Sei sulla pagina 1di 11

ARTICLE IN PRESS

Building and Environment 40 (2005) 12441254


www.elsevier.com/locate/buildenv

Judgmental risk analysis process development in


construction projects
Ahmet Oztas- , Onder Okmen
Civil Engineering Department, University of Gaziantep, Gaziantep, Turkey
Received 16 June 2003; accepted 22 October 2004

Abstract

Various risks and uncertainties exist in construction projects. These may not only prevent the projects to be completed within
budget and time limit, but also threaten the quality, safety and operational needs. In this context, risk analysis processes are the
systematic methods to analyze the potential project risks and develop risk response strategies in order to cope with risks and achieve
the desired objectives. This study proposes a new schedule risk analysis method named as judgmental risk analysis process (JRAP)
and offers a different project duration equation through JRAP. The process (JRAP) can be dened as a pessimistic risk analysis
methodology or a hypothesis based on Monte Carlo simulation that is effective in uncertain conditions due to its capability of
converting uncertainty to risk judgmentally in construction projects. A case study has also been developed to show how the
proposed process is applied on a construction project and to prove its validity.
r 2004 Published by Elsevier Ltd.

Keywords: Risk; Risk analysis; Monte Carlo simulation; Schedule analysis; Construction management

1. Introduction the previous data available. Since such a separation is


regarded as meaningless in the construction literature,
Each construction project has unique features that risk turns out to be the most consistent term to be used
differentiate it from even resembling projects. Construc- for construction projects because some probability
tion techniques, design, contract types, liabilities, weath- values can be attached intuitively and judgmentally to
er, soil conditions, politic-economic environment and even the most uncertain events [2]. The uncertainty
many other aspects may be different for every new represented quantitatively at some level is not the
commitment. This fuzzy atmosphere has been repre- uncertainty any more; rather it is the risk henceforth
sented with the terms uncertainty or risk by construc- and needs to be managed. In this context, this research
tion managers and researchers, and they tried to control aims to prove this hypothesis by developing judgmental
this systematically through risk management and risk analysis process (JRAP) and applying this process
analysis methods since the early 1990s [1]. Some in the assessment of schedule risks of a construction
researchers like Flanagan et al. [2] and Pilcher [3] put project through a case study.
differentiation between these two terms. They have One important way of controlling risks in construc-
mentioned that uncertainty represents the situations in tion projects is to develop reliable project estimates and
which there is no historical data; and risk, in contrast, schedules [4]. Probabilistic scheduling through conduc-
can be used for situations where success or failure is tion of simulations on prepared models provides more
determined in probabilistic quantities by beneting from powerful results fundamental to making decisions with
regard to the control of project risks. Barraza et al. [5]
Corresponding author. has brought a stochastic approach to traditional S-curve
E-mail address: aoztas@gantep.edu.tr (A. Oztas-). project performance control method by using simulation

0360-1323/$ - see front matter r 2004 Published by Elsevier Ltd.


doi:10.1016/j.buildenv.2004.10.013
ARTICLE IN PRESS
A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254 1245

