Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Ans : D
Ans : B
Ans : A
Ans : B
Page 1 of 90
Mohamed Nazaruddin
Ans : C
Ans : D
7. Point out the tools that are used as effective means in procurement
planning?
A. Analysis for make or buy, selection of the type of contract and system for
weighting
B. Analysis for make or buy, expert judgment and selection of the type of
contract
C. selection of the type of contract, conferences by bidders and expert judgment
D. Expert judgment, audits and conferences by bidders
Ans : C
Ans : B
Ans : D
Page 2 of 90
Mohamed Nazaruddin
Ans : A
Answer: A
11. Which type of leadership is best suited for optimizing team performance in
projects?
A. Democratic leadership.
B. Participative leadership.
C. Autocratic leadership.
D. Benevolent authoritative leadership
Answer: B
Answer: C
Answer: A
Page 3 of 90
Mohamed Nazaruddin
Answer: C
Answer: d
He discovers that two members assigned to the project have charged time
without performing any work.Upon further investigation, he determines that
this occurred because there were no other project assignments available for
these people.The customer is unaware of these facts.
A. Try to find some productive work for these staff members in the project and
leave them on the team.
B. The best thing is to do nothing.The customer will not realize the problem
anyway.
C. Try to find a responsible person for the over-assignment who can be made
accountable.
D. Take the two people off the team immediately and arrange for the refund of
the excess charges to the customer .
Answer: d
17.In the following network logic diagram start dates are defined as early
morning, finish dates are evening.
Page 4 of 90
Mohamed Nazaruddin
Answer: B
Answer: D
Answer: B
21. A project manager performs Earned Value Analysis and finds the following
values:
Page 5 of 90
Mohamed Nazaruddin
21.
Answer: B
Answer: D
24. A project management team is evaluating the causes that might contribute
to unsatisfactory performance and quality. Which of the following
statements is not true?
A. Normal process variation is attributable to random causes.
B. Special causes are easier to predict and handle than random causes.
C. Special causes are unusual events.
D. A process can be optimized to limit the bandwidth of variations due to random
causes.
Answer: B
25. You are performing a project management audit in your company and find
that most of the project plans are neither consistent nor up-to-date.
Page 6 of 90
Mohamed Nazaruddin
Answer: B
Answer: A
Answer: B
Answer: C
Answer: C
Page 7 of 90
Mohamed Nazaruddin
Answer: A
A. 36 days
B. 37 days
C. 39 days
D. 42 days
Answer: B
31.
Page 8 of 90
Mohamed Nazaruddin
Answer: D
33. All the following statements regarding "whistleblowing" are true except
A. It is the term used to define an employees decision to disclose information on
unethical, immoral or illegal actions at work to an authority figure.
B. An employee should always discuss the matter with people external to the
company before following the "chain of command" and discuss it with the
immediate superior.
C. The consequences of whistleblowing are often extreme and include possible
being branded as having bad judgment, firing, civil action and imprisonment.
D. Carefully considered whistleblowing can lead to the end of unethical business
practices.
Answer: B
Answer: C
Answer: B
Page 9 of 90
Mohamed Nazaruddin
Answer: B
Answer: C
Answer: A
Answer: A
Answer: B
Page 10 of 90
Mohamed Nazaruddin
Answer: c
41.
Answer: b
The project team received a note this morning informing them that the
software delivery will be delayed by 2 weeks.
This morning, the project team received a note that the software will be
delayed by 2 weeks.
Answer: C
Page 11 of 90
Mohamed Nazaruddin
A. Concurrent engineering.
B. Resource over-allocation.
C. Resource pooling.
D. Program management
Answer: c
45. What does the acronym RAM commonly stand for in project management?
A. Responsibility Assignment Matrix.
B. Remotely Applied Measurements.
C. Risk Aware Management.
D. Randomly Accessible Material.
Answer: A
Answer: C
Answer: C
Page 12 of 90
Mohamed Nazaruddin
Answer: D
49.A project manager performs Earned Value Analysis and finds the following
results:
BAC is 500,000.
What is right?
A. EAC = 400,000
B. EAC = 550,000
C. BTC = 400,000
D. ETC = 75,000.
Answer: B
50. The construction of a residential home will cost a certain amount per square
foot of living space. This is an example of what type of estimating?
A. Analogous estimating.
B. Bottom-up estimating.
C. Top-down estimating.
D. Parametric modeling.
Answer: D
51. Which of the following should not be reason for rebaselining in a project?
A. Scope changes.
B. Cost variances.
C. Major schedule changes.
D. New information indicating that the basis for the original project cost
estimates was incorrect
Answer: B
51.
52. When a change control systems provision for changes without formal
review in case of emergency is being utilized
Page 13 of 90
Mohamed Nazaruddin
Answer: B
Answer: A
Answer: C
55.You are the project manager and have contracted with a service provider to
develop a complicated software solution This software is necessary to
control the machinery equipment which your project team will develop. It is
a lump-sum contract with additional incentives for meeting predefined
schedule targets. The payment schedule and incentives are as follows:
10% with order
20% after submission of prototype (+ 5% if delivered one week
early)
50% after product delivery (+ 5 % if delivered one week early)
20% after final product acceptance (+ 5 % if delivered one week
early)
Yesterday the company submitted the prototype to your project team. This was
2 weeks after the scheduled delivery date and 3 weeks after the date necessary to
qualify for the incentive payment.
This morning, the manager of the contractor approached you to ask for changes to
the payment schedule. They found that their initial work and costs were much
Page 14 of 90
Mohamed Nazaruddin
During the discussion you got the impression that the company is in serious
financial trouble.
