Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/275685918
CITATIONS READS
0 98
2 authors, including:
S. Mohsen Haeri
Sharif University of Technology
68 PUBLICATIONS 422 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by S. Mohsen Haeri on 20 July 2015.
j
1 j
2
Preloading is a popular technique in ground improvement works on soft compressible soils. Observational methods
such as the Asaoka or hyperbolic methods are widely used in practical applications to assess final settlement and
the degree of consolidation during preloading. In this paper it is argued that the major cause of inaccuracy in the
final settlement predicted by the Asaoka method, especially in the early stages of preloading (short assessment
periods), is neglect of the effects of creep in Asaokas solution. This may also be the cause of the lack of agreement
between observational methods and the piezometer method at higher degrees of consolidation. In this paper a
method is proposed that can improve ultimate settlement predicted by the Asaoka method, by considering the
effects of creep. By applying this method to two sets of settlementtime data available in the literature, it was
found that the final settlements can be estimated with greater accuracy compared with the Asaoka method, even
in the early stages of consolidation. Additionally, the proposed method can predict future settlements accurately.
The degrees of consolidation predicted by this method showed good agreement with pore pressures recorded in
piezometers.
1
Geotechnical Engineering Improving final settlement predictions of
the observational method
Sasar and Haeri
1.1 Asaokas observational method settlementtime data of Figure 1. The best-fitted line to the data
Asaoka suggested a procedure applicable to consolidation pro- points in Figure 2 intersects the 458 line at (0.59, 0.59), which
blems with or without vertical drains. Assume that we have n + 1 indicates that Asaokas method predicts 59 cm of settlement at
settlement readings at a constant time interval of t (x0 , x1 , . . ., the end of consolidation. Hence the idea of the Asaoka method is
x n ) caused by placing a constant external load on a clay layer. based on observational procedure, in which future settlement is
Figure 1 shows an example of such settlementtime data, in predicted using past observations. This method is particularly
which seven settlement readings after the end of the preloading effective for settlement prediction, because the coefficient of
period (the end of placing the surcharge) are plotted against time consolidation, the depth of the clay layer and other boundary
at a constant time interval of one month. Asaokas solution then conditions of drainage and load are assumed to be unknown.
shows that n plotted points (x k , x k 1 ) for k 1, 2, . . ., n, will rest
on a straight line with coordinates (xi , xi1 ). Subsequently, the A brief literature review, however, reveals that with the Asaoka
intersection point of this line with the 458 line marks a stable method good predictions are usually possible after 60% consoli-
state in which both x k and x k 1 match the final settlement at the dation has been achieved (Bergado et al., 1991), but that the
end of consolidation. Figure 2 shows the Asaoka plot for the prediction is dependent on the time interval t, and on the
assessment period (Arulrajah et al., 2004). The assessment period
refers to the period of time after placing the surcharge during
Load: t/m2
06
1.2 Creep
05 In the field of land reclamation and clays, creep is usually defined
y 07263x 01624 as a continuous reduction in volume of the soil under constant
Settlement (i ): m
02
Regardless of the micromechanisms that cause creep (Bassett,
1978; Feda, 2004), most researchers assume a linear relationship
01 59 cm
between creep settlement and log time.
2
Geotechnical Engineering Improving final settlement predictions of
the observational method
Sasar and Haeri
04
H 3S C H 3S 10
Sc 3 3 log t 3 C 9 log t
3: ST 1 e0 ST 12
3
Geotechnical Engineering Improving final settlement predictions of
the observational method
Sasar and Haeri
12 12
y 08885x 00964 y 09062x 00902
R2 09968 R2 09982
10 10
08 08
Settlement (i ): m
Settlement (i ): m
06 06
04 04
02 02
45 45
Predicted final settlement 086 m Predicted final settlement 094 m
0 0
0 02 04 06 08 10 12 0 02 04 06 08 10 12
Settlement (i 1): m Settlement (i 1): m
(a) (b)
12 12
08 08
Settlement (i ): m
Settlement (i ): m
06 06
04 04
02 02
45 45
Predicted final settlement 102 m Predicted final settlement 107 m
0 0
0 02 04 06 08 10 12 0 02 04 06 08 10 12
Settlement (i 1): m Settlement (i 1): m
(c) (d)
12 12
08 08
Settlement (i ): m
Settlement (i ): m
06 06
04 04
02 02
45 45
Predicted final settlement 110 m Predicted final settlement 114 m
0 0
0 02 04 06 08 10 12 0 02 04 06 08 10 12
Settlement (i 1): m Settlement (i 1): m
(e) (f)
Figure 4. Asaoka plots for monitored timesettlement data of
Figure 3. Time interval 1 year. Surcharge duration: (a) 10 years;
(b) 15 years; (c) 20 years; (d) 25 years; (e) 30 years; (f) 45 years
4
Geotechnical Engineering Improving final settlement predictions of
the observational method
Sasar and Haeri
clayey soils in Sweden, and suggested ranges of C /Cc (Mesri, Table 1 summarises the equations of the best-fitted lines to the
1973), a value of 0.015 for C9 is deemed suitable for this clay. Asaoka plots sketched for the P dataset of Figure 3, using the
The monitored settlementtime graph is reproduced in Figure 3, same time interval and assessment periods as the Asaoka plots in
using a solid line. Figure 4. The predicted final settlements due to primary con-
solidation (intersection point of the best-fitted line with the 458
The Asaoka plots for the monitored timesettlement data of line) are also presented in Table 1.