techniques and probability distributions. Chehayeb et tion and classication techniques are present such as
al. [6] has developed a different simulation-based brainstorming, check lists, organizational charts and
scheduling method with continuous activity relation- mapping [1,16]. Risk analysis part is dominantly
ships to enable effective use of systems simulation in quantitative and, therefore, it includes mathematical
scheduling of construction projects. Similarly, Senior et and statistical operations [17]. Risk response is the last
al. [7] has discussed a new scheduling system based on risk management step at which the results of the
statistical simulation. The reliability of probability preceding steps are discussed and suitable risk mitiga-
distribution functions used as input data in stochastic tion actions are taken before facing risks.
scheduling systems has attracted the interest of research-
ers like Maio et al. [8] and Fente et al. [9].
Different methods have been used so far for measur- 3. JRAP methodology
ing the variations in activity durations and modelling
schedule risks of projects, e,g. Program Evaluation and The JRAP proposed in this research consists of a
Review Technique (PERT) [10], Probabilistic Network number of managerial steps to be carried out and an
Evaluation Technique (PNET) [11], Narrow Reliability equation that offers the variation in each activitys
Bounds (NRA) [12] and Monte Carlo simulation (MCS) duration in the schedule network. The characteristics of
[2,10,13]. Activity durations in construction projects are JRAP make this methodology effective in uncertain
likely to vary because of the inherent risks. For this conditions of which there is no or little previous data
reason, Dawood [13] and Ranashinghe [14] have also and increases its applicability for converting high level
developed equations for quantifying and modelling the of uncertainty to risk judgmentally. Since, judgmental
variation in activity durations and nding the overall decisions based on experience and intuition would insert
project duration. additional risks to the project network model, a
pessimistic way has been followed in analyzing the
overall project duration. In other words, the pessimistic
2. Risk analysis and risk management characteristic of JRAP decreases the effect of planning
engineers making inaccurate data estimation during
Each construction project has its own technical risk modelling. This pessimism is created through the
characteristics that vary according to the construction computing characteristics of the proposed equation that
type, execution time and its environment. This leads to a is introduced within JRAP.
different risk atmosphere for each construction project. Another important point that should be mentioned
In this context, risk management can be dened as a about JRAP is that it is not a whole risk management
systematic controlling procedure of risks that are system, rather it is considered as an analysis stage that is
predicted to be faced in an investment or project [15]. performed during the conguration of a risk manage-
However, it is neither an insurance system nor a magical ment system. JRAP can be dened as a pessimistic risk
risk elimination method. It only aims to identify the analysis methodology or a hypothesis that is effective in
potential risks as early as possible and manage them for schedule risk modelling of even the most uncertain
preventing the harmful effects of the risks to the project situations in construction projects.
aims. The system utilizes the historical data, statistical Fig. 1 illustrates the logic and steps of JRAP and
knowledge, computer modelling-running power, human claries the processs relationship with the other risk
intuition, judgment, experience, gut feel, common sense management stages. The tasks labelled as D, E, F and G
and willingness up to a full extent [2]. represent the steps of JRAP. They make up the risk
In the course of time, the management of risk has management system together with the other tasks, which
become a key element for the completion of projects are B, C, H and I. The task labelled as A, in contrast,
within time schedule and planned budget. It is now a represents the classical approach, i.e. the arrangement of
common opinion that controllable and uncontrollable project content by deterministic schedule planning.
risks can only be responded by utilizing risk manage- JRAP methodology comprises the analysis part of
ment process over the entire project, i.e. prior to the overall risk management system as seen in Fig. 1. In
tender and subsequently, by controlling and updating other words, JRAP can only be applied just after
the system periodically during the application of the pre- identifying and classifying the risks that would inuence
determined plan. the activity durations of the shedule.
Like every systematic procedure, risk management is Deterministic way of schedule analysis prior to setting
a stepwise phenomenon. These steps can be summarized up a risk management system (refer to Fig. 1) leads to a
basically as risk identication, risk classication, risk more appropriate risk-modelling environment for any
analysis, and risk response [2]. Risk identication and project, even though deterministic approach avoids the
classication comprise the qualitative investigation of use of statistical data and assumes certain xed values.
the risks. In the literature, a number of risk identica- The need for the deterministic model arises from its
ARTICLE IN PRESS
1246 A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254

Model
deterministic
time schedule
plan
Identify
of the project
risks
-A-
-B-

Classify
risks
-C-

RISK MANAGEMENT FRAMEWORK



Decide the critical risks Update the model
effective on activity durations
-D-

Assign probability
distributions
and max-min durations
-E- Control
the
progress
-I-

Establish activity-risk factor


matrix
-F-

Model stochastic time


schedule plan
of the project and Run Monte Respond
Carlo Simulation to risks
-G- -H-

JRAP METHODOLOGY

Fig. 1. The steps of judgmental risk analysis process (JRAP). Note: JRAP steps are labelled as D, E, F and G.

power of highlighting the potential project risks. In predetermined in the risk identication step (step B in
other words, it helps the planner especially during the Fig. 1) of risk management framework. For the sake of
risk identication step. simplication, the critical risks established in this way
are assumed to be effective on also non-critical activities.
3.1. Step 1deciding of main risks
3.2. Step 2assignment of probability distributions and
The rst task undertaken during the conduction of maximum minimum durations
JRAP is to nd out the critical risks that may be
effective on activity durations. This is achieved through The second step of JRAP is to attach probability
examining the critical activities of the deterministic distributions to the identied risks in the preceding step.
schedule network and then selecting the risks which This can be achieved through utilizing experience and
inuence these critical activities from the risk list engineering judgment in case there is not enough past
ARTICLE IN PRESS
A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254 1247

