Charter Objective
This charter serves to provide the ABC Company with the initiation of the Office Move project.
Assumptions:
We assume that staff members from the ABC Company will pack up their personal belongings
prior to the move, making it easier for the moving company to properly and efficiently complete
the move. We assume that there will be a loading dock for the movers to safely transfer all office
supplies. We assume that there will be sufficient space and supplies, such as outlets and
routers for all computers. We assume that the new space will be clean and ready for painting on
May 1st. We assume that some employees will not be pleased with this change of location and
alteration of hierarchy within the company forcing some individuals to leave the company. We
assume that all cubicles, offices, and conference rooms at the original location have their own
phones that will be transferred to the new location. We assume that the method and task of
assigning new offices to employees will be taken care of internally prior to the move. We
assume that the ABC Companys lease will extend until June 1st, allowing for adequate time for
the move. We also assume that the original office is left clean and undamaged.
Constraints:
We are planning for nice weather on the day of the move, but are prepared to adjust our means
of transportation in case of rain. Because of employee dissatisfaction with the move, we would
advise the company to provide incentives to stay with the company, such as compensating
individuals for the extra money he or she will spend commuting to work or provide those
employees with the opportunity to work from home on certain days of the week. We have
contacted a cleaning facility in case the facility is not clean, and therefore not ready to be
painted and carpeted.
Stakeholders
The stakeholders involved in this project include the entire staff and clientele of the ABC
Company, which is made up of three departments; Finance, Information Systems and Human
Resources. In addition, other stakeholders are the multiple suppliers and vendors for our new
furniture, carpeting, technology, and paint, as well as the moving contractors. Other potential
stakeholders would be other offices in the building, the original company that had the office
space before us, the old buildings of the offices, and the MBTA stop next the new building. In
addition, our consulting firm would be stakeholders.
Major Milestones
The major milestones are:
February 18th- Initial Planning Meeting
March 2nd- Informing The Staff of the Move
March 5th- Hire Painting, Carpeting, and Technology Consultant and Sign all Previously
Created Contracts
March 15th- Deciding Who Gets an Office Versus a Cubicle
April 27th-Purchasing Furniture For Conference Rooms and Offices
May 1st- New Office Space Available
May 1st- Ensure Everything Is Ready for Painting and Carpeting
May 2-3rd- Painting
May 6-8- Carpeting
May 11th- Begin Delivery/Installation of New Furniture
May 16th-17th- Move the Information Systems Department
May 23rd-24th- Move the Finance Department
May 30th-31st- Move the Human Resource Departments
Budget Estimate
The budget for the ABC Company Office Move, and will be provided by the ABC Company. A
total cost is estimated to be $58,450.
Communication Plan
May be a distruption during the move. Communicating with them after move, building
Other offices in the building New community in the building 11 2 owner to communicate prior if need be.
Assuming that there is another company
Owners of previous building Losing a renter 12 1 moving into the offices.
Increased MBTA use by newly relocated
MBTA employees. 7 1 Not applicable
Contract clearly defined, signed, specific time,
Cleaning company Making transition smooth if need be 13 1 date, cost, job description.