Sei sulla pagina 1di 7

Special Report

Modularization of chemical plants: An overview

T
Abstract Stefan Lier[1] and Marcus SATISH DIWAKAR
he discussion in this paper out- Grnewald, Ruhr-Universitt Bochum PRASHANT YEDE
lines modularization approach of Germany, compared the econo- SAGAR KHATAV
for standard chemical plants. mics of a modular chemical plant with TATA Consulting Engineers Ltd.
Each aspect is elaborated in general those of a traditional large-scale plant 4th Floor, Tower-B, 247 Park
starting from conceptualization till by investigating investment and ope- L B S Marg, Vikhroli
implementation including transporta- ration costs, combined with revenues, Mumbai 400 083
tion. These aspects are applicable to using a net present value analysis. sndiwakar@tce.co.in
any plant (chemical or industrial) with They concluded that: Modular plants pkyede@tce.co.in
standard parameters. consist of modules that autonomously skhatav@tce.co.in
operate parts of the plant. These mo-
Introduction dules are technically and organization- locally available construction men
Modularization was developed and ally limited areas of the plant that ful- & materials. When such in situ con-
adopted in the offshore structures to fill defined tasks. Starting with these struction is not feasible for any rea-
facilitate large volume of fabrication modules, companies can create capa- son, modularization can be adopted
work to be carried out in shop in a con- city either by equaling up modules from to reduce the in situ work. This can be
trolled environment. Later on, the need general structures or by numbering up achieved by using pre-fabricated and
was also felt for modular construction equipment. In the analysis carried out pre-assembled modules at locations
of other structure (Onshore) and is fast by them, the economics of a modular away from the site. Such pre-fabri-
catching up in many countries, espe- chemical plant are compared with those cated and pre-assembled modules are
cially developed countries. of a traditional large-scale plant by in- then transported either by road or ship
vestigating the net present value. The depending upon the logistics require-
This discussion in this paper is limi- modular plant presents a more efficient ments and erected at site.
ted to modularization approach for concept for fast growing products or
standard chemical plants, especially products with volatile demands. This Modules are generally a set of pre-
in developing countries like India. In is because the market impact during assembled equipments and ancillaries
India, modularization approach is not operation is more important than the such as piping, cable trays, cables, in-
very popular due to availability of large preceding influence of the investment. sulation etc. Modules may vary in size
& cheap labour force; high transpor- In those cases, the effects of flexibility depending on design, installation, inter-
tation cost due to varied geographical surpass the effects of scale. facing and transportation constraints.
parameters across the country; lesser
use of water transport etc. But in com- The conventional approach is Modularization facilitates re-us-
ing times, modularization approach in situ construction of facilities in- ability, as module can be developed,
will gain wider acceptance. volved in any chemical plant, using tested, modified and reused multiple
times reducing re-development time.
Also, the modularized plant can be re-
located from one location to another by
dismantling.

Key factors influencing modulariza-


tion
Modularization can be achieved by
taking a stick-build design and divide
into number of modules. Modulariza-
tion is dependent on a detailed assess-
ment of the key project parameters to
determine the feasibility and the extent
of modularization.