record to conduct detailed statistical analysis. This is programs performing spreadsheet modelling and MCS
already the advantage and practicality of JRAP during are the main tools of this step.
conditions when there is no previous data. At this step, MCS utilizes the activity-risk factor
The random values between 0 and 1 (refer to Eq. (1)) matrix developed at the third step in order to calculate
will be selected by the utilized software according to the the variation in activity durations. In order to enable
character of the assigned probability distributions and MCS to calculate the activity durations in a stochastic
correlation coefcients during MCS. While distributions manner, the following pessimistic equation (Eq. (1)) is
are being assigned, maximum and minimum durations developed after some reformation on Dawoods [13]
of activities should also be determined. Eventually, equation (Eq. (2)).
all of these values will be used in calculating activity
Duration of activity MAXMin:Time
durations. Common distributions like beta, triangle and
lognormal can be used for representing the critical risks. Risk Factor Affect;
However, negative skewness is not offered in JRAP, Max:Time
because it is less probable to face with a situation that  Risk Factor Effect;
the real execution time of a construction activity would
Duration of activity MAXMin:Time
be below the appraised most likely duration with a
greater chance than being above the most likely Max:Time  Min:Time
duration. This is one of the characteristics of JRAP,  RF1  Random1 RF2
which makes it a pessimistic approach.  Random2 RFn
The corner values such as maximum, likely and
 Randomn ; Max:Time
minimum durations of an activity can be determined
according to the type of key resources consumed for that  Max:Time  Min:Time
activity. The activities in construction projects can be  RF1  Random1 RF2
categorized as production-related, procurement-related  Random2 RFn
and administrative activities. The production-related
 Randomn ; 1
activities can either be labor-driven or equipment-
driven. According to this classication system, a variety where Min.Time is the minimum duration that an
of methods like heuristics, statistical studies, cycle time activity can be completed, Max.Time, the maximum
analysis, queuing theory and simulation are available to duration that an activity can be completed, RFn, the
calculate activity durations [10]. However, engineering percent effect of nth risk factor on an activity (taken
judgment, experience and intuition affect the consis- from activity-risk factor matrix), Randomn is a random
tency of the results obtained by these techniques. It is number, between 0 and 1, generated during MCS to
also possible to determine the corner duration values of represent the nth risk factors probability distribution.
the activities judgmentally as it is applied in the case
Duration of activity Min:Time Max:Time
study.
 Min:Time  RF1
 Random1 RF2
3.3. Step 3establishment of activity-risk factor matrix
 Random2 RFn
In this step of the process, activity-risk factor matrix  Randomn : 2
is established. Activity-risk factor is the percentage
Eq. (1) (activity duration equation), which is an
effect of each risk over each activity (refer to Table 2). In
important fragment of the JRAP model, consists of two
activity-risk factor matrix, the varying effect of each risk
main parts of which one of them is already Eq. (2) itself.
over each activity is quantied in percentages. However,
For this reason, the nal result of Eq. (1) is the
the total inuence of all risk factors should be 100% on
maximum of the results of these two parts. While Eq. (2)
any given activity [13]. This assessment is performed
calculates the duration of the activity by adding the risk
mainly in a judgmental way. In other words, if previous
factor effect to the minimum activity time; Eq. (1), in
data is unavailable and a fully uncertain situation
contrast, calculates also the subtracted value of the same
is encountered, a fully judgmental solution will be
risk factor effect from the maximum duration and
produced.
eventually gives the maximum of the two results as the
activity duration. This approach provides to stand at the
3.4. Step 4modelling and simulation worse side and creates a pessimistic view. This is one of
the cornerstones of the JRAP.
The fourth JRAP step is modelling and simulating the Now, as an example, assume that an activity of a
schedule network of the project. Deterministic schedule construction project has a maximum duration of 60 days
model developed in project planning software, package and a minimum duration of 30 days. Next, assume that
ARTICLE IN PRESS
1248 A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254

Table 1
Computations showing four manually conducted Monte Carlo iterations

Iteration number Data Computation

1 Random1 1.00 RF1 20%


Random2 0.00 RF2 20% Risk factor Effect 14.7
Random3 0.60 RF3 40% Duration of activity 45.3 days
Random4 0.25 RF4 20%
2 Random1 1.00 RF1 20%
Random2 1.00 RF2 20% Risk factor effect 16.2
Random3 0.00 RF3 40% Duration of activity 46.2 days
Random4 0.70 RF4 20% Max. duration 60 days

