KUMAR MARBLE UDYOG

PROGRAMM SHEDULE FOR CC-94

SCHEDULE OF WORK Remark


S.No. Activity Station Date of start Date of Finish
1 Brick of at C.C. Level 34 N/A
52 25/01/2017 15/03/2017
62 1/2/2017 15/03/2017
2 Internal Plaster 34 5/2/2017 28/02/2017
52 1/3/2017 15/03/2017
62 1/3/2017 15/03/2017

P.C.C. under Flooring at


3 C.C. Level 34 5/2/2017 28/02/2017
52 1/3/2017 15/03/2017
62 1/3/2017 15/03/2017

Granite Stone Flooring


4 at C.C. Level 34 15/02/2017 15/03/2017
52 5/3/2017 31/03/2017
62 5/3/2017 31/03/2017

Hardner/VDF Flooring
5 at C.C. Level 34 20/02/2017 28/02/2017
52 5/3/2017 15/03/2017
62 5/3/2017 15/03/2017
Kota Stone Flooring at
6 C.C. Level 34 20/02/2017 28/02/2017
52 5/3/2017 15/03/2017
62 5/3/2017 15/03/2017

Granite Stone Flooring


at Stair Case (From C.C.
Level to Plateform
7 Level) 34 1/3/2017 15/03/2017
52 15/03/2017 31/03/2017
62 15/03/2017 31/03/2017

Vitrified Tiles Flooring


8 at C.C. Level 34 1/3/2017 15/03/2017
52 15/03/2017 31/03/2017
62 15/03/2017 31/03/2017
Fixing of Fire/Metal
9 Doors 34 1/3/2017 31/03/2017
52 1/3/2017 31/03/2017
62 1/3/2017 31/03/2017
Fixing of Aluminium
10 Door & window 34 1/3/2017 31/03/2017
52 1/3/2017 31/03/2017
62 1/3/2017 31/03/2017
11 A.C.P. Cladding 34 1/3/2017 15/04/2017
52 1/3/2017 15/04/2017
62 1/3/2017 15/04/2017
Internal Painting With
12 Wall Putty 34 15/02/2017 31/03/2017
52 10/3/2017 10/4/2017
62 10/3/2017 10/4/2017
Fixing of S.S. Railing at
13 Stair Case 34 1/3/2017 15/03/2017
52 15/03/2017 31/03/2017
62 15/03/2017 31/03/2017
14 Rain Water Pipe Fixing 34 10/2/2017 15/03/2017
52 10/2/2017 15/03/2017
62 10/2/2017 15/03/2017

15 sanitary/Plumbing Work 34 10/2/2017 31/03/2017


52 10/2/2017 31/03/2017
62 10/2/2017 31/03/2017

16 Extenal Water Supply 34 10/2/2017 31/03/2017


52 10/2/2017 31/03/2017
62 10/2/2017 31/03/2017

It can be started
P.C.C. under Flooring at only after fixing
17 Plateform Level 34 the Rail&PEB
52 do
62 do
Kota Stone Flooring at
18 Plateform Level 34 do
52 do
62 do
Fixing of S.S. Railing at
19 Plateform Level 34 do
52 do
62 do

Entry Staircase Flooring


From Ground Level to
20 C.C. Level 34 do
52 do
62 do

21 External Development
(A) Laying of Hume Pipe 34 15/03/2017 15/04/2017
52 15/03/2017 15/04/2017
62 15/03/2017 15/04/2017

(B) Manhole/Harvesting pit 34 15/03/2017 15/04/2017


52 15/03/2017 15/04/2017
62 15/03/2017 15/04/2017
Road Work 34 15/03/2017 15/04/2017
52 15/03/2017 15/04/2017
62 15/03/2017 15/04/2017
22 Toilet Block

