International Journal of Civil Engineering and Technology (IJCIET)

Volume 8, Issue 1, January 2017, pp. 245256, Article ID: IJCIET_08_01_026


Available online at http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=1
ISSN Print: 0976-6308 and ISSN Online: 0976-6316
IAEME Publication

RELABILITY OF IMPLEMENTING PRIMAVERA P6 IN


FAST-TRACK PLANNING OF RESIDENTIAL
BUILDING
Jannu Saibabu
PG Student, Department of Civil Engineering,
K L University, Vaddeswaram, Andhra Pradesh, India

SS. Asadi
Associate Dean-Academics, Department of Civil Engineering,
K L University, Vaddeswaram, Andhra Pradesh, India

S.S. Bhanu Prakash


Assistant Professor, Department of Civil Engineering,
K L University, Vaddeswaram, Andhra Pradesh, India

ABSTRACT
Objectives: To understanding the process of project planning in primavera p6 by using project
calendar and develop the schedules. To control resources ex: - labour, non-labour, machines etc.
Methodology: Site visits of ongoing projects and understanding the various tasks, plans and
scheduling models, collection of project data, venture Planning and Scheduling by using Primavera
P6, interpretation and tabulation of Results, conclusion. Findings: Analysis of results in primavera
p6 observed that resources should be controlled are arranged to other activities of same project or
another project of same enterprise. Controlled the budgeted units to control the project cost.
Reliability of implementing primavera p6 it is more advantageous on ongoing parallel projects and
it shows the results accurately. From the analysis observed that project time is over run due to
following conventional method. Applications: This software is mainly used for getting more
accurate and reliable results occurring in planning and scheduling, resource planning labour, non-
labour, material etc, mainly in coding tenders, to start multiple projects at same time, requirement
of cash flows, labour, non-labour, and material for every month to start the project.
Key words: Fast-track planning, scheduling, resources, time, cost etc.
Cite this Article: Jannu Saibabu, SS. Asadi and S.S Bhanu Prakash, Relability of Implementing
Primavera P6 in Fast-Track Planning of Residential Building. International Journal of Civil
Engineering and Technology, 8(1), 2017, pp. 245256.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=1

1. INTRODUCTION
Fast-track arranging, when all is said in done can be portrayed as the capacity of selecting the project
structure. And also it can be described as the function of achieving the targets of a project by building up
the strategies, techniques, and projects. Main role of fast-track planning is to set the major milestones.

http://www.iaeme.com/IJCIET/index.asp 245 editor@iaeme.com


Jannu Saibabu, SS. Asadi and S.S Bhanu Prakash

What's more, the line directors trust that they can meet them. On the off chance that the line director can't
confer in light of the fact that the breakthroughs are seen as farfetched, the task administrator may need to
create choices, one of which might be to move the points of reference. Venture director is the way to
fruitful task arranging. Venture arranging ought to be precise, adaptable to handle one of kind exercises,
restrained through surveys and controls, and fit for having multifunctional inputs. The project time should
be minimize by using fast-tracking1. From the past research work carried by shorten duration raised by
fast-track construction can compare with traditional method2. Fuzzy project scheduling is used from past
20 years and also it is useful to for uncertainty and impression3.The research done in implementation of
constraint programming in production scheduling for precast plants4.Civil Engineering Standard Datas are
help full in Resource planning and scheduling5.

2. VENTURE PLANNING AND SCHEDULING BY USING PRIMAVERA P6


Visit was made to the site of residential project at Narsing (AARADHYA) in Hyderabad, their
construction planning is observed and data is collected from, data of conventional planning is collected. To
archive better than previous results must following fast-track planning process. In this company they are
following conventional planning. Plan area of AARADHYA was 50,000sft, G+5 Residential building.

2.1. Resource Planning


Planning of resources in primavera p6 can be done by using resource calendar and scheduling activity;
specifically, labour, non-labour, and material. Proper planning of resources are important key to success of
project. Analysis is done in primavera p6 it shows the results of labour, non-labour, material usage are
tabulated in tables.

2.1.1. Planning of Non-labour (Equipment)


Non-labour units are measured in terms of price per hour, price per day, reused between activities and
projects. For JCB Rs700/hr, for tipper Rs2000/day. From primavera p6 analysis of non-labour planning are
shown in Table 1. (budgeted vs actual units of non-labour)

Table 1 (Budgeted vs at completion units of Non- labour)


BUDGETED % OF ACTUAL REMAININ AT
RESOURCE UNITS COMPLETE UNITS G UNITS COMPLETION
ID D UNITS UNITS
JCB 1840 cum 100 1815 cum 0 1815 cum
Barbending 0 MT 100 66 MT 0 66 MT
machine
Tipper 1840 cum 100 1815 cum 0 1815 cum