3 Random1 0.50 RF1 20% Min. duration 30 days


Random2 0.35 RF2 20% Risk factor effect 15.3
Random3 0.40 RF3 40% Duration of activity 45.3 days
Random4 0.90 RF4 20%
4 Random1 0.00 RF1 20%
Random2 0.10 RF2 20% Risk factor EFFECT 9.0
Random3 0.30 RF3 40% Duration of activity 51.0 days
Random4 0.80 RF4 20%

the random numbers produced from the distributions 4.2. Project definition
assigned to four risks are (1, 0, 0.6, 0.25), (1, 1, 0, 0.7),
(0.5, 0.35, 0.4, 0.9) and (0, 0.1, 0.3, 0.8) to be used during The project is the decoration of a bank ofce, which is
four manual iterations of MCS. Besides, from activity- located at a rural area of the South-Eastern part of
risk factor matrix, the weather has 20%, design changes Turkey. The contract used is an admeasurement type
has 20%, soil conditions has 40% and labor productiv- with xed unit-price including specic clauses offered by
ity has 20% effect on the duration of the assumed the promoter. The promoter is the States biggest bank.
activity. All of this information is enough to calculate The project start date was 30th November 1999 and the
the duration of the activity using Eq. (1). The computa- completion date was 25th January 2000 in the contract.
tions are summarized in Table 1. In other words, the contractual project duration was 57
Nevertheless, manual application of MCS is incon- days. However, the project has been completed in 122
sistent while computer programs are capable of doing days, i.e. 65 days after the project deadline negotiated
the same job faster, more precisely and with much more within the contract documents.
running preferences. Furthermore, such programs pro-
vide an easy and effective environment for data entrance 4.3. Scope and major project risks
and worksheet modelling.
The assessment of correlation between risk factors is Since the project is the decoration of a bank ofce, the
as important as the identication of risks and is more usage of some special decorative materials is unavoid-
important than deciding on probability distributions of able. These special materials might be related to
risk elements. For this reason, any risk model should electrical or mechanical services, or related to internal
consist of the correlation coefcients, if correlation or external nishes according to the content of the
exists. Otherwise, the simulation results would not be architectural design. This is a risk for the contractor
realistic. from both cost and duration point of views because the
location of the construction site is far from the main
manufacturers, which exist in the western industrialized
4. Case study regions.
The second important risk creating characteristic of
4.1. Purpose the project is that the possible material changes
requested by the contractor after the approval of the
The purpose of this case study is to give an example to contract is not permitted. This is due to the image
the application of JRAP, to show how it works and to sensitivity of the architects of the bank, i.e. a standard
prove its validity. For achieving these goals and for the image style has been determined for the bank and all
sake of comprehensiveness, a small and real completed ofces have to be constructed according to this standard
construction project at which one of the authors all over the country. This situation creates an inexible
involved throughout the whole process has been chosen. environment for the contractor.
ARTICLE IN PRESS
A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254 1249

