Calcs By: Date: Version:

1.0 / 2015 / WBB


TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
CALCULATION Remarks

Rain Intensity:

Ac = Area of Catchment (Ha) = 0.415 Ha

Reference Table:-
Site Area (ha) Time of Concentration,tc (min)
0.2 - 2.0 5
2.0 - 6.0 10
6.0 - 10.0 15
10 15*
*QPs to substantiate with hydraulic calculation if tc>15min is used.

Area Served by Drainage System Return Period (T)


Catchment of less than 100 Ha 10 years
Catchment of 100 ~ 1000 Ha 25 years
Catchment of more than 1000 Ha
50 ~ 100 years
or Critical Installation

Return Period, T Value A Value B


10 8913 36

A 8913
I = = = 217.39 mm/hr Average rainfall Intensity
Tc + B 41

Rational Formula :
Runoff Coefficient Table :
Characteristic of catchment when fully developed Runoff Coefficient, Cpost

Road, Highways, Airport Runways, Paved up areas 1.00


Urban areas fully and closely built up 0.90
Residential/ Industrial areas densely built up 0.80
Residential/ Industrial areas not densely built up 0.65
Rural areas with fish ponds and vegetable gardens 0.45

Cpost I Ac 0.80 x 217.39 x 0.415


Qpost = = Peak Runoff From Site
360 360
= 0.20 m3/s
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
According Clause 7.1.5 in Code of Practice on Surface Water Drainage Remarks
Ctarget = 0.55 = Callowable Runoff coefficient

Ctarget I Ac 0.55 x 217.39 x 0.42


Qtarget = =
360 360 Target Peak Discharge
= 0.138 m3/s

8913 x Cpost x Ac 8913 x 0.80 x 0.415


K1 = = = 493.186
6 6

8913 x Ctarget x Ac 8913 x 0.55 x 0.415


K2 = = = 169.533
12 12

K3 = tc + 36 = 5 + 36 = 41

36K1 K3 36 x 493.186 x 41
txmax = -K3 +( )0.5 = -41 +( )0.5
K2 169.533

= 24.527 min

(Cpost - Ctarget)(tc+36) ( 0.80 - 0.55 )x( 5 + 36 )


txlimit = =
Ctarget 0.55

= 18.636 min

txcritical = Min of (txmax , txlimit ) = 18.636 min

tz = tcritical + tc = 18.636 + 5 Critical Rainfall Duration


= 23.636 min

8913 8913
Iz = =
tz + 36 Average Rainfall Intensity for Critical
( 23.636 + 36 ) Storm Event
= 149.46 mm/hr

Cpost Iz Ac 0.80 x 149.46 x 0.415


Qz = = Peak Inflow Rate for Critical Storm
360 360
Event
= 0.138 m /s
3

K1(tc+txcritical) K2(2tc+txcritical)
Vt = -
(K3+txcritical) K3

493.186 + ( 5 + 18.636 ) 169.533 x ( 2 x 5 + 18.636 )


= -
( 41 + 18.636 ) 41
= 77.06 m3 Detention Tank Volume
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
CALCULATION Remarks

Rain Intensity:

Ac = Area of Catchment (Ha) = 0.415 Ha

Reference Table:-
Site Area (ha) Time of Concentration,tc (min)

0.2 - 2.0 5
2.0 - 6.0 10
6.0 - 10.0 15
10 15*
*QPs to substantiate with hydraulic calculation if tc>15min is used.

Area Served by Drainage System Return Period (T)

Catchment of less than 100 Ha 10 years


Catchment of 100 ~ 1000 Ha 25 years
Catchment of more than 1000 Ha
50 ~ 100 years
or Critical Installation

Return Period, T Value A Value B


10 8913 36

Rational Formula :
Runoff Coefficient Table :
Characteristic of catchment when fully developed Runoff Coefficient, Cpost

Road, Highways, Airport Runways, Paved up areas 1.00


Urban areas fully and closely built up 0.90
Residential/ Industrial areas densely built up 0.80
Residential/ Industrial areas not densely built up 0.65
Rural areas with fish ponds and vegetable gardens 0.45
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
Remarks
Description Symbol Zone A Zone B Zone C Zone D

