TOWN OF APPLE VALLEY, CALIFORNIA
SUMMARY OF APPROPRIATIONS
BY ACCOUNT - ALL FUNDS
FY 11-12 FY 12-13 FY 13-14 FY 14-15
Description Actual Actual Amended Adopted
41
TOWN OF APPLE VALLEY FY 2014-2015
74
TOWN OF APPLE VALLEY FY 2014-2015
MEASURE I
LOCAL PASS-THROUGH FROM SANBAG
TOTAL BUDGET - $5,223,350
76
Replaced dilapidated netting and fencing at James grant, fundraising proceeds from Healthy Apple
Woody Park. Valley and a grant from Kaiser Permanente.
Coordinated with the local Little League, Pony Had a Public Address system installed at the Aquatic
baseball and A.A.E. to make improvements to the Center to improve safety and experience for the
ballfields at James Woody Park. patrons in attendance.
Installed Shade structure at James Woody Park to Continued the trend of increased participation the
increase picnic opportunities. annual Teen Art Festival to include more than 375
entries from throughout the High Desert school
Installed exercise equipment and completed signage
system.
for a walking trail in Civic Center Park. This project
was funded with remaining funds from the EDI 06
88
TOWN OF APPLE VALLEY FY 2014-2015
Most of the Town's planned arterials and collectors exist in some form, although not necessarily fully widened to allow for the
full number of lanes. Revenues are derived from Traffic Impact Fees, grants and other transportation funding from the State or
County. The Traffic Impact Fees are used to finish off these existing, but not yet fully improved, roads and bridges. The collected
fees are used to create additional lane miles and bridge lanes increasing carrying capacity. Additionally, this fund is used to
complete the system of signals that insures the smooth movement of vehicles through intersections.
122
Actual Actual Amended Estimated % of Adopted
Code Expenditure Classification Expense Expense Budget Expense Budget Budget
2011-12 2012-13 2011-12 2011-12 Expended 2014-15
-
Civic Center Park -
4806-9300-0000 Capital Projects 2,506 164,210 - 15,892 -
-
Special Purpose Grants -
2521-8988-0000 PetSmart Charities - 13,560 - 11,920 -
4810-7705-0000 California Beverage Container Grant 17,220 1,348 - - -
4810-9442-0000 Kiowa Rd(Bear Valley & Tussing) - 4,313 - (4,313) -
4810-9563-0000 SR25 Rancho Verde Elem.School - 992 492,000 8,344 1.7% -
4815-9588-0000 DOT Yucca Loma Bridge 174,351 - - - -
4817-7751-0000 Healthy Communities 10,034 - - - -
4819-9271-0000 Bear Valley Bike Path, Phase I 17,618 38,209 355,700 28,487 8.0% 355,700
4820-xxxx-xxxx County Supervisor Grant - 19,514 - 7,415 -
4823-9416-0000 Hwy 18 Village Area Median - 464,000 - - -
4824-xxxx-xxxx Illegal Disposal Site Abatement Grant - 4,931 - 5,000 -
4827-7340-0000 County Regional ED/Marketing Grant - 44,680 - 30,320 -
4828-xxxx-xxxx Kaiser Grant - - - 20,000 -
4829-xxxx-xxxx Municipal Spay Neuter - - - 4,774 -
4921-xxxx-xxxx First Five - 40,521 - 150,916 191,965
Total Expenditures 889,747 848,073 869,058 327,120 37.6% 547,665
132
ENGINEERING DEPARTMENT
Engineering Department (Authorized FTEs are 11.0; Budgeted FTEs are 6.75): Develops and maintains the Public Safety
Standard relating to traffic operations, traffic safety and pedestrian safety as a part of Vision 2020 goal #1, Implements CIP
and develops and constructs Local and Regional storm drain systems as a part of Town Public infrastructure program and
Vision 2020 Goal #2, processes, reviews, approves, permits and inspects development related construction as a part of
Vision 2020 goal #3, , develops local and regional Transportation networks as part of Vision 2020 Goal #4,.
207
Development Related Inspection of Public SANBAG Los Angeles Metro, including
Improvements: environmental clearance, approval, design and
-Off-site improvements for the Otoe Road and anticipated construction commencement in
Navajo Road Solar Sites 2016.