Next, the contract is an admeasurement type with 4.5. JRAP application


xed unit price, which can be considered as a risky
contract strategy from the contractors point of view. The rst task undertaken in application of JRAP on
The main reason of this is that the payment is at the end this project is determining the critical risks of the project
of each month after the measurement of the completed because the rst step of JRAP is the identication of
parts but the promoter does not compensate cost risks that are effective on critical activities explored
escalation, although there is high ination in the country during the critical path analysis (refer to Fig. 1). The
and interest rates are very high. Furthermore, transport- critical risks of the project are determined as: defective
ing cost is not paid to the contractor. The states bill of design, design changes, subcontractors default, uctua-
quantities and the banks own unit prices for special tion in labor productivity, delay in resolving disputes,
activities are used in measuring payment certicate difculties/delays in availability of materials, equipment
values. and labor, inadequate quality of work and need for
In case of late completion of the project, 0.2% of correction, promoter delays (unable to get approvals,
tender price is cut off as a liquidated damage for each lack of payment, etc.), and changes in quantity/scope of
day and this issue has been mentioned strictly in work [13,18].
contract documents. All of these oblige the contractor Three different computer package programs namely
to complete the project as early as possible before the MS Project, MS Excel and Crystal Ball have been used
project deadline, which is committed within the con- during this JRAP application. Before producing the
tract, because of the time value of money and the spreadsheet risk model, activity-risk factor matrix has
reputation of the company. been formed. Table 2 presents activity-risk factor matrix
Fortunately, weather conditions are not very effec- of the bank decoration project. Afterwards, the remain-
tive on the construction activities because most of them ing steps of JRAP, which are assigning probability
will be carried out in a closed environment; at the distributions and maximumminimum durations, and
ground and base oors of a multi-storey building. modelling and simulating have been carried out
Besides, soil condition is not a risk factor for the same subsequently. The statistical distributions assigned to
reason. risks and the correlation coefcients between them are
Although the construction site is at a region that has a given in Tables 3 and 4, respectively. Experience and
high human-resource potential, working quality is not engineering judgment have been utilized for setting up
high. The abundance of this resource means that there this data.
are no human-resource allocation and levelling pro- All the data gathered and processed up to here have
blems during scheduling. In other words, the activities been utilized in setting the spreadsheet risk model so
are mainly material driven, not labor driven. that it has become possible to perform MCS on the
produced model by the risk analysis software, Crystal
4.4. Schedule characteristics Ball. Table 5 shows the main spreadsheet model
developed by the spreadsheet program (MS Excel) for
The project start date was 30th November 1999 and the current case study. Tables 24 contain and provide
the completion date was 25th January 2000 in the the supportive data to Table 5. For instance, the cells
contract. The completion date has been determined by just near the means row in Table 3 are the assumption
negotiation between the promoter and the contractor cells as it is called in the program and here they
without preparing any deterministic schedule! represent the probability distributions assigned to the
In this context, rst, deterministic schedule of the critical risks. The cells at the last column and the cell at
project is developed using MS Project planning soft- the bottom of the late nish time column of Table 5 are
ware. Likely durations of the activities (refer to Table 5) called forecast cells and represent the resultant values
are determined whether judgmentally or by examining that vary with respect to the relevant assumption cells.
previous similar projects. Experience has also made it After running preferences and correlation coefcients
easier to construct the network logic and activity had been introduced into the risk analysis model,
interrelationships. Finally, the deterministic plan has simulation was conducted. The report produced by
shown that the likely project completion date was 12th Crystal Ball at the end of MCS mainly consists of
February 2000, which was 17 days after the contractual information about the assumption cells and forecast
completion date. This shows that even the deadline cells. Indeed, desired and necessary answers mostly exist
determined without risk analysis is a later date than the among the parts related to forecast cells in the
contractual completion date. It should be noted that simulation report.
JRAP will also provide the opportunity of comparing The spreadsheet model in Table 5 has two kinds of
this deterministic deadline with the other stochastic forecast cells: total project duration and critical activity
deadline values and show whether this deterministic query cells. The cell at the bottom of the late nish time
value is optimum or not. column gives the total project duration and it is related
1250
Table 2
Activity-risk factor matrix

Activity Risk no. 1 2 3 4 5 6 7 8 9 Total (%)


number
Activity name Defective Design Subcontractors Fluctuation in Delay in Promoter delays Difculties/ Inadequate Changes in
design (%) changes (%) default (%) labour resolving disputes (unable to get delays in quality of work quantity/scope of
productivity (%) (%) approvals, lack of availability of and need for work (%)
payment, etc.) materials, correction (%)
(%) equipment and
labour (%)

1 Tender
2 Sanction 70 30 100
3 Site delivery 70 30 100

A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254


4 Order materials 20 80 100
5 Procure materials 20 80 100
6 Remove existing old materials 70 30 100
7 Detail measurement; by aluminum 40 40 20 100
subcontractor
8 Order and procure aluminum 80 20 100
9 Manufacture aluminum joineries 10 10 20 10 10 20 20 100
10 Approval of weight records of 80 20 100

ARTICLE IN PRESS
aluminum joineries
11 Detail measurement; by glazier 40 40 20 100
12 Order and procure joinery glasses 80 20 100
13 Install electrical tting 20 10 10 30 20 10 100
14 Install suspended ceiling 10 10 20 10 20 20 10 100
15 Install HVAC, sanitary and 20 10 10 30 20 10 100
mechanical tting
16 Level slab cover sub-layer 60 40 100
17 Cover slab 10 30 40 10 10 100
18 Paint interior walls and columns 10 40 20 20 10 100
19 Cover WC walls and slab 10 40 30 10 10 100
20 Install aluminum joineries 20 30 20 30 100
21 Install joinery glasses 30 20 20 30 100
22 Install security alarm 30 20 20 30 100
23 Reinforcement and framework; 30 30 40 100
cash room walls
24 Approval and carriage of cash 20% 20 30 30 100
room door
25 Approval of reinforcement and 20 80 100
framework
26 Pour concrete 60 40 100
27 Remove frameworks 60 40 100
28 Cure concrete 60 40 100
29 Install cash room door 40 20 30 10 100
30 Paint walls and cover slab of cash 40 60 100
room
31 Delivery of money machine 100 100
32 Install money machine 40 60 100
33 Finish exterior works 10 10 30 40 10 100
34 Cover mechanical and electrical 30 30 30 10 100
units
35 Temporary commissioning 40 60 100
36 Approval of extra project duration 40 60 100
37 Approval of temporary 40 60 100
commissioning
Table 3
Probability distributions assigned to the risks

