1.3 Witness MT
As per ITP step 23(welding inspection-magnetic particle inspection) , GQIS inspector witnessed MT process
for weld seam of pipe 3568-C03-063; Before testing, GQIS inspector reviewed the certificates for MT
persons, checked calibration certificate for MT equipment and magnetic suspension liquid, test condition,
procedure, test process, applicable for calibration piece, confirm the that are satisfactory. Indication been
found at three location and manufacturer state they would remove the defect totally and repair according to
approval repair procedure, after that will checked by MT again.
1.4 Inspection cutting, dimension, surface quality and rolling for pile No.3568-C13-077-B1
As per ITP step 14(pile forming-visual and dimension inspection) ,GQIS inspector performed visual
inspection for pile No. 3568-C13-077-B1 about cutting, dimension, surface quality and rolling, confirm all the
inspection scope satisfactory the drawing and specification and not found any surface defect, also compare
with original inspection data and verified they are correspond.
Picture
Inspection cutting, dimension, surface quality and rolling for pile No.3568-C13-077-B1
Accepted Yes Non-Compliant No