Sei sulla pagina 1di 8

1

Frequency Stability Issues for Islanded Power


Systems
Jonathan Horne, Damian Flynn and Tim Littler

Power system stability is the ability of an electric power


AbstractFrequency stability has not necessarily been a major system, for a given initial operating condition, to regain a
problem for the majority of power systems in the past. However, state of operating equilibrium after being subjected to a
for economic and environmental reasons, power systems are now physical disturbance, with most system variables bounded so
operated closer to stability limits to maximise the use of the
that practically the entire system remains intact.
existing networks. Therefore, introduction of new, more efficient
and renewable generation technologies, and their effect on the From this definition, it can be deduced that the system does
power system must be fully understood if a reliable and secure not have to be in a particularly desirable configuration
electricity supply is to be maintained. Using the Northern following an event, but provided it settles to a new
Ireland, and interconnected Republic of Ireland electricity equilibrium from which normal operation may eventually be
networks as a case study, this paper addresses some of the issues restored, it may be deemed stable.
regarding integration and modelling of Combined Cycle Gas
Turbines (CCGTs), and Wind Turbine Generator (WTG) B. Types of Instability
technology on a small islanded power system.
There are many different ways in which a power system
may become unstable initiated by, for example, a fault on a
Index TermsFrequency Stability, Wind, Gas Turbine,
Power System Modelling. line, or the tripping of a generator. It is, therefore, important
to be clear as to the nature of instability being investigated. A
I. INTRODUCTION suitable classification is again offered in [1], and is shown in
Fig. 1. Three main types of instability are defined, with the
I T has become increasingly apparent that privatisation and
deregulation of power utilities, coupled with environmental
concerns of reinforcing existing networks with new build, has
relevant sub-categories and time scales defined with short
term covering the first 20 seconds following an event, and
long term relating to effects examined over several minutes.
lead to current electricity infrastructures becoming more
Note the absence of the term dynamic stability, due to the
heavily loaded than was previously encountered. An ever
same term being applied to different types of instability in
increasing demand for power, together with a requirement for
different parts of the world.
cheaper and greener energy, has forced the now profit
The focus of this paper is on frequency stability in small
oriented utilities to obtain new ways of maximizing use of the
island power systems. Frequency instability results when a
existing system. New and more efficient generation
power system cannot settle to a new equilibrium following a
technologies play an important part in fulfilling these
large generation / load imbalance. It is generally caused by
requirements, but their effect on the power system needs to be
tripping of large capacity tie-lines or generators. However,
fully understood if a secure and reliable electricity supply is to
there is no set definition of what a small system actually is.
be maintained. Furthermore, if diversity of supply is not
From a frequency stability point of view, and for the purposes
preserved, i.e. portions of coal, oil, gas, nuclear etc. then this
of this paper, it can be described as one in which any
can only add to the problems discussed here.
individual generator in-feed represents a substantial portion of
A. Power System Stability the total demand. Furthermore, a small system will not be
It is informative to introduce a clear definition, not only of heavily interconnected with other larger systems.
power system stability, but the various forms of instability
that can potentially occur. One of the most clear and concise
definitions, provided by the IEE / CIGRE Joint Task Force on
Stability Terms and Definitions [1], is presented as follows;

This work is supported by Northern Ireland Electricity plc (NIE) and the
Department for Employment and Learning, Northern Ireland.
Jonathan Horne, Damian Flynn and Tim Littler are with the Electric Power
and Energy Systems Research Group, Ashby Building, Queens University of
Belfast, Stranmillis Road, Belfast, BT9 5AH, Northern Ireland, UK.
(e-mail addresses: Jonathan.Horne@ee.qub.ac.uk, D.Flynn@ee.qub.ac.uk,
Fig. 1. Classification of Power System Stability
and T.Littler@ee.qub.ac.uk)
2