Risks: 1 2 3 4 5 6 7 8 9

Defective Design Subcontractors Fluctuation in Delay in Promoter delays Difculties/ Inadequate Changes in
design changes default labour resolving (unable to get delays in quality of work quantity/scope
productivity disputes approvals, lack availability of and need for of work
of payment, etc.) materials, correction

A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254


equipment and
labour

Distribution Type Triangle Lognormal Triangle Triangle Triangle Lognormal Lognormal Triangle Triangle
Mean 0.46 0.39 0.37 0.40 0.37 0.44 0.44 0.42 0.41

ARTICLE IN PRESS
Table 4
Correlation coefcients assigned to the risks

Risks 1 2 3 4 5 6 7 8 9

Defective Design Subcontractors Fluctuation in Delay in resolving Promoter delays Difculties/delays Inadequate Changes in
design changes default labour disputes (unable to get in availability of quality of work quantity/scope of
productivity approvals, lack of materials, and need for work
payment, etc.) equipment and correction
labour

1 1.0
2 0.6 1.0
3 0.0 0.0 1.0
4 0.0 0.0 0.0 1.0
5 0.3 0.3 0.0 0.0 1.0
6 0.1 0.2 0.0 0.0 0.1 1.0
7 0.0 0.3 0.0 0.0 0.0 0.0 1.0
8 0.0 0.0 0.3 0.0 0.1 0.0 0.0 1.0
9 0.2 0.1 0.0 0.0 0.0 0.0 0.1 0.0 1.0

1251
1252
Table 5
Spreadsheet risk model of the project

Time schedule risk analysis

Activity Activity name Predecessor and Lag Minimum Likely duration Maximum Simulated Early start Early nish Late start Late nish Total oat 0 critical
number relationship (days) duration (days) (days) duration (days) duration (days) time time time time (days) activity
1 non-critical
activity

1 Tender 0 0 0 0 0 0 0 0 0
2 Sanction 1 FS 2 2 4 3.3 0 3.3 0 3.3 0 0
3 Site delivery 2 FS 2 1 1 2 1.6 5.3 6.9 5.3 6.9 0 0
4 Order materialsa 2 FS 1 1 1 1 3.3 4.3 44.9 45.9 41.7 1

A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254


5 Procure materials 4 FS 10 15 40 27.8 4.3 32.1 47.2 75 42.9 1
6 Remove existing old materials 3 FS 2 3 4 3.1 6.9 10 6.9 10 0 0
7 Detail measurement; by aluminum 6 FS 1 1 2 1.7 10 11.7 10 11.7 0 0
subcontractor
8 Order and procure aluminum 7 FS 15 20 45 32.7 11.7 44.3 11.7 44.3 0 0
9 Manufacture aluminum joineries 8 FS 15 20 30 24.2 44.3 68.6 44.3 68.6 0 0
10 Approval of weight records of 9 FS 1 1 1 1 68.6 69.6 68.6 69.6 0 0

