Item Quantit Method Output Plant Labour Duration Reference

y (days)
BQ NO.2
DEMOLITIO
N AND
RECTIFICATI
ON WORKS

Demolition Demolish including foundation base, remove all debris


Works away from site, make good all defects (fill measured
separately).
176m - Monsoon Drain 3.4 m/hr Back hoe 4 labours 19 days Appendix
198m - Chain Link Fencing 3.4 m/hr Dump track 4 labours 21 days 2(a)
Bill 2
Dismantle including foundation base, remove all debris Demolition
away from site, make good all defects (fill measured
separately).
1 NO - Main Gates Back hoe 3 labours 1 day
Dump
truck
Rectification Hack off and remove surplus spoil from site to
Works Contractors own dump.
90m2 - Concrete floor slab 0.4m2/hr 5 labours 1 day Appendix
20m2 - Concrete floor surface 0.4m2/hr Concrete 1 day 2(b)
- Floor tile
10m2 8m2/hr breaker/Ha 2 days Bill 2
- Wall tile
1365m2 - Aluminium foil 1.2m2/hr cker 41 day Rectificatio
1481m2 - Composite timber louvre panel 1.1 m2/hr Air 41 day n works
54m2 - Ceiling finishes 4.8 m2/hr compressor 7 day
700m2 3.5 m2/hr 61 day

Dismantle and remove surplus soil from site to


Contractors own dump.
- Door frame
7 NO - Door leaf 0.4 no/hr 2 labours 1 day
7 NO 0.6 no/hr Jack 1 day
hammer