2.1.2. Planning of labour (Man-Power)


Labour units are measured in terms of number of members. Labour resources are generally, reused
between activities and projects and are recorded in terms of number of members primavera p6 analysis of
manpower planning is shown in Table 2. (budgeted vs actual units of man-power)

http://www.iaeme.com/IJCIET/index.asp 246 editor@iaeme.com


Relability of Implementing Primavera P6 in Fast-Track Planning of Residential Building

Table 2 (Budgeted vs At completion units of labour)


Resource Id Budgeted % of Actual Remaining At
Units Completed Units Units Units Completion
(Num) (Num) (Num) Units
(Num)
Mason 2883 85.06 2245 394 2639
Men mazdoor 2883 84.93 2222 394 2616
Women mazdoor 2883 84.83 2205 394 2600
Plumber 496 100 487 0 487
Sanitary worker 152 100 152 0 152
Electrician 152 100 152 0 152
Carpenter skilled 1860 100 1710 0 1710
Carpenter un-skilled 931 100 863 0 863
Barbender skilled 756 100 340 0 340
Barbender un-skilled 378 100 216 0 216
Tiles work mason 1834 84.16 1522 286 1808
Tiles work mazdoor 1834 84.16 1522 286 1808
Painter skilled 63.22 1067 1067 620 1687
Masson skilled 507 100 499 0 499
Plant operator 507 100 503 0 503
Compressor operator 507 100 499 0 499
Pipe layers 1491 100 1472 0 1472
Mechanic 253 100 243 0 243
Electrician operator 233 100 230 0 230
Forman 253 100 249 0 249

2.1.3. Planning of Material


Materials are measured in terms of cubic meters, bags, metric tons, square feet. Once material resources
are used not reused in the project. Table 3. shows (budgeted vs actual units of material)

Table 3 (Budgeted vs At completion units of materials)


Units %
Budgeted complete Remaining At completion
Resource ID Actual units
units units units
(%)
Cement OPC 14617 bags 74.81 10763 bags 3623 bags 14386 bags
Steel 341 MT 100 341 MT 0 MT 341 MT
RMC M-15 344 cum 100 342 cum 0 cum 342 cum
RMC M-25 22904 cum 100 22904 cum 0 cum 22904 cum
4 solid block 361125 100 361200 num 0 num 361200 num
(400200100) num
6 solid block (400 92565 num 100 92500 num 0 num 92500 num
200150)
8 solid block 9255 num 100 92565 num 0 num 92565 num
(300200200)
12 solid block 9750 num 100 9750 num 0 num 9750 num
(400200200)
River sand 1685 cum 78.18 1297 cum 362 cum 1297 cum
Rock sand 66 cum 100 63 cum 0 cum 63 cum

http://www.iaeme.com/IJCIET/index.asp 247 editor@iaeme.com


Jannu Saibabu, SS. Asadi and S.S Bhanu Prakash

Units %
Budgeted complete Remaining At completion
Resource ID Actual units
units units units
(%)
Diesel 2500 lit 100 2375 lit 0 lit 2375 lit
UPVC main door 95 num 84 80 num 15 num 95 num
(10002100)
UPVC D1 (900*2100) 249 num 85.54 213 num 36 num 249 num
UPVC D2 (800*2100) 274 num 85.4 234 num 40 num 274 num
UPVC PD (800*2100) 5 num 84 4 num 1 num 5 num
UPVC SD 69 num 86.09 59 num 10 num 69 num
(2400*2400)
UPVC SD1 4 num 60 2 num 2 num 4 num
(1800*2400)
UPVC SD2 14 num 77.14 11 num 3 num 14 num
(1500*2400)
UPVC W1 272 num 85.59 233 num 39 num 272 num
(1200*1200)
UPVC W2 (900*1200) 20 num 84 17 num 3 num 20 num
UPVC W3 (750*1200) 10 num 84 8 num 2 num 10 num
UPVC V (600*600) 182 num 85.05 155 num 27 num 182 num
UPVC V1 (500*600) 5 num 84 4 num 1 num 5 num
UPVC KW 28 num 85.71 24 num 4 num 28 num
(1200*900)
UPVC KW1 (900*900) 67 num 83.28 56 num 11 num 67 num
Snow sem (25kg) 220 bags 0 0 bags 220 bags 220 bags
Distember (20kg) 58 bags 0 0 bags 58 bags 58 bags
Exrerior wall painting 83 bags 0 0 bags 83 bags 83 bags
(20kg)
interior wall primer 788 num 84.06 662 num 126 num 788 num
(20ltr)
interior wall putty 628 num 84.08 528 num 100 num 628 num
(20ltr)
towel bar handels 200 num 64 128 num 72 num 200 num
super round frame 500 num 64 320 num 180 num 500 num
grating (FH)
handle showers 200 num 64 128 num 72 num 200 num
overhead showers 200 num 64 128 num 72 num 200 num
cere half turn pillar 200 num 64 128 num 72 num 200 num
cock florar cp101
cera half turn pillar 100 num 64 64 num 36 num 64 num
cock ocean cc122lir
Hindware health faucet 100 num 64 64 num 36 num 64 num
Cera half turn 2 - way 100 num 64 64 num 36 num 64 num
bib cock floral cp113
Cera half pedestal only 100 num 64 64 num 36 num 64 num
1175
Tiles 2202 boxes 84.36 18551 boxes 3440 boxes 21991 boxes