A. Offer to pay 25% now and to reduce the final payment down to 15%.
B. Point out that the contractor is not in a position to demand a change to the contract.
C. Demand an urgent meeting with the seller.
D. Revisit the planning processes of project risk management to understand the
upcoming risks in conjunction with the seller before any further decisions are made.
Answer: D
A. Audit.
B. Inspection.
C. Testing and measuring.
D. Screening.
Answer: A
A. It allows one to easily identify the breakdown level of the item in the resource structure.
B. It describes the coding structure used by the performing organization to report financial
information in its general ledger.
C. It is the collection of unique identifiers generally assigned to WBS items.
D. It defines ethical behavior in the project and the responsibilities to the customer and the
profession.
Answer: C
You are a member of your company's project office. The company is running many
concurrent projects; most of them share a resource pool. Understanding how resources are
utilized across projects is seen as being essential to cost effectiveness and profitability.
You recently received an inquiry to assess the benefits of using project management
software to manage the company's project portfolio.
A. Project management software has the capability to help organize resource pools.
Page 15 of 90
Mohamed Nazaruddin
Answer: A
A. Objectives specified with far more detail than necessary for a successful project.
B. Easily achievable objectives.
C. Objectives that should be achieved in order to attain formal recognition.
D. Objectives that have specific, measurable, assignable, realistic and time-related
specifications.
Answer: D
You have been assigned to a new project and have finished the scope statement. You and
your team are now going to create a Work Breakdown Structure. You are spending a lot of
time discussing how to create a completely decomposed Work Breakdown Structure.
A. Status/completion is measurable.
B. Time/cost is easily estimated.
C. Start/end events are clearly defined.
D. Resource availability can be reliably foreseen.
Answer: D
Sample Questions
61. A project manager performs Earned Value Analysis and finds the following
results:
A. CV = 0.
B. CV = 30,000.
C. CV = -30,000.
D. CV = 1
Answer: A
Page 16 of 90
Mohamed Nazaruddin
62. During a company event, you had the opportunity to talk to a colleague
project manager. He told you that in his current project actual costs are
15% under cumulated costs scheduled for today.
Answer: A
Answer: C
Answer: B
A. The processes, tools, and techniques used by project scope management are
mostly depending on the application area.
Page 17 of 90
Mohamed Nazaruddin
Answer: A
Answer: D
Answer: B
Page 18 of 90
Mohamed Nazaruddin
Answer: A
Answer: B
Answer: D
71. Regarding Delphi Technique all of the following statements are true except
A. It is a way to reach a consensus of experts.
B. Experts are identified but participate anonymously while a facilitator uses a
questionnaire to solicit ideas.
C. The experts are encouraged by the facilitator to make direct contact with each
other during the assessment process to create a higher number of feedback
loops.
D. The responses are submitted and are then circulated to the experts for further
comment.
Answer: C
71.
72. Regarding quality and grade all of the following statements are true except
A. Low quality is always a problem; low grade may not be. Grade is a category
or rank given to entities having the same functional use but different
requirements for quality. Quality is the totality of characteristics of an entity
that bear on its ability to satisfy stated or implied needs. Quality can simply
Page 19 of 90
Mohamed Nazaruddin
Answer: D
73. Network templates which contain only portions of a network are often
referred to as
A. Subnets or fragnets
B. Subprojects
C. Programs
D. WBS items
Answer: B
Answer: B
Answer: A
Answer: A
Page 20 of 90
Mohamed Nazaruddin
Answer: B
79. You are the project manager for a seminar and training session that
approximately 2,000-2500 employees will be attending. You have rented a
hall for the seminar; however, you are unsure exactly how many people will
attend. Moreover, the number of tables required will change depending on
attendance. The cost of the furniture should be considered?
A. Variable cost
B. Direct cost
C. Fixed cost
D. Transient cost
Answer: A
80. Which of the following is the correct formula for calculating present value of
a business or organization?
Answer: A
Answer: B
81.
Page 21 of 90
Mohamed Nazaruddin
Answer: A
Answer: C
Answer: B
85. The process of establishing clear and achievable objectives, measuring their
achievement, and adjusting performance in accordance with the results of
the measurement is called:
A. strategic planning.
B. alternative objectives inventory.
C. management by objectives.
D. contingency planning.
Answer: C
Page 22 of 90
Mohamed Nazaruddin
Answer: A
88. Your most recent project status report contains the following information:
BCWP = 3,000, ACWP = 3,500, and BCWS = 4,000. The schedule variance is:
A. + 1,000.
B. + 500.
C. - 500.
D. - 1,000.
Answer: D
Answer: B
Answer: B
91. The _________ is a time-phased budget that will be used to measure and
monitor cost performance in the project.
A. work breakdown structure
B. project schedule
C. cost baseline
D. cost budget
Answer: C
Page 23 of 90
Mohamed Nazaruddin
92. To transfer most of the cost risk to the contractor, the client may use a
___________ contract.
A. cost plus award fee
B. cost plus incentive fee
C. cost plus fixed fee
D. fixed price
Answer: D
Answer: A
Answer: D
Answer: D
Answer: A
Page 24 of 90
Mohamed Nazaruddin
Answer: C
Answer: D
Answer: A
100. Inputs into overall change control include all of the following except:
A. project plan.
B. change requests.
C. change control system.
D. performance reports
Answer: C
101. Activity duration estimate inputs include all of the following except:
A. resource requirements.
B. basis of estimates.
C. activity lists.
D. constraints.
Answer: B
101.