II. STABILITY OF SMALLER POWER SYSTEMS can be used to maintain simplicity.


The majority of the literature on power system stability has As frequency stability may not have been an issue in the
focused on rotor angle and voltage stability, with frequency past, it is possible that the governor and turbine models
stability often being neglected. A simple reason for this is that currently in use by many utilities are inappropriate for such
most of the worlds power systems are large interconnected studies. The primary reason being that studies previously
networks, where there is plenty of opportunity for power undertaken have usually either concentrated on transient
wheeling and therefore sharing of spinning reserve and unit stability, or steady state studies. Previously, observational
inertial response. This tends to result in a stiff system, where a experience of units was sufficient to maintain stability, but
large generation / load imbalance must occur before the this approach could lead to unnecessary load shedding in the
frequency will deviate to any significant level. Companies in future as systems are operated less conservatively due to the
the Western Electricity Coordinating Council (WECC) in the market structures.
USA have reported a loss of 1,250 MW will cause a There are numerous generic built in models, including
frequency drop of 0.15 Hz (from a nominal of 60 Hz) [2]. IEEE standard versions, in most favoured software packages
This can occur with the loss of a large station or with tripping that are suitable for representing the majority of plant. Power
of interconnecting tie lines. A comparatively smaller system Technologies PSS/E and DIgSILENT Power Factory both
like England and Wales may only require loss of 1,320 MW present an extensive library containing the majority of the
of generation, about the size of the UKs largest nuclear most popular models. These will produce acceptable results
station, for an excursion below 49.5 Hz (from a nominal of 50 provided the various parameters have been tuned correctly.
Hz) [3]. The same excursion can occur on the Ireland system Factors such as correct droop values, time lags, load
with the loss of a large single unit of around 260 MW [4], controllers, fuel type, boiler dynamics, operator intervention
where there are now multiple 400 MW infeeds. and overall general response of the plant all need to be
For smaller systems, frequency stability may be more of an accounted for if a correct representation is to be achieved.
urgent problem than the different forms of rotor angle However, since parameters are not always convenient to
stability. It is therefore imperative that adequate spinning obtain, standard values are often (inappropriately) chosen.
reserve (extra capacity to restore generation / load balance For certain plant these generic models may not be suitable.
following a generator trip) is available and provided by To overcome this problem the majority of simulation
machines with a sufficient governor response and a high packages allow so called manufacturer user models to be
inertia. The plant must be able to maintain this increased introduced. While this may slightly increase simulation time,
output, at least until other forms of generation can be it may be the only method of obtaining suitably accurate
synchronised. Any new types of generation added to the results.
system that contribute a substantial portion of the total, should In certain cases, the actual response of the various plant can
first be thoroughly investigated to ensure they supply be reduced from possible to contractual levels to increase
adequate frequency control capability. plant life and reduce maintenance requirements. For this
reason it is important to validate the models with real event
III. MODELLING ISSUES data, rather than manufacturers recommendations.
Validated models may not always be available, particularly
Time domain computer simulation is the normal method for
for new and previously uncommon types of generation. It is
assessing most types of stability, the exception being small
therefore advisable that models are developed so accurate
disturbance angle stability, where not all modes may be
studies can be performed to assess any adverse effects. In
excited sufficiently. Eigenanalysis is normally the preferred,
Europe, increase of renewable generation, and in particular
and most suitable, method here.
wind, has lead to the requirement for Wind Turbine Generator
Nevertheless, for all forms of stability assessment suitable
(WTG) models. Previously, these WTGs were only
models for the various components in a power system are
distribution connected and low capacity and were therefore
essential if the results obtained are to be credible. Even with
neglected in system simulations. Accurate models to represent
the most modern processors, the computational time required
the full effects of the various types and manufacturers of
to process detailed models for large interconnected power
WTGs are still in the development and verification stage. For
systems can be substantial. It may, therefore, be desirable to
frequency stability studies, a simpler model is often sufficient.
trim some aspects of these models to improve processing
If the wind speed, and therefore output of the WTGs are
speed. This can normally be achieved with very little effect on
assumed to be constant over the period of interest, the main
the results, provided the models are applied within the
factors that should be modelled are inertial response, primary
boundaries and intentions they were developed for.
frequency response (if appropriate), and unit protection.
For frequency stability studies the governor model (and
The development of adequate generator models is not
turbine model, if applicable) are the most important as they
unique to small island systems. Tests in the Western
are responsible for restoring the frequency following an event.
Electricity Coordinating Council (WECC) in America
While other models such as exciters, loads, and transmission
indicated that only approximately 40% of the simulated
lines do play a small part, standard values and generic models
governor response actually occurred [2]. As frequency
3

