1 Offer shell test at 37.10 kg/cm2.
2 Offer tube test at 104 kg/cm2
Page 17 of 26
TAG NO 133-E-308 TYPE BEM
SERVICE DMW PREHEATER LOCATION HGU
SHELL AND TUBE DETAILS
TUBE OD 20 MM TUBE LENGTH U-TUBE
TUBE THICK 1.6 MM TUBE MAT SA 213M TP 304L
NO OF TUBES 609 BUNDLE WEIGHT 7000
SHELL ID 0.7 meter AREA 283
SHELL HYD 24.7 TUBE HYD 37.10
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL INLET 6-150# 1
SHELL OUTLET 6-150# 1
TUBE INLET 16-300# 1
TUBE OUTLET 16-300# 1
VENT 2-300# 1
DRAIN 2-150# 1
803 GSKT,SS304SSPWND,761X701X4.5,PN:803,W/OP 1 85.41.12.753.5
INSERT NA NA
DRG NO 133-ME-3-34
SR NO DESCRIPTION OF WORK
1 Offer shell test at 24.70 kg/cm2.
2 Offer tube test at 37.10 kg/cm2
Page 18 of 26
TUBE OUTLET 2-600# 1
802 GSKT,IJA,393x413x3,PN:802,W/P 1 85.37.05.319.5
803 GSKT,IJA,393X413X3,PN:803,W/OP 1 85.37.05.314.5
INSERT NA -- NA
GASKET MAT SS316 SPWD WITH CA FILLER
DRG NO 133-ME-3-102
SR NO DESCRIPTION OF WORK
1 Offer shell test at 19.50 kg/cm2.
2 Offer tube test at 65.0 kg/cm2
SR NO DESCRIPTION OF WORK
1 Offer for UT gauging only. No hydro test is required.
LOBS:
Page 19 of 26
TUBE OD 25MM TUBE LENGTH 5000MM
TUBE THICK 2MM TUBE MAT SB-338(SEAM LESS)
GRD 2
NO OF TUBES 242 BUNDLE WEIGHT 1400/200 WT.
UNIT/BUNDLE
SHELL ID 0.65 meter AREA 92
SHELL HYD 24 TUBE HYD 31.1
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL INLET 3-150# 1
SHELL OUTLET 3-150# 1
TUBE INLET 3-150# 1
TUBE OUTLET 3-150# 1
DRAIN 1-300# 1
VENT 1-300# 1
PG Connection 2
3/4-300#
801 1
GSKT,MONEL JKT,676X702X3 MM,PN:801/2,W/ 85.43.96.676.5
802 1
GSKT,MONEL JKT,676X702X3 MM,PN:801/2,W/ 85.43.96.676.5
804 GSKT,MONEL JKT,681X707X3 MM,PN:804,W/P 1 85.43.96.681.5
INSERT NR 242 --
DRG NO. 132-ME-3-83-2
SR NO DESCRIPTION OF WORK
1 Carry out shell test at 24.00 kg/cm2
2 Carry out tube test at 31.10 kg/cm2
Page 20 of 26
TUBE INLET 3-150# 1
TUBE OUTLET 3-150# 1
DRAIN 2-150# 1
VENT 2-150# 1
GASKET PLUG
GASKET,PLUG,SOFT IRON,30X35X2 MM, W/OP 85.37.27.010.5
PLUG SA105 76.99.99.502.8
INSERT NA -- NA
DRG NO. 132-ME-3-18
SR NO DESCRIPTION OF WORK
1 Carry out external cleaning of the air fin cooler using foam method.
2 Carry out tube test at 8.45 kg/cm2
Page 21 of 26
TAG NO 132-EA-223 TYPE AFC
SERVICE WAXY 500N PRODUCT AIR COOLER LOCATION LOBS
SHELL AND TUBE DETAILS
TUBE OD 25MM TUBE LENGTH 10500MM
TUBE THICK 2.5MM TUBE MAT SA-179
NO OF TUBES 120 BUNDLE WEIGHT 3200
SHELL ID NA AREA 2312.64
SHELL HYD NA TUBE HYD 33.93
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
TUBE INLET 4-300# 1
TUBE OUTLET 4-300# 1
VENT 2-300# 1
DRAIN 2-300# 1
GASKET PLUG
GASKET,PLUG,SOFT IRON,30X35X2 MM, W/OP 85.37.27.010.5
PLUG SA105 76.99.99.502.8
INSERT NA -- NA
DRG NO. 132-ME-3-21
SR NO DESCRIPTION OF WORK
1 Carry out external cleaning of the air fin cooler using foam method.
2 Carry out tube test at 33.93 kg/cm2
Page 22 of 26
TUBE OUTLET 2-300# 1
VENT 2-300# 1
DEAIN 2-300# 1
GASKET MAT SS 304 SPWD WITH FLEXIBLE GRAPHITE FILLER
GASKET PLUG
GASKET,PLUG,SOFT IRON,30X35X2 MM, W/OP 85.37.27.010.5
PLUG SA105 76.99.99.502.8
INSERT NA -- NA
DRG NO. 132-ME-3-24
SR NO DESCRIPTION OF WORK
1 Carry out external cleaning of the air fin cooler using foam method.
2 Carry out tube test at 26.00 kg/cm2
Page 23 of 26
TAG NO 132-EA-228 TYPE AFC
SERVICE DW HHPS VAPOUR AIR COOLER LOCATION LOBS
SHELL AND TUBE DETAILS
TUBE OD 25MM TUBE LENGTH 10500MM
TUBE THICK 2.5MM TUBE MAT SA-213 T11
NO OF TUBES 165 BUNDLE WEIGHT 5600
SHELL ID NA AREA 2619.16
SHELL HYD NA TUBE HYD 31.98
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
TUBE INLET 6-300#RTJ 2
TUBE OUTLET 6-300#RTJ 2
VENT 2-300#RTJ 1
DRAIN 2-300#RTJ 1
GASKET PLUG GASKET,PLUG,SOFT,SS316L,37x42x2 MM,
W/OP 85.37.27.008.5
PLUG 76.99.99.504.8
SA182F11 76.99.99.505.8
GASKET MAT NA
INSERT NA -- NA
DRG NO. 132-ME-3-28
SR NO DESCRIPTION OF WORK
1 Carry out external cleaning of the air fin cooler using foam method.
2 Carry out tube test at 31.98 kg/cm2
PART C: For Part C, only carry out external scaffolding wherever required
and carry out insulation job as per general scope.
INSERT NA -- NA
DRG NO. 132-ME-3-15-1
GASKET SW 4.5 THK SS 321 GRAPH. FILLER 3.2 THK
MATERIAL SS321 OUTER RING
*** ALL NOZZLES ARE BUT WELDED
SR NO DESCRIPTION OF WORK
1 Open insulation for CUI excluding insulation rings and UT gauging
Page 24 of 26
TAG NO 132-E-255 TYPE NEN H
SERVICE DW MAKEUP HYDROGEN COOLER LOCATION LOBS
SHELL AND TUBE DETAILS
TUBE OD 25MM TUBE 5500MM
LENGTH
TUBE 3.7MM TUBE MAT SB622 UNS-10276
THICK
NO OF 224 BUNDLE 15450
TUBES WEIGHT
SHELL ID 0.6 meter AREA 94.5
SHELL ---- TUBE HYD ----
HYD
NOZZLE AND GASKET DETAILS
LOCATION DESCRIPTION QTY MESC
SHELL BUT WELDED
INLET
SHELL BUT WELDED
OUTLET
TUBE 8-1500#RTJ 1
INLET
TUBE 8-1500#RTJ 1
OUTLET
DRAIN 2-1500# RTJ 1
VENT 2-1500# RTJ 1
801 GSKT,MSW,760X768X4.5 MM,PN:801 RHS,W/OP 85.43.96.761.5
801 GSKT,MSW,760X768X4.5 MM,PN:801 LHS,W/P 85.43.96.762.5
INSERT NA -- NA
DRG NO. 132-ME-3-14-1
SR NO DESCRIPTION OF WORK
1 Open insulation for CUI including insulation rings and UT gauging
Page 25 of 26
Configuration details based on Heat Exchanger type
Page 26 of 26
ATTACHMENT 11 SECTION D
Carry out jobs on following steam generator as per the scope detailed below
NHGU:-
b) Carry out RLA study through GBI approved RLA agency and submit
report to BPCL inspection and GBI. Offer NDTs and testing to BPCL / GBI
during RLA study at site as per GBI requirements. The contractor should
take permission from GBI for carrying out RLA. It may be noted that
cutting of samples and their destructive testing as per IBR rules
shall be included in the contractor scope. Also supply of new
tubes/plugs including welding for replacing/plugging the sample
drawn locations shall be in the contractor scope.
I. General:
a) Open the man ways and clean the tubes internally / externally free of
scales/ muck and offer for inspection. Ensure that the refractory in the
west side tube sheet / cold collector outlet does not get wet.
b) Open 6 dia 600 # hand hole blind flanges of the shell , clean the
accessible tubes externally and offer for visual inspection.
Page 1 of 9
III. STEAM DRUMS (133-V-301)
d) Thoroughly clean the drum internally to bare metal, after removing all the
internal fittings.
g) Drop all first isolation valves and offer hydro test of seat and body as per
flange rating.
h) Offer NRV on main steam line for inspection after providing proper
scaffolding arrangement.
j) After dry inspection of the boiler by GBI, paint the drum internally and all
internals with 2 coats of ferrotol paint as per AES 5430.
k) On completion of the painting, fix back all the internals, box up man ways,
fix back all the drum mountings. The demisters if required shall be
replaced with new one.
a) Open man ways and erect scaffolding inside the duct to access all coils of
both modules on either sides and outside the duct to access the top
headers. Provide proper ladder arrangement wherever required.
b) Open complete insulation on top and bottom headers and offer for
inspection.
c) Clean all tubes externally free of scales using heavy duty industrial
vacuum cleaner and offer for inspection.
a) Open man ways in the duct and erect scaffolding inside the duct to
access all coils. Open man ways and panels on either side outside the
duct and provide scaffolding to access the headers / coil bends. Remove
Page 2 of 9
insulation in the header box to access the coil bends. Provide proper
ladder arrangement wherever required.
b) Open complete insulation in both inlet and outlet headers and offer for
inspection.
c) Clean all tubes externally free of scales using heavy duty industrial
vacuum cleaner and offer for inspection.
Open complete insulation of down comers and risers and offer for inspection.
Open insulation around vents and drains and offer for inspection. Provide
necessary scaffolding / ladder arrangement to carry out inspection of these
lines.
a) Offer hydrostatic test of the entire boiler at 75.0 kg/cm2g with all first isolation
valves in the circuit to BPCL inspection / GBI. After completion of hydro test of
the boiler circuit, carry out scrape cleaning and painting as per AES-5430 Rev 1.
Carry out the insulation of the entire piping/equipment as per BPCL Standard.
a) Delag the entire blow down lines fully and offer for inspection. Offer the
hydro test of the same as per flange ratings.
b) Paint the lines with 2 coats of zinc dust graphite and relag in standard
manner.
c) Overhaul the entire blow down valves of the boiler system.
THE DIRECTOR,
The Directorate of Steam Boilers,
Kamgar Bhavan, 7th floor,
C-20, E Block,
Opp. Reserve Bank, BKC,
Bandra (E), Mumbai-400051
Page 3 of 9
b) Obtaining visits from GBI office for Dry test/Bare Inspection and Hydro
testing.
c) Arrangement of AC Car for to and fro transportation of GBI official on full
day basis.
d) Collection of all the inspection reports and certificate from GBI office.
e) All statutory fees shall be settled by BPCL.
X. JOB COMPLETION
a) After completion of the hydro test inspection by GBI, box up all the duct /
boiler duct manways, remove all spades and scaffolding.
EQUIPMENT DETAILS
DEMISTER YES
Page 4 of 9
LOBS :-
Remove insulation of the waste heat boiler (MR 13892) and its connected
equipment/piping and offer the boilers for bare inspection to BPCL/GBI in
clean condition. After completion of hydro test of the boiler circuit, carry out
scrape cleaning and painting as per AES-5430 Rev 1.
Scope of work:-
Page 5 of 9
with 2 coats of zinc dust graphite and re-lag in standard manner. Overhaul the
entire blow down valves of the boiler system.
l) Offer entire circuit to GBI for dry inspection.
m) After approval by GBI, the bundles to be inserted in the shell after painting the
internal surface of the shells with 2 coats of ferrotol paint.
n) Prepare the shell test.
o) Service and repack the glands of all the first isolation valves including blow down
lines valves.
p) Service all the gauge glasses as per procedure.
q) Carry out hydrostatic test of the steam generators per the following test pressure.
r) GBI will witness the COMBINED HYDROTEST including shell side of steam
generator, Economizer and super heater coils located in convection zone of 132-
F-205 & 206. Offer hydro test to GBI at 31.5 kg/cm2g with out covers. All the first
isolation valves shall be included in the test.
Page 6 of 9
s) After completion of hydro test of the boiler circuit, carry out scrape cleaning and
painting as per AES-5430 Rev 1. Carry out the insulation of the entire
piping/equipment as per BPCL Standard.
THE DIRECTOR,
The Directorate of Steam Boilers,
Kamgar Bhavan, 7th floor,
C-20, E Block,
Opp. Reserve Bank, BKC,
Bandra (E), Mumbai-400051
Obtaining visits from GBI office for Dry test/Bare Inspection and Hydro
testing.
Arrangement of AC Car for to and fro transportation of GBI official on full
day basis.
Collection of all the inspection reports and certificate from GBI office.
All statutory fees shall be settled by BPCL.
u) After completion of the hydro test by GBI fix back all the cover and prepare tube
test.
v) After completion of the tube test remove all spades and scaffolding.
Page 7 of 9
SHELL INLET 1-300# 1
SHELL OUTLET 2-300# 1
TUBE INLET 3-300# 1
TUBE OUTLET 3-300# 1
IBD 1-300# 1
CBD 1-300# 1
DRAIN 1-300# 2
INST CONNECT 2-300# 6
INST CONNECT 1.5-300# 2
INST CONNECT 3/4-300# 2
VENT 1-300# 1
802 GSKT,IJA,384x410x3 THK W/P, PN:802 LHS 85.37.02.384.5
802 GSKT,IJA,384x410x3 THK W/P, PN:802 RHS 85.37.02.385.5
INSERT NA -- NA
DRG NO. 132-ME-3-77-1
Page 8 of 9
DRAIN 1-300# 1
VENT 1-300# 1
PG Connection 3/4-300# 2
802 GSKT,SS304,769X777X4.5MM THK W/P,802LHS 1 85.41.11.581.5
802 GSKT,SS304,769X777X4.5MM THK W/P,802RHS 1 85.41.11.582.5
INSERT NA -- NA
DRG NO. 132-ME-3-80-1
Page 9 of 9
ATTACHMENT 11 SECTION E
NHGU:-
Part A : Carry out all the jobs on the vessels as per scope of work
detailed in Appendix A attachment 5 including opening of the vessel
and specific jobs detailed against each equipment
Page 1 of 31
No. SIZE (lbs)
(inch)
1. naphtha i/l line to V-304 6" 150
2. LP steam line to V-304 2" 150
3. drain to CBD/OWS common line 1. 150
4. fuel naphtha o/l line to reformer 6" 150
5. gauge glass drain line 300
6. level switch drain line (2 Nos.) 300
7. jacketing steam line 300
8. naphtha i/l line to V-304 6" 150
SR NO DESCRIPTION OF WORK
1 Remove and replace the demister assembly.
2 Carry out hydro testing at 7.8 kg/cm2.
3 Remove and service the gauge glasses
4 Carry out insulation removal for inspection including insulation rings as per general scope and
carry out insulation in standard manner.
Page 2 of 31
TAG NO 133-V-307 LOCATION HGU
SERVICE DMDS DRUM DRG NO. 133-ME-2-14-1
Page 3 of 31
TAG NO 133-V-309 LOCATION HGU
SERVICE FUEL GAS KOD DRG NO. 133-ME-2-16-1
DEMISTER YES DEM DRAWING 133-2-ME-16-1&2 SH
1
VESSEL ID 0.433 meter HEIGHT 1.994 meter
HYD TEST 7.8
PR.(Kg/cm2)
Sr. No. X RATING
No. LOCATION SIZE (lbs)
6
(inch)
1. i/l fuel gas line from C-301 to vessel 4" 150
2. LP staem to V-309 2" 300
3. common o/l line to reformer and
SPADE LIST
RV'S 4" 150
4. drain to OWS/CBD common line 2" 300
5. gauge glass LP and HP steam
tapping 2" 300
6. level switch drain line (2 Nos.) 3/ 300
7. i/l fuel gas line from C-301 to vessel 4" 150
SR NO DESCRIPTION OF WORK
1 Remove and replace the demister assembly.
2 Carry out power brushing of all the weld joints 6 on either side of the weld and carry out
WFMPI testing
3 Carry out internal scrape cleaning and painting of Bottom half of the vessel with two coat of
CTE paint as per painting specification AES 5430.
4 Carry out hydro testing at 7.8 kg/cm2.
5 Remove and service the gauge glasses
Page 4 of 31
TAG NO 133-V-313 LOCATION HGU
SERVICE N2 SU DRG NO. 133-ME-2-19-1
SEPARATOR FOR
HDS
DEMISTER YES DEM DRAWING 133-ME-2-19-1 SH 1
VESSEL ID 0.9 meter HEIGHT 3.413 meter
HYD TEST 20.66
PR.(Kg/cm2)
Sr. No. X RATING
No. LOCATION SIZE (lbs)
8 (inch)
1. nitrogen i/l line 2" 300
2. i/l line from EA 301A/B 6" 300
3. LP steam i/l line 2" 150
4. top o/l to K-307 and RV'S common
SPADE LIST
line 6" 300
5. bottom o/l line to c-301 and
CBD/OWS 2" 300
6. gauge glass drain line to CBD/OWS
(2 Nos.) 300
7. level switch to drain line 3/4 300
8. nitrogen i/l line 2" 300
SR NO DESCRIPTION OF WORK
1 Remove and replace the demister assembly.
2 Carry out hydro testing at 20.66 kg/cm2.
3 Remove and service the gauge glasses
Page 5 of 31
9. CBD HDR FROM HGU 2nd block
valve u/s flange 8" 150
10. cooling water return line to RV U/S
valve u/s flange 3/ 150
SR NO DESCRIPTION OF WORK
1 Carry out internal shot blasting and EPOXY painting System 22 as per painting specification
AES 5430.