Page 25 of 90
Mohamed Nazaruddin
Answer: B
103. Initiation inputs for a project include all of the following except:
A. product description.
B. strategic plan.
C. project charter.
D. selection criteria.
Answer: C
Answer: D
Answer: D
Answer: C
Page 26 of 90
Mohamed Nazaruddin
Answer: A
Answer: D
110. All of the following are examples of tools often used in cost
estimating except:
A. parametric modeling.
B. analogous estimating.
C. bottom-up estimating.
D. activity duration estimates.
Answer: D
111. At XYZ InC., the hourly wage for semi-skilled workers is $14.00. The
annual audit shows that fringe benefits cost 30% of basic wages, and
that overhead costs are 60% of wages plus fringe benefits. What is the
"loaded" hourly wage for a semi-skilled worker at XYZ Inc.?
A. $27.14.
B. $28.96.
C. $30.03.
D. $29.12.
Answer: D
Page 27 of 90
Mohamed Nazaruddin
112. Of the following estimates, which most accurately reflect the actual
cost of the project?
A. conceptual estimates.
B. order of magnitude estimates.
C. preliminary estimates.
D. bottom-up estimates.
Answer: D
113. The most crucial time for project risk assessment is:
A. when a problem surfaces.
B. during the planning phase.
C. during the close-out phase.
D. after the project schedule has been published.
Answer: B
114. When there is uncertainty associated with one or more aspects of the
project, one of the first steps to take is to:
A. revise project plan.
B. conduct a risk-benefit analysis.
C. conduct a needs analysis.
D. increase the estimated cost of the project.
Answer: B
Answer: C
116. Given the information in the following table, what is the expected
value from this risk event? Probability Result
.4 -10,000
.3 -7,500
.2 -5,000
.1 +2,500
A. -10,000.
B. - 7,500.
Page 28 of 90
Mohamed Nazaruddin
Answer: D
Which of the following actions by the buyer is most likely to cause problems
for the project?
Answer: B
Answer: C
119. A project should be terminated for all of the following reasons except:
A. lack of team synergy.
B. the project no longer meets the company's objectives.
C. the resources are not available to complete project activities.
D. project funding has been significantly reduced.
Answer: A
Page 29 of 90
Mohamed Nazaruddin
Answer: B
121. Explanation: The 'Delphi technique' is a commonly used tool to secure expert
judgment while initiating a project.
'Peer review' is a project selection tool, 'Expected value' is a method quantitative risk
analysis, and 'WBS' is a project-planning tool.
122. Based on the information provided below, which project would you
recommend pursuing?
A. Project I
B. Project III
C. Either project II or IV
D. Can not say from the data provided
Answer: B
Explanation: Project III has an IRR of 15%, which means the revenues from the
project equal the cost expended at an interest rate of 15%.
This is a definitive and a favorable parameter, and hence can be recommended for
selection.
123. What the project manager to ensure that all work in the project is
included should do?
A. Create a contingency plan
B. Create a risk management plan
Page 30 of 90
Mohamed Nazaruddin
Answer: C
Answer: D
Explanation: A start-to-finish (SF) relationship between two activities implies that the
completion of successor is dependent on the initiation of its predecessor.
A finish-to-start (FS) relationship between two activities implies that the initiation of
successor is dependent on the completion of predecessor.
A finish-to-finish (FF) relationship between two activities implies that the completion
of successor is dependent on the completion of predecessor.
Answer: B
Explanation: The project team must complete a scope statement for developing a
common understanding of the project scope among stakeholders. This lists project
deliverables - summary level sub-products, whose full and satisfactory delivery
marks the completion of the project.
Scope verification is the process of securing a formal acceptance of the project scope
by stakeholders.
Page 31 of 90
Mohamed Nazaruddin
A risk management plan involves setting up processes for identifying and dealing
with project risks.
Answer: A
Explanation: The organization's reputation being at stake, the threshold for such a
risk would be very low.
Procuring an insurance against the risk would only transfer the monetary impact of
the risk, and not the intangible impact like, the reputation of the organization.
The best option would be to drop the approach - that is, complete avoidance of the
risk.
127. The following three tasks form the entire critical path of the project
network. The three estimates of each of these tasks are tabulated below.
How long would the project take to complete expressed with an accuracy of
one standard deviation?
Most
Task Optimistic Pessimistic
likely
A 15 25 47
Page 32 of 90
Mohamed Nazaruddin
C 16 27 32
A. 75.5
B. 75.5 +/- 5.08
C. 75.5 +/- 8.5
D. 75.5 +/- 2.83
Answer: B
Explanation: The critical path is the longest duration path through a network and
determines the shortest time to complete the project. The PERT estimates of the
tasks listed are 27, 22.5 & 26. Therefore, the length of the critical path of the project
is 27+22.5+26 = 75.5.
The standard deviations of the estimates of the three tasks are determined as (P-
O)/6 = 2, 3.83 & 2.67 respectively. The standard deviation of the total path is
determined as Sq. root (sum of variances), where variance = square of standard
deviation. Thus, standard deviation of critical path = Sq. root (4+14.67+7.13) =
5.08.
128. After a study of the work processes on a project, a quality audit team
reports to the project manager that irrelevant quality standards were being
used by the project, which might lead to rework. What was the objective of
the project manager in initiating this study?
A. Quality control
B. Quality planning
C. Checking adherence to processes
D. Quality assurance
Answer: D
Page 33 of 90
Mohamed Nazaruddin
Answer: D
Answer: A
Explanation: A Project plan is the basis of project plan execution and is a primary
input.