(A) Internal Plumbing Work 34 20/03/2017 15/04/2017


52 20/03/2017 15/04/2017
62 20/03/2017 15/04/2017
(B) Water Proofing 34 20/03/2017 15/04/2017
52 20/03/2017 15/04/2017
62 20/03/2017 15/04/2017
P.C.C. Under Floor 34 20/03/2017 15/04/2017
52 20/03/2017 15/04/2017
62 20/03/2017 15/04/2017
(D) Wall/Floor Tiles 34 20/03/2017 15/04/2017
52 20/03/2017 15/04/2017
62 20/03/2017 15/04/2017
(E) Sanitary Work Fixing 34 20/03/2017 15/04/2017
52 20/03/2017 15/04/2017
62 20/03/2017 15/04/2017

Handing over dates are given by YFC


FOR Stn at 34 1st & 5th span 1/31/2017
FOR Stn at 34 2nd, 3rd & 4th span 2/10/2017
FOR Stn at 52 1st & 2nd span 2/15/2017
FOR Stn at 52 3rd span 2/22/2017
FOR Stn at 52 4th & 5th span 2/28/2017
FOR Stn at 62 1st span 2/5/2017
For Stn at 62 2nd & 3rd Span 2/15/2017
For Stn at 62 4th & 5th span 2/28/2017