2 Carry out power brushing of all the weld joints 6 on either side of the weld and carry out
WFMPI testing
3 Carry out repair/ replacement of leaky cooling water coil.
4 Carry out hydro testing at 4.55 kg/cm2.
Page 6 of 31
BLOCK VALVE U/S FLANGE
4. SUSPECT CONDENSATE LINE AT
3" 150
PUMP O/L -2 NOS.
5. VESSEL VENT 2" 150
6. NHGU CONDENDATE LINE FIRST
4" 150
BLOCK VALVE D/S FLANGE
SR NO DESCRIPTION OF WORK
1 Carry out hydro testing at 4.55 kg/cm2.
2 Carry out power brushing of all the weld joints 6 on either side of the weld and carry out
WFMPI testing
TAG NO 133-V-317
SERVICE BEARING CW
SUMP
CONCRETE PIT
Sr. No. X RATING
No. LOCATION SIZE (lbs)
(inch)
1. CDU VDU BCW LINE REVERSE
8 150
SPADE IN PIT
12
2. CDU VDU NEW BCW LINE SPADE 6 150
3. HCU BCW LINE SPADE REVERSE
8 150
SPADE LIST IN PIT
4. NHGU BCW LINE REVERSE
12 150
SPADE IN PIT
5. PUMP 322 A O/L BLOCK VALVE
8 150
D/S FLANGE
6. PUMP 322 B O/L BLOCK VALVE
8 150
D/S FLANGE
7. VESSEL VENT 4 150
SR NO DESCRIPTION OF WORK
1 Carry out internal cleaning of sump and offer for inspection.
TAG NO 133-V-318
SERVICE CRU OFF GAS
KOD
VESSEL ID
HYD TEST 34.98
PR.(Kg/cm2)
Sr. No. X RATING
13 No. LOCATION SIZE (lbs)
(inch)
1. V 318 INLET LINE VESSEL BODY
6" 300
FLANGE
SPADE LIST 2. V 318 OUTLET LINE VESSEL
6" 300
BLOCK VALVE D/S FLANGE
3. V 318 TOP COMMON LINE TO RV
2" 300
FLANGE
4. DRAIN TO CBD COMMON LINE
2" 300
BLOCK VALVE D/S FLANGE
Page 7 of 31
SR NO DESCRIPTION OF WORK
1 Carry out replacement of the demister assembly.
2 Carry out hydro testing at 34.98 kg/cm2.
3 Remove and service the gauge glasses
TAG NO 133-V-
321/322/323/324/3
25/326/327/328/32
9/330
14 SERVICE PSA ADSORBER DRG NO 133-ME-2-38-1
Page 8 of 31
(inch)
1. DM WATER I/L LINE TO VESSEL 1. 150
2. O/L LINE TO P-351 2" 150
3. PUMP DISCHARGE COMMON
LINE TO V-370 2" 150
4. VENT LINE TO ATMOSPHERE 2" 150
5. DRAIN LINE 2" 150
SR NO DESCRIPTION OF WORK
1 Carry out water fill up test
2 Remove and service the gauge glasses
Page 9 of 31
TAG NO 133-V-373 LOCATION HGU
SERVICE AMINE DOSING DRG NO. 133-ME-2-
TANK
VESSEL ID HEIGHT
HYD TEST 35.5
PR.(Kg/cm2)
20 Sr. No. X RATING
No. LOCATION SIZE (lbs)
(inch)
1. DM WATER I/L LINE TO VESSEL 1. 150
SPADE LIST 2. O/L LINE TO P-351 2" 150
3. PUMP DISCHARGE COMMON
LINE TO V-370 2" 150
4. VENT LINE TO ATMOSPHERE 2" 150
5. DRAIN LINE 2" 150
SR NO DESCRIPTION OF WORK
1 Carry out replacement of the entire catalyst. Replace SS wire mesh/screen if found damaged.
2 Carry out power brushing of all the weld joints 6 on either side of the weld and carry out
WFMPI testing
3 Carry out hydro testing of vessel at 35.5 kg/cm2.
Page 10 of 31
(inch)
1. RAW COOLING WATER MAKE UP
LINE I/L VALVE D/S FLANGE 150
2. RECYLE WATER TO TANK I/L
FLANGE TO BE SPADED 2" 150
3. TANK O/L TO P-335 LINE TANK
BODY FLANGE TO BE SPADED 2" 150
4. DRAIN LINE TO OWS 3/4 150
SR NO DESCRIPTION OF WORK
1 Carry out internal scrape cleaning and painting with two coat of CTE paint as per painting
specification AES 5430.
2 Carry out hydro testing of vessel at 9.36 kg/cm2.
Page 11 of 31
4. O/L LINE FROM VESSEL 4 300
SR NO DESCRIPTION OF WORK
1 Carry out replacement of the demister assembly.
2 Carry out hydro testing at 56.1 Kg/ cm2.
3 Remove and service the gauge glasses
Page 12 of 31
TAG NO 133-V-306 LOCATION HGU
SERVICE STEAM DRG NO. 133-ME-2-13
CONDENSATE
FLASH DRUM
Page 13 of 31
Sr. No. X RATING
No. LOCATION SIZE (lbs)
(inch)
1. common i/l line from E-312 3" 600
SPADE LIST 2. top o/l to RV'S common line 2" 600
3. top o/l to vent and balance common
line 2" 600
4. bottom o/l line to LP steam
condensate header 2" 600
SR NO DESCRIPTION OF WORK
1 Carry out hydro testing at 75.0 kg/cm2.
2 Remove and service the gauge glasses
3 Carry out insulation removal for inspection excluding insulation rings as per general scope
and carry out insulation in standard manner
Page 14 of 31
2 Carry out hydro testing at 50.7 kg/cm2.
Page 15 of 31
15 EQUIPMENT NO 133-V-382 Service 2ND STAGE SUCTION
OF 133-K-306
VESSEL ID 0.12 meter HEIGHT/LENGTH 0.3 meter
SR NO DESCRIPTION OF WORK
1 Erect external scaffolding if required and offer vessel for external UT gauging.
2 Carry out hydro testing at 118.9 kg/cm2.
NHGU REACTORS
Part C: -
Following reactors require opening. Carry out spading and
provide external scaffolding wherever required and offer for
external UT gauging. Provide internal scaffolding for internal
visual inspection and repair wherever required. In addition to
the above carry out jobs as mentioned against specific
reactor. (Kindly note that catalyst replacement shall be
carried out by another agency)
Page 16 of 31
mobilize hydraulic torquing machines for measured
tightening of all flanges connected with reactor piping.
4. Minor repairs inside the reactor
5. All mechanical jobs associated with the internal of the
reactor are also included in the scope of work.
Page 17 of 31
SPADED (REVERSE SPECTACLE)
5. R-302A RV BYPASS LINE TO BE 2 600
SPADED (REVERSE SPECTACLE)
6. R-302 A EAST SIDE OF RV'S U/S B/V D/S 3 600
FLANGE TO BE SPADED
7. R-302 A WEST SIDE OF RV'S U/S B/V 3 600
D/S FLANGE TO BE SPADED
8. 3 NOS. SAMPLE POINTS TO BE 2 600
DISCONNECTED AND PROVIDE END
FLANGE
9. 1ST BED O/L SAMPLE POINT ON 2 600
REACTOR BODY TO BE
DISCONNECTED AND PROVIDE END
FLANGE
10. 2nd BED O/L SAMPLE POINT ON 2 600
REACTOR BODY TO BE
DISCONNECTED AND PROVIDE END
FLANGE
11. SAMPLE POINT ON R 302 A O/L LINE 2 600
12. SAMPLE POINTS FLARE LINE TO BE 600
POSITIVELY ISOLATED-3 Nos.
13. 2" N2 STUB LINE AT R-302A O/L TO BE 2 600
SPADED
Page 18 of 31
POSITIVELY ISOLATED-3 Nos.
SR NO DESCRIPTION OF WORK
1 Carry out in situ metallography
Page 19 of 31
TAG NO 133-R-304 LOCATION HGU
SERVICE MEDIUM TEMP SHIFT CONVERTER DRG NO. 133-ME-1-54
Page 20 of 31
LOBS
Part A : Carry out all the jobs on the vessels as per scope of work
detailed in Appendix A attachment 5 including opening of the vessel
and specific jobs detailed against each equipment
TAG NO 132-V-251 LOCATION LOBS
SERVICE FPU VACUUM DRG NO. 132-ME-2-154-1
COLUMN OVHD
DRUM
Page 21 of 31
TAG NO 132-V-252 LOCATION LOBS
SERVICE DW VACUUM DRG NO. 132-ME-2-155-1
COLUMN OVHD
DRUM
Page 22 of 31
HYD TEST 293.6
PR.(Kg/cm2)
Sr. No. X RATING
No. LOCATION SIZE (lbs)
(inch)
1. HHPS FEED INLET 8" 2500 RTJ
SPADE LIST
2. HHPS LIQUID OUTLET 8" 2500 RTJ
3. HHPS VAPOR OUTLET 2" 150
4. HHPS LIQUID OUTLET TO CFBD 2" 150
5. HHPS LIQUID OUTLET TO OWS 1" 150
SR NO DESCRIPTION OF WORK
1 Carry out hydro testing at 293.6 kg/cm2.
2 Remove and service the gauge glasses.
3 Open insulation for CUI excluding insulation rings and UT gauging
Page 23 of 31
1. HHPS SPILL BACK KOD INLET 6 300
2. KOD LIQUID TO CBD 1.5 300
3. KOD DRAIN TO CBD 1.5 150
4. KOD DRAIN TO OWS 1.5 150
5. STEAM OUT STEAM INLET 2 300
6. VAPOR O/L TO HCU MUG
6 300
SUCTION
7. VENT TO ATM 1.5 150
SR NO DESCRIPTION OF WORK
1 Remove and replace the demister assembly.
2 Carry out hydro testing at 30.03 kg/cm2.
3 Remove and service the gauge glasses.
Page 24 of 31
1 Replace the vessel with the new vessel. Shifting of new vessel from warehouse to site and
shifting of old vessel to scrap yard shall be in contractor scope.
2 All the fittings (valves,gauge glasses,etc ) to be removed from old vessel and fitted to new
vessel.
3 Ladder and platform from old vessel to be removed and fitted to new vessel.
2 Remove and service the gauge glasses.
Page 25 of 31
DRUM
VESSEL ID 0.8 meter HEIGHT 2.4 meter
DEMISTER YES DEM DRAWING 132-ME-2-181-2
HYD TEST 10.4
PR.(Kg/cm2)
Sr. No. X RATING
No. LOCATION SIZE (lbs)
(inch)
1. FG KOD O/L 6" 150
2. STEAM OUT STEAM SUPPLY 6" 150
SPADE LIST 3. KOD DRAIN TO FLARE LINE 2" 300
4. KOD DRAIN TO CBD 2" 300
5. KOD DRAIN TO OWS 2" 150
6. KOD VENT TO ATMOSPHERE 2" 150
7. FLARE LINE NEAR VESSEL 2" 300
8. FG KOD O/L 2" 300
SR NO DESCRIPTION OF WORK
1 Remove and replace the demister assembly.
2 Carry out power brushing of all the weld joints 6 on either side of the weld and carry out
WFMPI testing.
3 Carry out internal scrape cleaning and painting as with two coat of CTE paint as per company
painting specification AES 5430
4 Carry out hydro testing at 10.4 kg/cm2.
5 Remove and service the gauge glasses.
6 Carry out insulation removal for inspection including insulation rings as per general scope and
carry out insulation in standard manner.
Page 26 of 31
TAG NO 132-V-283 LOCATION LOBS
SERVICE CLOSED BLOW DRG NO. 132-ME-2-136
DOWN DRUM
VESSEL ID 1.45 meter LENGTH 6 meter
Page 27 of 31
TAG NO 132-V-285 LOCATION LOBS
SERVICE CONGEALING DRG NO. 132-ME-2-183-1
RELIEF BREAK
VESSEL
VESSEL ID 2 meter HEIGHT 5.3 meter
Page 28 of 31
PR.(Kg/cm2)
SR NO DESCRIPTION OF WORK
1 Open top cover, remove and clean filter elements(20 each) by ultrasonic cleaning method
(Refer Annexure I)
2 Fit back the filters after cleaning and box up the top cover.
3 Carry out hydro testing at 23.14 kg/cm2.
REACTORS
For following two nos. reactors in LOBS, all the jobs internal to the reactor
including spading / de-spading catalyst replacement shall be carried out by
another agency as applicable. Your scope includes carrying out the
following
Page 29 of 31
External inspection
1. Remove insulation up to 500 mm from all the nozzle welds and clean the surface,
carry out buffing (6 inches on both sides of weld) and offer for MPT and Phased Array
Ultrasonic Testing (PAUT)
2. Remove insulation up to 500 mm from all circumferential welds and clean the
surface, carry out buffing (6 inches on both sides of weld) and offer for Time of
Flight Diffraction (TOFD).
3. Remove insulation up to 500 mm from all around the skirt attachment weld,
clean the surface, carry out buffing (6 inches on both sides of weld) and offer
for MPT and PAUT.
4. After opening flange joints, clean the ring type gasket joints and offer gasket
and ring grooves for DP testing.
5. Provide scaffolding inside the skirt for inspection of bottom dish end.
Page 30 of 31
WITH COVER
FEED INLET 8-1500# RTJ 1
MANWAY 30-SPECIAL RTJ 1
THERMO 1.5-SPECIAL 5
WELL
Annexure I:
Scope of work for carrying out ultrasonic cleaning of feed filters
The scope of work for cleaning of feed filter through ultrasonic technique comprises of
following points.
1. Filter transportation from refinery to specialized vendor having experience and facility
for ultrasonic cleaning of filters.
2. The cleaning of ultrasonic filters by specified method shall be in your scope.
3. Same shall be brought back to refinery after successful completion of cleaning.
4. The specialized Vendor shall be approved by BPCL technology department.
5. Due care shall be taken for transportation of filter. Shall be transported in wooden
enclosure for support. Utmost care shall be taken for lifting and movement of filter.
6. BPCL OPS/Technology at discretion will witness the filter cleaning if possible and have
right to waive off.
7. BPCL OPS/Technology at discretion may depute the person to carryout visual inspection
of cleaned filters at vendor workplace before dispatch.
Page 31 of 31
ATTACHMENT 11 SECTION F
NHGU :-
Carry out jobs on following spindle operated ejector as per scope of work
detailed below.
131-JA-301
Page 1 of 3
LOBS:-
Carry out jobs on following ejectors as per scope of work detailed in General
scope of work on ejectors given in Appendix A Attachment 6.
Page 2 of 3
Page 3 of 3
ATTACHMENT 11 SECTION G
Carry out servicing of the isolation valves as per scope of work detailed in Appendix- A
Attachment 7
NHGU:-
SR NO LOCATION SIZE RATING QTY
1 MT I/L RSDV 602 18" 300 1
2 LT BYPASS VALVE 14" 300 2
3 MT LT B/P RSDV 604 14" 300 1
4 STEAM TO MIXING POINT U/S OF NRV 14" 600 1
5 STEAM TO MIXING POINT RFC 561 U/S & D/S B/V 10" 600 2
6 S/U STEAM RFC 563 U/S & D/S B/V 6" 600 2
7 PROCESS GAS TO MIXING POINT RFC 557 U/S & D/S
B/V 6" 600 2
8 S/U PROCESS GAS RFC 569 U/S & D/S B/V 3" 600 2
9 EJECTOR PROCESS GAS I/L B/V 10" 900 1
10 EJECTOR JA 301 STEAM I/L B/V 8" 600 2
11 EJECTOR JA 301 O/L B/V 12" 600 2
12 H2 TO HCU RPC-620 A U/S 10" 300 1
13 RSDV-607 U/S B/V 4" 300 1
14 PSA I/L RSDV 608 D/S B/V 14" 300 1
15 STEAM I/L B/V'S OF E-310 A/B 4" 600 2
16 STEAM O/L B/V'S OF E-310 A/B 6" 300 2
17 STEAM I/L B/V'S OF E-311 A/B 10" 600 2
18 STEAM OL B/V'S OF E 311 A/B 10" 600 2
19 E311A & E311B NAPHTHA SIDE O/L VALVE 6" 600 2
20 E311A & E311B NAPHTHA SIDE I/L VALVE 6" 300 2
21 E311B & E311A RV BYPASS D/S VALVE 2" 600 2
22 STEAM DRUM O/L B/V 14" 300 1
23 CCR OFF GAS BATTERY LIMIT BLOCK VALVES
PASSING 6" 300 2
24 IMPURE H2 HEADER B/L B/V 6" 300 3
25 RFC483 RLNG C/V BOTH THE BLOCK VALVES 6" 300 1
26 RFC405/406 C/V BOTH VALVES AND BYPASS
PASSING 2" 300 5
27 RPC501 C/V BYPASS BLOCK VALVE 3" A5A 1
28 RFC564 C/VBYPASS VALVE 2" D5A 1
29 RFC632 C/V BYPASS BLOCK VALVE 3" 600 1
30 RPC628 C/V BYPASS VALVE 8" D2D 1
31 RFC476 C/V D/S block valve 3" 600 1
Page 1 of 2
32 RFC480 C/V both block valves 4" 300 2
33 RFC480 C/V bypass valve 2" 300 1
34 RFC646 C/V both block valve 6" 300 2
LOBS:-
NO OF
SR NO LOCATION SIZE RATING
VALVES
1. C-221 col. bottom Common MOV 6" 150 1
2. P-258A Suction Valve (Bottom pump) 6" 150 1
3. P-258B Suction Valve (Bottom pump) 6" 150 1
4. P-266A Suction Valve (Excess waxy) 8" 150 1
5. P-266B Suction Valve (Excess waxy) 8" 150 1
DW Feed Pump P-259A Suction MOV
6. (Welded)
6" 150 1
DW Feed Pump P-259B Suction MOV
7. (Welded)
6" 150 1
DW Col. Bottom pump P-265A /B Common
8. suction valve MOV
6" 150 1
9. DW Col. Bottom pump P-265A suction valve 6" 150 1
10. DW Col. Bottom pump P-265B suction valve 6" 150 1
P-264A Suction valve (C-225 LT LUBE S/C
11. Stripper)
2" 150 1
P-264B Suction valve (C-225 LT LUBE S/C
12. stripper)