Whereas, Corrective and Preventive actions are inputs to the project plan execution
process from various controlling processes.
131. A project manager would find team development the most difficult in
which form of organization?
A. Weak Matrix organization
B. Balanced Matrix organization
C. Projectized organization
D. Tight Matrix organization
Answer: A
In a weak matrix organization, the power rests with the functional manager.
Page 34 of 90
Mohamed Nazaruddin
A Tight matrix organization refers to co-locating the project team and has nothing to
do with a matrix organization.
A. 25
B. 24
C. 1
D. 5
Answer: A
Originally the project has 25 members (including the project manager), which makes
the total communication channels as 25*24/2 = 300.
With the addition of the quality professional as a member of the project team, the
communication channels increase to 26*25/2 = 325.
Therefore, the additional channels as a result of the change, that is, 325-300 = 25.
133. Once the project is complete, the complete set of project records
should be put in which of the following?
A. Project Archives
B. Database
Page 35 of 90
Mohamed Nazaruddin
Answer: A
Answer: B
Explanation: Common formats for Performance Reports are, bar charts (also called
Gantt Charts), S-curves, histograms and tables etc.
135. If the cost variance is positive and the schedule variance is also
positive, this indicates the:
A. Project is under budget and behind schedule
B. Project is over budget and behind schedule
C. Project is under budget and ahead of schedule
D. Project is over budget and ahead of schedule
Answer: A
Answer: A
Explanation: The question is about correct accounting for risk events that occur and
updating the reserves.
Page 36 of 90
Mohamed Nazaruddin
Provisions for "unknown unknowns" are in management reserves while those for
"known unknowns" are accommodated in contingency reserves. Management
reserves are at the discretion of senior management while the contingency reserves
are at the project manager's discretion.
Residual and secondary risks are remaining unmitigated risks and resultant risks of
mitigation, respectively. These are not reserves.
In this case, the risk event is one of the identified risks and therefore, 'contingency
reserve' is the one where the cost and schedule impact would be accommodated in.
137. Which one of the following is the last step of project closing?
A. Client has accepted the product
B. Archives are complete
C. Client appreciates your product
D. Lessons learnt are documented
Answer: B
Answer: A
Explanation: 'Stakeholders' include everyone who are actively involved in the project
or whose interests may be affected as a result of the project execution or
completion.
Page 37 of 90
Mohamed Nazaruddin
As lessons learned should capture all variations and what could have been done
better for future deployment, 'stakeholders' should be involved in creation of lessons
learned.
Which of the following should the project manager provide for the team as a
proactive measure?
Answer: C
Choice A, that is, 'a training course on the laws of the country' is a subject of legal
experts and not of the project team.
Choice B, that is, ' a course on linguistic differences' would not serve the purpose of
understanding and appreciating cultural differences, for better teaming.
Choice D, that is, 'a communication management plan' is a document that provides
data gathering and dissemination amongst stakeholders of the project. It is
necessary for the project but does not help in bridging communication gaps across
different cultures
140. While reviewing the progress, the project manager assesses that an
activity has been missed out from the implementation plan. A milestone,
scheduled to be achieved within another week, would be missed with the
current implementation plan.
Which of the following is the next best action for the project manager in this
situation?
Page 38 of 90
Mohamed Nazaruddin
Answer: D
Explanation: Choice D, that is, 'assess alternatives to meet the milestone' indicates
confronting the issue with an attempt to resolve the issue. Hence this would be the
best approach.
Choices A and C, that is, 'report the error and the expected delay' or 'report the error
and the planned recovery actions' do not attempt to solve the problem.
An attempt to solve the problem is the next best thing to do in this situation, before
reporting the issue correctly.
Choice B, that is, 'omit the status update on the milestone' is unethical.
Answer: D
141.
142. In which phase of a project would you estimate activity duration and
resources?
A. Initiating
B. Executing
C. Planning
D. Controlling
Answer: C
Page 39 of 90
Mohamed Nazaruddin
Answer: A
Answer: A
Answer: C
Answer: A
Answer: C
Answer: C
Page 40 of 90
Mohamed Nazaruddin
Answer: D
Answer: B
151. You are managing the release of a new drug in the market. Your role
is that of a:
A. Functional Manager, because you have good understanding functional
knowledge of the pharmaceutical industry
B. Project Manager, because you are creating a unique product within specific
time schedules
C. Operations Manager, because you have to do several repetitive tasks
D. Program Manager, because you have to manage several sub-projects to
effectively do your job
Answer: B
151.
Explanation: Projects involve doing something that has not been done before and
which is, therefore, unique. A product or service may be unique even if the category
to which it belongs is large....
A project to bring a new drug to market may require thousands of doses of he drug
to support clinical trials
Answer: D
Page 41 of 90
Mohamed Nazaruddin
153. You are managing the release of a new drug in the market. Your role
is that of a:
A. Functional Manager, because you have good understanding functional
knowledge of the pharmaceutical industry
B. Project Manager, because you are creating a unique product within specific
time schedules
C. Operations Manager, because you have to do several repetitive tasks
D. Program Manager, because you have to manage several sub-projects to
effectively do your job
Answer: B
Explanation: Projects involve doing something that has not been done before and
which is, therefore, unique. A product or service may be unique even if the category
to which it belongs is large.
A project to bring a new drug to market may require thousands of doses of he drug
to support clinical trials.
