DAILY CONSTRUCTION PROGRESS REPORT

PIPELINE
AFE # 0 Project Name: Header Project Date:
Origin (U/S) Station No: 0 + 00 Contractor: MPG Pipeline Contractor M
Terminus (D/S) Station No: 214 + 59 Contractor PM: John-Ryan House
Total Project Length (LF): 21459 Contractor Supt.: Geoff Fontenot Total number of hour
Contractor/Crew Work
Total HDD Length (LF): 0 Contractor Welding FM Dennis Miller (Actual Hours)
Total Kicker Gas (LF): 0 Welding System: 0
WORKING CONDITIONS
Weather Conditions AM Storms Temperature: 7 A.M. 68 F 12 P.M. 77 F 5 P.M.
ROW Conditions: Muddy Wind: 7 A.M. SE @ 5 mph 12 P.M. SE @ 12 mph 5 P.M.
Did ABNORMAL conditions exist that adversely affected construction p Yes No (If YES, Exp
Any Crews affected by adverse weather, ROW or other working conditi Yes No (If YES, Exp
CONSTRUCTION PROGRESS
Contractor Mainline Pipeline Station # Feet REMARKS
Construction Operation From To Today (LF) Future Use
Base Lay
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
0 + 00 0 + 00 0
HDD
Pilot Hole Completion 0 + 00 0 + 00 0
Ream Pass Completion 0 + 00 0 + 00 0
Pipe Pull Back 0 + 00 0 + 00 0
Rock & Kicker Gas
Rock Ditch 0 + 00 0 + 00 0
Rock Shield 0 + 00 0 + 00 0
Kicker Gas Line Installed 0 + 00 0 + 00 0
Contractor Specialty
Construction Operation Station # Quantity Size
Pig Trap Testing 0 + 00 0
Pig Trap Repair 0 + 00 0
Pig Trap Installation 0 + 00 0
Meter Assembly Installation 0 + 00 0
Discharge Spool Installation 0 + 00 0
Above Ground Valve 0 + 00 0
WELDING DATA CONTRACTOR MANPOWER/EQUIP
Welds (ML) Today 0 X-rayed (ML) Today 0 Foreman 0 Dozers
Tie-Ins Today 0 Tie-Ins X-rayed Today 0 Straw 0 Excavators
Fab. Welds Today 0 Fab. Welds X-rayed Today 0 Welders 0 Skidsteers
Repairs Today 0 Repairs X-rayed Today 0 Welder Helpers 0 Bending Machines
Temporary Welds 0 Temporary Welds X-rayed 0 Laborers 0 Welding Rigs
Cut-Outs Today 0 TOTAL X-RAYED > 0 Operators 0 Pickup Trucks
TOTAL TODAY > 0 TOTAL REJECT WELDS > 0 Truck Drivers 0 1-Ton (>)Trucks
TOTAL WELDS TO DATE > 0 TOTAL X-RAY TO DATE > 0 X-ray Tech 0 Marooka/Compressors
COMPANY MANPOWER
Construction Management Jordan Hunter Safety Inspection 0 Environmental Inspection
Construction Inspection John Dougherty Survey Personnel Thomas Brooks ROW Personnel

Chief Inspector: Johnny Doughterty


Work Date:

Signature: _______________________________________________
Report No.:
Date: 5/20/2014
TION PROGRESS REPORT
PIPELINE
5/20/2014
Contractor Manpower

Total number of hours


Contractor/Crew Worked 0
(Actual Hours)

NG CONDITIONS
82 F
SE @ 15 mph
(If YES, Explain Below in Remarks)
(If YES, Explain Below in Remarks)
UCTION PROGRESS
REMARKS

CONTRACTOR MANPOWER/EQUIPMENT
0
0
0
0
0
0
0
0
ANY MANPOWER
0
0

5/20/2014

14