stability becomes more of an issue, it can only be of benefit to needs before interconnection in 1995. This resulted in the
have a system model that accurately represents power system smaller NI system having comparatively responsive plant, due
behaviour. to a large unit size to demand ratio. The larger RoI system had
less need for large amounts of primary reserve (within 5
IV. CASE STUDY THE NIE / ESB ISLAND POWER SYSTEM seconds) and instead concentrated on secondary (30 seconds)
The Northern Ireland (NI) electricity network is owned by and tertiary reserve (5 minutes) [6]. This mix of response for
Northern Ireland Electricity plc (NIE) with SONI ltd. (System the combined system has worked well with the growing need
Operator Northern Ireland) managing the transmission system for primary frequency control, together with a sustained
and generation scheduling. A double circuit 275/220 kV response from secondary and tertiary reserve plant.
1,200MVA synchronous link connects the Northern Ireland More recently, increasing numbers of Independent Power
and the Republic of Ireland (RoI) networks so that the two Producers (IPPs) have been appearing on the NIE / ESB
systems may benefit from energy trading, sharing of spinning network. Their choice of generation technology is influenced
reserve, and the stability benefits of a larger network. The RoI by many factors including the current prices of fuel,
network is owned by Electricity Supply Board (ESB) and government renewable targets, efficiency of plant and
operated by ESB National Grid (ESBNG). The NIE and ESB emission concerns. Currently, the favoured types of
systems currently have a maximum demand of around 1850 generation are Combined Cycle Gas Turbines (CCGTs) and
MW [4] and 4500 MW [5], respectively. Fig. 2 Shows a map Wind Turbine Generator (WTG) technology.
of the island, with main transmission system and power Previously, the largest generation unit, and consequently
stations. There is a mix of generation at present, dominated by the biggest possible loss to the system, was 260 MW in NI, or
coal, oil, and gas but with notable contributions of peat and 305 MW in RoI. The Moyle interconnector has increased this
hydro, and growing amounts of wind. The NI system is also possible loss to a theoretical 500 MW, although it is normally
connected to the UK mainland system via the Moyle only operated up to 450 MW (winter max). There are also
interconnector, a 500 MW HVDC link to Scotland. While the three new CCGT stations (one currently under construction)
link allows trading and power wheeling to the RoI, it does not representing possible losses in the region of 400 MW. Four
contribute any inertial or primary frequency response to the other CCGT plant are in operation with a total generating
Ireland system due to current contractual and economic capacity of approximately 1400 MW, each with a maximum
reasons. Consequently, the link displaces conventional possible loss to the system of in and around 200 MW.
generation resulting in the same reserve on fewer plant, and a Hence, in general, there are a smaller number of larger
reduced system inertia. Plans have also recently been power stations appearing on the network, displacing
announced for a 1000 MW (2 x 500 MW) link from RoI to conventional thermal generation with CCGT technology. This
Wales which may accentuate the problem if it is operated in represents a greater possibility of a significant generation loss
the same fashion. to the system, with the added complication of the non-
standard CCGT behaviour. WTGs have not as yet reached
sufficient numbers to displace any conventional generation.
Ireland has some of the windiest sites in Europe, and with
plenty of hills and coastline there are many opportunities for
both onshore and offshore wind generation. As WTGs are the
most mature renewable technology (the exception being
hydro, but suitable sites are limited), they are expected to
meet the majority of the government targets in NI of 13.4%
installed capacity of renewable generation by 2010, 24% by
2015. The corresponding RoI target is 13.2% of gross
electricity production by 2010. If full advantage is taken of
the resource, these figures could result in WTGs providing up
to 50% of the total instantaneous NI generation at times of
low demand. At present this figure only reaches about 8% of
the total NI generation, with 1.6% installed capacity [7]. In
the future, this will pose a difficult scheduling problem, were
either conventional plant is de-committed or a percentage of
the WTGs are curtailed to maintain stability margins.
A. Simulation of the System
Northern Ireland Electricity (NIE) and the System Operator
Fig. 2. The all Ireland main transmission network and major power stations. for Northern Ireland (SONI) have developed a model of the
all Ireland system in PSS/E format. The model consists of the
The two systems developed according to their respective 275 kV and 110 kV transmission system in Northern Ireland,
4