2" 150 1
13. Inlet to CBD Vessel V-283 (Underground) 6" 150 1
14. Inlet to CBD Vessel V-283 (Underground) 6" 150 1
15. Inlet to CFBD Vessel V-284 (Underground) 8" 150 1
16. Inlet to CFBD Vessel V-284 (Underground) 8" 150 1
17. Inlet to OWS Vessel AU-282 (Underground) 10" 150 1
18. Inlet to OWS Vessel AU-282 (Underground) 10" 150 1
Page 2 of 2
ATTACHMENT 11 SECTION H
Carry out jobs on following relief valves as per scope of work detailed in
Appendix- A Attachment 8
NHGU:-
Page 1 of 5
24 133RPSV1654A MP Steam Import / Export 6" x 10" 21 -
25 133RPSV1654B MP Steam Import / Export 6" x 10" 21 -
26 133RPSV1658A Steam Cond. Flash Drum, 6" x 8" 6.5 -
133-V-306
27 133RPSV1658B Steam Cond. Flash Drum, 6" x 8" 6.5 -
133-V-306
28 133RPSV1673A BFW Dearator, 133-V-305 6" x 8" 3.5 -
29 133RPSV1673B BFW Dearator, 133-V-305 6" x 8" 3.5 -
30 133RPSV2010 133-E-312A to Fuel Naphtha 2" x 3" 6.06 1.7
KOD
31 133RPSV2012 133-E-312B to Fuel Naphtha 2" x 3" 6.06 1.7
KOD
32 133RPSV2030A Emergency H2 Drum, 133-V- 1.5" x 3" 222.2 1.7
311
33 133RPSV2030B Emergency H2 Drum, 133-V- 1.5" x 3" 222.2 1.7
311
34 133RPSV2031A Emergency H2 Drum, 133-V- 1.5" x 3" 50 1.7
311 O/L.
35 133RPSV2031B Emergency H2 Drum, 133-V- 1.5" x 3" 50 1.7
311 O/L.
36 133RPSV2043 Silencer Disch. 3/4"X 1" 7 -
37 133RPSV2052 CWR From 133-E-317 3/4"X 1" 7 -
38 133RPSV2034 2nd Stage Disch. 133-K-304A 1.5" x 2" 43.01 1.7
39 133RPSV2035 2nd Stage Disch. 133-K-304A 1.5" x 2" 43.01 1.7
40 133RPSV2064 Outlet of 133-V-366/367 ( 1" x 2" 14.65 -
Pulse Dampener for 133-K-
304A/B)
41 133RPSV2101 1st Stage Disch. 133-K-304A 1.5" x 3" 37.32 1.7
42 133RPSV2102 1st Stage Diisch. 133-K-304B 1.5" x 3" 37.32 1.7
43 133RPSV2103 1st Stage Diisch. 133-K-304A 1" x 2" 24.2 1.7
44 133RPSV2104 1st Stage Diisch. 133-K-304B 1" x 2" 24.2 1.7
45 133RPSV2105 2nd Stage Disch. 133-K-304A 1" x 2" 38.95 1.7
46 133RPSV2106 2nd Stage Disch. 133-K-304B 1" x 2" 38.95 1.7
47 133RPSV2107 133-K-304A Lube Oil Pump 3/4" X 5.9 -
133-P-333 Disch. 1.5"
48 133RPSV2108 133-K-304B Lube Oil Pump 3/4" X 5.9 -
133-P-333 Disch. 1.5"
49 133RPSV2109 133-K-304A Lube Oil Pump 3/4" X 5.9 -
133-P-331 Disch. 1.5"
Page 2 of 5
50 133RPSV2110 133-K-304B Lube Oil Pump 3/4" X 5.9 -
133-P-332 Disch. 1.5"
51 133RPSV2113 1st Stage Cylinder of 133-K- 3/4" X 1" 7 -
304A
52 133RPSV2114 1st Stage Cylinder 133-K- 3/4" X 1" 7 -
304B
53 133RPSV2117 2nd Stage Cylinder of 133-K- 3/4" X 1" 7 -
304A
54 133RPSV2118 2nd Stage Cylinder of 133-K- 3/4" X 1" 7 -
304B
55 133RPSV2121 Outlet of 133-E-335 (Inter 3/4" X 1" 7 -
stage Cooler for 133-K-304A)
56 133RPSV2122 Outlet of 133-E-336 (Inter 3/4" X 1" 7 -
stage Cooler for 133-K-304B)
57 133RPSV2123 Outlet of 133-E-337 (Spill Back 3/4" X 1" 7 -
Cooler)
58 133RPSV2124 Outlet of 133-E-331 (Oil 3/4" X 1" 7 -
Cooler for K-304A)
59 133RPSV2125 Outlet of 133-E-332 (Oil 3/4" X 1" 7 -
Cooler for 133-K-304B)
60 133RPSV2126 Outlet of 133-E-333A (Water 3/4" X 1" 7 -
Cooler for 133-K-304A)
61 133RPSV2127 Outlet of 133-E-333B (Water 3/4" X 1" 7 -
Cooler for 133-K-304B)
62 133RPSV2128 N2 Purging for Cylinder 1" X 2" 0.71 -
63 133RPSV2129 N2 Purging for Cylinder 1" X 2" 0.71 -
64 133RPSV2130 N2 Purging for Cylinder 1" X 2" 0.85 -
65 133RPSV2131 N2 Purging for Cylinder 1" X 2" 0.85 -
66 133RPSV413 133-K-304A Lube Oil Pump 0.5" x 1" 3.4 -
133-P-333 Disch.
67 133RPSV414 133-K-304B Lube Oil Pump 0.5" x 1" 3.4 -
133-P-334 Disch.
68 133RPSV420 133-K-304A Lube Oil Pump 0.5" x 1" 3.4 -
133-P-331 Disch.
69 133RPSV13 133-V-321 1.5"x 2" 25.76 1.7
70 133RPSV23 133-V-322 1.5"x 2" 25.76 1.7
71 133RPSV33 133-V-323 1.5"x 2" 25.76 1.7
72 133RPSV43 133-V-324 1.5"x 2" 25.76 1.7
73 133RPSV53 133-V-325 1.5"x 2" 25.76 1.7
Page 3 of 5
74 133RPSV63 133-V-326 1.5"x 2" 25.76 1.7
75 133RPSV73 133-V-327 1.5"x 2" 25.76 1.7
76 133RPSV83 133-V-328 1.5"x 2" 25.76 1.7
77 133RPSV93 133-V-329 1.5"x 2" 25.76 1.7
78 133RPSV03 133-V-330 1.5"x 2" 25.76 1.7
LOBS:-
Carry out jobs on following rupture disc as per scope of work detailed in
Appendix- A Attachment 8
Carry out jobs on following relief valves as per scope of work detailed in
Appendix- A Attachment 8
Page 4 of 5
13 132-BPSV-1720A 132-V-256 4" x 6" 23.1 1.8
14 132-BPSV-1720B 132-V-256 4" x 6" 23.1 1.8
15 132-BPSV-1722A 132-V-254 1 1/2"x2" 182.4 1.8
16 132-BPSV-1722B 132-V-254 1 1/2"x2" 182.4 1.8
17 132-BPSV-1723 132-F-206,BFW LINE 1" x 2" 35.7 -
18 132-BPSV-1724 132-F-206,BFW LINE 1" x 2" 35.7 0
19 132-BPSV-1725 132-F-205,SUPERHEATER 2 1/2"x4" 21.6 -
O/L
20 132-BPSV-1726 132-F-205,SUPERHEATER 2 1/2"x4" 21.6 -
O/L
21 132-BPSV-1727 132-F-206,SUPERHEATER 2 1/2" x 4" 21.6 -
O/L
22 132-BPSV-1728 132-F-206,SUPERHEATER 2 1/2" x 4" 21.6 -
O/L
23 132-BPSV-1730A 132-V-271 2 1/2"x4" 21 -
24 132-BPSV-1730B 132-V-271 2 1/2"x4" 21 -
25 132-BPSV-1731A 132-G-204 A ,FILTER I/L 1" x 2" 17.8 1.8
26 132-BPSV-1731B 132-G-204 A ,FILTER I/L 1" x 2" 17.8 1.8
27 132-BPSV-1734 132-X-253,LP STEAM LINE 4" x 6" 6.5 -
28 132-BPSV-1903 132-X-254, LP STEAM 3" x 4" 6.5 -
29 132-BPSV-1904 132-X-255, LP STEAM 3" x 4" 6.5 -
Page 5 of 5
ATTACHMENT 11 SECTION I
NHGU:-
Offer all the following process piping for comprehensive inspection as per scope of work detailed
in Appendix A Attachment 9,
1. Lift the pipe lines at support location and offer for inspection. Carry out welding of support
pads as indicated below. All Cold pads to be removed and replaced with welded pads.
Scope shall include fabrication of the pad , lifting of the line at support location , insertion of
the pad , complete welding , pneumatic testing of the pad weld through tale tell hole and
finally plugging of the holes.
2. Carry out necessary repair as per the inspection finding and offer hydro testing of the line at
specified pressure. Repair of the line shall be paid as per the applicable SOR.
Page 1 of 27
SR LINE DESCRIPTION LINE NOS. Support HYD.
no pads PR.
(Nos.) Kg/cm2
g
1 RLNG feed 8/6-P-133-1131-B5A 4+8 36.0
cold pads
exist
2 Fuel RLNG 4-FG-133-4511-B1A 2 + 4cold 36.0
pads
exist
3 CCR off gas 6-P-133-1103-B5A - 36.0
4 Fuel Vap Naptha 3/4-FG-133-1920-A5A 4 18.0
5 133- EA- 302 process gas 8/12/16-P-133-1821- 4( 8 SS 36.0
outlet B54K pads) (DM
16-P-133-1822-B54K water)
6 10 dia Hydrogen line from 10-P-133-1921-B5A 8 36.0
PSA to HCU up to HGU 10-P-133-1925-B5A
Battery limit. 6-P-133-1923-B5A
3-P-133-1922-B5A
6-P-133-1951-B5A
7 4 FG line from 133-V-309 4-P-133-3403-A29A-IJ _ 18.0
to Reformer Furnace 133-f- 2-P-133-3405-A29A-IJ
301 2-P-133-3406-A29A-IJ
8 6 / 4 / 2 Naphtha lines 6-FG-133-3428-A29A- _ 18.0
from 133-V-304 to IJ
Reformer heater burners. and all connected 4
and 2 dia lines up to
burners.
9 Flare header and 0.5(Pne
connected piping umatic
)
Offer all the process lines (Insulated / Bare) inside the battery limit for comprehensive inspection.
For column overhead lines, make Bosuns chair arrangement for taking wall thickness
measurements.
Based on the RBI analysis and operating temperature, piping circuits have been
grouped in three tables. Following are the table description:
Table A: Insulated lines whose operating temperature falls in CUI range i.e. below
120 Deg C. For external inspection of these lines, insulation shall be
opened in following manner.
Vertical section: 1 meter Insulation band shall be opened after every 10
meters of straight length. Insulation shall also be opened at all the
Page 2 of 27
branches, support locations, elbows, T sections, reducers, drains and
vents.
Horizontal section: 1 meter insulation band shall be opened at every
support location. Insulation shall also be opened at all the branches,
elbows, T sections, reducers, drains and vents.
Table C: Bare pipe lines. Lift the pipe line at beam support locations and offer for
inspection.
Sr.
MR loop Pipe Size Circuit From Circuit To
No
DHDS/NHGU/00
1 9V(Line3"-WB- 3" Pipe 133-E-314 A-C 133-V-305
3228-D1A-IH)
DHDS/NHGU/00
MP STEAM
2 9W(Line1.5"-WB- 1.5" Pipe 133-314 A-C
HEADER
3002-D2A-IH)
DHDS/NHGU/00
Tube-side outlet of Inlet of 133-EA-
3 5B(Line16"-P- 16" Pipe
133-E-308 302
1811-B54K-IH)
DHDS/NHGU/00
DHDS/NHGU/008
4 1D(Line6"-P- 6" Pipe 133-E-310 A/B
H
1102-B5A-IH)
DHDS/NHGU/00
133-E-303
5 5G(Line14"-P- 3" Pipe 133-C-302
QUENCH
1941-B5A-IT )
Sr.
MR loop Pipe Size Circuit From Circuit To
No
DHDS/NHGU/00
1 1E(Line6"-P- 6" Pipe 133-E-310A/B 133-E-311
1111-B5A-IH)
DHDS/NHGU/00
2 1F(Line6"-P- 6" Pipe 133-E-311 A/B 133-R-301
1121-D5D-IH)
DHDS/NHGU/00
3 2A(Line6"-P- 6" Pipe 133-R-301 133-R-302A/B
1211-D5D-IH)
Page 3 of 27
DHDS/NHGU/00
4 2B(Line6"-P- 6" Pipe 133-R-302A/B 133-E-302
1250-D5D-IH)
DHDS/NHGU/00
5 2C(Line16"-P- 16" Pipe 133-E-302 133-R-303
1411-D5E-IH)
DHDS/NHGU/00
6 2D(Line16"-P- 16" Pipe 133-R-303 133-E-301
1430-D5E-IH)
DHDS/NHGU/00
7 2E(Line16"-P- 16" Pipe 133-E-301 Reformer tubes
1441-F51M-IH)
DHDS/NHGU/00
F-301 reformer Tube-side inlet of
8 3A(Line12"-P- 12" Pipe
tube outlets EW-301
1501-F51M)
DHDS/NHGU/00
9 4A(Line18"-P- 18" Pipe 133-EW-301 133-E-305 A/B
1601-B5D-IH)
DHDS/NHGU/00
DHDS/NHGU/004 DHDS/NHGU/00
10 4B(Line10"-P- 10" Pipe
A 4C
1602-B5D-IH)
DHDS/NHGU/00
11 4C(Line18"-P- 18" Pipe 133-E-305A/B 133-R-304
1611-B5D-IH)
DHDS/NHGU/00
12 4D(Line18"-P- 18" Pipe 133-R-304 133-E-306
1721-B5D-IH)
DHDS/NHGU/00
DHDS/NHGU/004 DHDS/NHGU/00
13 4E(Line10"-P- 10" Pipe
D 4F
1722-B5D-IH)
DHDS/NHGU/00
14 4F(Line18"-P- 18" Pipe 133-E-306 133-R-305
1723-B5D-IH)
DHDS/NHGU/00
15 4G(Line18"-P- 18" Pipe 133-R-305 133-E-307 A/B
1731-B5D-IH)
DHDS/NHGU/00
Shell-side outlet of Tube-side inlet of
16 5A(Line16"-P- 16" Pipe
133-E-307A/B 133-E-308
1741-B54K-IH)
DHDS/NHGU/00
17 5F(Line2"-P- 2" Pipe 133-E-314 A-C 133-C-302
3201-D1K-IH)
DHDS/NHGU/00
18 8I(Line6"-FG- 6" Pipe 133-E-312 A/B 133-V-304
3411-A29A-IJ)
Page 4 of 27
DHDS/NHGU/00
19 8J(Line6"-FG- 6" Pipe 133-V-304 133-F-301
3421-A29A-IJ)
DHDS/NHGU/00
20 8N(Line4"-P- 4" Pipe 133-C-301 133-V-309
3403-A2A-IH f)
DHDS/NHGU/00
21 8O(Line4"-P- 4" Pipe 133-V-309 PSA UNIT
3403-A29A-ij )
DHDS/NHGU/00
22 9B(Line6"-WDM- 6" Pipe 133-E-308 133-V-305
3101-A1K-IH)
DHDS/NHGU/00
23 9C(Line6"-WB- 6" Pipe 133-V-305 133-E-307 A/B
1703-D2A-IH)
DHDS/NHGU/00
24 9D(Line4"-WB- 4" Pipe 133-E-307 A/B 133-E-305 A/B
1603-D2A-IH)
DHDS/NHGU/00
25 9E(Line6"-WB- 6" Pipe 133-E-305 A/B 133-V-301
1612-D2A-IH)
DHDS/NHGU/00
DHDS/NHGU/00
26 9F(Line1.5"-SH- 1.5" Pipe 133-V-301
9G
3011-D2A-IH)
DHDS/NHGU/00
27 9G(Line1.5"-BD- 1.5" Pipe 133-EW-301 133-E-304
1602-D2A-IH)
DHDS/NHGU/00
28 9H(Line1.5"-SH- 1.5" Pipe 133-E-304 133-EW-301
3010-D2A-IH)
DHDS/NHGU/00
DHDS/NHGU/009
29 9I(Line3"-BD- 3" Pipe 133-V-301
H
1302-D2A-IH)
DHDS/NHGU/00
30 9J(Line4"-SH- 4" Pipe 133-V-301 133-C-302
3201-D2A-IH)
DHDS/NHGU/00
31 9K(Line3"-BD- 3" Pipe 133-V-301 133-V-303
1605-D2A-IH)
DHDS/NHGU/00
32 9L(Line1.5"-BD- 1.5" Pipe 133-V-303 133-E-313
1611-A1A-IH)
DHDS/NHGU/00
9M(Line6"-SL- DHDS/NHGU/00
33 6" Pipe 133-V-303
1601-A2A-IH) 9N
Page 5 of 27
DHDS/NHGU/00
LP STEAM
34 9N(Line10"-SL- 10" Pipe 133-V-305
HEADER
3101-A2A-IH)
DHDS/NHGU/00
35 9O(Line6"-CL- 6" Pipe 133-V-306 133-V-305
1302-A1A-IH)
DHDS/NHGU/00
DHDS/NHGU/00
36 9P(Line8"-SL- 8" Pipe 133-V-306
9N
3014-A2A-IH)
DHDS/NHGU/00
37 9Q1(Line6"-CL- 6" Pipe 133-V-310 133-V-306
1101-D2A-IH)
DHDS/NHGU/00
38 9Q2(Line3"-CL- 3" Pipe 133-V-312 133-V-306
3401-A2A-IH)
DHDS/NHGU/00
39 9R1(Line6"-CH- 6" Pipe 133-E-310 A/B 133-V-310
1101-D2A-IH)
DHDS/NHGU/00
40 9R2(Line3"-CH- 3" Pipe 133-E-312 A/B 133-V-312
3401-D2A-IH)
DHDS/NHGU/00
133-E-310 A/B &
41 9S(Line4"-SH- 4" Pipe 133-V-301
312 A/B
1101-D2A-IH)
DHDS/NHGU/00
DHDS/NHGU/009
42 9T(Line12"-SH- 12" Pipe 133-E-303
S
3001-D2A-IH)
DHDS/NHGU/00
43 9U(Line3"-WB- 3" Pipe 133-C-302 133-E-314 A-C
3201-D1A-IH)
DHDS/NHGU/00
MP STEAM
44 9X(Line14"-SH- 14" Pipe 133-E-303
HEADER
1411-D2D-IH)
DHDS/NHGU/00
MP STEAM
45 9Y(Line10"-SH- 10" Pipe 133-E-311 A/B
HEADER
3016-D2D-IH)
DHDS/NHGU/00
46 9Z(Line10"-SH- 10" Pipe 133-E-311 A/B 133-JA-301
1130-D2D-IH)
DHDS/NHGU/01
DHDS/NHGU/00
47 3A(Line6"-P- 6" Pipe 133-E-318
1D
1291-B5A-IH)
DHDS/NHGU/01
133-E- DHDS/NHGU/00
48 3B(Line10"-IG- 10" Pipe
315/317/318 4C
3651-A1A-IH)
Page 6 of 27
Table C (Bare line)
Sr.