ARTICLE IN PRESS
aluminum joineries
11 Detail measurement; by glazier 10 FS 1 1 2 1.7 69.6 71.3 69.6 71.3 0 0
12 Order and procure joinery glasses 11 FS 10 15 30 21.8 71.3 93.1 71.3 93.1 0 0
13 Install electrical tting 6 FS 2 3 5 3.7 10 13.7 61.9 65.6 52 1
14 Install suspended ceiling 13 FS 3 4 10 7.3 13.7 21 65.6 73 52 1
15 Install HVAC, sanitary and 6 FS 4 5 8 6.3 10 16.3 66.7 73 56.7 1
mechanical tting
16 Level slab cover sub-layer 14,15 FS 1 2 3 2 21 23 73 75 52 1
17 Cover slab 5,16 FS 1 2 4 2.6 32.1 34.7 75 77.6 42.9 1
18 Paint interior walls and columns 17 FS 3 3 4 10 6.6 37.7 44.3 80.6 87.2 42.9 1
19 Cover WC walls and slab 5,15 FS 1 2 3 2.1 32.1 34.1 85.2 87.2 53.1 1
20 Install aluminum joineries 10,18,19 FS 3 4 8 5.9 69.6 75.5 87.2 93.1 17.6 1
21 Install joinery glasses 12,20 FS 2 3 6 4.7 93.1 97.7 93.1 97.7 0 0
22 Install security alarm 21 FS 1 2 3 2.2 97.7 99.9 97.7 99.9 0 0
23 Reinforcement and framework; 6 FS 2 2 4 3.1 10.0 13.1 75.2 78.3 65.3 1
cash room walls
24 Approval and carriage of cash room 4 FS 2 2 4 3.3 4.3 7.5 92.1 95.3 87.8 1
door
25 Approval of reinforcement and 23 FS 1 1 1 1.0 13.1 14.1 78.3 79.3 65.3 1
framework
26 Pour concrete 25 FS 1 1 1 1.0 14.1 15.1 79.3 80.3 65.3 1
27 Remove frameworks 26 FS 3 1 1 1 1.0 18.1 19.1 83.3 84.3 65.3 1
28 Cure concrete 27 FS 7 4 4 4 4.0 26.1 30.1 91.3 95.3 65.3 1
29 Install cash room door 24,28 FS 1 2 3 2.4 30.1 32.5 95.3 97.7 65.3 1
30 Paint walls and cover slab of cash 29 FS 1 2 3 2.2 32.5 34.7 97.7 99.9 65.3 1
room
31 Delivery of money machine 4 FS 20 30 60 43.5 4.3 47.8 45.9 89.4 41.7 1
32 Install money machine 31 FS 3 3 7 5.3 47.8 53.1 89.4 94.7 41.7 1
33 Finish exterior works 32,5 FS 3 4 7 5.2 53.1 58.3 94.7 99.9 41.7 1
34 Cover mechanical and electrical 15,5 FS 3 4 6 4.8 32.1 36.9 95.1 99.9 63.1 1
units
35 Temporary commissioning 22,33,34,30 FS 1 1 2 1.7 99.9 101.6 99.9 101.6 0.0 0
36 Approval of extra project duration 35 FS 1 1 2 1.5 101.6 103.1 101.6 103.1 0.0 0
37 Approval of temporary 36 FS 1 1 2 1.5 103.1 104.7 103.1 104.7 0.0 0
commissioning
ARTICLE IN PRESS
A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254 1253

Table 6 considered as a different approach to the analysis stage


Probable durations in percentiles and critical activities with 100% of risk management systems. Judgmental risk analysis
certainty
process is comprised of a number of steps as shown in
Forecast: total project duration Critical activities (with Fig. 1. The methodology is mainly based on MCS and
100% certainty) an equation that is proposed in the preceding sections.
This equation (Eq. (1)) enables the planner to observe
Percentile (%) Days Activity no.
the variation in activity durations during MCS. These
0 97.5 2 simulated values regarding the activity durations are
10 101.1 3 then utilized in the spreadsheet risk model through
20 102.6 6 arithmetic formulas that are produced according to the
30 104.0 7
logical relationships between the activities of the time
40 105.5 8
50 106.9 9 schedule network.
60 108.4 10 The reason for the proposed risk analysis method to
70 110.1 11 be qualied as judgmental is that the lack of historical
80 112.1 12 data related to the activities of the time schedule
90 114.6 21
network does not interfere with performing risk analysis
100 124.8 22
35 on the network, i.e. engineering judgment, experience
36 and intuition of the planner have all been utilized
37 through JRAP. Obviously, such an analysis strategy
would create additional risks due to the subjective data
used. Nevertheless, the pessimistic character of the
to the other varying cells with the formula within the proposed activity duration equation (Eq. (1)) and
frame of the activity network logic. Moreover, Eq. (1) is skewness in probability distributions assigned to critical
utilized in the simulated duration column. On the other risks compensate this undesired situation.
hand, the remaining forecast cells (the cells at the last The other objective of the present research was to
column) show how often each activity becomes critical illustrate the application of JRAP using a construction
so that it can be decided on which activities managerial project data. For this, JRAP was applied on a bank
effort should be focused and necessary precautions decoration project using the computer package pro-
should be taken in advance. grams, which are MS Project, MS Excel and Crystal
Ball. The results of the case study have shown that
4.6. Discussion of the results JRAP has been capable of answering the questions
such as:
Table 6 shows the summary of the results of the
simulation performed with 10,000 trials. It consists of
In how many days and with how much probability it
the project duration frequency values and the critical is possible to complete the project?
activities with 100% certainty. For instance, the project
Which activities are the most critical activities?
can be completed in 110.1 days with 70% probability
Which risk elements are more effective on project
according to these results. If at least this extra duration?
information had existed prior to the sanction, project
overrun would not have occurred. In other words, the The answers to such questions are obviously useful to
risk percentiles of the project duration would have make sound decisions prior to the contracting. As in the
helped the parties agree on a more suitable and realistic case study, the project completion duration specied in
contractual deadline. Unfortunately, not carrying out the contract, which is 57 days, came out to be only a big
deterministic and stochastic network analysis of the mistake because the results of JRAP has shown that the
project prior to the sanction resulted in late completion total project duration is 114.6 days with 90% and 124.8
of the current project. That is, the project was completed days with 100% probability. The commissioning docu-
in 122 days, i.e. 65 days after the project deadline written ments of the project have already supported this result
in the contract documents. because the construction has been completed in exactly
122 days, i.e. 65 days after the negotiated contract
deadline.
5. Conclusion As a general concluding remark, JRAP stands as a
practical schedule risk analysis methodology in the
The aim of this paper was to propose a time schedule overall risk management framework and it also con-
risk analysis methodology that is applicable on con- tributes to the dynamism of the risk management system
struction projects. This methodology, which is named as through its stochastic characteristics. However, it is
Judgmental Risk Analysis Process (JRAP), can be open to development through its application over more
ARTICLE IN PRESS
1254 A. Oztas- , O. Okmen / Building and Environment 40 (2005) 12441254

