Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ABSTRACT
At Kidd Creek, the annual production of 4.5 million tonnes of ore has
been achieved primarily with sublevel blasthole stoping. This mining
method has allowed underground operations to meet the designed
production capacity wh.ile maintaining an outstanding safety record. To
achieve this goal, rock mechanics principles have been integrated into
each facet of mining in the planning stage, in the production stage, and
in various stages of ground support. This paper evaluates the two
adopted mining sequences based on ground stress patterns, blasting
control, ground reinforcement, backfill support, and numerical modelling
for stope stability at the mines.
BLASTHOLESTOPING AT KlDD CREEK MINES
INTRODUCTION
orebody from 1966 until 1977, when the pit I W".Z -7.7
c-m-m
-.
. . .
..- m
..
Development of the underground mine rn Is,- m , , t
Smooth 0.4 26
slickensided
Rough 0.7 31
slickensided
Rough 1.8 30
geologic
fractures
* S t r e n g t h r a t i n g b a s e d on t h e r a t i o o f t h e e l a s t i c modulus and u n i a x i a l
compressive s t r e n g t h v a l u e s l i s t e d i n T a b l e 1.
-
(1)
(2 853 53.2 1 077112 39.9 170118 16.3 318170
( 1 ) Using CSIR b i a x i a l ( d o o r s t o p p e r )
(2) Using CSIR t r i a x i a l
98 CEOMECHANICS APPLICATIONS, UNDERGROUND MINING
FIELD STRESSES
Measurements i n d i c a t e d t h a t t h e major p r i n c i p l e
s t r e s s i s o r i e n t e d roughly i n t h e e a s t - u e s t
d i r e c t i o n and t h e i n t e r m e d i a t e p r i n c i p l e s t r e s s i s
i n t h e north-south d i r e c t i o n . Both l i e w i t h i n a
s u b h o r i z o n t a l p l a n e , w i t h a p p r o x i m a t e l y 2 0 , 10 and
3% d i f f e r e n c e i n magnitude a t t h e 1600, 2400 and
2800 l e v e l s r e s p e c t i v e l y , and become i s o t r o p i c FIGURE 3: STRESS CHkWGE AT PIT BOTTOM
GEOMECHANICS APPLICATIONS, UNDERGROUND MINING
Our e s t a b l i s h e d r e l a t i o n s h i p s between t h e
c h a r g e weight p e r d e l a y and t h e d e g r e e of
v i b r a t i o n damage appeared t o b e i n good agreement
w i t h t h e p u b l i s h e d work [ C o a t e s , 19811.
PILLAR STRENGTH
It i s known t h a t t h e i n - s i t u compressive
"
s t r e n g t h of l a r g e rock masses, such a s mine
p i l l a r s , i s much lower t h a n t h e l a b o r a t o r y
compressive s t r e n g t h of s m a l l rock specimens.
T h i s i s due t o t h e e x i s t e n c e of g e o l o g i c a l
d i s c o n t i n u i t i e s w i t h i n t h e rock mass. The
,<-I ++' geometry of t h e p i l l a r and t h e d u r a t i o n of
PLAN VIEW e x p o s u r e have been i d e n t i f i e d as parameters
affecting the characteristics as well.
FIGURE 4 : ABUTMENT STRESS AS A FUNCTION OF
DISTANCE For g e n e r a l d e s i g n purposes t h e i n - s i t u
compressive s t r e n g t h of p i l l a r s , Qu, can be found
DYNAMIC LOADING FROM BLASTING EFFECTS from e q u a t i o n ( 4 ) .
