ADMINISTRATIVE RECORD DOCKET
BISHOP TUBE SITE
PROMPT INTERIM RESPONSE,
Date Opened: December 16, 2007
Date Closed: March 16,2007
te
September 1998
May 1999
June 10, 1999
Part II. Further Investigation
January 11, 2002
June 21, 2002
Tune 30, 2003,
August 27, 2003
September 9, 2003
October 31, 2003
January 29, 2004
March 4, 2004
July 2, 2004
Descriptis
* Site Characterization and Interim Remedial Action Plan.
Prepared by O'Brien & Gere Engineers, Inc. for Christiana
Metals Corp.
* Interim Remedial Action Workplan, Prepared by O’Brien &
Gere Engineers, Inc. for Christiana Metals Corp.
February 1999 Groundwater Sampling Results submitted by
O'Brien & Gere Engineers, Inc.
* Phase I Site Characterization Report Soils, Sediment, Surface
Water, and Sahllow Groundwater, Prepared by Baker
Environmental, Inc.
* Phase II Groundwater Investigation. Prepared by Baker
Environmental, Inc.
* Phase III Supplemental Soil Investigation Report. Prepared by
Baker Environmental, Inc,
Little Valley Creek Surface Water and Spring Monitoring:
Sampling Event Report. Prepared by Dustin A. Armstrong,
Project Officer.
HSCA Section 503 Information Request Letters sent to Johnson
Matthey, Whittaker Corp., and Marcegaglia USA.
* Response to HSCA Section 503 Letter. Prepared by Mr.
Robert W. Thomson, Esq., on behalf of Marcegaglia USA.
* Response to HSCA Section 503 Letter. Prepared by Whittaker
Corporation,
* Response to HSCA Section 503 Letter. Prepared by Johnson
Matthey.
* Phase III Supplemental Groundwater Investigation Report,
Prepared by Baker Environmental, Inc.April 2005 Surface Water Investigation — Data Summary, Upstream of
Lancaster Avenue ~ Source Area Discharge. Prepared by Dustin
A. Armstrong, Project Officer
Part III. Response Initi:
te De
March 17, 2005 Prospective Purchase Agreement between the PA Department of
Environmental Protection and Constitution Drive Partners, L.P,
January 26.2006 Scope of Work ~ Air Sparging/Hot Spot Response. Prepared by
Dustin A. Armstrong, Project Officer.
February 10,2006 Letter from Ryan C, Kostival, Contract Manager to Mr. Victor
‘Velez, Program Manager, Weston Solutions, assigning Bishop
Tube site work.
February 16, 2006 Initial Work Plan and Cost Estimate for Air Sparging/Hot Spot
Remediation. Prepared by Weston Solutions, Inc.
March 7. 2006 Letter from Ryan C. Kostival, Contract Manager to Mr. Victor
‘Velez, Program Manager, Weston Solutions approving Weston’s
intitial Work Plan and Cost Estimate.
November 20,2006 __* Final Remedial Design Report Air Sparging-Soil Vapor
Extraction — Former Bishop Tube Property. Prepared by
Environmental Standards, Inc, on behalf of Constitution Drive
Partners, L.P.
January 22, 2007 First Amendment to Consent Order and Agreement
between the PA Department of Environmental Protection and
Constitution Drive Partners, L.P.
Part IV. Notification and Public Participation
D Scr
Qn
May 5, 2000 HSCA Section 501 Notice letters sent to Alloy Steel Corporation,
Cristiana Metals Corp., Marcegaglia USA Damascus Division,
Whittaker Corporation, and Johnson Matthey, Inc,
May 17, 2000 Response to HSCA Section 501 Notice letter sent to Alloy Stee!
Corporation. Sent by Mr. Richard W. Roeder, Bankruptcy
Trustee for Electralloy Corporation,
May 12, 2006 Letter inviting Whittaker Corporation to a meeting to discuss
HSCA liability and participation in response actions,
May 24, 2006 Letter inviting Johnson Matthey to a meeting to discuss HSCA
liability and participation in response, actions.August 29, 2006
Undated
December 15, 2006
Letter to Mr. Robert Thomson, Esq. inviting Marcegaglia USA to
‘meeting to discuss HSCA liability and participation in response
actions.
Language for publication in the December 16, 2006
Pennsylvania Bulletin.
HSCA Section 506(b) Notice leters sent to Johnson Matthey,
Ine., Whittaker Corporation, and Marcegaglia USA.
Part V. Response Decision Documents
ate
March 13, 2000
December 14, 2006
escription
Response Justification Document ~ Bishop Tube Site prepared
by Dustin A. Armstrong, Project Officer.
Analysis of Alternatives and Proposed Response Document for
the Bishop Tube Site — Contaminant Source Area Remediation
prepared by Dustin A. Armstrong, Project Officer.
.; Notation indicates that this information is incorporated into the administrative record
by reference, in accordance with 25 PA Code Sec
documents are available for review in the South:
Record file.
ction 3.12(c), Copies of the designated
east Regional Office Administrative