MR loop Pipe Size Circuit From Circuit To
No
DHDS/NHGU/00
1 1A(Line2"-P- 2" Pipe B/L (NAT. GAS) 133-V-311
3542-F5A)
DHDS/NHGU/00
DHDS/NHGU/00
2 1B(Line2"-P- 2" Pipe 133-V-311
1D
3561-F5A)
DHDS/NHGU/00
3 1C(2"-P-133- 2" Pipe P-301 Mixing Point
1042-DIA )
DHDS/NHGU/00
Outlet of 133-EA- Shell-side inlet of
4 5C(Line16"-P- 16" Pipe
302 133-E-309A/B
1821-B54K)
DHDS/NHGU/00
Shell-side outlet of
5 5D(Line16"-P- 16" Pipe 133-V-302
133-E-309A/B
1831-B54K)
DHDS/NHGU/00
6 5E(Line2"-P- 2" Pipe 133-V-302 133-E-314 A-C
1875-D1K)
DHDS/NHGU/00
B/L (CRU OFF
7 6A(Line10"-P- 10" Pipe Outlet of PSA
GAS)
1921-B5A)
133-V-
DHDS/NHGU/00
321/322/323/324/
8 6B(Line8"-P- 8" Pipe Piping
325/326/327/328/
2122-B5A)
329/330
D/S of Diverter
valve of
DHDS/NHGU/00
133-V-
9 7A(Line18"-FG- 18" Pipe 133-V-335
321/322/323/324/3
2125-A5A)
25/326/327/328/32
9/330
DHDS/NHGU/00
10 7B(Line30"-FG- 30" Pipe 133-V-335 133-F-301
1911-A5A)
DHDS/NHGU/00
11 8A(Line4"-P- 4" Pipe B/L (SRUN) 133-C-301
1002-A1A)
DHDS/NHGU/00
12 8B(Line4"-P- 4" Pipe B/L (HCLN) 133-C-301
1002-A1A)
Page 7 of 27
DHDS/NHGU/00
13 8C(Line4"-P- 4" Pipe B/L (HCN) 133-C-301
1002-A1A)
DHDS/NHGU/00
14 8D(Line4"-P- 4" Pipe B/L (HAN) 133-C-301
1002-A1A)
DHDS/NHGU/00
15 8E(Line4"-P- 4" Pipe B/L (RAFFINATE) 133-C-301
1002-A1A)
DHDS/NHGU/00
DHDS/NHGU/001
16 8F(Line3"-P- 3" Pipe 133-C-301
A
1002-A1A)
DHDS/NHGU/00
17 8G(Line4"-P- 4" Pipe 133-V-302 133-C-301
1011-A5A)
DHDS/NHGU/00
18 8H(Line2"-P- 2" Pipe 133-C-301 133-E-312 A/B
1033-A1A)
DHDS/NHGU/00
19 8K(Line30"-FG- 30" Pipe PSA UNIT 133-F-301
1522-A5A-IH)
DHDS/NHGU/00 DHDS/NHGU/00
20 4" Pipe 133-E-342 T/S
8L 8H
DHDS/NHGU/00
21 4" Pipe B/L(NAT GAS) 133-E-342 T/S
8M
DHDS/NHGU/00
22 9A(Line6"-WDM- 6" Pipe B/L(DMW) 133-E-308
1801-A1K)
DHDS/NHGU/01
23 0A(Line8"-WCS- 8" Pipe CW HEADER 133-E-309A
3707-A5Y)
DHDS/NHGU/01
24 0B(Line3"-WCS- 3" Pipe CW HEADER 133-E-313
3706-A5Y)
DHDS/NHGU/01
DHDS/NHGU/00
25 2A(Line1"-C- 1" Pipe 133-V-307
1E
1081-B1K)
DHDS/NHGU/01
26 2B(Line1.5"-C- 1.5" Pipe 133-V-372 133-V-305
3101-A1K)
DHDS/NHGU/01
2C(Line1.5"-C-
DHDS/NHGU/00
27 3343-A1K) 1.5" Pipe 133-V-372
9C
Page 8 of 27
DHDS/NHGU/01
28 2D(Line1.5"-C- 1.5" Pipe 133-V-373 133-C-302
3217-D1K)
DHDS/NHGU/01
29 2E(Line1.5"-C- 1.5" Pipe 133-V-371 133-V-305
3102-A1K)
DHDS/NHGU/01
DHDS/NHGU/00
30 2F(Line1"-C- 1" Pipe 133-V-371
9C
3373-A1K)
DHDS/NHGU/01
31 2G(Line1"-C- 1" Pipe 133-V-370 133-V-301
3371-A1K)
OTHER LINES
Page 9 of 27
D) UNDERGROUND PIPING
In order to assess the condition of coating of under ground lines, excavation at 5
nos selected locations shall be carried out prior to shutdown / during shutdown.
After inspection, carry out back filing and PCC as existing.
E) MISC JOBS
1. Replace the fire affected main vertical column ISMB 500 built up section at
south-west corner of 133-R-302B after providing temporary support for height
about 3.6 m from 1m above fourth floor level .Design and drawing for temporary
support shall be made and submitted to BPCL for approval. Detailed
Methodology for replacement of beam shall be prepared and approved by Area
Incharge /Drawing office prior to carrying out the job.
2. Carry out insitu machining of following flanges (both sides) after groove filling and
opening of the flange/valve. After machining tighten the flange with new gasket.
LOBS:-
Offer all the following process piping for comprehensive inspection as per scope of work detailed
in Appendix A Attachment 9, carry out necessary repair as per the inspection finding and offer
hydro testing of the line at specified pressure. Repair of the line shall be paid as per the
applicable SOR.
Page 10 of 27
6"/3" dia fuel gas line from battery limit to 6"-FG-132-6550-1A3A 18.0
1
plant header. 3"-FG-132-6550-1A3A
Offer all the process lines (Insulated / Bare) inside the battery limit for comprehensive inspection
as per scope of work detailed in Appendix A Attachment 9. For column overhead lines, make
Bosuns chair arrangement for taking wall thickness measurements.
Based on the RBI analysis and operating temperature, piping circuits have been
grouped in three tables. Following are the table description:
Table A: Insulated lines whose operating temperature falls in CUI range i.e. below
120 Deg C. For external inspection of these lines, insulation shall be
opened in following manner.
Vertical section: 1 meter Insulation band shall be opened after every 10
meters of straight length. Insulation shall also be opened at all the
branches, support locations, elbows, T sections, reducers, drains and
vents.
Horizontal section: 1 meter insulation band shall be opened at every
support location. Insulation shall also be opened at all the branches,
elbows, T sections, reducers, drains and vents.
Page 11 of 27
Table B:High temperature insulated lines. For external inspection of pipeline,
pockets for UT gauging shall be opened at all elbow locations, Tees and
at every 10 meters in straight sections.
Table C: Bare pipe lines. Lift the pipe line at beam support locations and offer for
inspection.
Page 12 of 27
6 132-MR-108 4-P132-2550-1A3A-IT From Tankage to 132-
(Waxy Feed to F- G-204
205)
4-P132-2551-1A3A-IT From 132-G-204 to
132-E-253 S/S
7 132-MR-110 (DW 1-P-132-2955-8G1C4-IH From Line 2955 to line
Reactor Feed and 2956/2957
Effluent stream)
3-P-132-2952-8G1C4-IH From Line 2951 to
132-R-204
Page 13 of 27
10 132-MR-114 (Hot 4-P-132-3252-7A3B3- From 132-E-256 T/S
Hydrogen Gas) IH(Loop-114) to 132-E-254 T/S
11 132-MR-115 1.5-PZ-132-3452-2A3B3- From 132-V-256 to
(HHPS cold IH CBD header and 132-
vapour) 6-P-132-3453-2A3B3-IH V-228
Page 14 of 27
From Line 4252 to
1.5-P-132-4254-2A3A-IH 132-C-225 Bottoms
15 4/ 3 / 2
Hydrogen
quench gas line.
16 1.5 dia Startup
hydrogen to
HLPS
17 1.5 dia Cold
warm up oil from
132-E-226.
18 1.5 dia Hot
warm up oil to
132-P-265.
19 1 dia W-500N
sample point/
analyzer.
20 1 dia W-100N
sample point/
analyzer.
21 1 dia W-150N
sample point/
analyzer.
22 2 dia RV inlet Remove insulation
line of 132-G- up to 2 m from both
204A/B DW RVs and RV bypass
Feed filter line.
23 Remove insulation
2 dia RV inlet
from isolation valve
line of 132-V-
up to both RVs and
254 DW HHPS
RV bypass line.
24 Remove insulation
4 dia RV inlet
up to 2 m from both
line of 132-V-
RVs and RV bypass
255 DW HLPS
line.
25 6 dia RV inlet Remove insulation
line of 132-V- up to 2 m from both
256 DW HHPS RVs and RV bypass
Vapour KOD line.
Page 15 of 27
Table B - Insulated Lines Above CUI Range
Sr No Corrosion Loop Piping Description From and To
1 132-MR-101 (FPU 4-P-132-1351-2A5A-IT. From Line 1350 to
Feed) 132-F-204.
Page 16 of 27
132-MR-104 (Top 4-P-132-1852-2A3A-IT From Line 1851 to
side cut pump- Line 132-P-266A/B
around from FPU
column (132-C-
221))
132-MR-104 (Top 4-P-132-1859-1A3A-IT From Line 1857/1858
side cut pump- to 132-V-253
around from FPU
column (132-C-
221))
132-MR-104 (Top 6-P-132-1457-1A3A-IT From line 132-EA-
side cut pump- 221A/B/C/D TS to
around from FPU 132-G-205A/B
column (132-C-
221))
132-MR-104 (Top 6-P-132-1853-2A3A-IT From Line 1850 to
side cut pump- Line 132-G-206A/B
around from FPU
column (132-C-
221))
132-MR-104 (Top 8-P-132-1851-2A3A-IT From Line 1850 to
side cut pump- Line 1852/1854
around from FPU
column (132-C-
221))
132-MR-104 (Top 8-P-132-1854-2A3A-IT From Line 1851 to
side cut pump- Line E-261
around from FPU
column (132-C-
221))
132-MR-104 (Top 8-P-132-1855-2A3A-IT From Line 1851 to
side cut pump- Line 132-EA-
around from FPU 221A/B/C/D T/S
column (132-C-
221))
4 132-MR-105 8-P-132-1452-2A3A-IT From Line 132-C-221
(Waxy 100N side to 132-P-254A/B.
cut from FPU 6-P-132-1950/1952- From Line 132-P-
column C-221) 2A3A-IT. 254A/B to 132-G-207
A/B.
.
6-P-132-1458-2A3A-IT From Line 132-G-207
A/B to 132-C-221
above Bed 4
Page 17 of 27
254A/B
top to 132-C-222
Top.
Page 18 of 27
132-MR-106 4-P-132-2051-2A5A-IT From line 2050 to
(Waxy 150N side 132-C-223
cut from FPU
column C-221)
132-MR-106 4-P-132-2053-2A5A-IT From line P-256A/B
(Waxy 150N side to 132-G-209 A/B
cut from FPU
column C-221)
132-MR-106 4-P-132-2056-2A3A-IT From line 132-P-
(Waxy 150N side 257A/B to line 2057
cut from FPU
column C-221)
132-MR-106 6-P-132-1558-2A5A-IT From line 132-G-
(Waxy 150N side 208A/B to 132-C-221
cut from FPU above Bed 3
column C-221)
132-MR-106 6-P-132-1559-2A5A-IT From line 132-G-209
(Waxy 150N side A/B to 132-C-221
cut from FPU above Bed 2
column C-221)
132-MR-106 6-P-132-2052-2A5A-IT From line 2051 to E-
(Waxy 150N side 260
cut from FPU
column C-221)
132-MR-106 6-P-132-2055-2A3A-IT From line 132-C-223
(Waxy 150N side to 132-P-257A/B
cut from FPU
column C-221)
132-MR-106 6-P-132-2451-2A5A From line 2052 to
(Waxy 150N side 132-E-260 T/S
cut from FPU
column C-221)
132-MR-106 6-P-132-2452-2A5A-IT From line 132-E-260
(Waxy 150N side T/S to 132-G-208A/B
cut from FPU
column C-221)
132-MR-106 6-P-132-2453-2A5A-IT From line 2052 to
(Waxy 150N side line 2452
cut from FPU
column C-221)
132-MR-106 8-P-132-2050-2A5A-IT From line 132-P-
(Waxy 150N side 256A/B to line
cut from FPU 2051/2052
column C-221)
Page 19 of 27
6 132-MR-107 (FPU 3-P-132-1655-2A5A-IT From Line 1650 to
Vacuum Column 132-E-252 T/S
Bottom)
132-MR-107 (FPU 3-P-132-1657-2A5A-IT From Line1662 to
Vacuum Column 132-P-256A/B
Bottom)
132-MR-107 (FPU 3-P-132-1658-2A5A-IT From Line1662 to
Vacuum Column 132-P-254A/B
Bottom)
132-MR-107 (FPU 3-P-132-1659-2A5A-IT From Line1662 to
Vacuum Column 132-P-253A/B
Bottom)
132-MR-107 (FPU 3-P-132-1661-2A5A-IT From Line1650 to
Vacuum Column 132-C-221
Bottom)
132-MR-107 (FPU 3-P-132-2250-2A5A-IT From 132-E-252 T/S
Vacuum Column to 132-EA-223 T/S
Bottom)
132-MR-107 (FPU 4-P-132-1650-2A5AIT From line 132-P-
Vacuum Column 258A/B to line 1651
Bottom)
132-MR-107 (FPU 4-P-132-1651-2A5AIT From line 1650 to
Vacuum Column line 1652
Bottom)
132-MR-107 (FPU 4-P-132-1652-2A5AIT From line
Vacuum Column 1651/1957/2059 to
Bottom) line 1653
132-MR-107 (FPU 4-P-132-1656-2A5A-IT From Line 132-P-258
Vacuum Column A/B to 132-F-204
Bottom)
132-MR-107 (FPU 4-P-132-1662-2A5A-IT From Line 132-P-
Vacuum Column 258B to Line
Bottom) 1657/1658/1659
132-MR-107 (FPU 6-P-132-1557-2A5A-IT From line 132-C-221
Vacuum Column to 132-P-258A/B
Bottom)
132-MR-107 (FPU 6-P-132-1654-2A3A-IT From 132-P-266A/B
Vacuum Column to Stream going to
Bottom) HCU
132-MR-107 (FPU 6-P-132-1660-2A3A-IT From Line1654 to
Vacuum Column 132-F-204
Bottom)
132-MR-107 (FPU 8-P-132-1653-2A3A-IT From Line 1652/1852
Vacuum Column to line 132-P-266A/B
Bottom)
Page 20 of 27
7 132-MR-108 3-P132-2654-1A3A-IT From Line 2659 to
(Waxy Feed to F- 132-C-221
205)
132-MR-108 3-P132-2655-1A3A-IT From Line 2659 to
(Waxy Feed to F- 132-P-253A/B
205)
132-MR-108 3-P132-2656-1A3A-IT From Line 2659 to
(Waxy Feed to F- 132-C-225
205)
132-MR-108 3-P132-2657-1A3A-IT From Line 2659 B/I
(Waxy Feed to F- to HCU to 132-P-
205) 265B
132-MR-108 3-P132-2658-1A3A-IT From Line 2659 to
(Waxy Feed to F- 132-P-262A/B
205)
132-MR-108 3-P132-2753-1A3A-IT From 132-P-259A/B
(Waxy Feed to F- to Line 2552 I/L of
205) 132-V-253
132-MR-108 3-P132-3853-2A3A-IT From 132-P-265A to
(Waxy Feed to F- Line 2550 Inlet of
205) 132-G-204
132-MR-108 4-P132-1859-1A3A-IT From 132-EA-221
(Waxy Feed to F- T/S to Line 2653 Inlet
205) of 132-V-253
132-MR-108 4-P132-2552-1A3A-IT From 132-E-253 S/S
(Waxy Feed to F- to 132-V-253
205)
132-MR-108 4-P132-2651-1A3A-IT From line 2650 to
(Waxy Feed to F- 132-C-225
205)
132-MR-108 4-P132-2652-1A3A-IT Line 1859 O/L of
(Waxy Feed to F- 132-E-260 T/S to
205) 132-C-225 to Slops
header
132-MR-108 4-P132-2653-1A3A-IT From Line 1859 O/L
(Waxy Feed to F- of 132-E-260 T/S and
205) I/L of 132-V-253 to
line 2552
132-MR-108 4-P132-2659-1A3A-IT From Line 6108 to
(Waxy Feed to F- Line
205) 2654/55/56/57/58
132-MR-108 4-P132-2750-8A3A-IT From 132-P-259A/B
(Waxy Feed to F- to FV-738 Upstream
205) of 132-E-254 T/S
Page 21 of 27
132-MR-108 4-P-132-2850-8B3B3-IT From line 2750 to
(Waxy Feed to F- 132-P-259 o/l
205)
132-MR-108 4-P-132-2855-8B3B3-IT From 132-E-254
(Waxy Feed to F- bypass line to line
205) 2856
132-MR-108 4-P132-5911-1A3A-IT From 132-EA-207
(Waxy Feed to F- T/S B/l to HCU to
205) Line 2653
132-MR-108 4-P132-6108-1A3A-IT From 132-EA-208
(Waxy Feed to F- T/S B/l to HCU to
205) Line 2653
132-MR-108 6-P132-2650-1A3A-IT From 132-V-253 to
(Waxy Feed to F- 132-P-259A/B
205)
8 132-MR-109 (Oil- 4-P-132-2851-8B3B3-IT From line 2850 to
Gas loop) 132-E-254 T/S
9 132-MR-110 (DW 8-PZ-132-2852/2853- From 132-E-254 T/S
Reactor Feed and 8G1C4-IH. to F-205 I/L.
