Protocol
Protocol Number : VAL-IQ-E-0164/P Revision : A
Title : PCBA Depenalization Maestro 2M No. of Pages : 1 of 20
Revision History
This document describes the Installation Qualification Protocol for the PCBA
Depenalization Maestro 2M.
GENERAL INFORMATION
Not Applicable X
Hybrid Equipment N/A
The intended use of this document is to provide the Installation Qualification Protocol
for PCBA Depenalization Maestro 2M Main Plant Batam.
PCBA Depenalization Maestro 2M is stand- alone and located at fix location and is
not mobile.
Engineer Fathur
Director of Sivakumar
Engineering Thanupillai
Director of Sivakumar
Operational Thanupillai
Spacelabs Supplyier
Sophie Yang
Chain Engineer
INTRODUCTION / PURPOSE
The purpose of this Installation Qualification (IQ) protocol is to verify and ensure
that the PCBA Depenalization Maestro 2M is installed in accordance with OSIE
criteria and specifications. This equipment was designed and developed by Cab
Produkttechnik GmbH & Co KG Germany. This document also defines the
qualification requirements and the acceptance criteria required to ensure that the
PCBA Separator MAESTRO 2M is installed properly. This work will be
accomplished by verifying the proper installation of the PCBA Depenalization
Maestro 2M appropriately documenting the results.
SCOPE
The scope of this IQ protocol is limited to the PCBA Depenalization Maestro 2M
which is located at Back End Manual Insert 3.
DEFINITIONS
Term Definition
Establishing by objective evidence that all key aspects of the process equipment and
Installation
ancillary system installation adhere to the manufacturers approved specifications and
Qualification (IQ)
that the recommendations of the supplier of the equipment are suitably considered.
Master Validation A document that defines responsibilities and outlines the methods involved in the
Plan (MVP) qualification and validation of a specific process or group of processes.
Operational Establishing by objective evidence process control limits and action levels which result in
Qualification (OQ) product that meets all predetermined requirements.
Performance Establishing by objective evidence that the process, under anticipated conditions,
Qualification (PQ) consistently produces a product which meets all predetermined requirements.
Establishing by objective evidence that a process consistently products a result or
Process Validation
product meeting its predetermined requirements.
A document stating how a validation will be conducted, including test parameters,
Process Validation
product characteristics, manufacturing equipment, and decision points on what
Protocol
constitutes acceptable test results.
Confirmation by examination and provision of objective evidence that the specified
Verification
requirements have been fulfilled.
Decription Specification
Dimention H x D x W 330 X 620 X 195 mm
Separating Length Up to 300 mm
PCBA Thickness 0.8 ~ 3.2 mm
Separating Principle Circular Blades
Maximum cut thickness 0.8 mm
RESPONSIBILITY
The following matrix details the responsibilities for the Installation Qualification of
the PCBA Depenalization Maestro 2M.
Engineering/ Process/Test
Quality Assurance
Production
Task
REFERENCES
The following regulatory, guidance, documents and standard operating
procedures (SOPs) will be required for the protocol.
Document or SOP
Document
Number
ENVIRONMENT REQUIREMENT
The environmental requirements for this machine to operate as reference to
Temperature and Humidity Control procedure WI-MP05-87 as listed below:
Result
Environment Requirement Actual Result Pass Initial/Date
/Fail
Temperature
10 to 35 C
(Operation)
Humidity 10 to 85 % RH
Comments:
Comments:
Signature below (Verified by:) indicates data entered is accurate and complete.
Verified by: Date:
Comments:
Comments:
a) With equipment electrically isolated from main supply, inspect electrical components i.e. security and condition of base units & cabling.
Acceptance Criteria
Pass / Fail or
Test Requirements Actual Condition Initial Date
N/A
Note: Power loss testing is targeted at verifying the proper response of individual components and subsystems to an unexpected loss of power, such as during
a storm or equivalent event for the intent of power loss testing, is to demonstrate the equipment returns to operation in a manner that is consistent with the
operating requirements of the system, including appropriate equipment/system alarms and messages
Comments:
Comments:
Pass /
Step Test Requirements Actual Condition (Details) Initial Date
Fail
Is PM Schedule established?
1 Planned Preventative Maintenance Schedule established. Yes:______ / No:_______
PM schedule and report attached in Appendix:______________
All special ESD control requirements have been Is it special ESD control has been established?
4
established. Yes:______ / No:_______
Verify the instrument chassis is connected to an electrical Is it the machine connected to ground?
5
protective earth ground. Yes:______ / No:_______
Comments:
Step Instruction Expected Result Actual Result Pass / Fail Initial DatE
Switch OFF 220 10 Volt AC for PCBA Showing electric power lamp Is it electricity power lamp indicator OFF?
3
Depanelization Maestro 2M. indicator red colour is light OFF Yes:______ / No:_______
During machine continue run suddenly a power source of electric switched OFF
Comments:
Signature below (Verified by:) indicates data entered is accurate and complete
DEVIATIONS
List deviation forms issued in execution of this protocol.
Deviation
Description Appendix Initials Date
No.
Signature below (Verified by:) indicates data entered is accurate and complete.
Verified by: Date:
ACCEPTANCE CRITERIA
IQ Acceptance Criteria:
Approval of IQ protocol.
APPENDICES
List all supporting documentation used during the execution of this qualification.
Protocol
Appendix No of
Description Section Date Added
No Pages
Reference
Deviation Investigation Result and initial Impact Assessment (Attach supporting evidence as required)
Minor - Major -
A Minor issue with no significant potential to impact the A Major issue that has significant potential to impact
result of the Qualification. subsequent steps of the Qualification.
Qualification may proceed prior to resolution of Deviation Qualification not to proceed until Deviation is resolved
Corrective action taken (Attach supporting evidence as required)
Deviation Resolved (Y/N) ____ Adverse impact on Validity of Validation (Y/N) ____
Approvers
Title Name Signature Date