and the interconnected 400 kV, 220 kV and 110 kV RoI plant are added, the minimum value of frequency increases
transmission system, together with all associated generator slightly, although the system takes longer to recover. This
and load models. WTGs are not as yet included in the model suggests that the system inertia has been increased, at the
structure. initial rate of change of frequency is less severe. However,
Only the transmission systems are included in the model as even with this extra inertial effect, the frequency nadir still
the majority of generation is connected at these voltage levels. occurs at a slightly lower level and the frequency takes much
The effects of the distribution system can be accurately longer to recover. The main cause of this is due to the large
represented through suitable frequency and voltage dependent nature of the CCGTs replacing smaller conventional units.
load models. This reduces the total number of nodes and These smaller units would previously have provided some
therefore reduces computation and set-up times. Currently, reserve. Consequently, the reserve requirement is shifted to a
embedded generation is in sufficiently small numbers that it
fewer number of conventional units. Before drawing any
can be treated as a negative load. As the majority of stability
conclusions from these results, it is first necessary, to discuss
problems occur between generators and general loads, this
how CCGT plant typically behave to a frequency drop, and
method is satisfactory for now. If, in future, large amounts of
embedded generation are connected to the distribution secondly investigate how the model represents this behaviour.
system, the model may have to be extended to cover this
issue. Similarly, if the embedded generation will be required
to respond to an event, then suitable models will have to be
introduced. Conversely, if current practices remain, unit
protection will disconnect the plant, and they can be modelled
as a sudden increase in load.
For this study some minor modifications have been made,
primarily to governor models of the existing conventional
plant, for the reasons previously discussed. The new
parameters are based on, and validated against, examination
of unit responses following the loss of a large infeed. This has
yielded a more representative response, particularly in the
first fifteen to twenty seconds following an event.
There are many possible contingencies that could impact on
the all Ireland system and it is not unusual for the frequency
to reach values as low as 49.2 Hz on some occasions. The fast
response of conventional plant in the island has previously
been sufficient to restore frequency in all but the most severe
of cases, where load shedding has been initiated to maintain
Fig. 3. Frequency trace with (a) no CCGTs, (b) 3 CCGTs (c) 6 CCGTs
stability. There is, however, some concern that increasing
numbers of large CCGT plant may affect the overall dynamic
response of the system. Not only do gas turbines behave B. Combined Cycle Gas Turbine (CCGT) Technology
differently to conventional plant, but the larger ratings While combined cycle generation has been in existence
represent a greater possible loss of generation. Also, the larger since the mid 1950s [8], the current low cost of gas, together
plant could displace more, smaller conventional units, with the high efficiency of modern combined cycle plant has
possibly lowering the system inertia, and hence resulting in a lead to a dramatic increase in the numbers of CCGT plant
greater initial rate of change of frequency following a loss of installed. This, together with the rapid, modular construction,
generation. low footprint and reduced emissions compared to
This study utilises a complete utility approved transmission conventional thermal plant has lead to penetrations as high as
system model and data corresponding to actual plant. NI and 10% in Japan [9], and 22% in certain US regions [10]. In the
RoI generation is maintained at a set level and is dispatched as all Ireland system the figure is approaching 36%, not
per normal, with the exception of the CCGT plant. including open cycle units [4],[5].
Interconnector flows are maintained for all simulations, with When a single type of technology is introduced for the first
an initial flow from NI to RoI. The event is initiated by time in such high numbers, it is important to understand how
tripping the Moyle interconnector from a value of 400 MW. it will respond to particular disturbances. When considering a
Three simulation frequency traces are shown in Fig. 2. In the small island power system where significant frequency
first simulation, only conventional plant (steam and hydro) are excursions can occur, the response to changes in frequency is
on-line. The second and third simulations show the effect of clearly of utmost importance.
displacing base loaded conventional plant with three CCGT The manner in which CCGT plant respond when subjected
units at a time. to a frequency deviation depends on four main factors; inertial
While the frequency does appear to reach a lower value response, operation of the steam turbine, control of Inlet
with the first three CCGT plant, when the subsequent three Guide Vanes (IGVs), and the loading level of the unit.
5