3. INTERPRETATION AND TABULATION OF RESULTS


Project has been delayed due to improper planning and management in construction of residential building.
Table-4shows project planning and scheduling, this table shows planned dates of project planning vs actual

http://www.iaeme.com/IJCIET/index.asp 248 editor@iaeme.com


Relability of Implementing Primavera P6 in Fast-Track Planning of Residential Building

dates of project is running. This table very useful in successful in completion of project with in time. Any
delay it causes to delay of the project.

Table 4 Project planning (Planned dates vs Actual dates)


(*)BL (*)BL
Activity Activity Project Project Actual Actual Original
ID WBS Code Name Start Finish Start Finish Duration(d)
Project start 05-01- 05-01- 05-01-
A1000 FT-RB.1 date 2015 2015 2015 05-01-2015 0
Project finish 23-11- 23-11-
A1010 FT-RB.1 date 2016 2016 0
09-02- 25-02- 20-02-
A1020 FT-RB.2.1.1 stilt floor 2015 2015 2015 10-03-2015 20
18-01- 07-02- 21-01-
A1040 FT-RB.2.1.2 Stilit floor 2015 2015 2015 11-02-2015 20
25-02- 09-03- 10-03-
A1050 FT-RB.3.1.1 Stilit floor 2015 2015 2015 20-03-2015 10
09-02- 20-02- 20-02-
A1070 FT-RB.3.1.2 Stilit floor 2015 2015 2015 03-03-2015 10
09-03- 20-03- 30-05-
A1080 FT-RB.3.2.1 Stilit floor 2015 2015 2015 10-06-2015 10
21-02- 04-03- 30-04-
A1100 FT-RB.3.2.2 Stilit floor 2015 2015 2015 12-05-2015 10
FT- Excavation in 30-03- 17-04- 01-05-
A1110 RB.3.4.1.1 soft soil 2015 2015 2015 20-05-2015 15
FT- Excavation in 11-04- 23-04- 22-05-
A1120 RB.3.4.1.1 hard soil 2015 2015 2015 02-06-2015 10
FT- 23-04- 06-05- 03-06-
A1130 RB.3.4.1.2 footings 2015 2015 2015 13-06-2015 10
FT- Retaining wall 23-04- 25-04- 03-06-
A1140 RB.3.4.1.2 raft 2015 2015 2015 04-06-2015 2
FT- Flooring stilit 19-05- 25-05- 19-07-
A1150 RB.3.4.1.2 level 2015 2015 2015 24-07-2015 5
Flooring
FT- basement 13-05- 30-05- 13-07-
A1160 RB.3.4.1.2 level 2015 2015 2015 29-07-2015 15
FT- 29-04- 30-04- 29-06-
A1170 RB.3.4.1.2 Plinth beam 2015 2015 2015 29-06-2015 1
FT- Reinforcement 25-04- 20-05- 05-06-
A1180 RB.3.4.1.3 for footings 2015 2015 2015 27-06-2015 20
FT- Retaining wall 24-04- 30-04- 04-06-
A1190 RB.3.4.1.3 raft 2015 2015 2015 09-06-2015 5
FT- 29-04- 09-05- 08-06-
A1200 RB.3.4.1.3 Retaining wall 2015 2015 2015 16-06-2015 8
FT- 02-05- 06-05- 01-07-
A1210 RB.3.4.1.3 Plinth beam 2015 2015 2015 03-07-2015 3
columns
FT- uptostilit floor 02-05- 08-05- 01-07-
A1220 RB.3.4.1.3 slab 2015 2015 2015 06-07-2015 5
FT- 02-05- 26-05- 13-06-
A1230 RB.3.4.1.4 Footings 2015 2015 2015 06-07-2015 20
A1240 FT- RW raft 25-04- 04-05- 06-06- 13-06-2015 6