Effluent stream)
8-PZ-132-2854-8G1C4- From Line 132-F-205
IH. to 132-R-204.
Page 22 of 27
8-PZ-132- From 132-E-254D
2857/3050/3051-7B3B3- S/S to 132-V-254 via
IH 132-R-205.
11 132-MR-112 4-PZ-132-3151-7B3B3 From Line 3151
(HLPS liquid and 4--P-132- (132-V-254 O/L) to
Vapour) 3152/3153/3154-7B3B3- 132-E-257 via 132-V-
IT. 255.
4-PZ-132-3350-2B3B3-
IH. From 132-V-255 to
132-EA-202 T/S and
1.5-P-132-3351-2B3B3- Flare Header.
IH.
1.5-P-132-3360-4B3B3-
IH.
12 132-MR-115 6-P-132-3158-7B3B3-IH From Line 3157 to
(HHPS cold 132-EA-228
vapour)
13 132-MR-116 4-PZ-132-3550-2B3B3- From 132-E-257 to
(HLPS liquid feed)
IT. 132-C-224
14 132-MR-117 (DW 4-PZ-132-3551-2A5A-IT. From 132-C-224 to
3-PZ-132-3654-2A5A-IT.
Product Stripper 132-F-206.
Circuit) 3-PZ-132-3650-2A5A-IT.
15 132-MR-118 (DW 10-PZ-132-3651-2A6A- From line 132-F-206
Vacuum Column IT. to 132-C-225.
feed) 18-PZ-132-3652-2A6A-
IT.
3-PZ-132-3650-2A5A-IT.
16 132-MR-119 (DW 4-P-132-3856-2A5A-IT From 132-C-
Vacuum Column 225(bottom) to 132-
Bottoms) P-265A/B.
Page 23 of 27
From Line 3553 to
4-P-132-2553-2A5A-IT. Line 2554.
Page 24 of 27
Table C Bare Lines
Page 25 of 27
6 132-MR-123 8-WCS-132-1753/3250- From 132-P-280
1XOAC. 6352 Supply Line to
6-WCS-132-3450/4250- 132-E-271A/B/C, E-
1X0AC. 275A/B/C, E-
3-WCS-132-4251/2150- 255/258/259/263/265
1X0AC. T/S.
24-WCS-132-6352-
1XOAC.
14-WCS-132-1752-
1X0AC.
10-WCS-132-
1750/3950/3952-1X0AC.
7 132-MR-125 1.5-WP-132-3957/3958- From 132-V-252 to
(Sour water) 1A5BN. Suction of 132-P-261
A/B.
Page 26 of 27
line from 132-P-260 A/B discharge to battery limit. After pad welding
carry out hydrotest of the line .
12 132-E-254 A/B outlet line is found having tilted shoes in pipe rack in
plant. Rectify approx 6 nos. tilted shoes
Page 27 of 27
ATTACHMENT 11 SECTION J
NHGU:
1. COOLING WATER LINES, ELBOWS, TEES, MANWAYS AND END FLANGES
Following end flanges / elbows at following locations of cooling water lines shall
be opened during shutdown for inspection. Offer the lines internally in clean
condition
Page 1 of 9
B. 12 / 6 DIA C.W. RETURN HEADER:
1. 1 no. 10 dia elbow located in pipe rack near header south of 133-V-308.
2. 1 no. 10 dia miter elbow located above 133-E-306.
1. 1 no. 10 dia elbow located in pipe rack near header south of 133-V-308.
2. 1 no. 10 dia miter elbow located above 133-E-306.
1. 1 no. 6 dia elbow located in pipe rack near header south of 133-V-308.
2. 1 no. 6 dia elbow located above 133-E-315.
1. 1 no. 6 dia elbow located in pipe rack near header south of 133-V-308.
2. 1 no. 6 dia miter elbow located above 133-E-315.
1. 1 no. 10 dia elbow located in pipe rack near header south of 133-V-313.
2. 1 no. 10 dia TEE located above 133-EM-303.
3. 2 nos. 10 dia elbows located above 133-EM-303.
4. 2 nos. 10 x 8 reducer in supply lines of 133-E-309A/B
1. 1 no. 10 dia elbow located in pipe rack near header south of 133-V-313.
2. 1 no. 10 dia TEE located above 133-EM-303.
3. 2 nos. 10 dia elbows located above 133-EM-303.
2. RENEWAL OF CW LINES:
Page 2 of 9
3. 8 dia 133-E-309A CW O/L immediate elbow spool piece.
4. 4 dia 133-E-313 CW O/L line vertical spool piece on south side of
exchanger ( Approx. 2m length)
LOBS
1. COOLING WATER LINES, ELBOWS, TEES, MANWAYS AND END FLANGES
Page 3 of 9
Clean the line, end flanges, elbows, and tees internally by water washing and
offer for inspection.
Carry out touch up of cement lining at the flange face area on elbow / Tees /
Branches and pipe line flanges.
Carry out internal cement lining repair as required after cleaning and inspection
of the lines/ elbows / tees / branches. Cement lining of the newly fabricated
section as defined in scope of work and for touch repair at the edges of the
flanges is included in lump sum scope.
Box up the end flanges / elbows / Tees / Branches after inspection and repair.
Remove scaffolding after completion of the job.
Scope includes offering the cooling water line for inspection from the tap off from
main cooling water supply/return header including first isolation valve at battery
limit to complete circuit within the plant.
Excavation / back filling / pavement after completion of the job for inspection and
repair of the underground section of the cooling water line from main supply
header to plant , wherever required , is included in lump sum scope.
For soil to air interfaces, on completion of inspection, carry out external bitumen
wrapping and coating as existing.
End flanges / elbows at following locations of cooling water lines shall be opened
during shutdown for inspection. Offer the lines internally in clean condition. Also
carry out replacement of line as mentioned
Page 4 of 9
B) TAP OFFS
1. 2 nos. 6 dia elbows near tap off in pipe rack ( north of 132-E-263)
2. 2 nos. 6 dia elbows near 132-E-263.
3. Replace the 6 dia leaky vertical spool piece for both supply and
return line near 132-E-263 I/L and O/L.
4. Replace the leaky 6 dia elbow spool piece at 132-E-263 I/L and 6
dia spool piece with 3 stub near 132-E-263 O/L.
1. 2 nos. 8 dia elbows near tap off in pipe rack (north of 132-E-255).
2. 2 nos. 8 dia elbows near 132-E-255.
1. 1 nos. 24 dia elbow near tapping in pipe rack (location north of 132-
V-255).
2. 1 no. 24 elbow in pipe rack ( east of 132-P-264A)
3. 1 no. 24 dia equal Tee (bypass line of strainers 6302A/B).
4. Suction (24 x 14) and discharge spool pieces (24 x 12) of 132-P-
280A/B
5. 1 no. 24 dia equal Tee (discharge line of 132-P-280B).
Replace the corroded 3 dia elbow spool piece of bypass line on
west of 132-P-280B and vertical supports on discharge line of 132-P-
280A/B.
6. 1 no. 24 dia elbow in Pipe rack (top of 132-V-263).
7. 1 no. 24 dia blind flange in Pipe rack (west of 132- E-260).
8. 1 no. 6 dia drain stub flange near above referred 24 dia blind flange.
9. 1 no. 8 dia elbow of tapping from 24 dia CW supply header
supplying water to 132-e-265/258/259).
10. 1 no. 8 dia blind flange of the above mentioned 8 dia line ( west of
132- E-260)
1 nos. 24 dia elbow near tapping in Pipe rack (location north of 132-
V-255).
1 no. 24 dia blind flange in Pipe rack (west of 132- E-260).
2 nos. 6 dia elbow of interconnection line between 8 dia supply line
and 24 dia CW return header.
Page 5 of 9
2 NOS. 3 DIA TAPPING FROM/TO 8 DIA CW SUPPLY HEADER
AND 24 DIA RETURN HEADER TO 132-E-265
1. 2 nos. 3 dia elbows in Pipe rack near tap off (above 132-P-266B).
2. 2 nos. 3 dia elbows near exchanger.
3. 1 no. dia non standard CS gate valve along with CS nipple to be
replaced with brass valve and brass nipple on the return line.
4. Replace the leaky 3 dia vertical spool piece at 132-E-265 I/L and 3
dia elbow spool piece at 132-E-263 O/L.
1. 2 nos. 6 dia elbows in Pipe rack near tap off (above 132-P-262A).
2. 2 nos. 6 dia elbows near exchanger.
3. 1 no. dia non standard CS gate valve along with CS nipple to be
replaced with brass valve and brass nipple on the return line.
4. Replace the leaky 6 dia 2nd elbow spool piece at 132-E-258
I/L.
1. 2 nos. 3 dia elbows in Pipe rack near tap off (west of 132-E-259).
2. 2 nos. 3 dia elbows near exchanger.
3. 1 no. dia non standard CS gate valve along with CS nipple to be
replaced with brass valve and brass nipple on the return line.
4. Replace the leaky 2nos. 3 dia spool pieces on west of 132-E-
259 I/L.
Page 6 of 9
In 24 CW Supply header (counting from east)
2. Scaffolding:
Page 7 of 9
Near 10 Return header blind
9 flange 3" 1 Gate Valve
In CW supply 24header near 132- Butterfly Valve
10 P-280A/B pumps. 24 7
Between the two 24 Butterfly Gate valve
valves near 132-P-280A/B
11 pumps(drain valve) 3" 1
In CW supply 24header (
12 discharge of 132-P-280B) 24" 1 Gate Valve
In CW supply 24header ( in
discharge line of 132-P-280A/B
13 pumps) 3" 2 Gate Valve
In discharge line of 132-P-
14 280B(drain valve) 3 1 Gate Valve
In bypass line of 132-P-280A/B
15 pumps 3 2 Gate valve
In 24 CW supply header(near top
16 of 132-V-263) 3" 1 Gate Valve
In 6 interconnecting line (South of
17 132-P-263B) 6" 1 Gate Valve
In 6 interconnecting line, drain
18 valve (South of 132-P-263B) 3" 1 Gate valve
In 24 CW supply header, drain
19 valve ( near 24blind flange) 3" 1 Gate Valve
In 24 CW return header, drain
20 valve ( near 24blind flange) 3" 1 Gate Valve
In 24 CW supply header (at 3rd
21 floor level west of 132-V-282) 24" 1 Butterfly Valve
In 24 CW return header (at 3rd
22 floor level west of 132-V-282) 24" 1 Butterfly Valve
In 10 interconnecting line (at 3rd
23 floor level) 10" 1 Butterfly valve
In 24 CW supply header (at 3rd
24 floor level ) near 24 Butterfly valve 3" 1 Gate Valve
In 24 CW supply header, drain
valve ( near 24blind flange at 3rd
25 floor level) 3" 1 Gate Valve
In 24 CW return header, drain
valve ( near 24blind flange at 3rd
26 floor level) 3" 1 Gate Valve
27 CW inlet / outlet of 132-E-275A 10 3 Butterfly Valve
28 CW outlet of 132-E-275A 3" 2 Gate valve
29 CW inlet / outlet of 132-E-275B 10" 2 Butterfly Valve
30 CW drain of 132-E-275B 8" 1 Butterfly Valve
31 CW outlet of 132-E-275B 3" 2 Gate Valve
32 CW inlet / outlet of 132-E-275C 8" 2 Butterfly Valve
33 CW drain of 132-E-275C 6" 1 Butterfly Valve
34 CW outlet of 132-E-275C 3" 2 Gate valve
Page 8 of 9
35 CW inlet of 132-E-271A 18" 1 Butterfly Valve
36 CW outlet of 132-E-271A 10" 1 Butterfly Valve
37 CW drain of 132-E-271A 10" 1 Butterfly Valve
38 CW outlet of 132-E-271A 3" 2 Gate Valve
39 CW inlet of 132-E-271A 3" 1 Gate Valve
40 CW inlet / outlet of 132-E-271B 14" 2 Butterfly Valve
41 CW drain of 132-E-271B 10" 1 Butterfly Valve
42 CW outlet of 132-E-271B 3" 2 Gate Valve
43 CW inlet / outlet of 132-E-271C 8" 2 Butterfly Valve
44 CW drain of 132-E-271C 6" 1 Butterfly Valve
45 CW outlet of 132-E-271C 3" 2 Gate Valve
46 CW inlet of 132-E-259 3" 1 Butterfly Valve
47 CW inlet of 132-E-259 3" 1 Gate Valve
48 CW outlet of 132-E-259 3" 1 Butterfly Valve
49 CW outlet of 132-E-259 3" 2 Gate Valve
50 CW inlet of 132-E-258 6" 1 Butterfly Valve
51 CW inlet of 132-E-258 3" 1 Gate Valve
52 CW outlet of 132-E-258 6" 1 Butterfly Valve
53 CW outlet of 132-E-258 3" 2 Gate Valve
54 CW inlet of 132-E-265 3" 1 Butterfly Valve
55 CW inlet of 132-E-265 3" 1 Gate Valve
56 CW outlet of 132-E-265 3" 1 Butterfly Valve
57 CW outlet of 132-E-265 3" 1 Gate Valve
58 CW inlet of 132-E-263 6" 1 Butterfly Valve
59 CW inlet of 132-E-263 3" 1 Gate Valve
60 CW outlet of 132-E-263 6" 1 Butterfly Valve
61 CW outlet of 132-E-263 3" 2 Gate Valve
62 CW inlet of 132-E-255 8 1 Butterfly Valve
63 CW inlet of 132-E-255 3 1 Gate Valve
64 CW outlet of 132-E-255 8 1 Butterfly Valve
65 CW outlet of 132-E-255 3" 2 Gate Valve
Page 9 of 9
ATTACHMENT 11 SECTION K
NEW HYDROGEN GENERATION UNIT & LUBE OIL BASE STOCK UNIT
(NHGU / LOBS) : CIVIL JOBS
NHGU:-
2. All the quantities against each painting system for every equipments are
indicative, bidders are advised to visit the site, asses exact quantities
before quoting the tender & quote accordingly.
3. Painting works shall be carried out as per BPCL standard & quality
assurance plant and QAP document shall be maintained on regular
basis. Contractor shall stand guarantee for the complete painting quality
job for a period of 2 Years. Any defect arising during above period shall
be made good by the contractor without any cost to the BPCL.
4. All structure to be painted in silver color & other as per BPCL color
coding standards.
5. For better quality control measures contractor shall follow following steps
like:
a. Successful bidder shall be required to obtain approval of paint
manufacturer, before ordering for paint materials. Materials shall
preferably be purchased directly from manufacturers. All coats under
one particular system shall be from single manufacturer.
b. Delivery challan/ cash receipt vouchers issued by the
manufacturers/ dealers shall be used as entry challan at the main
gate of BPCL.
c. Materials challan to be processed based on packing slip of materials
not based on coating system and maintained based on PO.
d. On entry of materials inside the refinery, concerned engineer to be
approached for physical verifications of materials along with entry
challan and entered in respective QAP.
e. For monitoring the consumption, inventory to be maintained on daily
basis for surprise check.
f. Contractor is required to comply attached QAP (quality assurance
plan). Contractor shall maintain all relevant documents and produce
on demand during progress of the work. The contractor is required to
submit the entire QAP document at the time of submission of final
bill as a supporting document
6. All areas indicated below are in M2. Sign writing areas are given in
INM i.e. Inch meter.
7. For painting area mark up, please refer drawing in attachment.
8. All type of scraps including empty drums, bags, brushes, emery papers,
scrapped material generated from work to be disposed outside refinery
on regular basis at no extra cost. Reconciliation statement for paint
drums shall be produced at the time of final bill.
Process
Condensate
Stripper
(133-C-302)
with
associated
structures as
per area
marked in
layout
drawing.