Sub- Catchment Area A (ha) 0.136 0.166 0.097 0.016

Weighted Runoff Coefficient Cpost 0.800 0.800 0.800 0.450

Time of Concentration tc (min) 5.000 5.000 5.000 5.000

Average Rainfall Intensity for 10years Storm Event i10=A/(tc+B)


i10 (mm/hr) 217.390 217.390 217.390 217.390

Peak Discharge from Sub- Catchment Qpost=Cposti10A/360


Qpost (m3/s) 0.066 0.080 0.047 0.004

Maximum Allowable Peak Discharge From Entire Site


Qallowable=C0.55i10A/360 Qallowable (m3/s) 0.138

Target Runoff Coefficient Ctarget 0.55 0.55 0.55 0.45


Target Peak Discharge For Sub- catchment Qtarget=Ctargeti10A/360 Qtarget 0.045 0.055 0.032 0.004

Check Qtarget Qallowable - 0.137


Type of Detention System to Employ -

Constant K1=8913CpostAc/6
K1 161.622 197.274 115.275 10.562

Constant K2=8913CtargetAc/12
K2 55.558 67.813 39.626 5.281

Constant K3=tc+36 K3 41.0 41.0 41.0 41.0

tmax=-K3+(36K1K3/K2)0.5
tmax 24.527 24.527 24.527 13.332

txlimit=((Cpost-Ctarget)(tc+36))/Ctarget txlimit 18.636 18.636 18.636 0.000

txcritical=min of (tcmax ,txlimit) txcritical 18.636 18.636 18.636 0.000

Critical Rainfall Duration tz=txcritical+tc tz 23.636 23.636 23.636 5.000


Average Rainfall Intensity During Critical Rainfall Duration
Iz=8913/(tz+36) Iz
149.456 149.456 149.456 217.390
Peak Inflow Rate for Critical Storm Event
Qz=CpostizA/360 Qz
0.045 0.055 0.032 0.004
Required Detention Volume
Vt=(K1(tc+txcritical))/((K3+Cxcritical))- Vt
25.254 30.824 18.012 0.000
(K2(2tc+txcritical))/K3
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
CALCULATION Remarks

Rain Intensity:

Ac = Area of Catchment (Ha) = 0.415 Ha

Reference Table:-
Site Area (ha) Time of Concentration,tc (min)
0.2 - 2.0 5
2.0 - 6.0 10
6.0 - 10.0 15
10 15*
*QPs to substantiate with hydraulic calculation if tc>15min is used.

Area Served by Drainage System Return Period (T)


Catchment of less than 100 Ha 10 years
Catchment of 100 ~ 1000 Ha 25 years
Catchment of more than 1000 Ha
50 ~ 100 years
or Critical Installation

Return Period, T Value A Value B


10 8913 36

Rational Formula :
Runoff Coefficient Table :
Characteristic of catchment when fully developed Runoff Coefficient, Cpost

Road, Highways, Airport Runways, Paved up areas 1.00


Urban areas fully and closely built up 0.90
Residential/ Industrial areas densely built up 0.80
Residential/ Industrial areas not densely built up 0.65
Rural areas with fish ponds and vegetable gardens 0.45
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
Remarks
Description Symbol Zone A Zone B Zone C Zone D

Sub- Catchment Area A (ha) 0.136 0.166 0.097 0.016

Weighted Runoff Coefficient Cpost 0.800 0.800 0.800 0.450

Time of Concentration tc (min) 5.000 5.000 5.000 5.000

Average Rainfall Intensity for 10years Storm Event I10=A/(tc+B)


I10 (mm/hr) 217.390 217.390 217.390 217.390

Peak Discharge from Sub- Catchment Qpost=Cposti10A/360


Qpost (m3/s) 0.066 0.080 0.047 0.004

Maximum Allowable Peak Discharge From Entire Site


Qallowable=C0.55i10A/360 Qallowable (m3/s) 0.138

Target Runoff Coefficient Ctarget 0.8 0.43 0.42 0.45


Target Peak Discharge For Sub- catchment Qtarget=Ctargeti10A/360 Qtarget 0.066 0.043 0.025 0.004