Kidd C r e e k ' s f i r s t e x p e r i e n c e i n f i r i n g
l a r g e 200 mm d i a m e t e r b l a s t h o l e s f o r s t o p e
b l a s t i n g c a u s e d e x c e s s i v e damage t o t h e Where Oc = u n i a x i a l compressive s t r e n g t h of Bx
adjacent p i l l a r s . I n o n e c a s e , s l o u g h i n g of (41 m diameter) cores a t the length -
p i l l a r w a l l a l o n g t h e s t o p e boundary amounted d i a m e t e r r a t i o of 2
t o some 15,000 t o n n e s of o v e r - s i z e d o r e , which
l e d t o s e c o n d a r y b l a s t i n g problems. In the Because of t h e h i g h e r h o r i z o n t a l f i e l d s t r e s s
o t h e r c a s e s , o v e r b r e a k of t h e f o o t w a l l o r i n t h e mines a s d e s c r i b e d e a r l i e r , e v a l u a t i o n of
hanging w a l l r e s u l t e d i n t h e d i l u t i o n of o r e p i l l a r s t a b i l i t y was r e l a t e d t o t h e p i l l a r l e n g t t
g r a d e . Some o f t h e o v e r b r e a k c o u l d b e r a t h e r than its f r e e standing height.
a t t r i b u t e d t o u n r e c o g n i z e d major g e o l o g i c
s t r u c t u r e s , b u t a l a r g e p e r c e n t a g e was due t o
t h e dynamic l o a d i n g .
BLASTHOLE STOPING AT KlDD CREEK MINES 101
GROUND SUPPORT
S h o t c r e t i n g , mesh s c r e e n s , t i m b e r s e t s , and
c o n c r e t e w a l l s a r e o c c a s i o n a l l y used t o p r o v i d e
a d d i t i o n a l support.
I n t h e roof of some l a r g e e x c a v a t i o n s , o r i n
some s t o p e w a l l s , combinations of l o n g c a b l e b o l t s
DAYS g r o u t e d w i t h cembnt, and r e s i n g r o u t e d r e b a r s a r e
used. Most c a b l e b o l t s a r e t e n s i o n e d t o one-half
of t h e u l t i m a t e s t r e n g t h t o p r o v i d e a c t i v e
FIGURE 5: VARIATION OF ABUTMENT STRESS AS A support.
FUNCTION OF EXPOSURE TIME
GEOMECHANICS APPLICATIONS, UNDERGROUND MINING
Measurement o f t h e t r a n s i t i o n z o n e o f a n
abutment s t r e s s , shown i n F i g u r e 4 p r o v i d e s a EFFECTS OF GROUND STRESSES ON M I N I N G METHOD
g u i d e l i n e f o r t h e minimum l e n g t h r e q u i r e m e n t o f
c a b l e b o l t s t o support s t o p e w a l l s , one-half t h e I n s e l e c t i n g a n a p p r o p r i a t e mining method
s m a l l e r w i d t h of t h e o p e n i n g t o b e r e i n f o r c e d . f o r No.2 mine t o e x t r a c t o r e below t h e 2600
The s p a c i n g i s g e n e r a l l y 3.3 m x 3.3 m. l e v e l , r o c k mechanics c o n c e r n s had been
t h a t t h e ground p r e s s u r e s i n d e e p e r l e v e l s
The l a m i n a t e d beam t h e o r y i s t h e n u s e d t o f i n d would be c o n s i d e r a b l y h i g h e r t h a n t h o s e i n
t h e l e n g t h and s p a c i n g o f s h o r t b o l t s , i n s t a l l e d No.1 m i n e , and t h a t t h e a v e r a g e h o r i z o n t a l
between t h e c a b l e b o l t s . The s p a c i n g o f b o l t s i s f i e l d s t r e s s would be about two and h a l f t i m e s
k e p t s m a l l e r t h a n t h e l e n g t h and i s l e s s t h a n higher than t h e v e r t i c a l stress.
t h r e e times t h e average block s i z e , t o t a k e i n t o
consideration t h e degree of rock f r a c t u r i n g . To m a i n t a i n a s a f e working environment,
mining o p e r a t i o n s were d e s i r e d such t h a t no
The m i n e s have been u s i n g c o n s o l i d a t e d r o c k f i l l one would work under f r e s h l y b l a s t e d backs.