Answer: D
Explanation: For many projects, standards and regulations (by whatever definition)
are well known and project plans can reflect their effects. In other cases, the
influence is unknown or uncertain and must be considered under Project
Risk Management
Page 42 of 90
Mohamed Nazaruddin
Answer: A
Answer: D
Answer: D
Explanation: For many projects, standards and regulations (by whatever definition)
are well known and project plans can reflect their effects. In other cases, the
influence is unknown or uncertain and must be considered under Project
Risk Management.
Page 43 of 90
Mohamed Nazaruddin
Answer: D
Answer: D
160. You are working in the Project Office of your organization. What is
your job responsibility?
A. Managing the different activities of a project
B. Always being responsible for the results of the project
C. Providing support functions to Project Managers in the form of training,
software, templates etc.
D. Providing Subject Matter Expertise in the Functional areas of the project
answer: C
Explanation: Project Office: There is a range of uses for what constitutes a project
office. A project office may operate on a continuum from providing support functions
to project managersin the form of training, templates, etc. to actually being
responsible for the results of the project
Page 44 of 90
Mohamed Nazaruddin
Free buffer
Feeding buffer
Project buffer
See
references Marked for review
2. A company has to make a choice between two projects, because the available resources in money
and kind are not sufficient to run both at the same time. Each project would take 9 months and
would cost $250,000.
1. The first project is a process optimization which would result in a cost reduction of $120,000 per year.
This benefit would be achieved immediately after the end of the project.
2. The second project would be the development of a new product which could produce the following net
profits after the end of the project:
1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000
Assumed is a discount rate of 5% per year. Looking at the present values of the benefits of these
projects in the first 3 years, what is true?
Both projects are equally attractive.
See
references Marked for review
Page 45 of 90
Mohamed Nazaruddin
The measurements made at the end of the process yielded the following results:
See
references Marked for review
4. Your project management team includes two external consultants each from a different company.
You found that repeated conflicts between the two consultants already slow down project progress
and jeopardize achievement of objectives.Which stage of team development can be difficult to
overcome in such a situation?
Page 46 of 90
Mohamed Nazaruddin
See
references Marked for review
5. During a project, earned value analysis is performed, resulting in the following numbers:
See
references Marked for review
6. A project manager spent some days to create a multi-page document, which he called project
charter. The document should have been issued by the project sponsor. The sponsor found the
document outsized and asked for a condensed document.
High-level risks
Page 47 of 90
Mohamed Nazaruddin
7. A document called ____________ is created by decomposing the project scope into smaller, more
manageable elements.
Scope Statement
Requested Change
See
references Marked for review
8.
Page 48 of 90
Mohamed Nazaruddin
Diagramming techniques
See
references Marked for review
9. In order to speed up a project, you made a decision to fast-track a phase currently performed with
five team members, and another one which was planned to begin in four weeks time with another
five team members.
See
references Marked for review
10. A project manager has been asked to support an internal project request by developing a business
case.
Page 49 of 90
Mohamed Nazaruddin
See
references Marked for review
You found the following earned value analysis information for a project that was recently closed-
out:SPI = 0.7, CPI = 1.0
11.
The project has been cancelled while it was executed. At that time the project was behind
schedule and on budget.
The project's deliverables have all been finished. The project came in behind schedule but on
budget.
The project's deliverables have all been finished. The project came in ahead of schedule but
on budget.
The project's deliverables have all been finished. The project came in on schedule but over
budget.
See
references Marked for review
12.
It should describe how requirements activities will be planned, tracked, and reported.
See
references Marked for review
Page 50 of 90
Mohamed Nazaruddin
a chance to which no expected monetary value can be assigned so that a likely pay-off can
not be shown.
a decision to which no expected monetary value can be assigned so that a likely pay-off can
not be shown.
a chance to which an expected monetary value may be assigned to calculate the most likely
pay-off.
a decision to which an expected monetary value may be assigned to calculate the most likely
pay-off.
See
references Marked for review
A project management team has subcontracted work to a service company. Which of the following
tools is the best choice to assure that this company will be able to meet the quality requirements of
14. the project?
Quality audit
Deliverable inspection
Page 51 of 90
Mohamed Nazaruddin
15. With your team you are using judgment from subject matter experts to identify and analyze project
risks. There is a small number of experts available, but some of them have long been in a teacher-
student or manager-assistant relationship.
Which of the following techniques can ensure best that there is no dominating opinion during an
expert review?
Peer review
SWOT analysis
Delphi technique
See
references Marked for review
16. You are running a project for a customer based on a cost-reimbursable contract with the following
terms:
Which is the PTA (= point of total assumption, break point) of the project?
$1,300,000
$1,500,000
$80,000
$1,125,000
Page 52 of 90
Mohamed Nazaruddin
17. During execution of a project which is performed for a customer on a T&M (time and material)
contract base, a new project manager is taking over the assignment.
He discovers that two members assigned to the project have charged time without performing any
work for the project customer. Upon further investigation, he determines that this occurred because
there have been no other project assignments open for these employees. The customer is unaware
of these facts.
Try to find a responsible person for the over-assignment who can be made accountable.
Take the two people off the team immediately and arrange for the refund of the excess
charges to the customer.
See
references Marked for review
18. Start dates in the following network logic diagram are defined as early morning, finish dates are
evening.
Page 53 of 90
Mohamed Nazaruddin
See
references Marked for review
19. Your project is executed with a globally spread virtual team. The project progress has been found to
be too slow. Which measure is most likely to immediately speed up the project?
Page 54 of 90
Mohamed Nazaruddin
See
references Marked for review
A project management team wants to procure some customized products which are available in
identical grade and quality from many vendors. What should be included in the procurement
20. package to ensure that their offers will be comparable?