Check Qtarget Qallowable - 0.138


Type of Detention System to Employ -

Constant K1=8913CpostAc/6
K1 161.622 197.274 115.275 10.562

Constant K2=8913CtargetAc/12
K2 80.811 53.017 30.260 5.281

Constant K3=tc+36 K3 41.0 41.0 41.0 41.0

tmax=-K3+(36K1K3/K2)0.5
tmax 13.332 33.109 33.986 13.332

txlimit=((Cpost-Ctarget)(tc+36))/Ctarget txlimit 0.000 35.279 37.095 0.000

txcritical=min of (tcmax ,txlimit) txcritical 0.000 33.109 33.986 0.000

Critical Rainfall Duration tz=txcritical+tc tz 5.000 38.109 38.986 5.000


Average Rainfall Intensity During Critical Rainfall Duration
Iz=8913/(tz+36) Iz
217.390 120.269 118.863 217.390
Peak Inflow Rate for Critical Storm Event
Qz=CpostizA/360 Qz
0.066 0.044 0.026 0.004
Required Detention Volume
Vt=(K1(tc+txcritical))/((K3+Cxcritical))- Vt
0.000 45.700 27.469 0.000
(K2(2tc+txcritical))/K3
Maximum Depth d (m) - 0.500 0.500 -
Area A (m2) - 91.399 54.938 -
Length , Width L x d (m) - 9.560 7.412 -
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
CALCULATION Remarks

Rain Intensity:

Ac = Area of Catchment (Ha) = 0.415 Ha

Reference Table:-
Site Area (ha) Time of Concentration,tc (min)
0.2 - 2.0 5
2.0 - 6.0 10
6.0 - 10.0 15
10 15*
*QPs to substantiate with hydraulic calculation if tc>15min is used.

Area Served by Drainage System Return Period (T)


Catchment of less than 100 Ha 10 years
Catchment of 100 ~ 1000 Ha 25 years
Catchment of more than 1000 Ha
50 ~ 100 years
or Critical Installation

Return Period, T Value A Value B


10 8913 36

Rational Formula :
Runoff Coefficient Table :
Characteristic of catchment when fully developed Runoff Coefficient, Cpost

Road, Highways, Airport Runways, Paved up areas 1.00


Urban areas fully and closely built up 0.90
Residential/ Industrial areas densely built up 0.80
Residential/ Industrial areas not densely built up 0.65
Rural areas with fish ponds and vegetable gardens 0.45
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
Remarks
Description Symbol Zone A Zone B Zone C Zone D

Sub- Catchment Area A (ha) 0.136 0.166 0.097 0.016

Weighted Runoff Coefficient Cpost 0.800 0.800 0.800 0.450

Time of Concentration tc (min) 5.000 5.000 5.000 5.000

Average Rainfall Intensity for 10years Storm Event I10=A/(tc+B)


I10 (mm/hr) 217.390 217.390 217.390 217.390

Peak Discharge from Sub- Catchment Qpost=Cposti10A/360


Qpost (m3/s) 0.066 0.080 0.047 0.004

Maximum Allowable Peak Discharge From Entire Site


Qallowable=C0.55i10A/360 Qallowable (m3/s) 0.138

Target Runoff Coefficient Ctarget 0.8 0.21 0.8 0.45


Target Peak Discharge For Sub- catchment Qtarget=Ctargeti10A/360 Qtarget 0.066 0.02105 0.047 0.004

Check Qtarget Qallowable - 0.138


Type of Detention System to Employ -

Constant K1=8913CpostAc/6
K1 161.622 197.274 115.275 10.562

Constant K2=8913CtargetAc/12
K2 80.811 25.892 57.637 5.281

Constant K3=tc+36 K3 41.0 41.0 41.0 41.0

tmax=-K3+(36K1K3/K2)0.5
tmax 13.332 65.046 13.332 13.332

txlimit=((Cpost-Ctarget)(tc+36))/Ctarget txlimit 0.000 115.190 0.000 0.000

txcritical=min of (tcmax ,txlimit) txcritical 0.000 65.046 0.000 0.000

Critical Rainfall Duration tz=txcritical+tc tz 5.000 70.046 5.000 5.000


Average Rainfall Intensity During Critical Rainfall Duration
Iz=8913/(tz+36) Iz
217.390 84.049 217.390 217.390
Peak Inflow Rate for Critical Storm Event
Qz=CpostizA/360 Qz
0.066 0.031 0.047 0.004
Required Detention Volume
Vt=(K1(tc+txcritical))/((K3+Cxcritical))- Vt
0.000 82.912 0.000 0.000
(K2(2tc+txcritical))/K3
Maximum Depth d (m) - 0.500 - -
Area A (m2) - 165.823 - -
Length , Width L x d (m) - 12.877 - -
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
CALCULATION Remarks

Rain Intensity:

Ac = Area of Catchment (Ha) = 0.415 Ha

Reference Table:-
Site Area (ha) Time of Concentration,tc (min)
0.2 - 2.0 5
2.0 - 6.0 10
6.0 - 10.0 15
10 15*
*QPs to substantiate with hydraulic calculation if tc>15min is used.

