Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1) Introduction
3) Plate Forming
5) Welding Equipment
6) Testing
7) Heat Treatment
9) Documentation
Wefco lead kettles are normally supplied manufactured from the following materials, specially
rolled to give low Aluminium, Silicon and Manganese contents.
b) BS 2858 (Modified)
Note:-
The above are Wefco standard material specifications, these can be substituted to meet client
requirements as necessary.
3) Plate forming.
Kettle plate may be formed by either of the following two methods subject to the clients
specification.
a) Cold Forming
b) Hot Forming
The plate temperature during forming shell be above the minimum normalising
temperature.
Preparation of the joint faces shall be accomplished by one or more of the following methods.
Thermal cutting
Chipping
Grinding
Machining
The preparation method used must produce a clean smooth surface to the profile required. The
joint faces and immediately adjacent surfaces shall be free from heavy scale, moisture, oil paint
or any other substance, which may affect the quality of the weld or impede the welding process.
Non Destructive Testing may be carried out on cut edges to ensure they are free of defect prior
to welding.
All welding, where practical, shall be carried out using the submerged arc process with
resulting welds having the following chemical composition.
The care and storage of all welding consumables shall be in accordance with the
manufacturers recommendations so to avoid damage or deterioration.
Filler wires and electrodes which show any sign of damage or deterioration shall not be
used.
Storage of consumables shall be arranged so that they are stored in a heated area to the
manufacture recommendations.
All welding plant, cables, instrumentation and accessories shall comply with all current
regulatory standards.
All welding equipment shall have current calibration certificates and per our ISO 9001
procedures.
Welds shall be carried out in accordance with written procedure which are approved by
a Third Party Inspector (Lloyds Register). Weld procedures are to comply with the
specification requirements of individual contracts but likely ISO 15614 and/ or ASME IX.
All welders are qualified and tested to relevant standards and endorsed by a Notified
Body.
Joint geometry, together with acceptable tolerances, shall be shown on the appropriate
drawing and weld procedure. No deviations are permitted without prior approval.
5.6 Alignment of Butt Joints / Temporary Attachments
Alignment of the plate surfaces should be within 3 mm. To facilitate construction the use
of temporary attachment for the use of clamps, dogs, wedges etc is permitted.
Temporary attachments shall be carefully removed by cutting or shipping, not
hammering. Any damage of the surface shall be restored by welding and / or grinding
and checked for surface cracks by dye or magnetic particle inspection.
Precautions should be taken to avoid accidental stray arcing on the work piece. If any
stray arcing has occurred grinding of the scar is required followed by dye or magnetic
particle inspection.
6) Testing.
7) Heat Treatment.
All kettles shall be heat-treated to normalising temperatures in accordance with the below;
Note: Client requirements are to be checked to ensure they do not deviate from the above.
The kettle shall be wire brushed and/or shot blasted to remove all loose rust and millscale, then
given one coat of red oxide primer externally (or system required by specific client
requirement). The Wefco Job No. is to be marked on the outside in figures approx. 200 mm high
by welding along with all information required by the purchaser.
9) Documentation.
The client shall be provided with a full documentation pack consisting of, but not limited to;
Drawings
Material certificates including consumables
Welding procedures, & Procedure Qualifications
Welder qualifications
Heat treatment records
NDT test reports
Conformity Certificate
Third Party Inspection Certificate (if applicable)