-Off-site Improvements for the medical building
at the northeast corner of Apple Valley Road Continue to improve Apple Valley Road at SR18
and Kamana Road with plans to develop realignment and re-
-Off-site improvements for the Silver Valley contour of the intersection, allowing the
Propane site on Manhasset Road removal of the split-phase operation, and
-Off-site improvements for the medical building improve traffic movement in all directions.
on Kokanee Road between Kamana Road and Continue to work with San Bernardino County
Kasota Road
Flood Control, Zone 4 to develop a Regional
-Outer Bear Valley Road improvements for the
Dollar General project Retention/Detention facility at Tussing Ranch
-Off-site improvements for the multi-family Road and Juniper Road.
projects on Wato Road between Apple Valley Continue to work with a structural engineering
Road and Muni Road and Viho Road consultant to analyze and rehab the existing
Bear Valley Road Bridge.
Implement CIP projects including pavement
2014-15 GOALS AND OBJECTIVES
management projects.
Implement the Towns dry well program.
Serve as the Flood Plain Administrator, working
Approve Project Entitlements faster than any
with FEMA to manage storm related public
Other Community in California.
hazards within our community.
Continue to review, permit and inspect all
Develop Public Infrastructure and completion of
private and public land development projects
the Annual Capital Improvement Program,
faster and more efficiently than any other
particularly in the areas of streets, sidewalks,
community in California.
bikeways, traffic signals, storm drains, dry wells,
and traffic management related signage and
markings.
Continue to work closely with SCE to
underground utilities along Yucca Loma Road
between Rancherias Road and Mohawk Road, as
a component of a Safe Routes to School
improvement project
Continue to pursue the future development of
the High Desert Corridor with Caltrans District 7
& 8, Los Angeles and San Bernardino Counties,
Performance and Workload Measures - Engineering
Goal Actual Goal
2013-2014 2013-2014 2014-2015
Complete CIP projects 9 7 9
Complete design phase and bid CIP projects 9 7 9
Average # of active, funded CIP projects 6 7 9
# of Planning projects reviewed and conditioned 15 20 25
# of plan checks or map checks processed 20 42 50
First review of engineering plan checks or map checks completed in 10 100% 90% 100%
or less business days
Revisions to engineering plan checks and map checks reviewed in less 100% 90% 100%
than 7 working days
208
Town of Apple Valley
Capital Improvement Plan
7 Year Plan 2014-2021
Road Projects
Preliminary Design
Bear Valley Bridge (Mojave River Bridge) - co 672,650 700,000 - - - - - 1,372,650
Dale Evans Parkway @ Waalew Road (Realignment) - co 100,000 - - - - - - 100,000
High Desert Corridor 25,000 25,000 25,000 25,000 25,000 25,000 25,000 175,000
John Glenn roadway improvements 20,000 - - - - - - 20,000
Standing Rock Road Realignment / Hwy 18 Signal 150,000 - - - - - - 150,000
Full Design
Apple Valley Road Rehabilitation (Bear Valley to Town Center) 10,000 - - - - - - 10,000
Bear Valley Bridge (Mojave River Bridge) - - 1,200,000 - - - - 1,200,000
Central Road, from SR18 to Bear Valley Road - 100,000 - - - - - 100,000
Dale Evans Parkway @ Waalew Road (Realignment) - 300,000 - - - - - 300,000
Deep Creek Road, from Bear Valley Road to Tussing Ranch 10,000 - - - - - - 10,000
Hwy 18 West End Widening (Phase 1, AVR Realignment) - co 200,000 - - - - - - 200,000
Powhatan Road Street Improvements 18,000 - - - - - - 18,000
Standing Rock Road Realignment / Hwy 18 Signal - 350,000 - - - - - 350,000
Town wide Class II bikeway upgrade 45,100 - - - - - - 45,100
Town wide signal equipment review 10,000 - - - - - - 10,000
Town wide signal timing review 20,000 - - - - - - 20,000
Yucca Loma Road Widening (Apple Valley Rd to Rincon Rd) 500,000 - - - - - - 500,000
Construction
Apple Valley Road @ Bear Valley Rd SE Corner Improvements - - 390,000 - - - - 390,000
Apple Valley Road Rehabilitation (Bear Valley to Town Center) 400,000 - - - - - - 400,000