t o f i l l mined o u t s t o p e s t o s t a b i l i z e a d j a c e n t To s a t i s f y t h i s , b l a s t h o l e s t o p i n g was f i n a l l y
p i l l a r s , and t o p r o v i d e o v e r a l l mine s u p p o r t s o a d o p t e d . However, due t o t h e h i g h ground
t h a t t h e maximum e x t r a c t i o n o f o r e c a n b e a c h i e v e d p r e s s u r e , open s t o p i n g w i t h d e l a y e d
s a f e l y w i t h a minimum d i l u t i o n [Yu and C o u n t e r , b a c k f i l l i n g might pose s t a b i l i t y problems f o r
19831. s t o p e w a l l s , p a r t i c u l a r l y weak hanging w a l l s .
Hence s t o p e dimensions were l i m i t e d t o 1 5 m
From t h e m o n i t o r e d s t r e s s c h a n g e i n a p i l l a r wide by 30 m l o n g by 60 m h i g h , s m a l l e r t h a n
a d j a c e n t t o a s t o p e b e i n g f i l l e d , i t was o b s e r v e d t h o s e i n No.1 mine. Also, t h e s t o p e was
t h a t t h e b a c k f i l l not only prevented stope wall t r o u g h e d a t t h e bottom and peaked a t t h e t o p
sloughing, but it a l s o applied a confining s o t h a t t h e s t o p e c o u l d be t i g h t l y f i l l e d , f o r
p r e s s u r e on t h e p i l l a r , analogous t o a t r i a x i a l a d d i t i o n a l support.
c e l l . T h i s enhanced t h e p o s t y i e l d p i l l a r
s t r e n g t h s i g n i f i c a n t l y [Yu, 19831. To d a t e , t h e The r e l a t i v e l y low s t i f f n e s s o f t h e
b a c k f i l l produced from -150 mm a g g r e g a t e and 52 c o n s o l i d a t e d r o c k f i l l , o n e - t w e n t i e t h of t h e
cement by w e i g h t h a s shown f r e e s t a n d i n g e x p o s u r e s r o c k m a s s , would h a r d l y c o n t r i b u t e t o t h e
50 m wide x 135 m h i g h . No d i l u t i o n o f f i l l uniform s t r e s s d i s t r i b u t i o n . As a r e s u l t , r i b
m a t e r i a l was s e e n d u r i n g t h e s t o p e mucking. p i l l a r s would c a r r y a h i g h s t r e s s c o n c e n t r a -
t i o n r e s u l t i n g i n p i l l a r r e c o v e r y problems.
MINE PLANNING
F u r t h e r m o r e , i n view o f t h e " s p i t t i n g
At Kidd C r e e k , i t h a s been a s t a n d a r d p r a c t i c e ground" phenomena which o c c u r r e d d u r i n g
t h a t any underground m i n i n g p l a n s h o u l d b e i n i t i a l development work t h r o u g h d a c i t e and
reviewed by a l l d e p a r t m e n t s c o n c e r n e d , i n c l u d i n g some o f t h e m a s s i v e s u l p h i d e o r e on t h e 2800
r o c k m e c h a n i c s . Mining p l a n s car, g e n e r a l l y b e l e v e l , c a r e f u l mining sequencing was j u s t i f i e d
divided i n t o t h r e e categories; these a r e t h e short t o p r e v e n t t h e p o s s i b l e o c c u r r e n c e of
t e r m , i n t e r m e d i a t e t e r m and l o n g t e r m p l a n s . r o c k b u r s t s , e v e n though most r o c k s i n No.2
mine would s t o r e o n l y one t h i r d o f t h e s t r a i n
Short term p l a n s d e a l mainly w i t h d a i l y e n e r g y o f b u r s t prone r o c k s , such a s R e v e t t e
p r o d u c t i o n l a y o u t s . Rock m e c h a n i c s p r o v i d e s q u a r t z i t e from Idaho mines [Chan, 19701.
