03 MAR, HUGO NORTH LIFT1-SHAFT2 BATCH PLANT PROJECT

2017 CONSTRUCTION MANAGEMENT SERVICE


PLAN FOR TENDERING SUBCONTRACTORS


___________________________________________________________________________

PCDP LLC

Project Name: HUGO NORTH LIFT1-SHAFT2 BATCH PLANT 4

PLAN FOR TENDERING SUBCONTRACTORS


Objective

Plan for tendering subcontractors priority is dividing the construction scope of work into packages and
choosing the subcontractor whose proposal complied with the design and technical specification.

1. Tendering packages:

Tender Tender Material for Tender


Package
Work announce opening Schedule G, evaluation
No.
ment date date M accept date report date
Package Earthwork (Top soil removal, Excavation, Soil
2017.03.07 2017.03.10 2017.03.17 2017.03.11
1 removal, Compacting of original ground, Backfilling,)
Package Concrete work (Blinding concrete, Plant foundation,
2017.03.07 2017.03.10 2017.03.17 2017.03.11
2 Equipment foundation, Main concrete, Floor concrete)
Construction work (Steel work, Wall sandwich panel,
Package
Roof sandwich panel, Accessories, Flashings 2017.03.07 2017.03.10 2017.03.17 2017.03.11
3
Window, Door,)
Plumbing and Heating work (Sewer and water
systems piping work in ground, Water pipework,
Package Sewage pipework, Drainage pipework, Water system
2017.03.08 2017.03.10 2017.03.17 2017.03.11
4 valves, Fire services, Sanitary fixtures, Equipment
and Services of Piping systems, Control system for
piping system, temporary facilities)
Air ventilation work (Ducting work, Air conditioning
work, equipment work such as Fan, Cooling and
Package
heating coil, Humidifier, Damper, Valves, strainer and 2017.03.08 2017.03.10 2017.03.17 2017.03.11
5
other accessories, Main control system for
mechanical)
Electric Services (Main switchboards, Distribution
boards and panels, Earthing system, Lighting system,
Package Lightning protection system, all cabling work with
2017.03.08 2017.03.10 2017.03.17 2017.03.11
6 ladder, conduit, tray., etc., Outlets and Connectors,
Telecommunication system, Fire detecting system,
CCTV, Alarm, temporary facilities)


Premium Concrete LLC; Hugo north lift1shaft2, Batch plant#4 PCDP LLC
Page 1 of 1
Plan for Tendering subcontractors 2017.03.04