Chemical Weekly September 15, 2015 205


Special Report

The key factors[3] are generally The maximum size and weight will Modularization decisions or chan-
labour, site conditions, site access, vary from project to project, depend- ges made during later stages of project
schedule and safety. Refer Table 1 ing on the geographical features, avail- can result in considerable rework and
for key factors influencing modula- ability of equipments for erection and may increase overall cost & time to a
rization. dimensional & weight limitations of the great extent. A key consideration is the
transportation routes. overall plant layout or plot plan, which
It may not be possible to go should be designed to meet the extent
for full modularization every time. Modules shall be generally fabri- of modularization considering all the
Sometimes part modularization may cated at locations where labour rates points mentioned in Table 1. Also the
be desirable considering the project and productivity skill index are suitable interfacing between modules, erection
parameters and in some cases it may as compared to main construction site. sequencing, operation and maintenance
be possible to go for full modulariza- However, higher level of modulariza- requirements shall play an important
tion. At times it may not be advisable tion will not necessarily translate into role in making these decisions.
to opt for modularization. However, cost savings as these will be offset to
total modularization cannot eliminate some extent against the cost of addi- Modular design also facilitates par-
in situ construction activities such as tional steelwork, shipping and specia- allel activities, i.e. several modules can
site preparation, site enabling works, list land transportation. be fabricated & built in parallel and can
excavation, all civil works including get assembled with higher speed. This
foundations, erection of large fabri- Implementation helps in maintaining a smaller team at
cated steel vessels and final interfac- Constructability aspects for modu- site; overall reduction in time and man-
ing of the modules themselves. lar projects need to be reviewed well in power cost. It can reduce WIP and as-
advance as they impact decisions taken sociated financial costs.
The key factor in modularization is during feasibility and conceptual stages
the module size that can be fabricated, considering overall process, operation Modularization can be classified in
shipped, transported and erected at site. and maintenance requirements. three categories.
Table 1 First generation[2] modularization
Key factors influencing modularization such as pipe racks, platforms etc.;
Second generation[2] modulariza-
Factor Influencers tion such as customizing equip-
Labour Shortage of labour at the project site, or in the vicinity ment and other ancillaries mounted
due to any reason on structural steel skids; and
Required competencies of available labour force Third generation[2] modulariza-
Labour and productivity rate for site and shops; the pro- tion such as standardizing and not
ductivity rate of skilled labour in shop is higher than field customizing of the modules mount-
labour by 25-40%. ed with equipments and ancillaries.
Site conditions Impact of climatic conditions, e.g. cyclonic conditions, Considering strength and profes-
extreme cold, wind loading, rainfall, sandstorm, snow sional experience of any engineering
loads etc. consultant in India, it is feasible to go
Constraints on plot size and area for first and second generation modu-
Seismic zones, e.g. high seismic zones will require more larization as it involves primarily cus-
ductile structure with great amount of detailing of joints, tomization, i.e. detail engineering
large member sizes for lateral load resisting members etc. based on the available equipment and
Site access Available routes, infrastructure at site schematic plant layout either provided
by technology supplier or by customer.
Schedule Constraints or requirements of the project schedule,
which necessitate the implementation of modular ap-
For third generation modulariza-
proach or the schedule benefit that would be achieved us-
tion, it is necessary to have own, patent-
ing modular approach.
ed process technology or expertise of
Safety Stringent safety requirements of conventional construc- process licensor or technology supplier
tion compared to modularization work. capabilities of providing technologies

206 Chemical Weekly September 15, 2015


Special Report

for standardization of plant modules liquidated damages, guarantees, ef- cisions taken during conceptual stage
depending upon various capacities and ficiency demands, defects liability on overall equipment layout, equip-
volume. However, engineering consul- period etc. ment configuration, piping layouts etc.
tant may collaborate on long-term basis Knowledge of shipping and inland may prove critical at later date.
with technology supplier to acquire re- transportation constraints such as
quired expertise, if he doesnt possess maximum dimension of shipping Engineers or designers involved
one. consignment, maximum weight for should possess multi-disciplinary capa-
the individual module, etc. bility to provide a design that envelopes
First- and second-generation modu- Preliminary 3D model of the tech- domain expertise in process, structural,
larization nology structure showing major mechanical, piping, instrumentation &
The following inputs will be re- equipments & piping, if available. electrical design, procurement etc.
quired to carry out detail engineering of
various modules to be provided. These Conceptualisation Process engineering
inputs may help during conceptualiza- The conceptualisation stage is con- Process engineer shall have tho-
tion as well. sidered to be very significant in any rough knowledge of process involved,
plant design. The key elements of con- equipment layout, type of equipments
The geographical details of site loca- ceptualization are Process Optimiza- that are required and available in mar-
tion, seismic zones, wind/cyclone/ tion and Energy Optimization. ket, various process alternatives, etc.
hurricane factor, soil bearing capa- Sometimes it is recommended to de-
city, groundwater table, soil resis- The following factors largely affect sign & purchase smaller components
tivity, prevalent wind direction and modular design: of equipments to facilitate modular
basic wind speed, rainfall, tempera- Process engineering; design, instead of designing equipment
ture, humidity, snow loads, etc. Equipment selection; that will not fit in the pre-defined module.
Layout of the proposed plant Equipment layout and elevations;
Technological structure general ar- Piping and instrumentation; Optimizing key process stages dur-
rangement layouts showing tenta- Size of modules; ing the design phase leads to improve-
tive location of equipments. Interfacing of modules at site; and ments in plant operation and thereby
P & IDs for process and utilities. Availability of cranes in and around improve operating and maintenance
Customers design standards. the site. cost. Process equipment may be more
Hazardous area classification. efficiently utilized by applying proprie-
Data on industrial waste and waste- Modularization has an influence on tary designs, converting batch ope-
water treatment etc. equipment selection and configuration rations to continuous and reducing
Customers philosophy on sourcing for designing a compact plant layout. residence times from hours to minutes,
spares. Modular designs normally have an depending upon the requirements.
Details on the new electric power optimized footprint compared to con-
distribution system, viz. system ventionally erected plants. The major- Process dynamics and control
voltage levels, loads, standby power ity of the process equipments can be strategies can be optimized by care-
supply etc. modularized and located in such a way fully matching the operating ranges of
Master schedule for implementation to lower capital costs and thereby im- instrumentation and hydraulics to the
of the plant, with scheduled deli- proving plant efficiency. Modular de- equipment.
veries for directly sourced plant and sign takes advantage of both horizontal
equipment. and vertical layouts to locate equipment Energy optimization
Drawings, data sheets and founda- in a minimum space. A well-designed Modular systems are best suited
tion details for the equipment being module can help to minimize space re- for energy optimization because of the
sourced directly by customer. quirements, reduce piping and cable closed circuit of the process. Process loop
Module sizes intended depending lengths. or circuit lengths are shorter in modules,
upon the transportation, construc- which increases the overall efficiency of
tability, operation and maintenance Process engineer shall be brought the plant due to elimination of the long
requirements. on board during conceptualization lengths of piping. Shorter lengths of pip-
Procedures for letter of intent, stage to extract maximum cost benefits ing helps in minimizing heat loss and
terms of payment, letter of credit, out of modularization. The strategic de- condensation in the pipelines.