http://www.iaeme.com/IJCIET/index.asp 249 editor@iaeme.com


Jannu Saibabu, SS. Asadi and S.S Bhanu Prakash

(*)BL (*)BL
Activity Activity Project Project Actual Actual Original
ID WBS Code Name Start Finish Start Finish Duration(d)
RB.3.4.1.4 2015 2015 2015
FT- 02-05- 14-05- 15-06-
A1250 RB.3.4.1.4 Retaining wall 2015 2015 2015 25-06-2015 10
FT- 05-05- 11-05- 20-06-
A1260 RB.3.4.1.4 Plinth beam 2015 2015 2015 26-06-2015 5
FT- columns 05-05- 22-05- 21-06-
A1270 RB.3.4.1.4 uptostilit floor 2015 2015 2015 08-07-2015 15
FT- 06-05- 29-05- 18-06-
A1280 RB.3.4.1.5 Footings 2015 2015 2015 10-07-2015 20
FT- 27-04- 05-05- 10-06-
A1290 RB.3.4.1.5 RW raft 2015 2015 2015 16-06-2015 6
FT- 04-05- 15-05- 19-06-
A1300 RB.3.4.1.5 Retaining wall 2015 2015 2015 30-06-2015 10
FT- 07-05- 13-05- 25-06-
A1310 RB.3.4.1.5 Plinth beam 2015 2015 2015 30-06-2015 5
FT- columns 08-05- 26-05- 28-06-
A1320 RB.3.4.1.5 uptostilit floor 2015 2015 2015 15-07-2015 15
FT- stilt floor 15-05- 19-06- 30-06-
A1330 RB.3.4.1.5 beam & slab 2015 2015 2015 03-08-2015 30
FT- stilt floor 12-05- 16-06- 25-06-
A1340 RB.3.4.1.4 beam & slab 2015 2015 2015 29-07-2015 30
FT- Stilit floor 19-05- 11-06- 10-07-
A1350 RB.3.4.2.3.1 above 2015 2015 2015 10-08-2015 20
FT- 1st floor 04-06- 27-06- 11-08-
A1360 RB.3.4.2.3.1 above 2015 2015 2015 10-09-2015 20
FT- 2 nd floor 19-06- 13-07- 11-09-
A1370 RB.3.4.2.3.1 above 2015 2015 2015 10-10-2015 20
FT- 3 rd floor 04-07- 28-07- 12-10-
A1380 RB.3.4.2.3.1 above 2015 2015 2015 12-11-2015 20
FT- 4 th floor 21-07- 13-08- 13-11-
A1390 RB.3.4.2.3.1 above 2015 2015 2015 15-12-2015 20
FT- 5th floor 04-08- 28-08- 17-12-
A1400 RB.3.4.2.3.1 above 2015 2015 2015 11-01-2016 20
FT- 28-05- 20-06- 20-07-
A1410 RB.3.4.2.3.2 1st floor 2015 2015 2015 20-08-2015 20
FT- 13-06- 07-07- 20-08-
A1420 RB.3.4.2.3.2 2 nd floor 2015 2015 2015 21-09-2015 20
FT- 29-06- 22-07- 22-09-
A1430 RB.3.4.2.3.2 3 rd floor 2015 2015 2015 21-10-2015 20
FT- 14-07- 06-08- 22-10-
A1440 RB.3.4.2.3.2 4 th floor 2015 2015 2015 19-11-2015 20
FT- 31-07- 25-08- 20-11-
A1450 RB.3.4.2.3.2 5th floor 2015 2015 2015 21-12-2015 20
FT- Stilit floor 08-05- 12-06- 10-07-
A1460 RB.3.4.1.3 Beam & slab 2015 2015 2015 13-08-2015 30
FT- 12-08- 05-09- 22-12-
A1470 RB.3.4.2.3.2 Terrace 2015 2015 2015 23-01-2016 20
FT- 18-08- 20-08- 18-01-
A1480 RB.3.4.2.3.1 above terrace 2015 2015 2016 19-01-2016 2
FT- 12-08- 13-08- 25-01-
A1490 RB.3.4.2.3.2 above terrace 2015 2015 2016 25-01-2016 1

http://www.iaeme.com/IJCIET/index.asp 250 editor@iaeme.com


Relability of Implementing Primavera P6 in Fast-Track Planning of Residential Building