b l a s t i n g c o n t r o l by r e v i e w i n g e v e r y b l a s t d e s i g n ,
and a l s o p r o v i d e s i n f o r m a t i o n o n t h e e f f e c t s o f A m i n i n g sequence which t o o k i n t o a c c o u n t
b l a s t i n g t o ground s t a b i l i t y . A d d i t i o n a l ground t h e s e c o n s i d e r a t i o n s was d e v e l o p e d , l e a v i n g no
s u p p o r t recommendations, p r i o r t o b l a s t i n g , a r e remanent p i l l a r s . The sequence o f s t o p i n g was
also furnished. t o open a l e a d s t o p e i n t h e c e n t r e of a n o r e
z o n e , a g a i n s t t h e hanging w a l l , and b a c k f i l l
The i n t e r m e d i a t e t e r m p l a n s i n c l u d e p r o p o s a l s i t . A second s t o p e was t h e n mined
o n m i n i n g a m a j o r b l o c k between o n e l e v e l and i m m e d i a t e l y n e x t t o t h e f i r s t s t o p e towards
a n o t h e r , and t h e a s s o c i a t e d development work. In t h e f o o t w a l l [ B e l f o r d , 19811. S t o p e b l a s t i n g
such a p r o p o s a l , t h e e f f e c t s of s t o p e openings, o c c u r r e d on e i t h e r s i d e o f t h e i n i t i a l s t o p e ,
m i n i n g s e q u e n c i n g , and b l a s t i n g v i b r a t i o n s o n f o u r weeks a f t e r t h e placement of c o n s o l i d a t e d
l a r g e s c a l e ground s t a b i l i t y , a s w e l l a s b a c k f i l l r o c k f i l l a s shown i n F i g u r e 6.
requirements a r e studied.
Mining s e q u e n c i n g f o r l o w e r b l o c k s h a s
Evaluation of t h e s t a b i l i t y of s t o p e openings f o l l o w e d t h e same p a t t e r n by commencing
includes a n a l y t i c a l a n a l y s i s , physical modelling, s t o p i n g from t h e c e n t r a l z o n e , w i t h o u t l e a v i n g
and n u m e r i c a l m o d e l l i n g w i t h f i n i t e e l e m e n t and a crown p i l l a r under t h e b a c k f i l l e d s t o p e abovl
BLASTHOLESTOPING AT KlDD CREEK MINES
To date, most of the stopes on 2800 level Various forms of back analysis combined with
have been mined out and backfilled, creating a underground observations, are used to evaluate the
filled block approximately 180 m along strike by accuracy of the modelled results. The following
80 m wide by 60 m high. No deterioration of the sections describe some of the case studies used.
stope backs have been noticed, possibly because of
the tight stopefill.
Case Study - No.1 Mine
Tangential compression cracking had been
observed at both sides of two 1.8 m diameter bored As stated previously, one of the controlling
vertical raises which were 7.5 m from the stope factors on the stability of underground
faces. This indicated that the high abutment workings in a high horizontal stress field is
stress, in the order of 100 MPa, had exceeded the the length to width (L/B) ratio of the opening(s1.
rock mass strength. The cracks, extending along Figure 7 is a contour plot of the induced
the entire height of the raises, were opposite maximum and minimum stresses as a function of
each other and were in a plane normal to the the applied horizontal stress. The contours
advancing wall of the stope. outline the active failure zone for a typical
and initial stope/pillar arrangement in No.1
NO radial or diagonal tension cracks were mine. The model satisfied the following
observed however. conditions:
During the course of production mining on the o The major applied horizontal stress
2800 level, only two cases of snapping ground have (Q1) was in the E-W direction. It had
been reported. The first location was at the a magnitude of 40 MPa which was equivalent
extreme end of the mining zone, resulting from the to the stress field on the 2000 level
high abutment field stress. The other occurred at (610 m). Q1 was 1.25 times the N-S
the centre of the mining zone in the footwall component ( Q2).
drift, where a major fault cut across a high grade
massive sulphide ore zone, creating a localized o In reference to Table 1, the ore strength
high stress concentration. was 160 MPa. The rock mass was of very
good quality and had CSIR and NGI ratings
NUMERICAL ANALYSIS of 85 and 100 respectively.