Ambient conditions can also affect the performance of gas Generator (HRSG) for maximum efficiency. This can be
turbines by reducing the maximum power output. The two achieved through utilization of Inlet Guide Vanes (IGVs).
main factors are air pressure and temperature. The former is Their main purpose is to control the fuel to air ratio, and
approximately proportional, and the latter being a non-linear therefore the exhaust temperature at a certain value. This
complex inverse function to the maximum power output [10]. value is normally the maximum design temperature for the gas
This may result in the maximum operational limits being turbine, and therefore the most efficient for the HRSG. At
reached earlier, depending on ambient conditions. load values less than base load, air flow is reduced,
1) Inertial response of a CCGT maintaining exhaust temperature for the HRSG. If a load
As with conventional thermal plant, there is a short delay increase is demanded, fuel flow can only be increased once
before the governor is able to act following a change in the IGVs have opened in order to maintain the fuel to air ratio
frequency. During this time, the inertial response is of and therefore exhaust temperature under the maximum limit.
paramount importance, particularly in a small system, as it The rate of load pick-up is consequently limited by the
controls the initial rate of change of frequency. If the system response of the IGVs.
has less inertia, the initial rate of change is greater and a lower For CCGTs operating in small islanded power systems
value of frequency is reached in a shorter time, possibly where primary frequency response is a priority, the rate of
resulting in under-frequency load shedding. load pick-up may not be sufficient. It is for this reason so
In general, the inertia constants of CCGT plant are similar, called fast acting IGVs are included in the majority, but not
or slightly higher than existing thermal units [11]. However, all, of modern plant. As the entire unit is synchronized to the
to benefit from the highest efficiencies and minimum grid, a frequency dip results in a decrease in compressor
emissions, it can be desirable to run them as base loaded speed and therefore airflow. The controls will try to increase
plant. As a consequence, smaller, partly-loaded conventional fuel flow, but this will be restricted by the exhaust
units are displaced. This results in a small number of large temperature limit. The IGVs must open before fuel flow can
units on the system, and potentially a reduced system inertia. increase. The faster the IGVs can act, the faster the exhaust
2) Operation of the steam turbine temperature is lowered, and fuel flow and power output
Exhaust gasses from the gas turbine(s) are collected and increased. If the compressor is slowed sufficiently, for a
used to raise steam in a Heat Recovery Steam Generator certain period of time, the reduced air flow results in a
(HRSG) boiler, thus resulting in the high efficiency of the decrease of fuel. If the IGVs cannot open rapidly enough the
overall plant. gas turbine may not be able to sustain combustion, or will
The steam turbine section is normally operated in one of exceed temperature limits. Either way the unit will be tripped
two modes. The most common, sliding pressure mode is from the system. This critical value of frequency depends on
where the steam governor valves are left fully open and the the response of the IGVs, and the duration of the frequency
unit output depends on the exhaust temperature of the gas excursion.
turbine. Maximum efficiency is achieved by keeping the gas IGVs do not have an appreciable effect on gas turbine
turbine exhaust temperature, and therefore steam turbine torque and therefore power output, but they do affect exhaust
output, maintained at the maximum permissible value. temperature and as a result, the rate at which the gas turbine
Essentially, the steam turbine can be assumed to produce can pick up load.
constant power with an inertial response, for the purpose of 4) Gas Turbine Power Output;
modelling during frequency drops or primary reserve Conventional thermal plant used for base load operation
calculations. Even if the exhaust temperature does change, the will maintain power output when subjected to the majority of
effect on the steam turbine incorporates a time lag of around frequency excursions. CCGTs operating at base load will have
120 - 200 seconds [12],[13]. their IGVs fully open. So when a frequency drop occurs the
Alternatively, constant pressure mode involves throttling grid synchronized compressor slows, reducing air flow and
back the steam turbine governor valve so that it may provide increasing exhaust temperature. The temperature control takes
primary reserve. It has been suggested that this can be over and reduces fuel flow, reducing power output
achieved with no appreciable reduction in efficiency or ageing approximately in proportion to the square of the system
of the plant [14]. The extra reserve is of added benefit for frequency [12]. Again there is a critical frequency where the
small island power systems, or power systems with poor compressor slows too much and the turbine is tripped.
frequency control capability. In summary, the critical frequency depends on the loading
3)Inlet Guide Vanes of the machine, IGV operation and duration of the
At less than base load output in a gas turbine there is less disturbance. However, if the turbine is running at base load
fuel being burnt and therefore less heat in the exhaust. This is the critical frequency does not vary with IGV speed. If it is
not necessarily a problem for Open Cycle Gas Turbines running below base load the critical frequency depends on the
(OCGT), provided the fuel to air ratio is kept at a level to reserve available and more importantly the IGV speed [9].
maintain combustion and minimize emissions, but when
C. CCGT Model Representation
considering the steam section of a CCGT it is desirable to
maintain a high temperature in the Heat Recovery Steam Inspection of the individual CCGT model parameters, it
6