(*)BL (*)BL
Activity Activity Project Project Actual Actual Original
ID WBS Code Name Start Finish Start Finish Duration(d)
FT- 20-05- 12-06- 11-07-
A1500 RB.3.4.2.4.1 Stilit to 1st 2015 2015 2015 11-08-2015 20
FT- 06-06- 30-06- 12-08-
A1510 RB.3.4.2.4.1 1st to 2nd 2015 2015 2015 12-09-2015 20
FT- 20-06- 14-07- 14-09-
A1520 RB.3.4.2.4.1 2nd to 3rd 2015 2015 2015 15-10-2015 20
FT- 06-07- 29-07- 16-10-
A1530 RB.3.4.2.4.1 3rd to 4th 2015 2015 2015 17-11-2015 20
FT- 23-07- 17-08- 18-11-
A1540 RB.3.4.2.4.1 4th to 5 th 2015 2015 2015 18-12-2015 20
FT- 05-08- 29-08- 19-12-
A1550 RB.3.4.2.4.1 5th to terrace 2015 2015 2015 30-01-2016 20
FT- 19-08- 21-08- 01-02-
A1560 RB.3.4.2.4.1 above terrace 2015 2015 2016 04-02-2016 2
FT- 25-05- 17-06- 15-07-
A1570 RB.3.4.2.4.2 1st floor 2015 2015 2015 14-08-2015 20
FT- 10-06- 03-07- 17-08-
A1580 RB.3.4.2.4.2 2nd floor 2015 2015 2015 15-09-2015 20
FT- 25-06- 18-07- 16-09-
A1590 RB.3.4.2.4.2 3rd floor 2015 2015 2015 16-10-2015 20
FT- 10-07- 03-08- 17-10-
A1600 RB.3.4.2.4.2 4th floor 2015 2015 2015 14-11-2015 20
FT- 28-07- 21-08- 16-11-
A1610 RB.3.4.2.4.2 5 th floor 2015 2015 2015 21-12-2015 20
FT- 10-08- 12-08- 20-01-
A1620 RB.3.4.2.4.2 above terrace 2015 2015 2016 21-01-2016 2
FT- 21-05- 13-06- 11-07-
A1630 RB.3.4.2.5.1 Stilit to 1st 2015 2015 2015 11-08-2015 20
FT- 06-06- 30-06- 12-08-
A1640 RB.3.4.2.5.1 1st to 2nd 2015 2015 2015 11-09-2015 20
FT- 22-06- 15-07- 12-09-
A1650 RB.3.4.2.5.1 2nd to 3rd 2015 2015 2015 13-10-2015 20
FT- 07-07- 30-07- 14-10-
A1660 RB.3.4.2.5.1 3rd to 4th 2015 2015 2015 14-11-2015 20
FT- 24-07- 18-08- 16-11-
A1670 RB.3.4.2.5.1 4th to 5 th 2015 2015 2015 16-12-2015 20
FT- 06-08- 31-08- 17-12-
A1680 RB.3.4.2.5.1 5th to terrace 2015 2015 2015 19-01-2016 20
FT- 21-08- 24-08- 20-01-
A1690 RB.3.4.2.5.1 above terrace 2015 2015 2016 22-01-2016 2
FT- 01-06- 24-06- 25-07-
A1700 RB.3.4.2.5.2 1st floor 2015 2015 2015 25-08-2015 20
FT- 16-06- 09-07- 26-08-
A1710 RB.3.4.2.5.2 2nd floor 2015 2015 2015 26-09-2015 20
FT- 02-07- 25-07- 28-09-
A1720 RB.3.4.2.5.2 3rd floor 2015 2015 2015 28-10-2015 20
FT- 17-07- 10-08- 29-10-
A1730 RB.3.4.2.5.2 4th floor 2015 2015 2015 28-11-2015 20
FT- 01-08- 26-08- 30-11-
A1740 RB.3.4.2.5.2 5 th floor 2015 2015 2015 30-12-2015 20
A1750 FT- above terrace 14-08- 18-08- 02-01- 04-01-2016 2

http://www.iaeme.com/IJCIET/index.asp 251 editor@iaeme.com


Jannu Saibabu, SS. Asadi and S.S Bhanu Prakash

(*)BL (*)BL
Activity Activity Project Project Actual Actual Original
ID WBS Code Name Start Finish Start Finish Duration(d)
RB.3.4.2.5.2 2015 2015 2016
FT- 17-06- 16-07- 01-09-
A1760 RB.3.4.2.2 1st floor 2015 2015 2015 10-10-2015 25
FT- 02-07- 31-07- 12-10-
A1770 RB.3.4.2.2 2nd floor 2015 2015 2015 25-11-2015 25
FT- 18-07- 18-08- 20-11-
A1780 RB.3.4.2.2 3rd floor 2015 2015 2015 21-12-2015 25
FT- 03-08- 02-09- 30-12-
A1790 RB.3.4.2.2 4th floor 2015 2015 2015 29-02-2016 25
FT- 19-08- 18-09- 19-01-
A1800 RB.3.4.2.2 5 th floor 2015 2015 2016 18-03-2016 25
FT- 03-07- 01-08- 10-10-
A1810 RB.3.4.2.1.1 1st floor 2015 2015 2015 17-11-2015 25
FT- 18-07- 18-08- 18-11-
A1820 RB.3.4.2.1.1 2nd floor 2015 2015 2015 21-12-2015 25
FT- 04-08- 03-09- 22-12-
A1830 RB.3.4.2.1.1 3rd floor 2015 2015 2015 22-02-2016 25
FT- 20-08- 19-09- 23-02-
A1840 RB.3.4.2.1.1 4th floor 2015 2015 2016 23-03-2016 25
FT- 04-09- 07-10- 24-03-
A1850 RB.3.4.2.1.1 5 th floor 2015 2015 2016 10-05-2016 25
FT- External 05-09- 25-03- 10-05-
A1860 RB.3.4.2.1.2 plastering 2015 2016 2016 150
FT- 20-07- 19-08- 10-11-
A1870 RB.3.4.2.1.3 1st floor 2015 2015 2015 10-12-2015 25
FT- 04-08- 03-09- 11-12-
A1880 RB.3.4.2.1.3 2nd floor 2015 2015 2015 19-01-2016 25
FT- 21-08- 21-09- 10-02-
A1890 RB.3.4.2.1.3 3rd floor 2015 2015 2016 10-03-2016 25
FT- 05-09- 08-10- 11-03-
A1900 RB.3.4.2.1.3 4th floor 2015 2015 2016 11-04-2016 25
FT- 22-09- 30-10- 10-05-
A1910 RB.3.4.2.1.3 5 th floor 2015 2015 2016 25
FT- External 29-07- 11-11-
A1920 RB.3.4.2.1.4 painting 2016 2016 90
FT- 09-07- 07-08- 18-11-
A1930 RB.3.4.2.1.5 1st floor 2015 2015 2015 19-12-2015 25
FT- 24-07- 24-08- 21-12-
A1940 RB.3.4.2.1.5 2nd floor 2015 2015 2015 20-02-2016 25
FT- 10-08- 09-09- 23-02-
A1950 RB.3.4.2.1.5 3rd floor 2015 2015 2016 23-03-2016 25
FT- 26-08- 26-09- 24-03-
A1960 RB.3.4.2.1.5 4th floor 2015 2015 2016 09-05-2016 25
FT- 10-09- 13-10- 10-05-
A1970 RB.3.4.2.1.5 5 th floor 2015 2015 2016 25
FT- 29-06- 16-07- 17-11-
A1980 RB.3.4.2.1.6 1st floor 2015 2015 2015 03-12-2015 15
FT- 14-07- 31-07- 22-12-
A1990 RB.3.4.2.1.6 2nd floor 2015 2015 2015 18-01-2016 15
FT- 30-07- 18-08- 23-02-
A2000 RB.3.4.2.1.6 3rd floor 2015 2015 2016 10-03-2016 15