Area Served by Drainage System Return Period (T)


Catchment of less than 100 Ha 10 years
Catchment of 100 ~ 1000 Ha 25 years
Catchment of more than 1000 Ha
50 ~ 100 years
or Critical Installation

Return Period, T Value A Value B


10 8913 36

Rational Formula :
Runoff Coefficient Table :
Characteristic of catchment when fully developed Runoff Coefficient, Cpost

Road, Highways, Airport Runways, Paved up areas 1.00


Urban areas fully and closely built up 0.90
Residential/ Industrial areas densely built up 0.80
Residential/ Industrial areas not densely built up 0.65
Rural areas with fish ponds and vegetable gardens 0.45
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
Remarks
Description Symbol Zone A Zone B Zone C Zone D

Sub- Catchment Area A (ha) 0.136 0.166 0.097 0.016

Weighted Runoff Coefficient Cpost 0.800 0.800 0.800 0.450

Time of Concentration tc (min) 5.000 5.000 5.000 5.000

Average Rainfall Intensity for 10years Storm Event I10=A/(tc+B)


I10 (mm/hr) 217.390 217.390 217.390 217.390

Peak Discharge from Sub- Catchment Qpost=Cposti10A/360


Qpost (m3/s) 0.066 0.080 0.047 0.004

Maximum Allowable Peak Discharge From Entire Site


Qallowable=C0.55i10A/360 Qallowable (m3/s) 0.138

Target Runoff Coefficient Ctarget 0.475 0.475 0.8 0.45


Target Peak Discharge For Sub- catchment Qtarget=Ctargeti10A/360 Qtarget 0.039 0.04761 0.047 0.004

Check Qtarget Qallowable - 0.138


Type of Detention System to Employ -

Constant K1=8913CpostAc/6
K1 161.622 197.274 115.275 10.562

Constant K2=8913CtargetAc/12
K2 47.982 58.566 57.637 5.281

Constant K3=tc+36 K3 41.0 41.0 41.0 41.0

tmax=-K3+(36K1K3/K2)0.5
tmax 29.511 29.511 13.332 13.332

txlimit=((Cpost-Ctarget)(tc+36))/Ctarget txlimit 28.053 28.053 0.000 0.000

txcritical=min of (tcmax ,txlimit) txcritical 28.053 28.053 0.000 0.000

Critical Rainfall Duration tz=txcritical+tc tz 33.053 33.053 5.000 5.000


Average Rainfall Intensity During Critical Rainfall Duration
Iz=8913/(tz+36) Iz
129.075 129.075 217.390 217.390
Peak Inflow Rate for Critical Storm Event
Qz=CpostizA/360 Qz
0.039 0.048 0.047 0.004
Required Detention Volume
Vt=(K1(tc+txcritical))/((K3+Cxcritical))- Vt
32.830 40.071 0.000 0.000
(K2(2tc+txcritical))/K3
Maximum Depth d (m) 0.500 0.500 - -
Area A (m2) 65.659 80.143 - -
Length , Width L x d (m) 8.103 8.952 - -
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
CALCULATION Remarks

Rain Intensity:

Ac = Area of Catchment (Ha) = 0.415 Ha

Reference Table:-
Site Area (ha) Time of Concentration,tc (min)
0.2 - 2.0 5
2.0 - 6.0 10
6.0 - 10.0 15
10 15*
*QPs to substantiate with hydraulic calculation if t c>15min is used.

Area Served by Drainage System Return Period (T)


Catchment of less than 100 Ha 10 years
Catchment of 100 ~ 1000 Ha 25 years
Catchment of more than 1000 Ha
50 ~ 100 years
or Critical Installation

Return Period, T Value A Value B

10 8913 36
8913
Rational Formula :
Runoff Coefficient Table :
Characteristic of catchment when fully developed Runoff Coefficient, Cpost

Road, Highways, Airport Runways, Paved up areas 1.00


Urban areas fully and closely built up 0.90
Residential/ Industrial areas densely built up 0.80
Residential/ Industrial areas not densely built up 0.65
Rural areas with fish ponds and vegetable gardens 0.45
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
Remarks
Description Symbol Zone A Zone B Zone C Zone D

