EHS RISK ASSESSMENT

ACTIVITY: DISTRIBUTION BOARD (DB) & JUNCTION BOX (JB) INSTALLATION


PACKAGE NUMBER: CG-4750

Current Risk Final Risk


Task (Steps) Potential Hazard Existing Control Additional Control Prob
Cons. Prob. Risk Cons. Risk
.

Make sure a clear space where the


Falling of the load is to be placed.
6.1.1 to object on the Always size up the job and remove
3 2 6
6.1.3 body ,damage to any obstructions.
property Ensure to see over the load when
carrying it
Supervisor / Foreman to conduct
daily crew talks prior to start the
Not wearing
activity 3 2 6
appropriate P.P.E
Implement close supervision during
the activity
Examine the load to make sure it is
not too heavy or awkward
Always get close to the object to
carry.
Back injury to 3 3 9
Ensure to see over the load when
personnel. Hand
and foot injury carrying it.
Use proper Hand gloves and foot
protection

Maintain proper housekeeping at all


times
Fall, trip and
Foreman to conduct daily crew talk 3 2 6
slipping hazards.
prior to start the activity
Implement close supervision during
the activity

503406-AD0000-68AF-12303_R01 (2012-01-30) Page 1 of 6


EHS RISK ASSESSMENT

ACTIVITY: DISTRIBUTION BOARD (DB) & JUNCTION BOX (JB) INSTALLATION


PACKAGE NUMBER: CG-4750

Operator must pass third party


competency test for crane
operation and secure competency
certificate.
Operator should attend induction
course for carne operation.
Crane/Boom truck must have:
1. Valid registration from RTA
Unauthorized to Travel
6.2.5 operation of 2. Valid certificate of
conformity or through 4 3 12
crane / boom
truck crane /boom truck
inspection from approved
certification agencies.
3. Statement of insurance
policy.
4. Supervisor to ensure all
mobile equipments are
duly inspected by EMAL /
SLII with valid load test
certificates

Crane must be certified by approved


third party certification agencies
and EMAL/SLII..
Gears, chains, and belts should be
Mechanical Failure inspected, certified and colour 4 3 12
coded to use.
Avoid overloading of transport
equipment.
Lift load for its specific load limit or
safe working load

503406-AD0000-68AF-12303_R01 (2012-01-30) Page 2 of 6


EHS RISK ASSESSMENT

ACTIVITY: DISTRIBUTION BOARD (DB) & JUNCTION BOX (JB) INSTALLATION


PACKAGE NUMBER: CG-4750

Use tag lines or tag ropes to guide


Having no control
the load towards its destination. 3 2 6
of the load
Assign a certified rigger.
Activity shall be carried out the
personal supervision of receiving
activity.
Supervisor to ensure all applicable
PTW to be available prior to
Unauthorized commencement of the task.
6.2.6 to workers at working Tool box talk to be held at site, this
6.2.11 area may injure shall cover the method statement 3 3 9
due to curiosity. and job safety analysis.
Only competent and authorized
personnel to be
deployed,supervisor to ensure all
workers involve in the activity
received Big 5 training of emal

Using damaged Inspect step ladder before use, one


step ladder. man should hold the ladder on the
Use of damaged ground while is in used.
4 3 12
hand power tools. Competent operator for the use of
Electrocution/fire power tool and inspect before use
ensure valid colour coding.

Supervisor to inspect the drill


machine and make sure it is in
Using of drill good condition.
machine. Dont use excessive force to drill 3 4 12
Electrocution machine during drilling.
Only competent and authorized
worker for the using if power tools
Only 110V to be used at site

503406-AD0000-68AF-12303_R01 (2012-01-30) Page 3 of 6


EHS RISK ASSESSMENT

ACTIVITY: DISTRIBUTION BOARD (DB) & JUNCTION BOX (JB) INSTALLATION


PACKAGE NUMBER: CG-4750

Dust while drilling Provide appropriate safety glass 3 2 6


&dust mask while drilling

Manual handling. Supervisor to give toolbox regarding


Slip and fall of DB/ proper manual handling. 3 3 9
JBs while fixing. Extra care while fixing DB/ JBs.

Workers may slip,


Maintain house keeping around the
trip & fall at same
area 3 2 6
ground or from
height Walkway and gangway to be kept
free of obstruction

All personnel involve in the activities


Working without must wear proper PPEs (hard hat, 3 3 9
proper PPEs appropriate safety glass, dust
mask long sleeve shirt and
reflective vest).

Only competent and authorized


Unauthorized person to do the inspection, ensure
6.2.13 workers notified the client with all
3 2 6
necessary documents.

503406-AD0000-68AF-12303_R01 (2012-01-30) Page 4 of 6


EHS RISK ASSESSMENT

ACTIVITY: DISTRIBUTION BOARD (DB) & JUNCTION BOX (JB) INSTALLATION


PACKAGE NUMBER: CG-4750

Maintain good housekeeping around


Slip / Trip / Fall -
the area.
same level 3 2 6
All temporary cable should be
properly organized.

Wear P.P.E.'s at all times


(hard hat, appropriate safety glass,
safety shoes, hand gloves, dust 3 3 9
Not using P.P.E.'s mask, fire retardant long sleeve
shirt / pants.

NOTE: All Current Risk ranked above C-15 must have additional control measures: Risk = Consequence x Probability (R = C x P)
Tolerable Risk (Low) = 1-6, Medium = 8 -12, (Methods statement), Intolerable Risks (High) = 15 25 (Method Statement plus additional Control Measures in place)
Consequence
Consequence ( Severity) Rating Factors (5) Probability Rating Factors (5) Frequency/Probability
(Severity)
No Safety Health Environ. Financial No Frequency A B C D E
1 First Aid Immediate Minor <AED 1k <1 hr A (1) Practically impossible or Once in 10 years 5 5 10 15 20 25
2 Medical Temporary Short term <AED50K 1-2 hrs B (2) Not likely or Once per year 4 4 8 12 16 20
3 Lost Time Short term Long term >AED300k 2-4 hrs C (3) Could happen or Monthly 3 3 6 9 12 15
4 Disability Long term Serious >AED500k 4-8 hrs D (4) Has happened or Weekly 2 2 4 6 8 10
5 Fatality Fatal Catastrophic >AED1m >1 shift E (5) Common or Daily 1 1 2 3 4 5

503406-AD0000-68AF-12303_R01 (2012-01-30) Page 5 of 6


EHS RISK ASSESSMENT

ACTIVITY: DISTRIBUTION BOARD (DB) & JUNCTION BOX (JB) INSTALLATION


PACKAGE NUMBER: CG-4750

Risk assessment compiled by :

Risk Assessor:

SACHIN BABU EHS ADVISOR 08-05-2012

Name Designation Signature Date

Risk assessment approved by :

EHS Department:

Name Designation Signature Date

Construction:

Name Designation Signature Date

Management:

Name Designation Signature Date

503406-AD0000-68AF-12303_R01 (2012-01-30) Page 6 of 6