http://www.iaeme.com/IJCIET/index.asp 252 editor@iaeme.com


Relability of Implementing Primavera P6 in Fast-Track Planning of Residential Building

(*)BL (*)BL
Activity Activity Project Project Actual Actual Original
ID WBS Code Name Start Finish Start Finish Duration(d)
FT- 14-08- 02-09- 24-03-
A2010 RB.3.4.2.1.6 4th floor 2015 2015 2016 11-04-2016 15
FT- 31-08- 18-09- 10-05-
A2020 RB.3.4.2.1.6 5 th floor 2015 2015 2016 15
FT- 27-07- 13-08- 21-12-
A2030 RB.3.4.2.1.7 1st floor 2015 2015 2015 11-01-2016 15
FT- 11-08- 29-08- 22-02-
A2040 RB.3.4.2.1.7 2nd floor 2015 2015 2016 09-03-2016 15
FT- 28-08- 15-09- 24-03-
A2050 RB.3.4.2.1.7 3rd floor 2015 2015 2016 11-04-2016 15
FT- 12-09- 03-10- 09-05-
A2060 RB.3.4.2.1.7 4th floor 2015 2015 2016 15
FT- 25-05- 10-06-
A2070 RB.3.4.2.1.7 5 th floor 2016 2016 15

FT- 31-10- 23-11-


A2130 RB.3.4.2.1.9 Handing over 2016 2016 20
FT- 29-06- 16-07- 17-11-
A2140 RB.3.4.2.1.10 1st floor 2015 2015 2015 03-12-2015 15
FT- 14-07- 31-07- 22-12-
A2150 RB.3.4.2.1.10 2nd floor 2015 2015 2015 18-01-2016 15
FT- 30-07- 18-08- 23-02-
A2160 RB.3.4.2.1.10 3rd floor 2015 2015 2016 10-03-2016 15
FT- 14-08- 02-09- 24-03-
A2170 RB.3.4.2.1.10 4th floor 2015 2015 2016 11-04-2016 15
FT- 31-08- 18-09- 10-05-
A2180 RB.3.4.2.1.10 5 th floor 2015 2015 2016 15
12-02- 07-03- 23-02-
A1030 FT-RB.2.1.1 Ground floor 2015 2015 2015 17-03-2015 20
14-02- 10-03- 25-02-
A1060 FT-RB.2.1.1 1st floor 2015 2015 2015 19-03-2015 20
16-02- 11-03- 28-02-
A1090 FT-RB.2.1.1 2nd floor 2015 2015 2015 24-03-2015 20
18-02- 12-03- 02-03-
A2190 FT-RB.2.1.1 3rd floor 2015 2015 2015 25-03-2015 20
19-02- 13-03- 05-03-
A2200 FT-RB.2.1.1 4th floor 2015 2015 2015 30-03-2015 20
5th floor and 20-02- 14-03- 07-03-
A2210 FT-RB.2.1.1 above 2015 2015 2015 01-04-2015 20
21-01- 11-02- 24-01-
A2220 FT-RB.2.1.2 Ground floor 2015 2015 2015 14-02-2015 20
23-01- 13-02- 27-01-
A2230 FT-RB.2.1.2 1st floor 2015 2015 2015 20-02-2015 20
24-01- 14-02- 30-01-
A2240 FT-RB.2.1.2 2nd floor 2015 2015 2015 23-02-2015 20
25-01- 16-02- 02-02-
A2250 FT-RB.2.1.2 3rd floor 2015 2015 2015 25-02-2015 20
26-01- 18-02- 05-02-
A2260 FT-RB.2.1.2 4th floor 2015 2015 2015 28-02-2015 20
5th floor and 27-01- 19-02- 07-02-
A2270 FT-RB.2.1.2 above 2015 2015 2015 03-03-2015 20