becomes apparent that the inertia of the new CCGT plant is problem to a small islanded power system. It is however
considerably higher than the plant that it is replacing. This is possible to add a supplementary control loop to a DFIG and
particularly visible between trace (b) and (c), where the final direct drive generator to simulate an inertial response by
three CCGT plant are added to the simulation. The initial rate extracting the energy from the rotor. It is thought that the
of change of frequency is much less severe, resulting in it not majority of new DFIG turbines will incorporate this feature in
falling as far. In actual fact, the additional CCGT units the future [16].
provide approximately 15% more stored energy than the Concerns had been raised about the possibility of all wind
conventional plant they replaced. The reason for this is mainly based generation collapsing instantaneously due to the wind
due to the large low pressure steam turbines employed in a effectively stopping. A separate study has shown that this
multi-shaft unit. would be extremely unlikely in NI provided the locations of
Examination of the gas turbine governor models used for the wind farms are well dispersed [17]. Nevertheless, it has
the simulation reveals that airflow from the compressor is been suggested that for 10% wind power generation the
assumed to be constant, which is a reasonable assumption for requirements for spinning-reserve margin and system ramping
a large stiff interconnected systems. However, for a base rates would have to be increased by approximately 25% and
loaded machine in a small island power system, the reduced 5%, respectively [18].
output due to the compressor slowing following a large To help overcome the problems outlined, changes to grid
frequency deviation, as previously discussed, can be codes to specifically cover wind based generation are
noticeable. In fact, as more CCGT units appear on the system, expected, such as those outlined for the RoI system [19].
the effect increases exponentially, as more base loaded plant Firstly, large wind farms will be forced to remain connected to
reduce output, resulting in a lower frequency, resulting in a the system during severe frequency excursions, where
lower output and so on. As the maximum output of the plant previously they were disconnected by their protection.
is dependent on system frequency, gas turbine output remains Secondly, wind farms, particularly large offshore farms
below rated for as long as the frequency is below 50 Hz [15]. connected to the transmission network may be requested to
If these effects are not correctly represented for a system provide primary frequency response by the TSO. The turbines
with a high percentage of CCGT plant, particularly when will therefore have to spill energy in order for there to be
frequency deviations below 49.5 Hz are not unusual, then energy to call on if the frequency drops.
optimistic frequency stability simulation results could occur. These changes in operating procedure may help to reduce
the effects that high wind power penetration may have on
D. Wind Turbine Generator (WTG) Technology
small isolated power systems. However, to avoid increasing
Although WTGs were not represented in this simulation, the likelihood of wind power playing a major part in causing
they are beginning to appear in sufficient numbers in the all system instability, the full effects of high numbers of WTGs
Ireland system that their effects will need to be considered. must be extensively researched. It is for this reason that in late
Electricity generation from fossil fuels is one of the main 2003, ESB National Grid (ESBNG), the TSO in the RoI, was
contributors to greenhouse gas emissions around the world. granted a temporary moratorium on new connections of wind
The Kyoto Protocol is an international agreement by farms until security and reliability concerns have been
industrialised countries to reduce emissions. This has lead to resolved [20].
many governments setting targets and forming initiatives to
promote renewable generation. Generating electricity from E. Further Stability Concerns
WTGs is by far the most advanced and economically viable Frequency stability is not an independent phenomenon.
method of meeting these targets, with the exception of hydro When one type of stability is compromised, other forms of
if the opportunities exist. The disadvantage of wind being that stability are often affected. Once the combined effects of high
at present, although it may provide an inertial response, they numbers of WTG and CCGT plant are combined, there is the
are not expected to respond to changes in frequency. Also, increased possibility of exciting sub-synchronous oscillations
extra spinning reserve must be carried to cover forecast errors between the interconnected systems. While the total wind
and wind variability. For this reason installing WTGs does not based generation output may remain relatively constant, the
displace the same amount of conventional thermal generation. power outputs of the geographically spaced individual wind
The three main types of WTG are fixed-speed induction farms will vary to a greater extent, with the possibility of
generator, variable-speed Doubly Fed Induction Generator oscillations occurring across the Island. Additional or re-
(DFIG), and a variable-speed direct drive WTG. tuning of existing Power System Stabilisers (PSS) should help
The variable speed generators are all or partly decoupled to alleviate the problem.
from the power system by ac-dc-ac converters. While the In this simulation, the event, caused by tripping the Moyle
variable speed WTGs offer an obvious advantage over the interconnector, introduced a disturbance without greatly
fixed speed versions, being able to operate more efficiently at affecting the power system parameters such as inertial
a wider range of wind speeds, decoupling the generators from response, frequency response, and voltage support (reactive
the grid means that they do not inherently provide an inertial injection and filters are tripped along with the interconnector).
response. As previously discussed, this can pose an added In simple terms, the interconnector is operated as a negative
7