Figure 3 are sketched in Figure 4 using t of one year and
assessment periods of 10, 15, 20, 25, 30 and 45 years. It can be The reduced variation in the predicted final primary settlement in
seen in Figure 4 that, as the consolidation process continues, and Table 1, compared with Figure 4, shows that the best-fitted line is
more data points are introduced into the Asaoka plot, the relatively independent of the assessment period, especially
predicted ultimate settlement increases. Note that the best-fitted beyond 15 years. As a result, the predicted final settlement due to
line to the data points on the Asaoka plot is quite sensitive to the primary consolidation can be assumed to be insensitive to the
number of data points used. assessment period. This means that this settlement can be
predicted with better accuracy, even in the early stages of
The effects of time interval and assessment period on the preloading.
estimated final settlement have been well described in more detail
by Arulrajah et al. (2004). 5. Shape of the best-fitted curve to Asaoka
plots
4. Extracting creep settlements Since the P dataset conforms better to the assumptions of
It is assumed that the settlement of a preloaded layer due to creep Terzaghi theory, it fits on a unique straight line on the Asaoka
can be obtained using Equation 3. In other words, if xi is the plot. This unique line can be defined using
monitored settlement at t t i , then, according to Equation 3, the
creep-related portion of the settlement is
6: X i AX i1 B
ti
Sc xi log
4: t0
in which A and B are constants. Substituting Equation 5 in
Equation 6 and rearranging gives
in which
7: xi axi1 b
HC 9
ST
in which
5
Geotechnical Engineering Improving final settlement predictions of
the observational method
Sasar and Haeri
B 050
b y 0897x 0046
9: 1 log t i =t0 045
R2 1
040
Equation 7 shows the true shape of the curve on which the 035
Settlement (i ): m
monitored settlementtime data points lie on the Asaoka plot.
030
The term a decreases slightly at the beginning, but then remains
essentially the same. The term b, however, increases notably 025
during the entire consolidation process, and might cause serious
020
error if Equation 7 is replaced by a straight line. In Figure 5, the
non-dimensional parameters a/A and b/B are plotted against time. 015
010
6. Predicting final settlement Primary settlement
In order to demonstrate how the data for primary consolidation 005 45 degree line
settlement against time can be used to assess the final settlement
0
and degree of consolidation, the best-fitted line for the assessment 0 005 010 015 020 025 030 035 040 045 050
period of 30 years is selected from Table 1. The first settlement Settlement (i 1): m
reading is then used as a starting point, and by substituting it in
the equation given in Table 1 for 30 years, the next settlement Figure 7. Asaoka plot for P data of Figure 6
reading is reproduced, and so forth. In other words, by substitut-
ing Xi (the primary consolidation settlement at t t i ) in the
mentioned equation, Xi1 (the primary consolidation settlement at t t i1 ) can be obtained. The data reproduced in this manner
are very close to the former P data, but without the imperfections
130
that cause a slight scatter in the data points in the Asaoka plots.
The advantage of this method is that now the data can be
125
reproduced for any desired time duration. In Figure 6 the P data,
120 reproduced in this manner for 125 years, are plotted against time.
Figure 7 shows the Asaoka plot for these data.
a/A, b/B
115
a/A
Theoretically, 100% primary consolidation is never achieved.
110 Hence, as can be seen in Figure 7, the data points will continue
b/B
to draw near the 458 line, but they will not intersect with it.
105 Therefore, in order to set an end to the primary consolidation, a
degree of consolidation of 99.999% is selected as a benchmark
100 for the end of primary consolidation. Reproduction of the data in
1 6 11 16 21 26 31 36
Time: year Figure 6 showed that this benchmark is reached after approxi-
mately 125 years.