A statement of work describing the needs of the project in sufficient detail to enable vendors
to make suitable proposals
A statement of work specifying attributes and metrics of the requested deliverables in detail to
allow vendors submission of bids
The approved project scope statement, the WBS which should be broken down to work
package level and the WBS dictionary
The risk management plan and the reports from those risk management reviews which have
been made so far
See
references Marked for review
21. Which of the following becomes increasingly important in a virtual team environment?
Requirements engineering
Page 55 of 90
Mohamed Nazaruddin
Network diagramming
See
references Marked for review
22. You are assigned as the project manager to a project which is executed for a customer under FP
contract. Your customer informed you this morning that they insist on certain "refinements" of the
project scope. You agree that the requested actions make really sense to the project, but believe
that they constitute a major change increasing the project scope. What should you do next?
Accept the request of the customer. Diligently document the additional costs and working
hours spent by yourself and the team on the implementation of the change and invoice these
to the customer at appropriate rates.
Perform earned value analysis to assess the current status of the project and get all the
numbers you need to communicate the case to the change control board which then will have
to make the best decision regarding the customer request.
Check the contract, the project charter, the scope statement and other documents related to
the project and the contract. Implement ADR (alternative dispute resolution) procedures if the
conflict cannot be resolved otherwise.
Page 56 of 90
Mohamed Nazaruddin
See
references Marked for review
23. A prime contractor in a customer project under CPFF contract has run into unexpected technical
problems. Fixing them will require a lot of additional work to be done. The company made a decision
to book more staff and equipment from their subcontractors in order to adhere to the agreed
timeline. The customer agreed to this decision. What will most likely happen?
The contractors indirect costs will increase and the customers payment for them will
increase, too.
The contractors indirect costs will increase, but the customers payment for them will not
increase.
The contractors indirect costs will not increase, but the customers payment for them will.
Both the contractor's indirect costs and the customers payment for them will not increase.
Page 57 of 90
Mohamed Nazaruddin
24. A project management team is evaluating the causes that might contribute to unsatisfactory
performance and quality. Which of the following statements is not true?
Normal process variation is attributable to random causes and sometimes also called "white
noise".
Special causes are easier to predict and handle than random causes (also called common
causes).
Special causes are unusual events which are difficult to foresee and often produce outliers.
A process can be optimized to limit the bandwidth of variations due to random causes.
See
references Marked for review
25. You are performing a project management audit in your company and find that most of the project
plans are neither consistent nor up-to-date.
Page 58 of 90
Mohamed Nazaruddin
See
references Marked for review
26. You want to perform active risk acceptance. What should you do?
See
references Marked for review
27. A project manager made 3-point estimates on a critical path and found the following results:
Page 59 of 90
Mohamed Nazaruddin
You can not derive the path standard deviation from the information given.
See
references Marked for review
28.
See
references Marked for review
Page 60 of 90
Mohamed Nazaruddin
A measuring instrument solely used to describe process capability. The process is found
capable if the 3 sigma range is exceeded by not more than 0.3% of a tested sample lot.
The limits of the six sigma area on either side of a control chart to plot measured values; data
found outside the area are out of specification and can lead to rejection of an entire batch.
The area consisting of typically three standard deviations on either side of a mean value of a
control chart to plot measured values found in statistical quality control
The area consisting of typically three standard deviations on either side of a mean value of a
control chart to plot measured values found in quality assurance
See
references Marked for review
30.
Page 61 of 90
Mohamed Nazaruddin
31. Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6
days.
37 days
39 days
42 days
See
references Marked for review
Which tool and technique is used in the processes Create WBS and Define activities?
32.
Page 62 of 90
Mohamed Nazaruddin
Decomposition
See
references Marked for review
b, c
c, d
See
references Marked for review
Attribute sampling is the process of assessing whether results conform to specifications or not.
Page 63 of 90
Mohamed Nazaruddin
Variables sampling means that the result is classified into one of the 3 categories:"acceptable"
- "acceptable after rework" - "rejected".
Inspection is often mainly done to keep errors out of the hands of the customer instead of as
a means of process control.
See
references Marked for review
35. Which statement describes best why you should document assumptions?
Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows
baseline adjustments in case of project crisis.
Assumption analysis is a valuable tool and technique to explore the validity of assumptions
during risk identification.
Assumptions limit the project management team's options for decision making because they
can not be controlled by the team.
Page 64 of 90
Mohamed Nazaruddin
See
references Marked for review
Prevention costs
Maintenance cost
Appraisal costs
Failure costs
See
references Marked for review
Page 65 of 90
Mohamed Nazaruddin
As you are not responsible for lifecycle costing, you don't have to worry about operation
profits. Focus on project costs from initiation through handover.
Ensure maximum profits by buying the best and cheapest items, components and
modulespotentially from a big number of different suppliersand integrating them.
Create a realistic plan broken down to a sufficient level of detail. Perform all risk management
processes. Ensure real-time communications with all stakeholders.
Try to get a second project manager assigned to share decision making and accountability to
shareholders with the person.
See
references Marked for review
Page 66 of 90
Mohamed Nazaruddin
See
references Marked for review
39. You are project manager in a global project with a team consisting of people from various countries.
What can you try to prevent misunderstandings due to cross-cultural differences?
Use all communication methods available that are suitable for the team and follow up in
writing when communicating verbally. Remember that cultural and individual diversity may
help project teams solving unforeseen problems during the course of the project.