load device. As the generating plant are the building blocks high efficiency, fast response and the ability to transport
for voltage control in a power system, an event initiated by energy as hydrogen make fuel cells an attractive possibility.
tripping of a large generator could also lead to a possible Ni-Cd Battery storage may also be an option. A recent
voltage stability problem. A synchronous compensator in NI, installation in Alaska is capable of maintaining an output of
and two Static Var Compensators (SVCs) in the RoI help to 40 MW for 15 minutes until other forms of generation can be
provide dynamic voltage control in the NIE / ESB system, started and synchronized [21]. As all of these forms of energy
with the majority provided by the rotating generating plant. storage include Voltage Source Converters, they are able to
Hence, if a large portion of this support is lost by the tripping operate as real and reactive power sources and sinks. The
of a generator, local voltage collapse could become an issue. controls permit rapid, and remote or fully automated
responses to various types of event, but the major drawback at
F. Methods for Improving Stability in the NIE /ESB System present being the initial cost.
There are a number of methods already in place in the There are a growing number of embedded generators within
Ireland system to help maintain stability. Turlough Hill, a 292 the distribution system, primarily used as peaking plant at
MW pumped storage facility in the RoI should always provide times of high demand when electricity costs are highest. With
a certain amount of primary reserve, and sufficient secondary a suitable centralised control system this previously untapped
and tertiary reserve until other generation can be dispatched. resource could be used the remainder of the time as secondary
For this purpose, there are numerous fast-start gas turbines or tertiary reserve to balance out wind or help restore
that can be brought on-line in a matter of minutes. Some frequency following a large generator trip.
conventional units have implemented fast wind down Currently, consumers have no limits, within reason, on the
procedures where instead of tripping a unit instantly, the unit amount of load they connect. This results in excessive
output is reduced to zero over 30 50 seconds, resulting in a amounts of non-essential load on the system. If this demand
much less severe frequency transient. Switching in of shunt could be separated from essential loads and centrally
reactors, to reduce voltage and therefore demand has also controlled, it would be a valuable source of cost effective
been used. primary, secondary and tertiary reserve. The loads could be
In the future these techniques may not be sufficient to
divided into different categories, depending on the period of
maintain stability and so a number of possible options are
time they can be interrupted for. Interruptible tariffs would
available, including steam turbine throttling, energy storage,
compensate the consumers for the inconvenience with a
HVDC modulation, and interruptible customers.
reserve payment, probably in the form of cheaper electricity.
Throttling back of the steam turbine sections of CCGT
plant is a viable option. This reserve can be used to mitigate Heating loads and air conditioning units are examples of the
the effects of reduced compressor speed on the gas turbine. types of load that can be interrupted for considerable lengths
As the exhaust temperature of the gas turbines should remain of time without obvious effects. The major cost in this
at maximum, the steam turbine can provide primary, approach would be the separation of essential and non-
secondary and continued tertiary reserve. In some cases, it is essential loads, although this would be considerably easier in
also possible to allow over-firing where the gas turbine new buildings.
temperature limit is temporarily raised enabling at least a
sustained output of power during a substantial frequency V. CONCLUSIONS
deviation. This is at the expense of increased wear on the This paper has highlighted some of the stability concerns
turbine and HRSG [12],[15]. when introducing large numbers of new generation
The Moyle HVDC link can, in theory be set to control the technology in the form of CCGTs and WTGs. Using the
frequency in the Ireland system, and it could maintain a 50 Hz Northern Ireland and interconnected Southern Ireland system
system during the majority of events, including periods of as a case study, the issue of frequency stability has been
high wind power penetration. This, however, is not
discussed. Frequency stability is dominated by governor
commercially viable at present. The Scottish and
response, and it is clearly important that simulation represents
interconnected England and Wales system is comparably
the true behaviour of the system. In some cases, there may
larger, and should be able to absorb a certain amount of
variation in the link. The amount allowed, possibly set blocks therefore be a need for tuning and modification of models for
of power import / export at certain frequencies, would have to various power system components. In particular the effect of
be decided after extensive simulation of the Scottish system. slowing of the compressor in a gas turbine during a frequency
Any variation from the link can only add to the stability of the drop should be included in the governor model, especially if
entire Ireland system. the system frequency is particularly variable.
Energy storage would be one of the most technologically As frequency stability becomes more of an issue,
advanced and long term solutions. Extending the principle of particularly in small island power systems, new and
a pumped storage site like Turlough Hill, more modern innovative control schemes can be introduced, maintaining the
examples using rapid, easily controlled power electronics can reliability and security that is demanded by consumers, while
help to avoid most types of instability. Fuel cell technology, permitting new and greener forms of generation.
where the energy is stored as hydrogen, may be a viable This paper is part of an ongoing study to determine the
option in the near future when the capital cost is reduced. A effects of new generation trends on the Northern Ireland, and
8