http://www.iaeme.com/IJCIET/index.asp 253 editor@iaeme.com


Jannu Saibabu, SS. Asadi and S.S Bhanu Prakash

(*)BL (*)BL
Activity Activity Project Project Actual Actual Original
ID WBS Code Name Start Finish Start Finish Duration(d)
09-02- 04-03- 20-02-
A2280 FT-RB.2.1.3 Stilit floor 2015 2015 2015 14-03-2015 20
12-02- 07-03- 23-02-
A2290 FT-RB.2.1.3 Ground floor 2015 2015 2015 17-03-2015 20
14-02- 10-03- 25-02-
A2300 FT-RB.2.1.3 1st floor 2015 2015 2015 19-03-2015 20
16-02- 11-03- 28-02-
A2310 FT-RB.2.1.3 2nd floor 2015 2015 2015 24-03-2015 20
18-02- 12-03- 02-03-
A2320 FT-RB.2.1.3 3rd floor 2015 2015 2015 25-03-2015 20
19-02- 13-03- 05-03-
A2330 FT-RB.2.1.3 4th floor 2015 2015 2015 30-03-2015 20
5th floor & 20-02- 14-03- 07-03-
A2340 FT-RB.2.1.3 above 2015 2015 2015 01-04-2015 20
09-03- 19-03- 21-03-
A2350 FT-RB.3.1.1 Ground floor 2015 2015 2015 04-04-2015 10
11-03- 23-03- 23-03-
A2360 FT-RB.3.1.1 1st floor 2015 2015 2015 04-04-2015 10
12-03- 24-03- 24-03-
A2370 FT-RB.3.1.1 2nd floor 2015 2015 2015 06-04-2015 10
13-03- 25-03- 25-03-
A2380 FT-RB.3.1.1 3rd floor 2015 2015 2015 07-04-2015 10
14-03- 26-03- 26-03-
A2390 FT-RB.3.1.1 4th floor 2015 2015 2015 08-04-2015 10
5th floor & 14-03- 27-03- 28-03-
A2400 FT-RB.3.1.1 above 2015 2015 2015 10-04-2015 10
31-01- 11-02- 23-02-
A2410 FT-RB.3.1.2 Ground floor 2015 2015 2015 05-03-2015 10
14-02- 26-02- 25-02-
A2420 FT-RB.3.1.2 1st floor 2015 2015 2015 07-03-2015 10
16-02- 27-02- 28-02-
A2430 FT-RB.3.1.2 2nd floor 2015 2015 2015 11-03-2015 10
18-02- 28-02- 03-03-
A2440 FT-RB.3.1.2 3rd floor 2015 2015 2015 13-03-2015 10
19-02- 02-03- 05-03-
A2450 FT-RB.3.1.2 4th floor 2015 2015 2015 16-03-2015 10
5th floor & 20-02- 03-03- 09-03-
A2460 FT-RB.3.1.2 above 2015 2015 2015 19-03-2015 10
19-03- 02-04- 21-07-
A2470 FT-RB.3.2.1 Ground floor 2015 2015 2015 31-07-2015 10
23-03- 06-04- 21-08-
A2480 FT-RB.3.2.1 1st floor 2015 2015 2015 31-08-2015 10
24-03- 07-04- 21-09-
A2490 FT-RB.3.2.1 2nd floor 2015 2015 2015 30-09-2015 10
25-03- 08-04- 22-10-
A2500 FT-RB.3.2.1 3rd floor 2015 2015 2015 05-11-2015 10
26-03- 09-04- 21-12-
A2510 FT-RB.3.2.1 4th floor 2015 2015 2015 05-01-2016 10
5th floor & 27-03- 10-04- 27-01-
A2520 FT-RB.3.2.1 above 2015 2015 2016 06-02-2016 10
A2530 FT-RB.3.2.2 Ground floor 12-02- 24-02- 11-07- 22-07-2015 10

http://www.iaeme.com/IJCIET/index.asp 254 editor@iaeme.com


Relability of Implementing Primavera P6 in Fast-Track Planning of Residential Building