Sub- Catchment Area A (ha) 0.302 0.097 0.016

Weighted Runoff Coefficient Cpost 0.800 0.800 0.450

Time of Concentration tc (min) 5.000 5.000 5.000

Average Rainfall Intensity for 10years Storm Event I10=A/(tc+B)


I10 (mm/hr) 217.390 217.390 217.390

Peak Discharge from Sub- Catchment Qpost=Cposti10A/360


Qpost (m3/s) 0.146 0.047 0.004

Maximum Allowable Peak Discharge From Entire Site


Qallowable=C0.55i10A/360 Qallowable (m3/s) 0.138

Target Runoff Coefficient Ctarget 0.475 0.8 0.45


Target Peak Discharge For Sub- catchment Qtarget=Ctargeti10A/360 Qtarget 0.087 0.047 0.004

Check Qtarget Qallowable - 0.138


Type of Detention System to Employ -

Constant K1=8913CpostAc/6
K1 358.897

Constant K2=8913CtargetAc/12
K2 106.547

Constant K3=tc+36 K3 41.0

tmax=-K3+(36K1K3/K2)0.5
tmax 29.511

txlimit=((Cpost-Ctarget)(tc+36))/Ctarget
txlimit 28.053

txcritical=min of (tcmax ,txlimit) txcritical 28.053

Critical Rainfall Duration tz=txcritical+tc tz 33.053


Average Rainfall Intensity During Critical Rainfall Duration I =8913/(t +36)
z z Iz
129.075
Peak Inflow Rate for Critical Storm Event
Qz=CpostizA/360 Qz
0.119
Required Detention Volume
Vt
Vt=(K1(tc+txcritical))/((K3+Cxcritical))- 72.901
Proposed Volume (K2(2tc+txcritical))/K 3 78
Maximum Depth d (m) 1.275 - -
Area A (m2) 61.176 - -

Q for Pump 1 at 0.300 m


Q for 2 Pumps at 0.500 m
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
Remarks
Time Qin Qout dV V d' Remarks
0 0.000 0.000 0.000 0.000 0.000
1 0.024 0.000 1.428 1.428 0.023
2 0.048 0.000 2.857 4.285 0.070
3 0.071 0.000 4.285 8.571 0.140
4 0.095 0.000 5.714 14.284 0.233
5 0.119 0.043 4.543 18.828 0.308 Start of 1st Pump
6 0.119 0.043 4.543 23.371 0.382
7 0.119 0.043 4.543 27.915 0.456
8 0.119 0.087 1.945 29.859 0.488 Start of 2nd Pump
9 0.119 0.087 1.945 31.804 0.520
10 0.119 0.087 1.945 33.749 0.552
11 0.119 0.087 1.945 35.694 0.583
12 0.119 0.087 1.945 37.638 0.615
13 0.119 0.087 1.945 39.583 0.647
14 0.119 0.087 1.945 41.528 0.679
15 0.119 0.087 1.945 43.473 0.711
16 0.119 0.087 1.945 45.417 0.742
17 0.119 0.087 1.945 47.362 0.774
18 0.119 0.087 1.945 49.307 0.806
19 0.119 0.087 1.945 51.252 0.838
20 0.119 0.087 1.945 53.196 0.870
21 0.119 0.087 1.945 55.141 0.901
22 0.119 0.087 1.945 57.086 0.933
23 0.119 0.087 1.945 59.031 0.965
24 0.119 0.087 1.945 60.975 0.997
25 0.119 0.087 1.945 62.920 1.028
26 0.119 0.087 1.945 64.865 1.060
27 0.119 0.087 1.945 66.809 1.092
28 0.119 0.087 1.945 68.754 1.124
29 0.119 0.087 1.945 70.699 1.156
30 0.119 0.087 1.945 72.644 1.187
31 0.119 0.087 1.945 74.588 1.219
32 0.119 0.087 1.945 76.533 1.251 End of Rainfall duration
33 0.095 0.087 0.516 77.049 1.259
34 0.071 0.087 -0.912 76.137 1.245
35 0.048 0.087 -2.341 73.797 1.206
36 0.024 0.087 -3.769 70.028 1.145
37 0.000 0.087 -5.197 64.830 1.060
38 0.000 0.087 -5.197 59.633 0.975
39 0.000 0.087 -5.197 54.435 0.890
40 0.000 0.087 -5.197 49.238 0.805
41 0.000 0.087 -5.197 44.041 0.720 2nd Pump off
42 0.000 0.043 -2.599 41.442 0.677
43 0.000 0.043 -2.599 38.843 0.635
44 0.000 0.043 -2.599 36.244 0.592
45 0.000 0.043 -2.599 33.646 0.550
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
46 0.000 0.043 -2.599 31.047 0.507 Remarks
47 0.000 0.043 -2.599 28.448 0.465
48 0.000 0.043 -2.599 25.850 0.423
49 0.000 0.043 -2.599 23.251 0.380
50 0.000 0.043 -2.599 20.652 0.338
51 0.000 0.043 -2.599 18.053 0.295
52 0.000 0.043 -2.599 15.455 0.253
53 0.000 0.043 -2.599 12.856 0.210
54 0.000 0.043 -2.599 10.257 0.168
55 0.000 0.043 -2.599 7.658 0.125
56 0.000 0.043 -2.599 5.060 0.083
57 0.000 0.043 -2.599 2.461 0.040
58 0.000 0.043 -2.599 0.000 0.000 1st Pump off
59 0.000 0.043 -2.599 0.000 0.000
60 0.000 0.043 -2.599 0.000 0.000
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
CALCULATION Remarks