hence, Southern Ireland electricity networks. As new wind [7] B. Fox, D. Flynn, D. Morrow, S. Persaud, Operation of Power Systems
with Significant Wind Power Import, The BLOWING Network, available
farms and CCGT plant are currently under construction, from www.ee.qub.ac.uk/blowing/
solutions to the problems posed need to be implemented [8] P. Boyce, Gas Turbine Engineering Handbook, Second Edition, Gulf
within the next few years. Some of the most promising Professional Publishing, 2002
possible solutions are CCGT steam turbine throttling for [9] N. Kakimoto, K. Baba, Performance of Gas Turbine-Based Plants During
Frequency Drops, IEEE Transactions on Power Systems, Vol. 18, No.3,
reserve, and centrally controlled embedded generation and August 2003.
interruptible non essential load. Cost implications, [10] P. Pourbeik, The dependence of Gas Turbine Power Output on System
positioning, footprint, environmental impact and the Frequency and Ambient Conditions, Cigre Session 2002, 38-101
[11] North America Reliability Assessment 2003 2012, available from
comparative effectiveness of all these various solutions need www.nerc.com
to be thoroughly explored before investing in one or more. [12] Cigre Task Force 38-02-14, Analysis and modeling needs of power
Time domain simulation, and eigenanalysis are the systems under major frequency disturbances, January 1999.
[13] J. Shin, Y. Jeon, D. Maeng, J. Kim, S. Ro, Analysis of the dynamic
proposed methods of assessing the stability problems and the characteristics of a combined-cycle power plant, Energy, 27, 1085
possible solutions. 1098, 2002
This situation is not unique to the NIE / ESB system, but [14] B. Guzman, J. Vugdelija, Achieving a primary frequency response with
CCGT steam turbines, Modern Power Systems, November 2002.
applies to many small island systems around the world. The
[15] G. Lalor, M. OMalley, Frequency Control on an Island Power System
cause of the 1996 blackout in Malaysia was attributed to the with Increasing Proportions of Combined Cycle Gas Turbines, IEEE
effects of the gas turbine controllers. At the time Transactions on Power Systems,
approximately 67% of the generation originated from gas [16] J. Ekanayake, L. Holdsworth, N. Jenkins, Control of DFIG wind
turbines, Power Engineering Journal, Vol. 17, No. 1, pp 28-32, Feb
turbines or CCGTs [12]. Some 922 MW of generation was 2003.
initially lost due to a circuit breaker fault causing a frequency [17] S. Persaud, B. Fox, D. Flynn, Modeling the impact of wind power
excursion to 49.1 Hz (from a nominal of 50 Hz). A further fluctuations on the load following capability of an isolated thermal power
system, Wind Engineering Journal, Vol. 24, No. 6, pp 399-415, 2000
2143 MW of gas turbine / CCGT plant tripped out on exhaust [18] S. Persaud, B. Fox, D. Flynn, Effects of Large Scale Wind Power on
temperature limits, or were unable to sustain combustion due Total System Variability and Operation: Case Study of Northern Ireland,
to the decreased fuel flow. Load shedding of 1580 MW was Wind Engineering Journal, Vol. 27, No. 1, pp 3-20, 2003
[19] Frequency Issues for Wind Turbine Generators and Wind Farms, available
unsuccessful and a blackout occurred 16 seconds after the
from www.eirgrid.com.
initial event [12]. This event could be an early warning signal [20] The 2003 moratorium, available from www.eirgrid.com
for the US system. The Eastern and Western Interconnections [21] T. DeVries, J. McDowall, N. Umbricht, G. Linhofer, Cold Storage
have reported that over the last ten years the generation / load Battery Energy Storage System for Golden Valley Electric Association,
ABB Review, pp 38-43, January 2004, available from www.abb.com
imbalance required to produce a 0.1 Hz frequency deviation
has decreased by approximately 70 MW per year. The major
cause has been put down to the rising numbers of CCGTs on
the system [11]. While a failure on the Malaysian scale may VIII. BIOGRAPHIES
be unlikely at the present time, testing and tuning of gas Jonathan Horne received a B.Eng (Hons) degree in Electrical and
turbine controls could avoid similar incidents. Electronic Engineering from the Queens University of Belfast in 2002. He is
currently studying for a Ph.D. in the area of power system stability at the
Queen's University of Belfast.
VI. ACKNOWLEDGMENTS
Damian Flynn is a lecturer in Power Engineering at The Queens University
The authors gratefully acknowledge the contributions of of Belfast. His research interests involve an investigation of the effects of
embedded generation sources, especially renewables, on the operation of power
Michael Preston, Raymond Skillen, Leslie Bryans and Alan
systems. He is also interested in advanced modeling and control techniques
Kennedy at SONI, and Julia Ritchie at QUB. applied to power plant. He is a member of the IEEE.
Tim Littler is a lecturer in Power Systems, Software Engineering and
VII. REFERENCES Mathematics at The Queens University of Belfast. His research interests include
power system monitoring, protection systems, instrumentation, signal algorithms
and analysis, DSP, mathematics and software engineering. He is a member of
[1] P. Kundur, J. Paserba, V. Ajjarapu, G. Andersson, A. Bose, C. Canizares, the IEEE and PES.
N. Hatziargyrion, D. Hill, A. Stankovic, C. Taylor, T. Van Cutsem, V.
Vittal, "Definition and Classification of Power System Stability," IEEE
/CIGRE Joint Task Force on Stability Terms and Definitions, Electra, No.
208, pp. 75-79, June. 2003.
[2] L. Pereira, J. Undrill, D. Kosterev, D. Davies, S. Patterson, A New
Thermal Governor Modeling Approach in the WECC, IEEE
Transactions on Power Systems, Vol. 18, No.2, May 2003.
[3] National Grid Security and Quality of Supply Standard, Issue 2, available
from www.nationalgrid.com/uk
[4] Northern Ireland Electricity Seven Year Statement, available by request
from www.SONI.ltd.uk.
[5] Electricity Supply Board Seven Year Statement, available from
www.eirgird.com.
[6] P. Mangan, Operational Implications of the ESB /NIE Power System
Interconnection, ESB Operating Policy

Potrebbero piacerti anche