(*)BL (*)BL
Activity Activity Project Project Actual Actual Original
ID WBS Code Name Start Finish Start Finish Duration(d)
2015 2015 2015
27-02- 10-03- 11-08-
A2540 FT-RB.3.2.2 1st floor 2015 2015 2015 22-08-2015 10
28-02- 11-03- 11-09-
A2550 FT-RB.3.2.2 2nd floor 2015 2015 2015 23-09-2015 10
02-03- 12-03- 10-10-
A2560 FT-RB.3.2.2 3rd floor 2015 2015 2015 28-10-2015 10
03-03- 13-03- 10-11-
A2570 FT-RB.3.2.2 4th floor 2015 2015 2015 23-11-2015 10
5th floor & 04-03- 14-03- 10-12-
A2580 FT-RB.3.2.2 above 2015 2015 2015 21-12-2015 10
16-03- 30-03- 01-06-
A2590 FT-RB.3.2.3 Stilit floor 2015 2015 2015 11-06-2015 10
19-03- 02-04- 16-07-
A2600 FT-RB.3.2.3 Ground floor 2015 2015 2015 27-07-2015 10
23-03- 06-04- 17-08-
A2610 FT-RB.3.2.3 1st floor 2015 2015 2015 27-08-2015 10
24-03- 07-04- 17-09-
A2620 FT-RB.3.2.3 2nd floor 2015 2015 2015 30-09-2015 10
25-03- 08-04- 19-10-
A2630 FT-RB.3.2.3 3rd floor 2015 2015 2015 05-11-2015 10
26-03- 09-04- 26-11-
A2640 FT-RB.3.2.3 4th floor 2015 2015 2015 07-12-2015 10
5th floor & 27-03- 10-04- 28-12-
A2650 FT-RB.3.2.3 above 2015 2015 2015 08-01-2016 10
05-03- 16-03- 25-03-
A2660 FT-RB.3.1.3 Stilit floor 2015 2015 2015 07-04-2015 10
09-03- 19-03- 28-03-
A2670 FT-RB.3.1.3 Ground floor 2015 2015 2015 10-04-2015 10
11-03- 23-03- 30-03-
A2680 FT-RB.3.1.3 1st floor 2015 2015 2015 10-04-2015 10
12-03- 24-03- 02-04-
A2690 FT-RB.3.1.3 2nd floor 2015 2015 2015 14-04-2015 10
13-03- 25-03- 04-04-
A2700 FT-RB.3.1.3 3rd floor 2015 2015 2015 15-04-2015 10
14-03- 26-03- 07-04-
A2710 FT-RB.3.1.3 4th floor 2015 2015 2015 17-04-2015 10
5th floor & 14-03- 27-03- 08-04-
A2720 FT-RB.3.1.3 ab ove 2015 2015 2015 18-04-2015 10
Collection of 05-01- 17-01- 05-01-
A2730 FT-RB.1 inputs 2015 2015 2015 20-01-2015 10

4. CONCLUSION
Arranging engineer has a standout amongst the most critical parts in development ventures. Arranging
specialists are in charge of guaranteeing that the venture will be finished according to venture
administration arrangement due dates
Planning engineer should know how to process the planning techniques via software and producing
visual aids to help explain the schedule of work. In this journal Primavera P6 is used in planning, and also
planning engineers dealing with big amount of data try to say and not just pass them to others.

http://www.iaeme.com/IJCIET/index.asp 255 editor@iaeme.com


Jannu Saibabu, SS. Asadi and S.S Bhanu Prakash

By comparing the results in primavera p6 is most useful for the analysis and getting more accurate
results. Mainly focus on the critical activities to complete the project within the time, if fail project time
should over run.
By comparing the results in from table-4 time is over run due to improper planning of the organization,
they are followed conventional planning, I am giving suggestion to Muppa constructions and Pvt. ltd,
they are following conventional methods, I advised the importance of fast-track planning method and
importance of primavera software for faster construction of project within time.

REFERENCES
[1] Ashraf M E, Ahmed A G. Finance-Based Scheduling Of Construction Projects Using Integer
Programming. Journal of Construction Engineering and Management. 2004 January; 130, 15-24.
[2] Min Y C, Ming H T. Axomatic-Design Scheduling Method for Fast-Track Construction. 24th
International Symposium on Automation and Robotics in Construction. Construction Automation
Group, I.I.T. Madras, 24, 435-441.
[3] Pierre Bonnal, Didier Gourc, Germain Lacosti. Where Do We Stand With Fuzzy Project Scheduling.
Journal of Construction Engineering and Management. 2004 January; 130, 114-123.
[4]
Chan W T, Hao Hu. Constraint Programming Approach to Precast Production Scheduling. Journal of
Construction Engineering and Management. 2002 November; 128(6), 513-521.
[5] Civil Engineering Standard Datas. https://www.scribd.com/doc/183513023/civil-guide123-pdf. Date
accessed : 26/10/2015
[6] Anees, S. U. M. and Bhat, M. S. Assessment of the Seismic Vulnerability of Residential Buildings of
Srinagar City Jammu and Kashmir. International Journal of Advanced Research in Engineering and
Technology, 6(2), 2015, pp. 21-29