The recent introduction of a boundary o The stope L/B ratio was 1.7, while the
element program (BEP) [Hoek and Brown 19801 at pillar L/B ratio was 1.25.
Kidd Creek, allows for a fast, detailed
analysis of the induced stress distributions It should be noted that in Figure 7, the
around various stope and/or pillar geometries. symmetry around the X-axis was taken advantage
This information is used for outlining active of to minimize computer time. Therefore, only
failure zones in order to design ground one half of the stope/pillar layout was shown.
support, to ensure that development is not
located in overstressed ground, and to identify
critical stopes requiring prompt backfilling.
GEOMECHANICS APPLICATIONS, UNDERGROUND MINING
m ACT-
(a
FAILURE ZONE
-1 n-0.8 1
t
ID
(b)
-
0 5 D
FIGURE 8: ACTIVE FAILURE ZONE FOR A No. 1 MINE PILLAR WITH A LOW ROCK MASS RATING
F i g u r e 7 a i s a p l o t of t h e Urnax/ U1
c o n t o u r s w h i l e F i g u r e 7b shows t h e
Umin/ U1 c o n t o u r s . The magnitude of t h e
maximum t a n g e n t i a l s t r e s s a t mid l e n g t h a l o n g
t h e p i l l a r w a l l a t A , was 1.5 t i m e s g r e a t e r
t h a n a t t h e s t o p e w a l l a t B. Again a t mid
l e n g t h , t h e magnitude of t h e induced s t r e s s a t
t h e c e n t e r of t h e p i l l a r a t C , was 1.5 times
l a r g e r t h a n a t t h e p i l l a r w a l l s a t A. Review
of F i g u r e 7b shows t h a t t h e c o n f i n i n g s t r e s s a t
t h e c e n t e r of t h e p i l l a r a t C was reduced by
o n l y 10% i n comparison t o t h e s t r e s s l e v e l i n
t h e s t o p e w a l l a t D. No t e n s i l e s t r e s s e s were
developed i n t h e p i l l a r .
i l l u s t r a t e s t h e e x t e n t of c r u s h i n g o f t h e d r i f t I n summary, t h e u s e of BEP h a s h e l p e d i n
corners a s well a s t h e 'arched' f a i l u r e s u r f a c e of defining the c r i t i c a l parameters f o r e v a l u a t i n g
the wall. I n t h i s c a s e , t h e c a u s e of t h e h i g h t h e s t a b i l i t y of s t o p e s and p i l l a r s i n No.1 mine.
s t r e s s c o n c e n t r a t i o n was due t o t h e t r a n s f e r o f The most c r i t i c a l p a r a m e t e r f o r s t a b i l i t y , a s i d e
t h e abutement s t r e s s f i e l d a s s o c i a t e d w i t h mining f r o m dynamic l o a d i n g , i s t h e g e o l o g i c a l s t r u c t u r e
of an a d j a c e n t p i l l a r . These c o n d i t i o n s of which c o n t r o l s t h e e x t e n t of t h e a c t i v e f a i l u r e
extended s h e a r f a i l u r e o c c u r r e d more f r e q u e n t l y i n zone. It c a n be c o n c l u d e d t h a t f o r ~ i l l a r sh a v i n g
e x c a v a t i o n s where t h e r o c k mass was o f low q u a l i t y t h e same geometry a s i n F i g u r e 7 , t h e c o n d i t i o n s
and t h e g e o l o g i c a l s t r u c t u r e ( f a u l t s , s c h i s t o s i t y ) of o v e r s t r e s s e d ground i n p r i m a r y e x t r a c t i o n i s
was a l i g n e d p a r a l l e l t o t h e b o u n d a r i e s of t h e h i g h l y u n l i k e l y t o o c c u r f o r mining above t h e 2000
opening. level.
o A post y i e l d p i l l a r s t r e n g t h can e x i s t i n a n
overstressed area. I f a stope i s allowed t o
r e m a i n empty l o n g e r t h a n t h e s t a n d u p t i m e o f
t h e r o c k mass, s l o u g h a g e of t h e p i l l a r w a l l s
w i l l occur. It h a s b e e n o b s e r v e d
llnderqround t h a t t h e s t a n d u p t i m e o f o r e i s
i n t h e o r d e r of s i x months w h i l e t h e
hanging w a l l s h e a r zone i s i n t h e r a n g e o f
one t o two months. In c r i t i c a l areas, the
s t o p e / p i l l a r walls a r e cable bolted o r
prompt b a c k f i l l i n g i s s c h e d u l e d .