Bear Valley Bike Path - co 355,700 355,700
Bear Valley Bridge (Mojave River Bridge) - - - 16,600,000 - - - 16,600,000
Central Road, from SR18 to Bear Valley Road - - 660,000 660,000 - - - 1,320,000
Civic Center Parking Lot Circulation Improvements - co 10,000 - - - - - - 10,000
Dale Evans Parkway @ Waalew Road (Realignment) - - 500,000 - - - - 500,000
Deep Creek Road, from Bear Valley Road to Tussing Ranch 300,000 - - - - - - 300,000
Hwy 18 West End Widening (AVR to TAO) - - - - 11,000,000 - - 11,000,000
Hwy 18 West End Widening (Phase 1, AVR Realignment) - co 175,000 - 1,500,000 3,500,000 - - - 5,175,000
Navajo Road Rehabilitation (Bear Valley Rd to Hwy 18) - co 10,000 - - - - - - 10,000
Paving Priorities (50% Categorical/50% Non-Categorical) 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 7,000,000
Powhatan Road Street Improvements 196,000 - - - - - - 196,000
Ramona Road Widening (Navajo Rd to Central Rd) 665,000 - - - - - - 665,000
Rancherias Road Resurfacing (SR18 to 1,000' north) - co 10,000 - - - - - 10,000
Rancho Verde Elementary School - SR2S 512,000 - - - - - - 512,000
SANBAG Congestion Management Plan 5,000 5,000 5,000 5,000 5,000 5,000 5,000 35,000
Signal, BVR@Mohawk Rd 405,000 - - - - - - 405,000
Standing Rock Road Realignment / Hwy 18 Signal - - 1,250,000 1,250,000 - - - 2,500,000
Town wide Class II bikeway upgrade 473,500 - - - - - - 473,500
215
Town of Apple Valley
Capital Improvement Project
FY 2014-2015
Previous Cost: $ -
O&M Impact: $ -
Department: Engineering
Description:
The Engineering Department has retained a consultant for engineering services to design the Class I Bike Path along Bear
Valley Road from Reata Road to the bridge over the Mojave River and from the bridge to the College. Tasks for this
project include the design and construction of the Class I Bike Path.
Operating & Maintenance Budget Impact FY14-15 FY15-16 FY16-17 FY17-18 FY18-19 5 Year Total
Operations 0
Maintenance 0
Capital Outlay 0
Total 0 0 0 0 0 0
221
Town of Apple Valley
Capital Improvement Project
FY 2014-2015
Operating & Maintenance Budget Impact FY14-15 FY15-16 FY16-17 FY17-18 FY18-19 5 Year Total
Operations 0
Maintenance 0
Capital Outlay 0
Total 0 0 0 0 0 0
222
Town of Apple Valley
Capital Improvement Project
FY 2014-2015
Previous Cost: $ -
O&M Impact: $ -
Department: Engineering
Description:
This project will ensure that the Town's existing bike lane network meets current standards set by Caltrans' recently updated
MUTCD. This will be achieved by changing classifications or adding appropriate signage. The project will consist of reviewing and
modifying outdated and defficient existing facilities and revising existing street or road plans to reflect the upgrades to current
standards.
Operating & Maintenance Budget Impact FY14-15 FY15-16 FY16-17 FY17-18 FY18-19 5 Year Total
Operations 0
Maintenance 0
Capital Outlay 0
Total 0 0 0 0 0 0
228
Town of Apple Valley
Capital Improvement Project
FY 2014-2015
Department: Engineering
Operating & Maintenance Budget Impact FY14-15 FY15-16 FY16-17 FY17-18 FY18-19 5 Year Total
Operations 0
Maintenance 0
Capital Outlay 0
Total 0 0 0 0 0 0
233
Town of Apple Valley
Capital Improvement Project
FY 2014-2015
O&M Impact: $ -
Department: Engineering
Description:
This project entails the complete removal and reconstruction of Rancherias Road from the northern edge of the Caltrans
right of way at the intersection of State Highway 18 to a point 300 feet north of Zuni Road. As part of the
reconstruction, segments of Rancherias Road will be widened to 44 feet to include a center turn lane and bike lanes in
addition to the travel lanes. Roads that intersect with Rancherias Road, i.e. Thunderbird Road, Serrano Road, Symeron
Road, Rimrock Road East, and Zuni Road, will also be reconstructed at their respective connections to Rancherias Road.
The project will also address localized drainage issues by way of installing Class 5 Drywells at specific locations along the
right of way.
Operating & Maintenance Budget Impact FY14-15 FY15-16 FY16-17 FY17-18 FY18-19 5 Year Total
Operations 0
Maintenance 0
Capital Outlay 0
Total 0 0 0 0 0 0
234