When you are about to form a team for your project, keep in mind that some cultures are
developed, others are more primitive. Some have values, some not. You should consequently
avoid choosing members from countries with cultures that are not similar to your own.
Cultural dilemmas can prevent any project from being successful. They should therefore be
smoothed or suppressed so as to make sure that they cannot disrupt project work. Your effort
should concentrate on communication that can help reach that goal.
Page 67 of 90
Mohamed Nazaruddin
See
references Marked for review
See
references Marked for review
Page 68 of 90
Mohamed Nazaruddin
In order to avoid such a situation, rejected change requests should be consistently communicated to
stakeholders through which process?
Report performance
Verify scope
See
references Marked for review
A warning sign that a previously identified risk might be occurring or has occurred
Page 69 of 90
Mohamed Nazaruddin
43. According to the project plan, a contractor is scheduled to deliver some software components today
afternoon. A regular payment is due to be made to this contractor tomorrow.
You and your project team received a note this morning informing you that the software delivery
will be delayed by 2 weeks.
You should conduct a meeting with the contractor to resolve the delivery issues before making
the payment.
You should make the payment and reschedule the project plan.
See
references Marked for review
44. In a software company a large number of simultaneously performed projects utilize the same
groups of human and other resources.
Page 70 of 90
Mohamed Nazaruddin
Resource pooling
Program management
See
references Marked for review
45. What does the acronym RACI commonly stand for in project management?
See
references Marked for review
Page 71 of 90
Mohamed Nazaruddin
Remove physical constraints and replace hard logic with soft logic.
See
references Marked for review
47. Liquidated damages (LDs) are contractually agreed payments in order to...
Page 72 of 90
Mohamed Nazaruddin
...cover the customer's costs caused by late completion or failure to meet specifications by the
contractor.
...make a bid or proposal binding for the offerer while the customer has time to select among
various bidders.
See
references Marked for review
Page 73 of 90
Mohamed Nazaruddin
49. You are assigned as the project manager to a project which had a one-time cost variance in the past
caused by unexpected rework which has meanwhile been finished. You perform earned value
analysis and get the following results:
BAC is 500,000.
What is right?
EAC = 550,000
EAC = 525,000
EAC = 500,000
EAC = 425,000
See
references Marked for review
50. An estimation has been made that the construction of a residential home will cost a certain amount
per square foot of living area. This is an example of what type of estimating?
Analogous estimating
Bottom-up estimating
Page 74 of 90
Mohamed Nazaruddin
Parametric estimating
See
references Marked for review
They are tangible and allow for early feedback on requirements by stakeholders.
Prototypes are mostly developed toward the end of a design or build phase.
Page 75 of 90
Mohamed Nazaruddin
A change request that helps improving the project and its product, service or result and is
discussed generally in a friendly style.
A direction by the buyer or an action taken by the seller that the other party considers an
undocumented change to the contract.
A field change or ad-hoc change mandated by the project customer in a public construction
project.
A change request which will lead to the re-construction of an older version of the project
performance baseline by the contractor.
See
references Marked for review
53. Which of the following is generally not regarded to be a motivator according to Frederick Herzberg?
Page 76 of 90
Mohamed Nazaruddin
See
references Marked for review
54. What is true for modern project management? Project managers need...
Page 77 of 90
Mohamed Nazaruddin
55. You are the project manager in an engineering project and have recently signed a contract with a
software vendor for the development of a complicated control solution. The software will be used to
control machinery equipment which your project team is currently developing. The contract is a
lump-sum contract. The contractor has target cost estimated which seem rather low to you. Which
of the following statements is not true for this situation?
It is the contractor's risk in this type of contract that their profit may vanish if costs have been
underestimated.
This form of contract should only be chosen when all the requirements for the building of the
product are well-known by all parties involved.
In a fixed-price contract, change requests can cause issues regarding additional time and
extra costs for the changes to be applied.
It is likely that your organization may have to assume any unexpected additional costs for the
software development.
See
references Marked for review
Page 78 of 90
Mohamed Nazaruddin
Quality auditing
Inspection
Quality testing
Reject screening
See
references Marked for review
It allows one to easily identify the breakdown level of the item in the resource structure.
It describes the coding structure used by the performing organization to report financial
information in its general ledger.
It defines ethical behavior in the project and the responsibilities to the customer and the
profession.
Page 79 of 90
Mohamed Nazaruddin
58. You are the manager of your company's project management office. The company is running many
concurrent projects; most of them share a resource pool of technical staff. Understanding how
resources are utilized across projects has been found essential to overall project performance,
including cost effectiveness and profitability.
This morning you received a message that the resource pool members will be unable to perform as
planned for the next months because the overall work load has grown too high and while delays are
adding up, the morale of the staff is going down.
See
references Marked for review
You have been criticized that certain specifications in your scope statement do not pass the test for
SMART objectives. What are SMART objectives?
59.
Objectives specified in far more detail than necessary for a execution of a successful project.
Easily achievable objectives which help you reducing the pressure on yourself and the team.
Page 80 of 90
Mohamed Nazaruddin
See
references Marked for review
60. You have been assigned as a project manager to a software project. While you and your team are
working on a WBS (work breakdown structure), estimations for activity durations based on the
activity list vary significantly. Which additional documents may help you clarify this situation?
See
references Marked for review
Page 81 of 90
Mohamed Nazaruddin
After budget approval, an additional and unexpected cost item has been identified, which made the
project more expensive some weeks ago. The item has meanwhile been paid by the project team,
and it is expected that for the remaining duration of the project, costs will be as budgeted.