I n r e f e r e n c e t o F i g u r e 9 a , and u s i n g t h e
same for;;.at a s t h e p r e v i o u s example, t h e
t a n g e n t i a l s t r e s s a l o n g t h e p i l l a r a t A was
2.2 t i m e s l a r g e r t h a n a l o n g t h e s t o p e w a l l a t
H. The m a g n i t u d e o f t h e s t r e s s a t t h e c e n t e r
of t h e p i l l a r , a t C, was 1 . 1 t i m e s g r e a t e r t h a n
t h e boundary s t r e s s a t A . The a v e r a g e No.2
mine p i l l a r s t r e s , was 1 . 3 t i m e s l a r g e r t h a n i n
t h e No.1 mine model ( F i g u r e 7 a ) .
F i g u r e 9 h , i s t h e p l o t of t h e minimum o r
c o n f i n i n g s t r e s s a s a f u n c t i o n of t h e maximum
horizontal stress. Significant tensile stresses
were d e v e l o p e d w i t h i n t h e p i l l a r c o r e ,
eliminati-ng the confining s t r e s s , r e s u l t i n g i n
7HCTU 2: PTLLAR FRACTURE ZONE CBSERVED 1 N A DRIFT t h e complete f a i l u r e of t h e p i l l a r .
106 GEOMECHANICS APPLICATIONS, UNDERGROUND MINING
The c r i t i c a l d e p t h f o r p i l l a r s t a b i l i t y c a n b e T h i s c u r v e c a n b e used t o a p p r o x i m a t e t h e
estimated using t h e following relationship. l i m i t i n g l e n g t h o f s t o p e s i n No.2 mine. For
e x a m p l e , a s t o p e o n t h e 3200 (975 m) b l o c k was
(7) e x c a v a t e d f o r a inaximum l e n g t h o f 45 m w i t h a L / R
r a t i o o f 3. Some s l o u g h a g e o c c u r r e d a l o n g t h e
Where Z = c r i t i c a l d e p t h (m) h a n g i n g w a l l o f t h e s t o p e . The c a l c u l a t e d s a f e t y
Qu = estimated i n - s i t u compressive f a c t o r a g a i n s t s l o u g h a g e was 0.77. This safety
s t r e n g t h (10-11 IIPa) f a c t o r was d e t e r m i n e d u s i n g a s t r e n g t h / s t r e s s
F = s a f e t y f a c t o r (1.2) r e l a t i o n s h i p and F i g u r e l o , a s shown below:
C = s p e c i f i c g r a v i t y (3.2)
A = ~ i l l a rb o u n d a r v s t r e s s r a t i o ( 1 . 3 6 )
K = h o r i z o n t a l s t r e s s r a t i o (2.5)
The c a l c u l a t e d c r i t i c a l d e p t h f o r t h e
s t o p e / p i l l a r g e o m e t r y i n F i g u r e 9 was 8 1 3 m, Where F = safety factor
and c o r r e l a t e d v e r y w e l l w i t h u n d e r g r o u n d Qu = e s t i m a t e d i n - s i t u
observations. For example, due t o p r o d u c t i o n c o m p r e s s i v e s t r e n g t h ( 7 6 MPa)
r e q u i r e m e n t s , a t e m p o r a r y p i l l a r was d e v e l o p e d U 1 = p r i n c i p a l s t r e s s ( 6 0 MPa)
b e t w e e n t h e 2600 ( 8 0 0 m) a n d t h e 2800 ( 8 5 3 m) Qtw = s t r e s s c o n c e n t r a t i o n ( 1 . 6 5 )
l e v e l s a t No.? mine. The p i l l a r had d i m e n s i o n s f o r L/B=3
o f 1 5 m w i d e , by 3 0 m l o n g , b y 6 0 m h i g h . D u r i n g
the preparation of the adjacent stope for F o r c o m p a r i s o n , a c o n v e n t i o n a l s t o p e i n No.2
b a c k f i l l i n g , sloughage i n t h e o r d e r of 9,000 m i n e h a s a L/B r a t i o o f 2.0. Using t h e same
tonnes occurred along t h e p i l l a r wall. The f a i l e d p r i n c i p a l s t r e s s m a g n i t u d e a s d e f i n e d above and
zone e x t e n d e d b e t w e e n t h e 28-3 ( 8 2 3 m) s u b l e v e l F i g u r e 1 0 , t h e s a f e t y f a c t o r a g a i n s t hanging w a l l
and t h e 2600 l e v e l . A f t e r b a c k f i l l i n g was s l o u g h a g e would a p p r o a c h 1.0.