Note:- The above Activities Date will change accordingly as per clearance of site.
Schdule for Finishing Work for Station 34, 52 & 62
SCHEDULE OF WORK Station Noida Sec. 34 Station Noida Sec. 52 Station Noida Sec. 62 Remark
S.No. Activity Days Start Finish Days Start Finish Days Start Finish
1 Brick of at C.C. Level N/A 49 25-Jan-17 15-Mar-17 42 1-Feb-17 15-Mar-17
2 Internal Plaster 23 5-Feb-17 28-Feb-17 14 1-Mar-17 15-Mar-17 14 1-Mar-17 15-Mar-17
3 P.C.C. under Flooring at C.C. Level 23 5-Feb-17 28-Feb-17 14 1-Mar-17 15-Mar-17 14 1-Mar-17 15-Mar-17
4 Granite Stone Flooring at C.C. Level 28 15-Feb-17 15-Mar-17 26 5-Mar-17 31-Mar-17 26 5-Mar-17 31-Mar-17
5 Hardner/VDF Flooring at C.C. Level 8 20-Feb-17 28-Feb-17 10 5-Mar-17 15-Mar-17 10 5-Mar-17 15-Mar-17
6 Kota Stone Flooring at C.C. Level 8 20-Feb-17 28-Feb-17 10 5-Mar-17 15-Mar-17 10 5-Mar-17 15-Mar-17
Granite Stone Flooring at Stair Case (From C.C. Level
7 to Plateform Level) 14 1-Mar-17 15-Mar-17 16 15-Mar-17 31-Mar-17 16 15-Mar-17 31-Mar-17
8 Vitrified Tiles Flooring at C.C. Level 14 1-Mar-17 15-Mar-17 16 15-Mar-17 31-Mar-17 16 15-Mar-17 31-Mar-17
9 Fixing of Fire/Metal Doors 30 1-Mar-17 31-Mar-17 30 1-Mar-17 31-Mar-17 30 1-Mar-17 31-Mar-17
10 Fixing of Aluminium Door & window 30 1-Mar-17 31-Mar-17 30 1-Mar-17 31-Mar-17 30 1-Mar-17 31-Mar-17
11 A.C.P. Cladding 45 1-Mar-17 15-Apr-17 45 1-Mar-17 15-Apr-17 45 1-Mar-17 15-Apr-17
12 Internal Painting With Wall Putty 44 15-Feb-17 31-Mar-17 31 10-Mar-17 10-Apr-17 31 10-Mar-17 10-Apr-17
13 Fixing of S.S. Railing at Stair Case 14 1-Mar-17 15-Mar-17 16 15-Mar-17 31-Mar-17 16 15-Mar-17 31-Mar-17
14 Rain Water Pipe Fixing 33 10-Feb-17 15-Mar-17 33 10-Feb-17 15-Mar-17 33 10-Feb-17 15-Mar-17
15 sanitary/Plumbing Work 49 10-Feb-17 31-Mar-17 49 10-Feb-17 31-Mar-17 49 10-Feb-17 31-Mar-17
16 Extenal Water Supply 49 10-Feb-17 31-Mar-17 49 10-Feb-17 31-Mar-17 49 10-Feb-17 31-Mar-17
17 P.C.C. under Flooring at Plateform Level
18 Kota Stone Flooring at Plateform Level
It can be started only after
19 Fixing of S.S. Railing at Plateform Level
fixing the Rail&PEB
Entry Staircase Flooring From Ground Level to C.C.
20 Level
21 External Development
(A) Laying of Hume Pipe 31 15-Mar-17 15-Apr-17 31 15-Mar-17 15-Apr-17 31 15-Mar-17 15-Apr-17
(B) Manhole/Harvesting pit 31 15-Mar-17 15-Apr-17 31 15-Mar-17 15-Apr-17 31 15-Mar-17 15-Apr-17
(C) Road Work 31 15-Mar-17 15-Apr-17 31 15-Mar-17 15-Apr-17 31 15-Mar-17 15-Apr-17
22 Toilet Block
(A) Internal Plumbing Work 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17
(B) Water Proofing 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17
(C) P.C.C. Under Floor 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17
(D) Wall/Floor Tiles 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17
(E) Sanitary Work Fixing 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17 26 20-Mar-17 15-Apr-17
Schdule for Finishing Work for Station 34, 52 & 62
SCHEDULE OF WORK Station Noida Sec. 34
S.No. Activity Days Start Finish
1 Brick of at C.C. Level N/A
2 Internal Plaster 23 5-Feb-17 28-Feb-17
3 P.C.C. under Flooring at C.C. Level 23 5-Feb-17 28-Feb-17
4 Granite Stone Flooring at C.C. Level 28 15-Feb-17 15-Mar-17
5 Hardner/VDF Flooring at C.C. Level 8 20-Feb-17 28-Feb-17
6 Kota Stone Flooring at C.C. Level 8 20-Feb-17 28-Feb-17
Granite Stone Flooring at Stair Case (From C.C. Level
7 to Plateform Level) 14 1-Mar-17 15-Mar-17
8 Vitrified Tiles Flooring at C.C. Level 14 1-Mar-17 15-Mar-17
9 Fixing of Fire/Metal Doors 30 1-Mar-17 31-Mar-17
10 Fixing of Aluminium Door & window 30 1-Mar-17 31-Mar-17
11 A.C.P. Cladding 45 1-Mar-17 15-Apr-17
12 Internal Painting With Wall Putty 44 15-Feb-17 31-Mar-17
13 Fixing of S.S. Railing at Stair Case 14 1-Mar-17 15-Mar-17
14 Rain Water Pipe Fixing 33 10-Feb-17 15-Mar-17
15 sanitary/Plumbing Work 49 10-Feb-17 31-Mar-17
16 Extenal Water Supply 49 10-Feb-17 31-Mar-17
17 P.C.C. under Flooring at Plateform Level
18 Kota Stone Flooring at Plateform Level
19 Fixing of S.S. Railing at Plateform Level
Entry Staircase Flooring From Ground Level to C.C.
20 Level
21 External Development
(A) Laying of Hume Pipe 31 15-Mar-17 15-Apr-17
(B) Manhole/Harvesting pit 31 15-Mar-17 15-Apr-17
(C) Road Work 31 15-Mar-17 15-Apr-17
22 Toilet Block
(A) Internal Plumbing Work 26 20-Mar-17 15-Apr-17
(B) Water Proofing 26 20-Mar-17 15-Apr-17
(C) P.C.C. Under Floor 26 20-Mar-17 15-Apr-17
(D) Wall/Floor Tiles 26 20-Mar-17 15-Apr-17
(E) Sanitary Work Fixing 26 20-Mar-17 15-Apr-17