complex construction projects of longer durations from of Construction Engineering and Management 2000;126(4):
different categories. Furthermore, the methodology can 28592.
[9] Fente J, Schexnayder C, Knutson K. Dening probablity
be modied and converted into a more data (past
distribution function for construction simulation. ASCE Journal
record)-dependent characteristic by adaptation of mod- of Construction Engineering and Management 2000;126(3):
ern techniques like genetic algorithms, articial neural 23441.
networks and expert systems. [10] Grifs FH, Farr JV. Construction planning for engineers.
Singapore: McGraw-Hill; 2000.
[11] Illumoka AA. A tolerance analysis approach to network
References scheduling for engineering project management. International
Journal of Production Research 1987;25(4):53147.
[1] Edwards L. Practical risk management in the construction [12] Chapman CB. A risk engineering approach to project risk
industry. London: Thomas Telford; 1995. management. International Journal of Project Management
[2] Flanagan R, Norman G. Risk management and construction. 1990;8(1).
Cambridge: Backwell Scientic; 1993. [13] Dawood N. Estimating project and activity duration: a risk
[3] Pilcher R. Project cost control in construction. London: Collins; management approach using network analysis. Construction
1985. Management and Economics 1998;16:418.
[4] Isidore LJ, Back WE. Multiple analysis for probabilistic cost and [14] Ranasinghe M. Qualication and management of uncertainty in
schedule integration. ASCE Journal of Construction Engineering activity duration networks. Construction Managemant & Eco-
and Management 2002;128(3):2119. nomics 1994;12(1):1529.
[5] Barraza GA, Back WE, Mata F. Probabilistic monitoring of [15] Okmen O. Risk analysis and management of construction projects
project performance using SS-curves. ASCE Journal of Con- tendered under design-build (turnkey) contract system. M.Sc.
struction Engineering and Management 2000;126(2):1428. Thesis. Gaziantep: University of Gaziantep, 2002.
[6] Chehayeb NN, AbouRizk SM. Simulation-based scheduling with [16] Kartam NA. Risk and its management in the Kuwaiti construc-
continuous activity relationships. ASCE Journal of Construction tion industry: a contractors perspective. International Journal of
Engineering and Management 1998;124(2):10715. Project Management 2001;19(4):32535.
[7] Senior BA, Halpin DW. Simplied simulation system for [17] Oztas- A, Okmen O. Risk analysis in xed-price design-build
construction projects. ASCE Journal of Construction Engineering construction projects. Building and Environment 2004;39:22937.
and Management 1998;124(1):7281. [18] Gursel AP. Risk perception and trends of Turkish construction
[8] Maio C, Schexnayder C, Knutson K, Weber S. Probablity companies. M.S. Thesis. Ankara: Middle East Technical Uni-
distribution functions for construction simulation. ASCE Journal versity, 1998.

Potrebbero piacerti anche