c o m p l e t e d , a c r o s s c u t was d e v e l o p e d a l o n g t h e
center l i n e of the pillar. L a r g e , o p e n ( 2 5 mm) I n summary, t h e u s e o f BEP h a s p r o v i d e d
r a d i a l and t a n g e n t i a l c r a c k i n g was o b s e r v e d i n t h e v a l u a b l e i n s i g h t i n t o t h e v a r i o u s [nodes o f f a i l u r e
crosscut. The r a d i a l c r a c k s a p p e a r e d t o e x t e n d observed underground. This information can then
a c r o s s t h e e n t i r e width of t h e p i l l a r . b e u s e d f o r e v a l u a t i n g and d e v e l o p i n g o p e r a t i n g
p r o c e d u r e s f o r proposed mining p l a n s with a
Figure 10, is a plot of the variation of the r e l a t i v e l y h i g h l e v e l of confidence.
boundary s t r e s s c o n c e n t r a t i o n s a s a f u n c t i o n o f
t h e L/B r a t i o o f a s i n g l e o p e n i n g ( s t o p e ) u n d e r a n
i s o t r o p i c s t r e s s f i e l d . The v a l u e s p l o t t e d w e r e ROCK MECHANICS INSTRUMENTATION
g e n e r a t e d u s i n g REP. The s t r e s s c o n c e n t r a t i o n s
were c a l c u l a t e d a l o n g t h e s t o p e w a l l s a t Kidd C r e e k h a s r e g a r d e d r o c k m e c h a n i c s i n s t r u -
mid-length ( Q t l ) , mid-width ( Q t w ) , and ments a s indispendable t o o l s , a i d i n g i n t h e
near t h e c o r n e r s ( On,). d e t e c t i o n and p r e d i c t i o n o f g r o u n d i n s t a b i l i t y .
The m e a s u r e d d a t a have a l s o p r o v i d e d u s e f u l
p a r a m e t e r s i n t h e d e s i g n o f more s t a b l e under-
g r o u n d w o r k i n g s , which w e r e e s t a b l i s h e d
e m p i r i c a l l y i n t h e past.
V a r i o u s c o n v e n t i o n a l and c u s t o m b u i l t
i n s t r u m e n t s a r e b e i n g u s e d f o r m o n i t o r i n g ground
movement, g r o u n d s t r e s s , b l a s t i n g v i b r a t i o n , and
r o c k p r o p e r t i e s b o t h i n t h e l a b o r a t o r y and i n t h e
w o r k i n g a r e a s [Yu, 19831.
.4n AGA G e o d i m e t e r 7 1 0 , u t i l i z i n g 5 7 p r i s m
r e f l e c t o r s i n s t a l l e d on t h e p i t benches, has been
m o n i t o r i n g t h e p i t w a l l f o r s e v e r a l y e a r s . The
a v e r a g e r e l a x a t i o n rates i n t h e h a n g i n g w a l l and
t h e f o o t w a l l a r e 1 . 6 a n d 1 . 1 cm p e r y e a r
respectively.