In this case, which is the best formula to calculate EaC (Estimate at Completion)?
EaC = BaC - CV
EaC = AC + BtC / CV
See
references Marked for review
62. During a company event, you had the opportunity to talk to a colleague project manager. He told
you that in his current project actual costs are 15% under cumulated costs budgeted for today.
The project will probably be completed with total costs remaining under budget until the end.
A significant cost increase during the further course of the project will probably bring the costs
back to baseline level.
Original cost forecasting and budgeting for the project must have been poor to allow this
variance.
See
references Marked for review
Page 82 of 90
Mohamed Nazaruddin
Project managers should visit their customers far more often than what is usual in order to
avoid misunderstandings and bad emotions.
International projects may have an increased need for traveling which can lead to additional
costs and troubles with time zones.
Committee decisions can have the paradox outcome, that a jointly made or approved decision
is not desired by any individual group member.
See
references Marked for review
64. Which of the following statements describes best the relationship between project phases and the
project life cycle?
The project life cycle includes the time when the project is performed and the expected
product lifespan after that.
Page 83 of 90
Mohamed Nazaruddin
The project life cycle is regarded as a sequence of project activities while phases are defined
to control overlapping activities.
The project life cycle describes how iterations of project management processes are used
when a project schedule is developed.
See
references Marked for review
Which is an appropriate order in most project situations for the development of scope-related
documents?
65.
1. Project SOW (statement of work), 2. Project charter, 3. Project scope management plan, 4.
Project scope statement, 5. WBS (work breakdown structure) and WBS dictionary.
1. Work breakdown structure, 2. Scope statement, 3. Project charter, 4. CSOW (contractual
statement of work), 5. Contractual work breakdown structure
1. Feasibility study3. Contract, 4. CWBS (contractual work breakdown structure), 5. Scope of
work descriptions, 6. PID (project initiation document).
1. BOM (Bill of materials), 2. CAP (control account plan), 3. Project charter4. Change
management plan,5. Scope baseline.
See
references Marked for review
Page 84 of 90
Mohamed Nazaruddin
A metaphoric description of the short term uncertainties that are present in every project.
The graph that describes the typical growth of earned value during the course of the project.
See
references Marked for review
An output of the process Estimate activity resources is a document called "activity resource
requirements". It identifies the types and quantities of resources...
67.
See
references Marked for review
Page 85 of 90
Mohamed Nazaruddin
Verification that the configuration identification for a configuration item is accurate, complete,
and will meet specified program needs.
Ensuring that proposed and approved changes to configuration items are fully analyzed.
Ensuring that proposed and approved changes to configuration items are fully documented.
Managing and controlling the frequently requested changes to a project by applying agreed
rules.
See
references Marked for review
Which statement describes best the meaning of the term cost baseline?
69.
A cost baseline is always created by translating time-phased cost information into cost data on
activity or work-package level.
A cost baseline is an approved time-phased budget that will be used to measure and monitor
cost performance on the project.
Data to draw a cost baseline can be easily generated and updated as necessary from
information related to actual project cost.
A cost baseline is usually displayed in the form of an inverse S-curve drawn from the
beginning of the project until data date.
See
references Marked for review
70. Which is not true in regard of RoI (return on investment) for a project?
Page 86 of 90
Mohamed Nazaruddin
It includes investment, direct and indirect costs and may include allowances for capital cost,
depreciation, risk of loss, and/or inflation.
See
references Marked for review
A project sponsor requested earned value data on two concurrent projects from the project
managers. Both projects are regarded as equally important and strategically beneficial and have
71. been finished by over 80%. He received the following information:Project A: PV: $1,800,000 EV:
$2,300,000 AC: $2,100,000Project B: PV: $2,000,000 EV: $1,500,000 AC: $1,600,000The
sponsor considers to shift some resources from project A to project B to speed up the second
project which is currently behind schedule. What is the most likely outcome of such a measure?
Changing team assignments during late course of a project typically increases cost efficiency.
Changing team assignments during late course of a project typically increases time efficiency.
According to the law of diminishing returns, the consolidated cost variance of the two projects
will decrease.
According to the law of diminishing returns, the consolidated cost variance of the two projects
will increase.
Page 87 of 90
Mohamed Nazaruddin
72. Which of the following statements describes best the relationship of quality and grade?
Low grade is always a problem; low quality may be overcome by a good rework and repair
process.
Grade is a category or rank given to entities having different functional requirements but the
same need for quality.
Both quality and grade can often be improved through intelligent measuring, testing and
examining.
Low quality is always a problem as it bears on the ability of an item to meet requirements; low
grade may sometimes be acceptable.
See
references Marked for review
Network templates which contain only portions of a network are often referred to as
73.
Subprojects
Programs
WBS items
Page 88 of 90
Mohamed Nazaruddin
74. You have been asked to calculate the internal rate of return (IRR) of a project? What will you
assess?
The time period needed to pay back the investment from a project when future income is
discounted.
The inherent discount rate or investment yield rate produced by the project's deliverables over
a pre-defined period of time.
The rate of negative risk that can be accepted for a project without turning the expected net
present value negative.
The expected benefit from a projects deliverable calculated as a percentage of the original
investment over a specified time period.
See
references Marked for review
You just created the following network logic diagram to describe the planned flow of activities for
your project which will start tomorrow:
75.
Page 89 of 90
Mohamed Nazaruddin
Activity F is open ended in relation to the path divergence after the start milestone.
You cannot calculate a critical path when lags and/or leads are calculated in percent.
Page 90 of 90