(Painting of
external
surface of
3 1000 250 120 50
heater +
platform +
hand railing +
cat ladder +
pipelines
+lagged
surfaces
+Concrete
surfaces +sign
writing +color
coding as per
BPCL color
coding
standards.)
Scrape clean the surface thoroughly (to quality grade st.2) so as to make the
surface free of loose mills scales, oil, grease, dirt and dust as per specifications &
as directed by engineer in charge.
System 13
Apply primer of one coat of Self Priming surface tolerant Epoxy Mastic Paint (1*125
brush)
Then apply intermediate coat of High build two pack polyamide cured epoxy (1*125
brush)
And final coat of Aliphatic acrylic modified high solids weather resistant recoatable
two pack polyurethane (1*40 roller or brush)
B. External thermal indicative paint for cold collector vessels of reformer furnaces
(NHGU regenerator ): abrasive cu slag shot blasting to sa 2.5 as per direction of
engineer in charge.
System 27
Apply primer of one coat of Inorganic Zinc Ethyl Silicate Primer (1*65 Air Spray/
Airless)
Then apply two coats of single pack, temperature indicating paint based upon a
modified silicone (2*25 Air Spray)
C. Steel surfaces (hot un-insulated surfaces like heaters, hot pipelines, vessels,
columns)
Scrape clean the surface thoroughly (to quality grade st. 2) so as to make the
surface free of loose mill scales, oil grease, dirt and dust.
System 19
Apply two coats of Silicon Based Heat Resistant Aluminum Paint (Temperature
Resistance : 250 540 degree cel.) - (2 x 20 brush)
Scrape clean the surface thoroughly (to quality grade st. 2) so as to make the
surface free of loose mill scales, oil grease, dirt and dust.
System 20
Apply two coats of Zinc Dust Graphite paint (Temperature Resistance : 450 degree
Cel.)- (2 x 40 brush)
Paint the lagged surface with one coat of oil based aluminum paint 1 x 20 brushes
Scope includes covering of total 23 nos. of SWS pit opening over the gratings
with bricks & cement sand mortar. The vent shall be provided in the
covering for release of gases as per the direction of Engineer-in-Charge.
Removal of pit covering and cleaning of SWS pits for removal of any
accumulated sludge/silt during start up of the plant & disposal of the
debris outside the refinery. The scope also includes covering of OWS funnels
using asbestos cloth & removal of the same after the shutdown activities.
3) REFRACTORY WORK
Scope includes refractory work at various Furnaces, APH, Stack, Ducts etc.
for replacement/repairs of muffle blocks, castable lining, brick lining,
ceramic modules, ceramic blankets, calcium silicate boards as per
inspection recommendation. The refractory work includes dismantling of
existing refractory/ceramic modules/refractory brick lining, welding of
anchors/chain link, application of zinc dust graphite paint on the shell
surfaces, covering of anchor tip with insulating tape & application of
refractory lining using gunniting technique or hand application as per
inspection recommendation. All refractory debris shall be disposed outside
the refinery on daily basis.
4) EXCAVATION WORK
Scope includes excavation work for various activities associated & included
in LSTK scope like inspection/repair/replacement of underground pipelines,
underground vessels, and structural foundations. The excavation work
includes breaking of concrete/bitumen pavement, excavation using
JCB/Manually, disposal of unserviceable material, dewatering of excavated
trenches, backfilling with sand/stone dust for a cushion of 300mm &
balance backfilling of excavated areas using excavated earth and paving of
the area. with RCC/ PCC of desired thickness as directed by BPCL.
Scope includes misc. civil work for various activities associated & included
in LSTK scope. It includes cement lining, breaking of concrete supports,
breaking of foundations, breaking of steps, dismantling of brickwork,
chipping of concrete/plaster, grouting of foundation bolts, dewatering of
existing valve pits/underground vessels/drain channels and construction of
the same to facilitate maintenance activities of mechanical, electrical &
instrument works.
6) SCAFFOLDING
2. All the quantities against each painting system for every equipments are
indicative, bidders are advised to visit the site, asses exact quantities
before quoting the tender & quote accordingly.
3. Painting works shall be carried out as per BPCL standard & quality
assurance plant and QAP document shall be maintained on regular
basis. Contractor shall stand guarantee for the complete painting quality
job for a period of 2 Years. Any defect arising during above period shall
be made good by the contractor without any cost to the BPCL.
4. All structure to be painted in silver color & other as per BPCL color
coding standards.
5. For better quality control measures contractor shall follow following steps
like:
6. All areas indicated below are in M2. Sign writing areas are given in
INM i.e. Inch meter.
7. For painting area mark up, please refer drawing in attachment.
8. All type of scraps including empty drums, bags, brushes, emery papers,
scrapped material generated from work to be disposed outside refinery
on regular basis at no extra cost. Reconciliation statement for paint
drums shall be produced at the time of final bill.
Scrape clean the surface thoroughly (to quality grade st.2) so as to make the
surface free of loose mills scales, oil, grease, dirt and dust as per specifications &
as directed by engineer in charge.
System 13
Apply primer of one coat of Self Priming surface tolerant Epoxy Mastic Paint (1*125
brush)
Then apply intermediate coat of High build two pack polyamide cured epoxy (1*125
brush)
And final coat of Aliphatic acrylic modified high solids weather resistant recoatable
two pack polyurethane (1*40 roller or brush)
B. Steel surfaces (hot un-insulated surfaces like heaters, hot pipelines, vessels,
columns)
Scrape clean the surface thoroughly (to quality grade st. 2) so as to make the
surface free of loose mill scales, oil grease, dirt and dust.
System 19
Apply two coats of Silicon Based Heat Resistant Aluminum Paint (Temperature
Resistance : 250 540 degree cel.) - (2 x 20 brush)
Scrape clean the surface thoroughly (to quality grade st. 2) so as to make the
surface free of loose mill scales, oil grease, dirt and dust.
System 20
Apply two coats of Zinc Dust Graphite paint (Temperature Resistance : 450 degree
Cel.)- (2 x 40 brush)
Paint with one coat of compatible primer and two coats of synthetic enamel paint
2 x 25 brush as directed by engineer in charge.
Paint the lagged surface with one coat of oil based aluminum paint 1 x 20 brushes
Scope includes covering of total 32 nos. of SWS pit opening over the gratings
with bricks & cement sand mortar. The vent shall be provided in the
covering for release of gases as per the direction of Engineer-in-Charge.
Removal of pit covering and cleaning of SWS pits for removal of any
accumulated sludge/silt during start up of the plant & disposal of the
debris outside the refinery. The scope also includes covering of OWS funnels
using asbestos cloth & removal of the same after the shutdown activities.
3) REFRACTORY WORK
Scope includes refractory work at various Furnaces, APH, Stack, Ducts etc.
for replacement/repairs of muffle blocks, castable lining, brick lining,
ceramic modules, ceramic blankets, calcium silicate boards as per
inspection recommendation. The refractory work includes dismantling of
existing refractory/ceramic modules/refractory brick lining, welding of
anchors/chain link, application of zinc dust graphite paint on the shell
surfaces, covering of anchor tip with insulating tape & application of
refractory lining using gunniting technique or hand application as per
inspection recommendation. All refractory debris shall be disposed outside
the refinery on daily basis.
4) EXCAVATION WORK
Scope includes excavation work for various activities associated & included
in LSTK scope like inspection/repair/replacement of underground pipelines,
underground vessels, and structural foundations. The excavation work
includes breaking of concrete/bitumen pavement, excavation using
JCB/Manually, disposal of unserviceable material, dewatering of excavated
trenches, backfilling with sand/stone dust for a cushion of 300mm &
balance backfilling of excavated areas using excavated earth and paving of
the area with RCC/ PCC of desired thickness as directed by BPCL.
Scope includes misc. civil work for various activities associated & included
in LSTK scope. It includes cement lining, breaking of concrete supports,
breaking of foundations, breaking of steps, dismantling of brickwork,
chipping of concrete/plaster, grouting of foundation bolts, dewatering of
existing valve pits/underground vessels/drain channels and construction of
the same to facilitate maintenance activities of mechanical, electrical &
instrument works.
6) SCAFFOLDING
SCOPE OF WORK
THE DIRECTOR,
The Directorate of Steam Boilers,
Kamgar Bhavan, 7th floor,
Page 1 of 3
C-20, E Block,
Opp. Reserve Bank, BKC,
Bandra (E), Mumbai-400051
NHGU:
SR.
MOC NO. JOB DESCRIPTION DRAWINGS
NO
NHGU-13- Providing platform connecting AFC floor
1 133-SE-3-208
1733 with E311A/B top floor
The guillotine dampers of ID301A/B to be 133-CE-3-
NHGU-11-
2 shifted above/downstream the discharge 30,Rev.E,133-CE-3-
1194
dampers. 29)
NHGU-15- Provision of DP indication across the PSA
3 133-P-1-145
2322 instrument air filter
Provision of block and bleed valves on
NHGU-15- 133-P-1-147 Sheet 1
4 reformer jacketing steam supply and
2123 &2
condensate return lines
MAGNETIC FILTER AND DUAL
REDUNDANCY AIR FILTER TO BE
NHGU-16-
5 PROVIDED ON INSTRUMENT AIR LINE 133-P-1-150
2565
(INLET OF PSA) AS PER ATTACHED
SCHEME
TO PROVIDE TWO Nos. OF NEW 4"
NOZZLE WITH ISOLATION VALVE AND
NHGU-16- 133-SE-3-145 R5,
6 FLANGE TO STACK F-301 FOR FLUE
2595 133-SE-3-148 R4,
GAS SPM ANALYSER AND MANUAL
FSK-2672
SAMPLINGS PURPOSE.
Page 2 of 3
LOBS:
Page 3 of 3
ATTACHMENT 11 SECTION M
1. Open the end flange of Y type strainer / top cover of the basket strainer.
2. Pull out the element out of the shell / body.
3. Provide metal tag on the element indicating location of the same.
4. Clean the strainer element and body.
5. If strainer element mesh is damaged, then sent it to owners construction shop
for repair.
6. If no damaged is there to element mesh, then offer the element in clean condition
to operations and assemble the same.
7. In case of repair, after rectification of the element by owner, transport the
element back to equipment location and assemble the same.
8. After assembly of element tighten the end flange / top cover.
9. Metal tag shall be removed while installation of the element.
NHGU:-
NHGU:-
SR NO EQUIPMENT SERVICE LINE SIZE
1 133P301A 133P301A-NAPTHA FEED PUMP 4 x 300
2 133P301B 133P301B-NAPTHA FEED PUMP 4 x 300
3 133P302A 133P302A-BFW PUMP 8 x 600
4 133P302B 133P302B-BFW PUMP 8 x 600
5 133P303A 133P303A-PROCESS CONDENSATE PUMP 3 x 600
6 133P303B 133P303B-PROCESS CONDENSATE PUMP 3 x 600
7 PSA instrument air filter 1 x 150
8 PSA instrument air filter 1 x 150
9 Pure Hydrogen basket filter 8 x 300
10 BCW to K304A/B basket filter 2 x 150
11 P335A BCW pump suction strainer 2 x 150
12 P335B BCW pump suction strainer 2 x 150
13 P332 & P334 lube oil suction strainer 1 x 150
14 G332A lube oil filter of K304B 1 x 150
15 G332B lube oil filter of K304B 1 x 150
16 G331A lube oil filter of K304A 1 x 150
17 G331B lube oil filter of K304A 1 x 150
Page 1 of 3
18 P331 & P333 lube oil suction strainer of K304A 1 x 150
19 V356 of K304B suction strainer 4 x 300
20 V360 of K304B suction strainer 4 x 300
21 V355 of K304A suction strainer 4 x 300
22 V359 of K304B suction strainer 4 x 300
23 V365 of K305 suction strainer 2 x 300
24 P337 & P338 lube oil suction strainer of K305 x 150
25 G333A lube oil filter of K305 1 x 150
26 G333B lube oil filter of K305 1 x 150
LOBS:-
Page 2 of 3
25 132P264A 132P264A-DW LT LUBE S/C STRIPPER PUMPS 2 X 150
26 132P264B 132P264B-DW LT LUBE S/C STRIPPER PUMPS 2 X 150
27 132P265A 132P265A-VAC COLMN BOT PUMP (FRACT) 6 X 150
28 132P265B 132P265B-VAC COLMN BOT PUMP (FRACT) 6 X 150
132P266A-VAC COLUMN.EXCESS WAXY PDT
29 132P266A 8 x 150
PUMP
132P266B-VAC COLUMN EXCESS WAXY PDT
30 132P266B 8 x 150
PUMP
31 132P280A 132P280A-COOLING WATER BOOSTER PUMP 24 x 150
32 132P280B 132P280B-COOLING WATER BOOSTER PUMP 24 x 150
41 132P286A 132P286A-WAXY FEED PUMP 8 X 150
42 132P286B 132P286B-WAXY FEED PUMP 8 X 150
43 132P288A 132P288A-150N PRODUCT PUMP 10 X 150
44 132P288B 132P288B-150N PRODUCT PUMP 10 X 150
45 132P289A 132P289A-500N PRODUCT PUMP 12 X 150
46 132P289B 132P289B-500N PRODUCT PUMP 12 X 150
47 132P290A 132P290A-OFF SPEC PRODUCT PUMP 6 X 150
48 132P290B 132P290B-OFF SPEC PRODUCT PUMP 6 X 150
49 132P281A CBD PUMP (SUBMERSIBLE) 6 X 150
50 132P281B CBD PUMP (SUBMERSIBLE) 6 X 150
51 132P282A CFBD PUMP (SUBMERSIBLE) 2 X 150
52 132P282B CFBD PUMP (SUBMERSIBLE) 2 X 150
53 132P284A OWS PUMP (SUBMERSIBLE) 2 X 150
54 132P284B OWS PUMP (SUBMERSIBLE) 2 X 150
BEARING COOLING WATER PUMP
55 132P285A 6 X 150
(SUBMERSIBLE)
BEARING COOLING WATER PUMP
56 132P285B 6 X 150
(SUBMERSIBLE)
57 132P06A OPTISPERSE DOSING PUMP X 150
58 132P06B OPTISPERSE DOSING PUMP X 150
59 132P291A PIPELINE TRANSFER PUMP 14 X 150
60 132P291B PIPELINE TRANSFER PUMP 14 X 150
Page 3 of 3
ATTACHMENT 11 SECTION N
NEW HYDROGEN GENERATION UNIT & LUBE OIL BASE STOCK UNIT
(NHGU / LOBS): BATTERY LIMIT SPADE
For positive isolation of the unit, carry out spading / de-spading at following battery limit
locations of NHGU / LOBS.
Note: For flare line spading, adequate size working platform with double escape route
shall be provided using scaffolding pipes and planks. Escape route shall have stairs
made of scaffolding planks.