Figure 5. a/A and b/B against time
The total settlement at any given time could be evaluated by
rearranging Equation 5 to give
Time: year
0 20 40 60 80 100 120 140 1
0 xi X i
10: 1 log t i =t0
02
04
Settlement: m
6
Geotechnical Engineering Improving final settlement predictions of
the observational method
Sasar and Haeri
04
Depth: m
50
06
75
08
10 100
7
Geotechnical Engineering Improving final settlement predictions of
the observational method
Sasar and Haeri
method, unlike the proposed method, cannot predict degrees of consolidation process was much shorter, it might appear that
consolidation beyond the duration over which the settlement secondary consolidation has a negligible effect. Nevertheless,
time data are monitored. even in this case better final settlement predictions and better
degree of consolidation estimations (more compatible with the
Since ST must be evaluated iteratively, this whole process may piezometric data) were achieved. Table 3 presents the degrees of
seem cumbersome, but for the purpose of this paper a spreadsheet consolidation for 12, 24 and 32 months after the end of
program was prepared to carry out the entire calculations in a preloading calculated using the piezometer method, and the
reasonably short time. predicted degrees of consolidation for the Asaoka and proposed
methods.
8. Changi East reclamation project in
Singapore Equation 3 was obtained for a clay layer under constant surcharge
The same methodology is applied to the settlementtime data of load. The poor agreement between the monitored timesettlement
test site A2S-71 in the Changi East reclamation project. Figure data and the obtained timetotal settlement data during the
10 shows the monitored timesettlement data up to 12 months preloading period (when the surcharge is being gradually applied)
after the end of the preloading period. The thickness of the clay indicates that Equation 3 probably does not provide a good
layer for this site is reported to be 35 m, and the C 9 secondary estimate of creep settlements when load is being applied
consolidation coefficient (estimated in the same manner as gradually. Timetotal settlement data show noticeably higher
before) is assumed to be 0.007. The data for primary consolida- settlements during this period.
tion settlement against time can be obtained using Equation 5.
The Asaoka plot for primary consolidation settlement against By reproduction of the P and T datasets for the A2S-71 test site,
time was drawn using a time interval of 28 days and an the proposed method predicted that the defined benchmark for
assessment period of 12 months. The equation of the best-fitted the end of primary consolidation would be reached approximately
line to the Asaoka plot is then used to obtain timeprimary 8 years after the end of the preloading period resulting in a final
consolidation and timetotal settlement datasets in a similar settlement of 1.84 m. Using the same time interval and assess-
manner as before. These data series are also shown in Figure 10 ment period, the Asaoka method would predict a final settlement
for the time period of 12 months after preloading. of 1.72 m for the site.
Since vertical drains were used in this site, and the whole 9. Conclusion
The possible role of secondary consolidation in the miscalcula-
Time: day tion of final settlement by the Asaoka method has been illu-
0 100 200 300 400 500 600 700 strated. Without any adjustments to the timesettlement data,
0
Monitored timesettlement data prediction of the ultimate settlement with the Asaoka method is
02 Timetotal settlement data in error, especially for the early stages of preloading. As the
04 Timeprimary consolidation
loading proceeds, and more timesettlement data are acquired,
Settlement: m
settlement data
06 the ultimate settlement predicted by the best-fitted line to Asaoka
08
plot approaches the actual value of ultimate settlement.
10
End of surcharge It was argued that settlement due to creep starts from the
12 placement period beginning of the consolidation process, and increases with time.
14 Because of the presence of creep, the timesettlement data points
Figure 10. Monitored, P and T datasets for 12 months after end do not stay on a straight line on the Asaoka plot. As more data
of preloading period for A2S-71 test site points are introduced to the Asaoka plot, they tend to incline the
trend of the fitted line towards the actual ultimate settlement.