Chemical Weekly September 15, 2015 207


Special Report

In the current industrial scenario of Size limitation of the module The module size shall be selected as
alternative fuels, a properly designed Each module shall be sized, based a self-standing structure for avoid-
modular system using innovative pro- on the maximum transportable ing imbalance during shipment.
cess techniques can reduce CAPEX & length, breadth and height in con-
OPEX, thereby reducing utility loads sultation with process collaborator Analysis of the modules
through process & energy optimization. or technology supplier. The entire structure as a single mo-
Planning of each module shall cater, dule will be analyzed with PIN
Civil & Structural engineering as far as possible, for self-contain- connection at module interface.
The design of modular fabrication ment of equipment and associated This analysis is intended to arrive at
shall have following Civil and Struc- piping works. overall structural integrity once the
tural design requirements: Cutting section plane for the modules. plant is commissioned.
The plant is sub-divided in to vari-
ous modules as explained earlier.
Start Each module will be analysed as
independent structure during erec-
Integrated in place
tion. The erection scheme needs to
structural analysis
be discussed with the contractor or
Incorporate in
combined model can be decided by engineering con-
sultant.
Individual module in
place analysis T he modules during shipment
Permanent Temporary bracing
and transportation may have to
No be arranged in a manner different
Reinforce Acceptable
structure result than its intended position. Such
Yes
changes require separate set of
analysis. A typical flow chart indi-
Lifting analysis cating the different stages that
are involved in modular design is
Permanent Temporary bracing
given in Figure 1.
No Acceptable
Reinforce
structure result
Structural design
Yes
The structural members shall be
designed to account for the forces
acting during handling, lifting and
Up righting analysis
transportation.
Permanent Temporary bracing
All structures shall be analyzed and
No
Acceptable
qualified for such loads other than
Reinforce
structure result the normal design loads like equip-
ment load, seismic load, normal
Yes
wind load etc.
Additional strengthening may be
Transportation analysis
provided to resist critical forces or
Permanent Temporary bracing
to avoid any deformity during trans-
Reinforce No Acceptable portation
structure result Identifying the module sections and
lifting points.
Yes
Structure to be stable and safe in
assembled module as well as in the
End
final constructed form.
All site joints to be designed as bolt-
ed joints and all shop joints shall be
Fig. 1: Typical flow chart of modular design welded joints.

208 Chemical Weekly September 15, 2015


Special Report

Encasement and/or fire-proof con-


creting.