NHGU
SR NO LINE DESCRIPTION STARTING FROM GOING TO SIZE RATING
START UP H2(IMP/EXP
1 OLD H2 B/L NHGU 6" 300
TO OLD H2)
2 HCN FEED TO NHGU HCU B/L NHGU 3" 150
3 SRLN FEED TO NHGU ARU SPHERE NHGU 3" 150
4 O/G EX CRU CRU B/L NHGU 8" 300
RAW COOLING WATER
5 NCDU NHGU 6" 150
(EX NCDU)
6 MEOH EX ARU ARU NHGU 1.5" 300
7 MEOH TO ARU NHGU ARU 1.5" 300
8 RAFFINATE FEED EX NSU NSU B/L NHGU 2" 150
9 HIGH AR NAPTH FEED PH/5 NHGU 4" 150
10 SLOP NGHU P/H-1 4" 300
11 HCLN FEED HCU B/L NHGU 2" 150
12 DRINKING WATER BOILER HOUSE NHGU 1" 150
13 HYDROGEN NHGU HCU 10" 300
14 HYDROGEN NHGU H2 GRID 8 300
15 HYDROGEN ex RFV661 NHGU H2 GRID 6 300
16 RLNG CCU NHGU 8 600
II ND
FLOOR
17 BCW RTN NHGU B/HOUSE 10" 150
18 BCW SUPPLY BOILER HOUSE NHGU 10" 150
19 DM WATER BOILER HOUSE NHGU 6" 150
20 N2 HDR ARU NHGU 6" 150
21 FUEL GAS HDR CCU NHGU 2" 150
22 INST AIR HDR BOILER HOUSE NHGU 3" 150
23 PLANT AIR HDR BOILER HOUSE NHGU 3" 150
24 SERVICE WATER BOILER HOUSE NHGU 3" 150
SUSCEPT CONDENSATE BOILER
25 NHGU 3" 150
HDR HOUSE
WATER SPRAY & SALT WATER
26 NHGU 8" 150
SPRINKLE CURTAIN P/HOUSE
SALT WATER
27 FIRE HYDRANT HDR NHGU 12" 150
P/HOUSE
28 HP STAEM NHGU NCDU 6" 600
29 LP STAEM BOILER HOUSE NHGU 12" 150
30 MP STEAM BOILER HOUSE NHGU 16"
FLARE
NHGU
31 FLARE HDR HDR 28" 150
32 DM WATER NHGU CDU3 4 150
EAST
SIDE
SEA COOLING WATER SALT WATER
33 NHGU 12 150
SUPPLY P/HOUSE
SALT
SEA COOLING WATER
34 NHGU WATER 12" 150
RTN
P/HOUSE
FIRE WATER SUPPLY SALT WATER
35 NHGU 8" 150
LINE P/HOUSE
SALT WATER
36 FIRE WATER RTN LINE NHGU 12" 150
P/HOUSE
SUSPECTED
37 CONDENSATE UNDER HCU NHGU 3"
GROUND EX NCDU 150
38 BCW RTN EX NVDU NCDU NHGU 10" 150
SOUTH
SIDE
39 BCW RTN EX HCU HCU NHGU 8" 150
40 CBD RTN EX HCU HCU NHGU 6" 150
SUSPECTED
CONDENSATE UNDER HCU NHGU
41 GROUND EX HCU 3" 150
LOBS
SR .NO. SERVICE SIZE RATING
1 LOBS FLARE HEADER 18" 150
2 SEA COOLING WATER SUPPLY 26" 150
3 SEA COOLING WATER RETURN 26" 150
4 OWS HEADER 4" 150
5 FLUSHING OIL SUPPLY 4" 150
6 DM WATER SUPPLY 2" 150
7 CFBD TO UCO HDR TO CCU/FOB 3" 300
8 CBD/CFBD TO HCU SLOP HDR 4" 300
9 FUEL GAS 6" 150
10 FUEL OIL RETURN 2" 300
11 FUEL OIL SUPPLY 2" 300
12 MP STEAM 8" 300
13 LP STEAM 6" 150
14 BOILER FEED WATER 4" 300
15 BEARING COOLING WATER SUPPLY 6" 150
16 BEARING COOLING WATER RETURN 6" 150
17 NITROGEN 4" 150
18 PLANT AIR 3" 150
19 INSTRUMENT AIR 3" 150
20 DRIKING WATER 3" 150
21 SERVICE WATER 6" 150
22 OFFSPEC PRODUCT TO TANKS 8" 300
23 WAXY 100N PRODUCT TO TANKS 3" 300
24 WAXY 150N PRODUCT TO TANKS 3" 300
25 WAXY 500N PRODUCT TO TANKS 3" 300
26 WAXY FEED FROM TANK FARM 4" 300
27 LIGHT LUBE TO TANKFARM 2" 300
28 LUBE PRODUCT TO TANK FARM 4" 300
29 SOUR WATER TO SWS-I 3" 150
30 SLOP OIL FROM VACUUM SYSTEM TO 0.05 'S' HSD HEADER 1" 150
31 LUBE BYPRODUCT TO HCU 2" 300
32 DW PRDT. STR. VAPOR TO HCU 4" 300
33 SLOP OIL TO DHDS FROM LOBS 1" 150
34 DW HLPS VAPOR TO HCU 1" 300 RTJ
35 DW HHPS VAPOR (EX V-256) TO HCU 6" 300
36 DW HHPS VAPOR TO HCU 6" 1500 RTJ
37 MAKE UP HYDROGEN EX HCU 4" 1500 RTJ
38 WAXY LIGHT DIESEL FROM HCU 4" 150
39 WAXY HEAVY DIESEL FROM HCU 6" 150
40 EXCESS WAXY PRODUCT TO HCU 4" 300
41 ATM FRACTIONATOR BOTTOM TO F-204 6" 300
42 UNCONVERTED OIL FROM HCU 3" 300
43 LUBE BY PDT, LT. LUBE, LUBE PDT TO 0.05, 0.035 HSD HDR 4 300
44 H2 FROM CCR TO HPCL HYDROGEN LINE 6 300
45 H2 FROM GRID TO HPCL HYDROGEN LINE 8 300
46 BPCL-HPCL HYDROGEN IMPORT-EXPORT LINE (Near P-259) 10 300
TANK FARM
1 INSTRUMENT AIR SUPPLY 2" 150
2 NITROGEN SUPPLY 2" 150
3 LP STEAM 3" 150
4 FLUSHING OIL 3" 150
5 OFF SPEC EX LOBS 8" 300
6 W-100 PRODUCT 3" 300
7 W-150N PRODUCT 3" 300
8 W-500N PRODUCT 3" 300
9 LUBE PRODUCT EX LOBS 4" 300
10 WAXY FEED TO LOBS 4" 300
11 LIGHT LUBE EX LOBS 2" 300
12 OFF SPEC TO HCU 4" 150
ATTACHMENT 11 SECTION O
Carry out following Instrument jobs as per scope of work detailed below,
NHGU
LOBS
2. TRANSPORTATION OF VALVES
The CONTRACTOR shall transport the valves carefully to avoid any damage, from the
site to the Instrument shop.
Transport the valve from the Instrument Shop to the proper field location.
NHGU
LOBS
NHGU
LOBS
LOBS
NHGU
SR. NO. TAG NO.
1 Manifolds Isolation valve replacement
RFT601
by welding
2 RFT605 Manifolds Isolation valve replacement
by welding
3 5 nos. as a provisional
New Manifolds to be Fabricated as per Main pipe line metallurgy by welding including
installation at site, testing as per standard and correct metallurgy. Hydro testing /
radiography of the manifolds / lines to be carried out and offer to BPCL for witnessing.
The payment for Fabrication of manifold in addition to the following tags if any shall be
made as per applicable SOR.
Manifold modification
3 RFT557
Manifold modification
4 RFST558A/B/C
3 nos. as a
5 provisional (legs)
8. Manpower supply
Supply following no. of manpower for entire turnaround period for misc jobs /
as assistance to BPCL instrument crew.
a. 2 no. Fitters
b. 1 no. Rigger
c. 2 no. Helpers
Electrical Jobs :
Carry out following Electrical jobs as per scope of work detailed below,
1. Cleaning of fan covers and cooling tubes for all HT and LT motors. Repairing of fan
covers wherever necessary. Site cleaning will include following job
a) Opening of fan cover
b) Fan and its cover cleaning
c) Repair of fan cover if required by welding, etc
d) Cleaning of cooling tubes/fins of motor using wire brush.
e) Fixing fan cover back to motor.
Sr
no Motor tag KW Voltage
1 133PM335A 3.7 415V
2 133PM335B 3.7 415V
3 133EAM301A 11 415V
4 133EAM301B 11 415V
5 133EAM302A 11 415V
6 133EAM302B 11 415V
7 133EAM302C 11 415V
8 133EAM302D 11 415V
9 133PM315A 15 415V
10 133PM315B 15 415V
11 133PM303A 30 415V
12 133PM303B 30 415V
13 133KM306 30 415V
14 133PM320A 37 415V
15 133PM320B 37 415V
16 133KM305 45 415V
17 133PM322A 45 415V
18 133PM322B 45 415V
19 133PM301A 90 415V
20 133PM301B 90 415V
21 133PM321A 93 415V
22 133PM321B 93 415V
23 133KM307 160 6600V
24 133KM304A 227 6600V
25 133KM304B 227 6600V
26 133KM303 350 6600V
27 133PM302A 380 6600V
28 133PM302B 380 6600V
29 133FD301A 750 690V
30 133FD301B 750 690V
31 133IDM302A 870 690V
32 133IDM302B 870 690V
Sr
no Motor tag KW Voltage
132-P-259A-P-
3.7 415
1 01
132-P-259B-P-
3.7 415
2 01
3 132-EM-225A 3.7 415
4 132-EM-225B 3.7 415
5 132-P-263 A 7.5 415
6 132-P-263 B 7.5 415
7 132-P-264 A 7.5 415
8 132-P-264 B 7.5 415
9 132-P-265 A 7.5 415
10 132-P-265 B 7.5 415
11 132-EMV-222A 7.5 415
12 132-EM-222B 7.5 415
13 132-EM-228D 7.5 415
14 132-EMV-223A 9.3 415
15 132-EMV-223B 9.3 415
16 132-EM-223C 9.3 415
17 132-EM-223D 9.3 415
18 132-EM-226A 9.3 415
19 132-EM-226B 9.3 415
20 132-EM-226C 9.3 415
21 132-EM-226D 9.3 415
22 132-P-252 A 11 415
23 132-P-252 B 11 415
24 132-P-260 A 11 415
25 132-P-260 B 11 415
26 132-P-261 A 11 415
27 132-P-261 B 11 415
28 132-P-281 A 15 415
29 132-P-281 B 15 415
30 132-EMV-224A 15 415
31 132-EMV-224B 15 415
32 132-EM-224C 15 415
33 132-EM-224D 15 415
34 132-EMV-227A 15 415
35 132-EM-227C 15 415
36 132-EM-228A 15 415
37 132-EM-228B 15 415
38 132-EM-228C 15 415
39 132-P-290 18.5 415
40 132-P-254A 22 415
41 132-P-254B 22 415
42 132-P-282 A 22 415
43 132-EMV-221A 22 415
132-EMV-
22 415
44 221C
45 132-EM-221B 22 415
46 132-EM-221D 22 415
47 132-P-284 A 30 415
48 132-P-285 A 30 415
49 132-P-285 B 30 415
50 132-FD-251A 37 415
51 132-FD-251B 37 415
52 132-ID-251 37 415
53 132-P-255 A 45 415
54 132-P-255 B 45 415
55 132-P-257 A 55 415
56 132-P-257 B 55 415
57 132-P-258 A 75 415
58 132-P-258 B 75 415
59 132-P-280 A 75 415
60 132-P-280 B 75 415
61 132-P-286 A 75 415
62 132-P-286 B 75 415
63 132-P-288 A 75 415
64 132-P-288 B 75 415
65 132-P-256 A 110 415
66 132-P-256 B 110 415
67 132-P-262 A 110 415
68 132-P-262 B 110 415
69 132-P-289 A 110 415
70 132-P-289 B 110 415
71 132-P-253 A 125 415
72 132-P-253 B 125 415
73 132-P-266 A 125 415
74 132-P-266 B 125 415
75 132-P-291 A 300 6600
76 132-P-291 B 300 6600
77 132-P-259 A 750 6600
78 132-P-259 B 750 6600
ATTACHMENT 11 SECTION P
A) SILENCER
Erect scaffolding as required and offer the following silencers for inspection:-
a) 133-JU-301
b) 133-JU-302
c) 133-JU-303
d) 133-JU-304
e) 133-JU-305
f) 133-JU-306
B) Manpower Supply
NEW HYDROGEN GENERATION UNIT & LUBE OIL BASE STOCK UNIT ( NHGU / LOBS)
: INSPECTION SERVICES
1) Inspection of columns, vessels, exchangers and Air Fin Coolers shall be carried out as per
API-510 (Pressure Vessel Inspection Code: Maintenance Inspection, Rating, Repair and
Alteration) and API-RP-572 (Inspection of Pressure vessels {Towers, Drums, Reactors,
Heat Exchangers and Condensers).
3) Inspection of piping shall be carried out as per API-570 (Piping inspection code
Inspection, repair, alteration and rerating of In-service piping systems).
6) Refer API-RP-571 for Damage Mechanisms Affecting Fixed Equipment in the Refinery
Industry.
7) All Non Destructive Examinations shall be carried out as per ASME Section V.
9) Welding inspection shall be carried out as per API-RP-577 (Welding Inspection and
Metallurgy).
10) All other design codes like ASME Sec VIII Div 1 & 2, ASME B 31.3 to be followed as
mentioned in the relevant inspection codes.
13) The NDT requirements and extent of inspection shall be as per Annexure-1.
The detailed scope of work of contractor with respect to inspection in Train3 HGU/LOBS
shutdown shall be as follows:
5) Contractor shall carry out conventional NDT like Liquid Penetrant testing, Magnetic
Particle Inspection, Ultrasonic Scanning, Eddy current testing, Remote Field
Electromagnetic Testing, Insitu metallography and Long Range Guided Wave
Testing as per the details given in this section as well as during recommended
repairs. Contractor shall submit the final signed observations/results of NDT to
BPCL Inspection. All personnel, consumables and equipment for NDT shall be in
contractors scope of supply. Contractor shall submit details of qualifications and
experience of NDT personnel to BPCL for approval.
7) Contractor shall submit the final signed Visual inspection reports / check list to
BPCL Inspection.
8) Based on the records indicated, contractor inspector shall make the required
recommendations for repair or release for hydro testing, box up etc. after approval
of BPCL Inspection. Such recommendations shall be made in Microsoft word
software.
9) Contractor shall be qualifying the welders deployed for repair jobs as per ASME sec
IX.
10) Contractor shall deploy the required NDTs to verify the effectiveness of repairs.
11) Contractor is responsible for the integrity and reliability for the next four years run of
the equipment and piping inspected and inspected during repairs by him. He shall
certify the equipment and piping fit for in service use till 4 more years.
12) Contractor shall liaise with all statutory authorities like GBI and Factory inspectorate
and obtain the Boiler certificates and Form 13 for all equipment and piping
inspected during shutdown. Equipment / piping sketches with thickness readings
duly signed and stamped by competent person authorized by DISH shall be
attached with form-13.
13) Contractor inspectors shall witness RV testing at shop and sign the test records.
14) Separate Large 40 ft long and clean porta cabin with sufficient tables & chairs, AC,
drinking water to be provided by the contractor for the inspectors and inspection
coordinators for both the plant. Adequate number of Laptops/desktops (minimum 6
to 8 nos.) to be provided to the inspectors. Housekeeping of porta cabin to be
maintained.
15) Separate Large 40 ft long and clean porta cabin with sufficient tables & chairs, AC,
drinking water to be provided by the contractor for NDT personnel for both the plant.
Housekeeping of porta cabin to be maintained.
16) All inspection engineers shall be provided with an Inspection kit comprising of 500
grams ball pin hammer, torch, scrapper, pit gauge and tool bag.
17) The NDT requirements and extent of inspection shall be as per work list/as per site
inspection engineers requirements.
1) All the Ultrasonic thickness, visual inspection and other NDT reports shall be
submitted prior to Hydrostatic testing / box up of equipments.
4) Contractor shall arrange one soft copy and one hard copy of Form 13 signed by the
competent person prescribed under Rule 65 of Maharashtra Factory rules 1963, as
per factories act, for equipment and piping inspected during the turnaround and
submit the same to BPCL.
5) The contractor shall take ultrasonic thickness measurements and write the same in
the Sketches at TMLs (Thickness Measurement Locations) shown in the sketch.
The contractor shall also fill the values of thicknesses at TMLs in the excel file
attached to the sketch. Contractor shall compile all TML values of all similar assets
in a single excel file and submit to BPCL for mass upload in Meridium system.
6) All attendance sheets of Inspection manpower and entry challans for NDT
equipment to be submitted.
8) Inspectors shall prepare RV reconciliation statement towards the end of the turnaround.
They shall scrutinize all the RV testing records, lists etc. They shall physically visit each
equipment and pipeline where RVs are installed as per master list and check the tag
nos. of RVs to ensure correct RVs are installed and RVs have been tested. The
reconciliation list to indicate missing RVs or RVs not tested and any other discrepancies
etc
1) Contractor shall carry out liaisoning and coordination work with GBI Authorities
for the various GBI related activities like material identification, approval of
drawings if any, repair of waste heat Boilers / steam piping, cleaning of
boilers/steam piping, Inspection of boilers / steam piping, dry inspection of
Boilers, hydrostatic inspection of boilers / steam piping, obtaining of certificate of
use for boilers/piping, IBR welders etc. as per the case applicable.
2) All coordination work involving bringing the inspector to site and taking him back
shall be in contractors scope. Only conveyance to and fro for GBI inspector and
inspection fees for Boilers shall be in BPCLs scope.
3) The details of work/repair required on Boilers/steam piping shall be as per the
work list and recommendations released during turnaround based on the
observations by the GBI/BPCL Inspection.
NHGU:
ANNEXURE-1 for NHGU
SCOPE OF NDT
1. Visual Inspection:
Visual inspection shall be carried out as per applicable codes and standards for
inspection of various equipments. Internal and external visual inspection shall be
carried out on equipment and shall cover all pressure and non-pressure parts.
The pressure parts of all the equipment shall be ultrasonically gauged for thickness
and the thickness readings shall be recorded on inspection sketches showing
corresponding Thickness Measurement Locations (TMLs). The number of
thickness monitoring locations shall be adequate enough to assess any metal loss.
In case of any significant metal loss is observed, the effected area shall be closely
scanned. The following shall be considered as a guide line for each type of
equipment for deriving the TMLs.
2.1 Columns:
a) Shell plate: In 4 compass directions at each tray level.
b) Dished ends: In 4 compass directions in crown and knuckle area.
c) All connected nozzles neck thickness in four compass directions.
d) Skirt: In 4 compass directions.
e) Internals: Trays (10% of trays, 4 locations on each tray) and distributors (100%,
one set of readings {4 compass directions} at every one meter length).
2.3 Heaters:
Radiation Section:
a) Straight tubes: In 4 compass directions at 3 levels (1st level shall be approx. 1
mtr. from floor level).
b) Return bends: All bends, min. 3 readings on the outer radius of each bend.
Convection Section (Hydrocarbon Coils, BFW Coils, Steam Generating Coils and
Super Heater Coils):
a) Tubes (straight sections): In 4 compass directions adjacent to each bend.
b) Return bends: All bends, min. 3 readings on the outer radius of each bend.
c) Bottom shock tubes: In 3 compass directions at 3 locations.
Stack:
One set of readings on each shell course along the staircase.
2.4 Exchangers:
a) Shell & shell cover: In 4 compass directions for all shell courses (At min. 3
locations).
b) Dished ends: In 4 compass directions at crown and knuckle area.
c) All connected nozzles neck thickness in four compass directions.
d) Tube OD measurement on peripheral tubes, Thickness by measuring ID & OD.
2.6 Piping:
a) All elbows, tees and reducers.
b) Pipe: one set of readings in 4 compass directions at every 10 mtrs length. In
case of small pipe sections i.e. less than 10 mtrs. length, one set of readings in
every section of straight pipe.
a) Reformer heater catalyst tube inspection shall be carried out on all tubes by an
agency specialized in this job. Following inspection activities shall be carried
out:
1. Complete inspection and assessment of all the tubes using Laser Optic Tube
Inspection technique (LOTIS). After inspection, all the tubes shall be
categorized considering various defects in the tubes.
2. Dye Penetrant test of all Reformer tube welds, pig tail welds to tubes and
headers.
3. Visual inspection.
4. Bowing measurement.
b) All necessary man power, equipment and consumables for the specialized
inspection of Reformer tubes is in the scope of party.
c) The report shall be submitted in soft copy (CD) and one hard copy.
a) Carryout Liquid penetration test (LPT) of stainless steel welds of piping, heaters
and weld overlays as per scope of work.
b) Liquid Penetration Examination shall be carried out as per ASME Section V
Article 6.
6) Eddy current testing:
a) Eddy current testing (ECT) shall be carried out as per ASME Section V Article 8.
The contractor to submit NDT party details and procedure to BPCL for approval.