Rain Intensity:

Ac = Area of Catchment (Ha) = 2.300 Ha Return Period, T Value A Value B


10 8879 36.5
Reference Table:-
Site Area (ha) Time of Concentration,tc (min) Area Served by Drainage System Return Period (T)
0.2 - 2.0 5 Catchment of less than 100 Ha 10 years
2.0 - 6.0 10 Catchment of 100 ~ 1000 Ha 25 years
6.0 - 10.0 15 Catchment of more than 1000 Ha
50 ~ 100 years
10 15* or Critical Installation
*QPs to substantiate with hydraulic calculation if t c>15min is used.

Rational Formula :
Runoff Coefficient Table :
Characteristic of catchment when fully developed Runoff Coefficient, Cpost

Road, Highways, Airport Runways, Paved up areas 1.00


Urban areas fully and closely built up 0.90
Residential/ Industrial areas densely built up 0.80
Residential/ Industrial areas not densely built up 0.65
Rural areas with fish ponds and vegetable gardens 0.45

Sub- Catchment Area A (ha) = 2.300

Weighted Runoff Coefficient Cpost = 0.800

Time of Concentration tc (min) = 10.000

Average Rainfall Intensity for 10years Storm Event I10 (mm/hr) = 190.946
Peak Discharge from Sub- Catchment Qpost (m3/s) = 0.976
Peak Discharge from Sub- Catchment (+PFC) Qtotal = 1.114

Drain Information: Roughness Coefficient n = 0.015


Width of Drain B = 0.450 m

Depth of Drain D = 1.000 m

Drain Depth with 15% Freeboard Yn = 0.85 m

Flow Area A = 0.383 m2

Wetted Perimeter P = 2Yn+b = 2.150 m


Hydraulic Radius R = A/P = 0.178
Bed Gradient S = 0.01
Drain Capacity Qc = 0.807
Calcs By: Date: Version:
1.0 / 2015 / WBB
TWP 4/7/2017
194 Pandan Loop #07-19 Checked By: Project Ref:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: 73A JTC Food Centre Revision: 0
Remarks
Roughness Coefficient n = 0.015
Width of Drain B = 0.300 m

Depth of Drain D = 0.550 m

Drain Depth with 15% Freeboard Yn = 0.4675 m

Flow Area A = 0.140 m2

Wetted Perimeter P = 2Yn+b = 1.235 m


Hydraulic Radius R = A/P = 0.114
Bed Gradient S = 0.004
Drain Capacity Qc = 0.139
Calcs By: Date:

WB 4/7/2017
194 Pandan Loop #07-19 Checked By:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: Revision: 0
CALCULATION
Calcs By: Date:

WB 4/7/2017
194 Pandan Loop #07-19 Checked By:
Pantech Business Hub
Singapore 128383
CIVIL & STRUCTURAL PROJECT MANAGEMENT Tel : (65) 6872 3411 Fax : (65) 6873 0935
WB/SC
Project Name: Revision: 0
Version:
1.0 / 2015 / WBB
4/7/2017
Project Ref:

WB/SC
0
Remarks
Version:
1.0 / 2015 / WBB
4/7/2017
Project Ref:

WB/SC
0
Remarks