Mechanical design
Mechanical designs shall follow
the relevant standards, codes of prac-
tices such as ASTM, ASME, TEMA,
API, IBR and BIS etc. Flexibility shall
be one of the key components of me-
chanical design. Bolted joints shall be
preferred over welded joints. Interfac-
ing for the pipes between two modules
Permanent or temporary reinforce- tions, checking/testing of weld con- shall be with spool pipe.
ment techniques shall be adopted nections & materials.
for members likely to be over- Completion of painting and touch Sizing of equipment, pipelines for
stressed during lifting and trans- up painting before release of the process & utility and selection & loca-
portation. Connections shall be de- modules for shipment. tion of valves & instruments shall be
signed for maximum capacity of the Additional temporary bracing a part of detailed engineering as per
member and checked for stresses members to cater to stresses aris- the Project/Plant Design Manual, P &
arising during lifting and transpor- ing from transportation as well as IDs, Data Sheets and relevant codes
tation analysis. Set Down and Load out Beam and standards. Equipment layout shall
analysis. feature adequate space for O & M,
Material of construction Completion of the tag numbers to aesthetics and ergonomics, headroom
Rolled steel members, Wide/paral- all the modules, spare connecting clearances and adherence to the local/
lel flange sections and plates from members and match marking. international safety norms such as
approved Indian or foreign suppli- Demonstrate rigidity of the mo- OSHA.
ers shall be used as structural mem- dule by lifting it to a small height
bers. duly slung to the lifting hook. Preferably all the equipment, com-
Special corrosion protection allow- Prior to shipment, check mark- ponents, instruments, valves, pipes,
ance or paints to be used to take care ing of centre of gravity (COG) on gaskets, fasteners, special tools, con-
of transport and handling. modules for lifting operations. sumable and capital spares etc., should
Weight control report shall be pre- be sourced from indigenous reputed and
Additional loading during handling pared before despatch of modules to ISO certified manufacturers/sources.
Tensile and compressive stresses site. Provision for easy and fast mounting
arising from lifting & transportation of imported items, if any, with minimal
analysis of the modules. Civil and structural works required deployment of men & machinery shall
Rolling, pitching, heave & yaw at site feature in the module.
effects of the ship on modules. Foundations.
Adequate packing or temporary Installation of the modules as per Process pumps that are to be posi-
supports (wooden/steel bracings/ the erection sequencing procedure. tioned on the modules shall be aligned
lacings, shock absorbing materials, Grouting. with suction and delivery pipes con-
etc.) need to provided for the equip- Interconnection of the modules with nected. Pumps that are to be installed
ments and other ancillaries mounted prefabricated structural members outside the modules shall be shipped
on modules during transportation. either by bolting or welding. separately with the pump and its drive
Generally for lifting and transpor- Installation of the prefabricated ope- aligned but short of dowel pins. This
tation analysis, API RP-2A & GL rating platforms after erection of arrangement shall also be applicable to
Noble Denton guidelines may be stand-alone equipment. other rotary equipment.
followed. Installation of prefabricated pipe
supports, minor equipment struc- Access, i.e. walkway/inter-connect-
Checks required prior to shipment tures outside of the module. ing platforms, to the tall towers such

Completeness of the end connec- Touch up painting. as reactors, stacks, refiners, distillers,

Chemical Weekly September 15, 2015 209


Special Report

strippers etc., shall be featured from re- system packages shall be sourced Instrumentation and control system
lated modules. either locally or abroad as these re- design and documentation shall be car-
quire vendors assistance for en- ried out by using internationally proven
On the fabricated module, posi- abling, commissioning and fine tun- software such as INTOOLS.
tioning of the equipment shall be com- ing as per process requirements. As
pleted first. Placement of pipelines part of the module, the following I&C system design shall follow the
shall be after alignment of majority of shall be housed: relevant code, standards and practices
the equipment. Prior to erection of the Field instruments, control valves, such as NFPA, UL/CSA, IEC, EN and
fabricated pipes onto the modules, the junction boxes and power supply ISA.
inside surfaces shall undergo thorough distribution boards.
mechanical cleaning using a combina- Cabling between the field instru- Electrical design
tion of sponge balls and compressed air ments, junction boxes and power Electrical design shall comply with
or other acceptable practices. Where distribution boards, which are con- the relevant codes, standards and prac-
flange joints are involved, such joints tained within the module. tices such as NFPA, ANSI/IEEE, UL/
should be at the interface of the mo- Cable trays and conduits for the ca- CSA, IEC and EN.
dules or with flanged pipe spool. bling within the module.
All impulse tubing, fittings supports Modules shall house the local power
Welded pipe joints requiring stress required for transmitters. distribution board, control consoles,
relieving shall be completed to the Local control panel, pneumatic fire alarm panel etc. Cable carrier sys-
maximum extent on the modules. Metal control panels and hydraulic power tem consisting of cable trays, tray sup-
ring type flanged joints may be used for pack required for equipment con- ports shall be included along with the
high pressure lines at the point of sepa- tained within the modules. pipe rack. The module shall include
rating out from the module to eliminate poles, towers, & other supports for
onsite weld joints with stress relieving. The multi-core cables and cable mounting of lighting fixtures complete
Pipe isometrics running outside the trays from junction boxes to DCS/PLC with wiring. However, the fixtures will
modules shall be fabricated in single system in the control room shall be be fitted on site. The protection enclo-
or multiple loops and housed in corre- laid at site. Analyzer shelter along with sure within the modules shall be speci-
sponding modules for shipment. analyzer panels & sample conditioning fied and provided as per hazardous area
panels installed in it shall be transport- classification for that module.
Each module shall be identified with ed as one module. The sampling lines
a distinct number. Pipeline designation and cabling for same shall be carried For cables emanating & terminating
number and tag number for equipment, out at site. within the module, cable pulling and
valves, instruments etc. shall be pre-
fixed with the module identification
number. Tags, punch marks or perma-
nent inscriptions shall be used for iden-
tification. Match marks are preferred
for pipe loops for onsite assembly.