Battery operated equipment is to be deployed. ECT shall be deployed for
checking of non magnetic tubes like non ferrous tubes and stainless steels.
b) Refer work list for exchangers / AFCs for ECT.
c) Based on inspection findings, ECT % per bundle may be increased or reduced.
Cracks identified by NDTs like DP and MPI in equipment will require to be sized
using SWUT (shear wave ultrasonic testing). Provide one no. SWUT battery
operated machine and operators for sizing of cracks found by DP/MPI.
9) RADIOGRAPHY:
All radiography work shall be in the scope of contractor. No storage for source and
processing space shall be provided by BPCL
9.1 Piping:
9.2 Equipment:
a) All butt joints of pressure vessels and nozzle flange butt joints 100 %.
b) Stress relieved joints 100 % before and after SR.
For the equipment where NDT needs to be done refer work list. Above resources
shall be used to carry out NDT as required in the NHGU complex during
turnaround.
e) All NDT activities shall be carried out by persons with suitable experience and
having minimum ASNT Level-2 qualification.
f) SWUT (Shear Wave Ultrasonic Testing shall be carried out by the Inspection
agency having experienced personnel with valid ASNT level-2 qualification
under supervision of Level -3 NDT specialist. The reports shall be reviewed and
certified by Level -3 NDT specialist.
ANNEXURE-2 for NHGU
Years of Experience
Description Nos. Engineers Diploma
Inspection Coordinators 2 10 12
All shortlisted Inspectors and coordinators will be finally selected thru a technical
interview conducted by BPCL Inspection Department.
4) The contractor shall mobilize 2 nos. API 570 piping inspectors 7 days prior to plant
shutdown. All remaining inspectors and coordinators shall be mobilized 2 days prior
to shutdown.
6) API conversant inspector shall be familiar with various API Codes like API-510, API-
RP-572, API-RP-573, API-570, API-574, API-576, API-571, API-577, API-936 (for
refractory) and applicable Codes.
7) Inspectors should be conversant with ASME Sec II, V, VIII, IX, ANSI, API, AWS, and
Indian Standards.
9) Inspector should be well conversant with WPS, PQR, and Welder Qualification as
per ASME Sec. IX.
10) Inspector should be able to carry out stage wise inspection of fabrication of piping,
vessels etc. viz. fit ups / edge preparation, Preheat / post heat/ inter pass temp. /
Stress relieving cycles monitoring, consumables checking, final welding, and co-
ordination with Radiographic agency during radiography, interpretation of
radiographs, witnessing hydro test, documentation, mechanical clearance etc. during
fabrication of new & old piping.
11) Inspector should be able to document all activities during fabrication and stage wise
inspection of repairs and new piping modification, in a standard manner.
12) The age of inspection coordinator shall not be more than 50 years.
15) All inspectors and coordinators should be medically fit for working in confined space.
Their medical fitness shall be certified by MBBS Doctor.
16) Inspector should communicate fluently in at least one of the following languages: Hindi,
Marathi, and English.
17) Inspector must be able to make observations about equipment status/condition and provide
feedback to BPCL inspection in written format. He must be good at writing skills
18) Civil inspector shall have experience as mentioned in table above (Point no 2) for on stream
inspection of refractory work, civil structures, mechanical structures, cement lining of pipes
etc.
LOBS:
ANNEXURE-1 for LOBS
SCOPE OF NDT
2. Visual Inspection:
Visual inspection shall be carried out as per applicable codes and standards for
inspection of various equipments. Internal and external visual inspection shall be
carried out on equipment and shall cover all pressure and non-pressure parts.
The pressure parts of all the equipment shall be ultrasonically gauged for thickness
and the thickness readings shall be recorded on inspection sketches showing
corresponding Thickness Measurement Locations (TMLs). The number of
thickness monitoring locations shall be adequate enough to assess any metal loss.
In case of any significant metal loss is observed, the effected area shall be closely
scanned. The following shall be considered as a guide line for each type of
equipment for deriving the TMLs.
2.1 Columns:
f) Shell plate: In 4 compass directions at each tray level.
g) Dished ends: In 4 compass directions in crown and knuckle area.
h) All connected nozzles neck thickness in four compass directions.
i) Skirt: In 4 compass directions.
j) Internals: Trays (10% of trays, 4 locations on each tray) and distributors (100%,
one set of readings {4 compass directions} at every one meter length).
2.3 Heaters:
Radiation Section:
c) Straight tubes: In 4 compass directions at 3 levels (1st level shall be approx. 1
mtr. from floor level).
d) Return bends: All bends, min. 3 readings on the outer radius of each bend.
Convection Section (Hydrocarbon Coils, BFW Coils, Steam Generating Coils and
Super Heater Coils):
d) Tubes (straight sections): In 4 compass directions adjacent to each bend.
e) Return bends: All bends, min. 3 readings on the outer radius of each bend.
f) Bottom shock tubes: In 3 compass directions at 3 locations.
Stack:
One set of readings on each shell course along the staircase.
2.4 Exchangers:
e) Shell & shell cover: In 4 compass directions for all shell courses (At min. 3
locations).
f) Dished ends: In 4 compass directions at crown and knuckle area.
g) All connected nozzles neck thickness in four compass directions.
h) Tube OD measurement on peripheral tubes, Thickness by measuring ID & OD.
2.6 Piping:
c) All elbows, tees and reducers.
d) Pipe: one set of readings in 4 compass directions at every 10 mtrs length. In
case of small pipe sections i.e. less than 10 mtrs. length, one set of readings in
every section of straight pipe.
c) Carryout Liquid penetration test (LPT) of stainless steel welds of piping, heaters
and weld overlays as per scope of work.
d) Reactor attachment welds of all the nozzles, thermocouple, bottom vortex
breaker, tray and catalyst support cone from inside.
e) For ring type gasket joints, all the gasket and ring grooves of all the three
reactors.
f) Bed thermocouple weld joints of all reactors from inside and outside the reactor
shell.
g) Liquid Penetration Examination shall be carried out as per ASME Section V
Article 6.
a) Eddy current testing (ECT) shall be carried out as per ASME Section V Article 8.
The contractor to submit NDT party details and procedure to BPCL for approval.
Battery operated equipment is to be deployed. ECT shall be deployed for
checking of non magnetic tubes like non ferrous tubes and stainless steels.
b) Refer work list for exchangers / AFCs for ECT.
c) Based on inspection findings, ECT % per bundle may be increased or reduced.
Cracks identified by NDTs like DP and MPI in equipment will require to be sized
using SWUT (shear wave ultrasonic testing). Provide one no. SWUT battery
operated machine and operators for sizing of cracks found by DP/MPI.
Observation Action
Isolated cavities Monitor
Oriented cavities Formalize NDE program
Cavity linkage (micro-cracks) FFS, with limited service time to repair
Macro-cracks Plan to repair immediately
f) Based on above NDTs, in case FFS is applicable, contractor shall carry out level
3 Fitness for Service (FFS) as per API RP 579 through the specialist in FFS
within 5 days from the date of observation of the flaw. The FFS agency shall be
approved by BPCL. The FFS report shall give the pressure/temperature
withstanding capacity and in service monitoring requirements, repairs and
replacements.
g) Velocity ratio comparison, Advanced Ultrasonic Backscatter Technique (AUBT)
and Insitu-metallography shall be carried at 2 nos. circumferential weld joints
and 2 nos. selected locations on shell of each Reactor by NDT specialist.
10) RADIOGRAPHY:
All radiography work shall be in the scope of contractor. No storage for source and
processing space shall be provided by BPCL.
10.1 Piping:
10.2 Equipment:
c) All butt joints of pressure vessels and nozzle flange butt joints 100 %.
d) Stress relieved joints 100 % before and after SR.
For the equipment where NDT needs to be done refer work list. Above resources
shall be used to carry out NDT as required in the LOBS complex during
turnaround.
a) All NDT activities shall be carried out by persons with suitable experience and
having minimum ASNT Level-2 qualification.
b) SWUT (Shear Wave Ultrasonic Testing shall be carried out by the Inspection
agency having experienced personnel with valid ASNT level-2 qualification
under supervision of Level -3 NDT specialist. The reports shall be reviewed and
certified by Level -3 NDT specialist.
c) TOFD, PAUT, AUBT and Velocity Ratio Comparison shall be carried out by the
Inspection agency having experienced personnel with valid ASNT level-2
qualification under supervision of Level -3 NDT specialist. The reports shall be
reviewed and certified by Level -3 NDT specialist. Both NDT technician and
NDT specialist should have experience in carrying out these jobs for
thicknesses more than 100 mm. Prior to deploying the Inspection agency for
this job, all supporting documents shall be submitted to BPCL Inspection Dept.
for verification and approval. The procedure and data shall be evaluated by
ASNT/EN level-3 NDT specialist with more than 10 years of experience in the
relevant field.
ANNEXURE-2 for LOBS
Years of Experience
Description Nos. Engineers Diploma
Inspection Coordinators 2 10 12
All shortlisted Inspectors and coordinators will be finally selected thru a technical
interview conducted by BPCL Inspection Department.
4) The contractor shall mobilize 2 nos. API 570 piping inspectors, 7 days prior to plant
shutdown. All remaining inspectors and coordinators shall be mobilized 2 days prior
to shutdown.
6) API conversant inspector shall be familiar with various API Codes like API-510, API-
RP-572, API-RP-573, API-570, API-574, API-576, API-571, API-577, API-936 (for
refractory) and applicable Codes.
7) Inspectors should be conversant with ASME Sec II, V, VIII, IX, ANSI, API, AWS, and
Indian Standards.
9) Inspector should be well conversant with WPS, PQR, and Welder Qualification as
per ASME Sec. IX.
10) Inspector should be able to carry out stage wise inspection of fabrication of piping,
vessels etc. viz. fit ups / edge preparation, Preheat / post heat/ inter pass temp. /
Stress relieving cycles monitoring, consumables checking, final welding, and co-
ordination with Radiographic agency during radiography, interpretation of
radiographs, witnessing hydro test, documentation, mechanical clearance etc. during
fabrication of new & old piping.
11) Inspector should be able to document all activities during fabrication and stage wise
inspection of repairs and new piping modification, in a standard manner.
12) The age of inspection coordinator shall not be more than 50 years.
15) All inspectors and coordinators should be medically fit for working in confined space.
Their medical fitness shall be certified by MBBS Doctor.
16) Inspector should communicate fluently in at least one of the following languages: Hindi,
Marathi, and English.
17) Inspector must be able to make observations about equipment status/condition and provide
feedback to BPCL inspection in written format. He must be good at writing skills.
18) Civil inspector shall have experience as mentioned in table above (Point no 2) for on
stream inspection of refractory work, civil structures, mechanical structures, cement
lining of pipes etc.
ATTACHMENT 11 SECTION R
All windows / doors shall be provided with monsoon protection made out of MS sheet
and all the window glasses shall be provided with sun films. Also, sliding curtains to be
provided from inside for all the windows in all the cabins.
The scope also includes all transportation / placement services / unloading / loading at
BPCL refinery site.
Similarly contractor will be required to collect and transport the porta cabin from BPCL
site back to their works on instructions of engineer in-charge.
For loading / unloading at BPCL premises, the required crane shall be provided by
Contractor. Contractor shall arrange sufficient nos. of Slings, D shackles & manpower
for making rigging arrangement and loading / unloading of the porta cabins including
placement at designated place.
For any problem related to the electrical fitting / equipment, contractor shall arrange to
rectify the defective equipment within 12 hrs and same shall be made good without any
cost to BPCL.
20' x 10' x 8'6" (all dimension in feet) with suitable lifting arrangements. Total quantity 2
nos.
Exterior
Windows
3 nos. aluminum sliding glass windows with sun films and curtain rods & curtains for 20
x 10 feet cabin
Suitable locking facility both inside and outside with number locks. The doors shall be
provided along the width of the cabins.
Electrical Facilities
1 no. main supply board for lighting with ELCB shall be mounted outside in a M.S.
board. The board shall have an isolator 63 Amp and connector suitable for terminating 4
core 16 sq.mm copper cables for incoming supply. Electric distribution shall be 1 phase
distribution and 1 phase ELCB + MCB with 25 A , 30 mA sensitivity.
The porta cabin shall be supplied with complete internal wiring facilities. The porta cabin
shall be in ready to use condition with all electrical accessories as listed below once the
incoming supply is provided by BPCL.
4 nos. 5 x 15 Amps plug point and 4 nos. spike guards with all wiring from the main
incoming board. Please ensure availability of spike guards in all the cabins.
Suitable capacity power points are to be provided in the office cabins for window air
conditioners.
Two additional spare power points to be provided near the doors as spare to take care
of any additional requirements.
1 no. 1.5 to 2 ton window air conditioner for 20 x 10 feet porta cabins
2 nos. Rotary grill ceiling fans with complete wiring for 20 x 10 feet porta cabin
Other Accessories
All the 20 x 10 feet cabin shall be provided with two nos. computer table , one no. book
shelf with glass doors & locks, 10 nos.Plastic molded chairs (In Red / Green / White
color) & 3 nos. tables (Wooden with sun mica top) of size 4 feet. x 2 feet
All the cabins shall be provided with one 'WHITE BOARD' of 5'x3' size (Each
cabin) along with two marker pens and magnetic duster.
Ground clearance for all the cabins shall maintained by build on four legs of 9 inch high
from the ground level.
Special requirement
All cabins shall be provided with wash basin & mirror with drain and incoming line
connection mounted / coming outside the cabin.
B) TEMPORARY TEA POINTS & SUPPLY OF CHAIRS, TABLES AND FANS (AIR
CIRCULATORS) DURING RMP COMPLEX TURNAROUND 2017 for PERIOD OF
2 MONTHS
Make temporary tea points for BPCL staff of size 50 x 15 x 10 2 nos using
scaffolding pipes and the same shall be covered with good quality precoated sheets of
blue colour from sides and top. There should be proper entry and top 2 shall be open
from sides for ventilation. The exact location for tea point shall be shown by Area
Incharge during Turnaround.
Supply following items at tea points of RMP Turnaround for a period of 2 months (60
days) -
Plastic molded chairs (In Red / Green / White color) - Total quantity 200 nos.
Tables (Wooden with sun mica top) of size 4 feet. x 2 feet - Total quantity 50 nos.
600 mm Fans (Pedestal type 230 V with oscillation) - Total quantity 6 nos.
To and Fro transportation of the chairs/ tables / fans from BPCL Mumbai refinery to
contractors place is in Contractors scope.
Contractor shall supply chairs, tables and fans of good quality and as per details given
in Scope of Work. Broken / damaged /inferior quality chairs / tables / fans will be
rejected and will not be paid for.
Any problem in running of fans (air circulators) shall be attended by contractor on urgent
basis on the same day.
Chairs / tables / fans shall be delivered at the plant locations inside BPCL Mumbai
refinery as per instructions of Engineer-in-Charge. Loading / unloading of chairs / tables
/ fans at site and contractors place shall be arranged by contractor.
Contractor will be required to supply and collect chairs / tables / fans in two or more trips
on different days. Exact dates of delivery will be intimated later.
Contractor shall arrange to collect back the chairs/ tables / fans within one day on
instruction of Engineer-in-Charge. Collection of chairs /tables / fans will be required in
phases on different days.
ATTACHMENT 11 SECTION S
1. For package no. 3, with respect to insulation work on all the equipment and piping,
lumpsum scope shall include following quantities.
a. Insulation removal and application : 8700 m2
b. Removal and application of asbestos rope : 1000 Inch Meter
c. Making inspection windows for equipment / piping: 4500 nos.
Any upward / downward variation in the insulation quantities estimated above
shall be dealt through applicable SOR.
Kindly note
1. The job involves transportation of free issue materials from warehouse, cutting /
rolling of aluminum sheet in required size/ shape/ form suiting the piping / equipment,
insulation of surfaces with LRB mattress / rock wool of various thicknesses and
provide aluminum cladding with overlapping at all heights . GI screws shall be
screwed at regular intervals of 100 / 150 / 200 mm based on site conditions.
Application of salli-coat or equivalent mastic materials and cladding if any required
for the job is also included. Scrap shall be disposed as directed by BPCL site in-
charge. The job shall be done strictly as per BPCL specifications. Payment will be
effected for finished surface area of insulation. Scaffolding if required shall be
provided by the contractor with his material for execution of the job and the same to
be removed upon completion of the job as directed by the Engineer in charge. Rate
Shall Be Applicable for Insulation up to 100 mm thickness and is inclusive of removal
of old insulation / cladding / cleaning / painting of the lines with two coats of zinc dust
graphite paint.
2. After removal of insulation (cladding and mineral wool), carry out thorough cleaning
for UT gauging and offering to Inspection.
3. If no insulation windows exist on the shell, then contractor shall cut the insulation
window as per insulation standard procedure. The removable window shall be of the
same basic material and thickness as the rest of the insulation and of sufficient
rigidity to withstand handling.
Page 1 of 2
4. Before fixing insulation, carry out painting as per AES 5430 Rev 1.
5. After completion of the job, carry out insulation and cladding as per BPCL insulation
procedure given in Attachment 12.
6. Insulation wool and cladding sheet shall be free supply from M/s BPCL. However,all
ancillary material for insulation work like Self tapping screws of slotted pan
head/round head. (Size 7 & 10 - 1/2 & 3/4 long), Bituminized anticorrosive paint,
Bituminous felt (Tar felt), Asian paint make Apcolite knifing paste filler grey,
Tarpaulin, Mastic sealing compound, fiber solution, A1 strapping band (25 mm x 24
SWG), 1.5 x 25 MM carbon steel strip support ring, 3 mm thick Asbestos mill board
and 25 mm x 3 mm thick asbestos band / tape, Mesh woven glass fiber for moisture
barrier, Asbestos flop shall be in Contractor scope.
7. The measurement shall be as per IS 14164:2008 and application shall be as per
BPCL Standard AE-DEP-M-12 Rev 3.
8. Application of asbestos rope includes supply and application of weather proofing
Compund and quick setting plaster.
Page 2 of 2