8
Geotechnical Engineering Improving final settlement predictions of
the observational method
Sasar and Haeri
Deriving the Asaoka equations again, using more sophisticated consolidated marine clays as related to the settlements of
theories that do consider creep settlements, might be very buildings. Geotechnique 17(2): 83118.
complicated. Therefore it was assumed that the timesettlement Bo MW, Chu J, Low BK and Choa V (2003) Soil Improvement:
data can be made to fit better to the assumptions of the Asaoka Prefabricated Vertical Drain Techniques. Thomson Learning,
method instead. This was accomplished by eliminating creep Singapore.
settlements from the timesettlement data. By applying the Feda J (2004) Physical models of soil behavior. Engineering
discussed method to the data available in the literature, it was Geology 72(12): 121129.
concluded that all timeprimary consolidation settlement data Hansbo S (2005) Experience of consolidation process from test
points on Asaoka plots remain on approximately the same unique areas with and without vertical drains. In Ground
straight line from the beginning, and appear to predict the Improvement: Case Histories (Indraratna B and Chu J (eds)).
ultimate settlement due to primary consolidation only. (Primary Elsevier, Amsterdam, the Netherlands, pp. 349.
consolidation settlement data are monitored settlement data minus Mesri G (1973) Coefficient of secondary compression. Journal of
settlement due to creep.) the Soil Mechanics and Foundations Division, ASCE 99(1):
123137.
The creep settlements were then reincorporated into this dataset, Mesri G and Rokhsar A (1974) Theory of consolidation for clays.
and the final settlement was estimated with greater accuracy. It Journal of the Geotechnical Engineering Division, ASCE
was shown that with this method, unlike the traditional Asaoka 100: 889904.
method, the ultimate settlement could be estimated with higher Mikasa M (1963) Consolidation of Soft Clay. Kajima-shuppan-
accuracy, even in the early stages of consolidation. Additionally, kai, Tokyo, Japan (in Japanese).
the proposed method, unlike the Asaoka method, can predict Tan S-A (1993) Ultimate settlement by hyperbolic plot for clays
degrees of consolidation beyond the duration for which the with vertical drains. Journal of Geotechnical Engineering,
settlementtime data are monitored. ASCE 119(5): 950956.
Tan S-A (1995) Validation of hyperbolic method for settlement in
The degree of consolidation obtained by the Asaoka method is clays with vertical drains. Soils and Foundations 35(1): 101
not in good agreement with the piezometric data, except in the 113.
early stages of consolidation, when creep settlements are small. Terzaghi K (1925) Erdbaumechanik auf Bodenphysikalischer
This also seems to be the result of increasing creep settlements. Grundlage. Deutichke, Vienna, Austria.
The degree of consolidation assessed with piezometric data seems Terzaghi K (1953) Discussion. Proceedings of the 3rd
to be more reliable; because pore pressures are assumed to be International Conference on Soil Mechanics, Zurich,
dependent on the primary consolidation only, regardless of the Switzerland, vol. 3, p. 158.
amount of secondary consolidation occurring during the consoli- Wheeless LD and Sowers GF (1972) Mat foundation and preload
dation process. By applying the discussed modification, the fill, VA Hospital, Tampa. Proceedings of the Specialty
predicted degrees of consolidation are in better agreement with Conference on Performance of Earth and Earth-Supported
the piezometer method. Structures. ASCE, Vol. 1, Part 2, pp. 939951.
Yin J-H (1999) Non-linear creep of soils in oedometer tests.
Geotechnique 49(5): 699707.
REFERENCES
Arulrajah A, Nikraz H and Bo MW (2003) Factors affecting field
assessment and back-analysis by Asaoka and hyperbolic
methods. Australian Geomechanics 38(2): 2937.
Arulrajah A, Nikraz H and Bo MW (2004) Factors affecting field
instrumentation assessment of marine clay treated with
prefabricated vertical drains. Geotextiles and Geomembranes WH AT DO YO U T HI NK?
22(5): 415437. To discuss this paper, please email up to 500 words to the
Asaoka A (1978) Observational procedure of settlement editor at journals@ice.org.uk. Your contribution will be
prediction. Soils and Foundations 18(4): 87101. forwarded to the author(s) for a reply and, if considered
Bassett RH (1978) Time-dependent strains and creep in rock and appropriate by the editorial panel, will be published as a
soil structures. In Creep of Engineering Materials (CD discussion in a future issue of the journal.
Pomeroy (ed.)), Mechanical Engineering Publications, Proceedings journals rely entirely on contributions sent in
London, UK, pp. 1138. by civil engineering professionals, academics and students.
Bergado DT, Asakami H, Alfaro MC and Balasubramaniam AS Papers should be 20005000 words long (briefing papers
(1991) Smear effects of vertical drains on soft Bangkok clay. should be 10002000 words long), with adequate illustra-
Journal of Geotechnical Engineering, ASCE 117(10): 1509 tions and references. You can submit your paper online via
1530. www.icevirtuallibrary.com/content/journals, where you
Bjerrum L (1967) Engineering geology of Norwegian normally will also find detailed author guidelines.
9
View publication stats