Sei sulla pagina 1di 4

TENDER DOCUMENT

VOLUME III: SPECIFICATIONS


CONSTRUCTION OF BENANAIN AND APPURTENANCES
(LOT NO. 1)
MALAKA WEIR IRRIGATION SUB-PROJECT
(JBIC ODA Loan IP-499)

PART I
GENERAL SPECIFICATIONS

PART II
TECHNICAL SPECIFICATIONS
Section 1 River Diversion and Dewatering Works
Section 2 Earthworks
Section 3 Concrete Works
Section 4 Masonry Works
Section 5 Hydro-mechanical Works
Section 6 Metal Works
Section 7 Electrical Works
Section 8 Road Works
Section 9 Headrace Canal Works
Section 10 Building and Associated Works
Section 11 Miscellaneous Works

TENDER DOCUMENT
VOLUME III: SPECIFICATIONS
CONSTRUCTION OF BENANAIN AND APPURTENANCES
(LOT NO. 1)
MALAKA WEIR IRRIGATION SUB-PROJECT
(JBIC ODA Loan IP-499)

PART I: GENERAL SPECIFICATIONS

CONTENTS
Page
1. PROJECT SITE............................................................................................................... GS-1
2. BENANAIN WEIR AND APPURTENANCES................................................................... GS-1
2.1 Scope of Works ...................................................................................................... GS-1
2.2 Construction Period ................................................................................................ GS-2
2.3 Technical Features ................................................................................................. GS-2
3. PROJECT SITE .............................................................................................................. GS-4
3.1 Access .................................................................................................................... GS-4
3.2 Climate ................................................................................................................... GS-4
3.3 Hydrology ............................................................................................................... GS-5
3.4 Geology .................................................................................................................. GS-5
4. DESIGN AND DRAWINGS MODIFICATIONS ................................................................ GS-6
4.1 Contract Drawings .................................................................................................. GS-6
4.2 Drawing to be Furnished by the Contractor ............................................................ GS-6
4.3 Right to Change Design and Drawings .................................................................. GS-7
5. PROJECT MANAGEMENT AND OPERATION .............................................................. GS-7
5.1 Construction Plan and Schedule ........................................................................... GS-7
5.2 Reports and Meetings ........................................................................................... GS-8
5.3 Audits by the Engineer .......................................................................................... GS-9
5.4 Works by Other Contractor ................................................................................... GS-9
6. SECURITY AND SAFETY CONTROL ............................................................................ GS-9
6.1 General ................................................................................................................. GS-9
6.2 Security Control System ....................................................................................... GS-9
6.3 Sanitary Arrangement ........................................................................................... GS-10
6.4 Explosives and Blasting ......................................................................................... GS-10
6.5 Fire Prevention ...................................................................................................... GS-10
6.6 Lighting .................................................................................................................. GS-10
6.7 Sign ........................................................................................................................ GS-11
6.8 Safety Instruction ................................................................................................... GS-11
7. TEMPORARY WORKS ................................................................................................... GS-11
7.1 Temporary Access Road ........................................................................................ GS-12
7.2 Temporary Fencing ................................................................................................ GS-12
7.3 Contractors Staff Quarters and Labor Camps ...................................................... GS-12
7.4 Contractors Offices, Stores, Workshop and Motor Pool ........................................ GS-12
7.5 Employer/ Engineers Office .................................................................................. GS-13
7.6 Water Supply System ........................................................................................... GS-13
7.7 Electric Power Supply System ............................................................................... GS-13
7.8 Telecommunication System ................................................................................... GS-13
7.9 First-Aid Medical Facilities ..................................................................................... GS-14
7.10 Removal of Temporary Building and Facilities ....................................................... GS-14
8. LABORATORY AND TESTING ....................................................................................... GS-14
9. QUARRY AND BORROW AREAS .................................................................................. GS-14
9.1 Quarry for Concrete and Asphalt Aggregate ........................................................ GS-15
9.2 Borrow Areas and Rock for Other Construction Materials ...................................... GS-15
9.3 Restoration of Borrow Area and Quarry Sites ........................................................ GS-15
10. MATERIAL AND PLANT TO BE FURNISHED BY CONTRACTOR ............................... GS-16
10.1 General ................................................................................................................. GS-16
10.2 Construction Plant .................................................................................................. GS-16
10.3 Substituted Materials ............................................................................................. GS-16
10.4 Inspection of Plant and Materials ........................................................................... GS-16
10.5 Program and Notice of Transportation ................................................................... GS-17
10.6 Standards and Specifications ................................................................................. GS-17
10.7 Packing .................................................................................................................. GS-17
10.8 Loading Limits on Roads ....................................................................................... GS-18
11. OTHER ............................................................................................................................ GS-18
11.1 Setting Out of All Reference Points ....................................................................... GS-18
11.2 Assistance to Engineers Staff ................................................................................ GS-18
11.3 Works to be Kept Clean of Water ......................................................................... GS-18
11.4 Transportation Facilities ......................................................................................... GS-19
11.5 Additional Site Investigation and Survey ............................................................... GS-19
11.6 Payment ................................................................................................................. GS-19

APPENDIX-1 LIST OF TESTING APPARATUS


A. Soil Testing Apparatus
B. Aggregate Testing Apparatus
C. Concrete Testing