Sei sulla pagina 1di 4

MEASUREMENT FORM OF AN T.W.

PARTITION
Name of work: FURNITURE
No Description of work or No. UNIT Lengt Bread Height Quantit
. Material h th y
1 SEAL WOOD 30*35 MM
PARTITION
FRAME
(A) VERTICAL FRAME 4 R.M 3.0 12
(B)HORIZONTAL FRAME 3 R.M 1.8 5.4
(C)SEAL HORIZONTAL FRAME 2 R.M 3.2 6.4
(D) VERTICAL DOOR FRAME 1 R.M 2.1 2.1
(E) HORIZONTAL DOOR 1 R.M 1.2 1.2
FRAME

TOTAL 27.1

2 6 MM THK MARINE PLYWOOD


OF
CENTURY PLY USED FOR
PARTITION
(A) PLY AFTER FINISHING 6 SQ.M 1.8 0.9 9.72
THE
PARTITION FRAME
(B) PLY AFTER FINISHING 2 SQ.M 1.8 0.3 1.08
THE
PARTITION FRAME .
(C) PLY AFTER FINISHING 2 SQ.M 1.2 0.9 2.16
THE
PARTITION FRAME

TOTAL 12.96

3 TEAK WOOD 9 MM THK


SKIRTING
(A)TEAK WOOD SKIRTING 2 R.M 1.8 0.1 3.6

4 CLEAR GLASS DOOR


(A) GLASS DOOR 1 SQ.M 2.1 1.2 2.52

5 LIPPING PATTI
(A)LIPPING PATTI 30 *12MM 23 R.M 3.0 0.02 1.38
IN
VERTICAL
(B)LIPPING PATTI 30 *12MM 23 R.M 3.0 0.02 1.38
IN
HORIZONTAL
TOTAL 2.76

6 0.8 MM THK LAMINATE FROM


CENTURY PLY
(A) PLY AFTER FINISHING 6 SQ.M 1.8 0.9 9.72
THE
PARTITION FRAME
(B) PLY AFTER FINISHING 2 SQ.M 1.8 0.3 1.08
THE
PARTITION FRAME .
(C) PLY AFTER FINISHING 2 SQ.M 1.2 0.9 2.16
THE
PARTITION FRAME
TOTAL 12.96

ABSTRACT SHEET OF AN PARTITION


Name of work: PARTITION
No Description of work or Unit Rate Quantity Amount
. Material

1 SEAL WOOD 30*35 MM R.M 210 Sq/m 27.1 5,691


PARTITION
FRAME

2 6 MM THK MARINE PLYWOOD SQ.M 738 Sq/m 12.96 9,564


OF
CENTURY PLY USED FOR
PARTITION

3 TEAK WOOD 9 MM THK R.M 195 Sq/m 3.6 702


SKIRTING

4 CLEAR GLASS DOOR SQ.M 1245 2.52 3,137


Sq/m

5 LIPPING PATTI R.M 62 R/M 2.76 1,211

6 0.8 MM THK LAMINATE FROM SQ.M 635 Sq/m 12.96 8,229


CENTURY PLY

7 HARD WARE

TOTAL 28,541
SUMMARY SHEET OF AN PARTITION
Name of work: FURNITURE

DESCRIPTION OF WORK OR AMOUNT


MATERIAL
TOTAL COST FOR PARTITION 28,541

HARDWARE FOR PARTITION 3,250

TOTAL 31,791
15%WASTAGE 4,768
TOTAL 36,559
LABOUR( 5 DAYS) 6,600
TOTAL 43,159
20% CONTRACTORS PROFIT 8,631
TOTAL 51,790
5%CARTAGE 2,589
TOTAL 54,379
60% ON 54,379 32,627
13.5% VAT ON 32,627 4,405
TOTAL 37,032
40% ON 54,379 21,751
15%SERVICE TAX ON 21,751 3,263
TOTAL 25,014

OVER ALL TOTAL COST 62,046

OVER ALL TOTAL COST IN WORDS: SIXTY TWO THOUSAND


FOURTY SIX RUPEES.