1 s
1
. . .
2 3 4 5
I m
6
p r e c i s e movement m o n i t o r i n g .
Some c u s t o m b u i l t d e v i c e s s u c h a s c r a c k g a u g e s ,
c r a c k m e t e r s , s l o u g h n e t e r s , and reinote r e a d i n g
LIB c o n v e r g e n c e m e t e r s h a v e b e e n d e s i g n e d t o meet
FIGURE 1 0 : VARIATION OF STOPE WALL STRESS WITH t h e s p e c i a l monitoring requirements of c e r t a i n
SPAN OF OPENIWG areas.
A b l a s t i n g v i b r a t i o n monitor was assembled t o REFERENCES
monitor t h e peak p a r t i c l e a c c e l e r a t i o n and peak
p a r t i c l e v e l o c i t y u s i n g a c c e l e r o m e t e r s and The Management and S t a f f of E c s t a l l Mine Ltd.,
velocity sensors. 1974, "The E c s t a l l S t o r y " , CIM B u l l e t i n ,
Volume 67, No.745, 1974, 95 pp.
A SINCO MS-2 Geo-monitor w i t h e i g h t t r a n s d u c e r s Herget, G. and M i l e s , P., 1974, "Mining
i s o c c a s i o n a l l y used t o monitor s e i s m i c Research a t t h e Kidd Creek Mine, Timmins,
a c t i v i t y i n a r e a s f r e e from any machine made P a r t 1: G e o t e c h n i c a l I n v e s t i g a t i o n s " ,
n o i s e t o avoid i n t e r f e r e n c e . CANMET I n t e r n a l Report 74133,-1974, 48 pp.
M i l e s , P. and H e r g e t , G., 1976, "Underground
A McPhar s t r e s s monitor, capable of S t r e s s ~ e t e r m i n a t i o n sUsing t h e D O O ~
d e t e c t i n g high frequency m i c r o s e i s m i c i t y , i s Stopper Method a t Timmins, Ontario", CANMET
undergoing t e s t i n g on rock specimens and REPORT MRPIMRL 76-148 TR, 1976, 41 pp.
underground f o r a g r e a t e r understanding of s e i s m i c Yu, Y.S., 1975, "Mining Research a t t h e Kidd
phenomena. Creek Mine, Timmins, P a r t 4: The E f f e c t o f
R e s i d u a l T e c t o n i c S t r e s s e s on S t a b i l i t v of
Pre-mining f i e l d s t r e s s e s i n t h e mines were t h e Excavations", CANMET REPORT MRP/M&
measured p r e v i o u s l y u s i n g CSIR s t r a i n c e l l s by 75-99(TR), 1975. 4 3 -p -p .
t h e over-coring method, w h i l e abutment s t r e s s Hedley, D., Herget, G., M i l e s , P., and Yu, Y.S.,
changes have been measured w i t h IRAD v i b r a t i n g 1979, "CANMET'S Rock Mechanics Research a t
w i r e s t r e s s meters a s mentioned i n t h e t h e Kidd Creek Mine", CANMET REPORT
preceding s e c t i o n s . M38-13/79-11, 1979, 52 pp.
Yu, T.R., 1982, " V a r i a t i o n s i n t h e Abutment
Laboratory and f i e l d t e s t i n g equipment S t r e s s F i e l d s Due To S t o ~ eExcavation and
i n c l u d e a 30 tonne c a p a c i t y Versa t e s t e r , Backfilling"., presented a t t h e 14th
p o i n t l o a d t e s t e r , rock b o l t p u l l t e s t e r , and Canadian Rock Mechanics Symposium,
assembled p l a t e load t e s t e r . Vancouver.
Blakey, P.N., Yu, T.R. and Tansay, D.O., 1976,
"Kidd Creek's I n n o v a t i v e B l a s t h o l e S u b l e v e l
CONCLUSIONS S t o p i n g " , J o u r n a l of Mining Engineering,