Equipment, pipes and valves requir-


ing thermal insulation shall be wrapped
in the approved insulation material with
aluminium sheet cladding. Configured
spare insulation shall be supplied loose
for onsite fixing at interface of the mo-
dules. Fireproofing, also, shall be pro-
vided where applicable.

Instrumentation design
All the control room mounted
equipment such as DCS/PLC/SCADA

210 Chemical Weekly September 15, 2015


Special Report

termination will be executed as a part of etc., and/or against injury, accident or plant and equipment installed on
the module. Cable pulling for the cables death of labour deployed on this job. the modules to ensure adequate lee
joining one module to another will be ways, head room clearances, clear
carried out on site. Safety norms for electrical equip- passage for movement of person-
ment shall be in conformity with the nel and materials handled by the
The main earth strip will be in- rules and regulations stipulated by the monorails, access for external crane
stalled on the cable tray and individual competent authorities of the country in hook, adequate space around the
equipment earth leads will be welded to which the plant is being installed and equipments for maintenance etc.
this main earth strip. All connections to operated. Layout and spacing of the cable car-
earth pits/earth electrodes will have to riers should facilitate safe and easy
be done at site. Special design considerations cable pulls. Light fittings shall be
The plant shall be modeled in 3D easily accessible for replacement of
The lightening protection for build- environment. The model shall initially lamps. Layout of the lights shall be
ing/structure/vessels, if required, shall show the following: spread to provide desired illumina-
be done at site. Structural steel supporting frame- tion lumens.
work for individual module.
Safety aspects Lifting points and guying points for Conclusion
Safety standards and codes as ap- the modules. Modular design and construction is
plicable to the industry and as required Structural steel columns, beams, most suited to almost all plants having
by the concerned local authorities shall stairways, walkways/leeways, floor standard parameters with less degree
be adhered to while designing the plant, gratings, hand railing, toe plates, of variability. It has brought significant
equipment, layouts and utility services. monorails etc. change in the nature of engineering ser-
Plant and equipment. vices that are being offered today espe-
The agency(s) appointed for fabrica- Pipelines, valves, and specialties. cially. In India, it may gain acceptance
tion of the modules shall be required to Cable trays. and momentum little slower as com-
submit their safety plans for approval, Monorails. pared to the developed countries, due to
prior to commencement of work. The Identify large/over-sized equipment availability of large labour. To remain
vendor shall indemnify the purchaser such as columns/reactors/vessels competitive in the international market
against charges/penalties on the vendor etc., which needs to be transported in the future, it is necessary for engineer-
for violation of safety norms resulting or shipped and erected separately at ing consultants in India to provide engi-
in damages to the equipment, machi- the plant site. neering services (in India and abroad)
nery, handling apparatus/equipment Emphasis shall be to spread the for Third Generation modular design
by either joint venture or
long term association with
technology suppliers (in-
ternational and domestic).

References
1. S. Lier. Net Present
Value Analysis of Modu-
lar Chemical Production
Plants, Chemical Engi-
neering & Technology,
05/2011.
2. IQPC Modular Con-
struction and Fabrication
2013 Conference.
3. Chemical Plant Design
and Construction, Rich-
ard Brookfield and Jere-
mey Cooke.

Chemical Weekly September 15, 2015 211

Potrebbero piacerti anche