PRESUPUESTO SUBESTACIONES

RESUMEN GENERAL DE INVERSIONES

S.E. PARQUE TELECOMUNICA-


S.E. SOCABAYA PRESUPUESTO
ITEM DESCRIPCIN INDUSTRIAL CIONES Y SCADA
(S/.) TOTAL (S/.)
(S/.) (S/.)

A SUMINISTROS DE EQUIPOS Y MATERIALES 1,078,716.88 8,507,047.95 481,556.00 10,067,320.83


B TRANSPORTE DE EQUIPOS Y MATERIALES 52,400.00 119,900.00 25,600.00 197,900.00
C OBRAS CIVILES 63,066.77 322,496.24 385,563.01
D MONTAJE ELECTROMECANICO 157,830.95 524,402.93 17,321.64 699,555.52

E COSTO DIRECTO 1,352,014.60 9,473,847.12 524,477.64 11,350,339.36


RESUMEN GENERAL DEL PRESUPUESTO
LINEA DE TRANSMISION EN 138 KV SOCABAYA - PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS

LINEA 138 kV
REUBICACIONES DE S.E. PARQUE TELECOMUNICACIO-
SOCABAYA-PARQUE S.E. SOCABAYA
ITEM DESCRIPCION LNEAS 33 kV INDUSTRIAL NES Y SCADA COSTO TOTAL (S/.)
INDUSTRIAL (S/.)
(S/.) (S/.) (S/.)
(S/.)
1.1 SUMINISTRO DE MATERIALES 4,622,500.00 588,195.63 1,078,716.88 8,507,047.95 481,556.00 15,278,016.46

1.2 TRANSPORTE DE SUMINISTROS 346,687.50 44,114.67 52,400.00 119,900.00 25,600.00 588,702.17

1.4 OBRAS CIVILES 1,448,305.88 223,820.86 63,066.77 322,496.24 0.00 2,057,689.75

1.3 MONTAJE ELECTROMECANICO 444,572.76 114,452.05 157,830.95 524,402.93 17,321.64 1,258,580.33

A TOTAL COSTO DIRECTO 6,862,066.14 970,583.21 1,352,014.60 9,473,847.12 524,477.64 19,182,988.72

B GASTOS GENERALES (S/.) 529,118.73 74,839.52 104,250.85 730,507.38 40,441.31 1,479,157.79

C UTILIDADES (S/.) 10% (A) 686,206.61 97,058.32 135,201.46 947,384.71 52,447.76 1,918,298.87

D TOTAL GENERAL (S/.) NO INCLUYE IGV 8,077,391.48 1,142,481.05 1,591,466.91 11,151,739.21 617,366.71 22,580,445.38

E TOTAL GENERAL (S/.) MAS IGV 26,644,925.54


SUMINISTRO DE MATERIALES LINEA138 kV SOCABAYA-PARQUE INDUSTRIAL
(S/.)

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)

A SUMINISTRO DE MATERIALES 4,622,500.00

D COSTO DIRECTO (C.D.) 4,622,500.00


E GASTOS GENERALES 356,430.74
F UTILIDADES 1.00% 46,225.00
G VALORIZACION BRUTA FINAL 5,025,155.74

TRANSPORTE DE MATERIALES LINEA138 kV SOCABAYA-PARQUE INDUSTRIAL

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)

A TRANSPORTE DE MATERIALES 346,687.50

D COSTO DIRECTO (C.D.) 346,687.50


E GASTOS GENERALES 26,732.31
F UTILIDADES 1.00% 3,466.88
G VALORIZACION BRUTA FINAL 376,886.69

MONTAJE ELECTROMECANICO LINEA138 kV SOCABAYA-PARQUE INDUSTRIAL

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)

B MONTAJE ELECTROMECANICO 444,572.76

D COSTO DIRECTO (C.D.) 444,572.76


E GASTOS GENERALES 34,280.02
F UTILIDADES 1.00% 4,445.73
G VALORIZACION BRUTA FINAL 483,298.51

Mano de obra 37117.21


OBRAS CIVILES DE LINEA138 kV SOCABAYA-PARQUE INDUSTRIAL Equipo, Maquinaria 18856.14

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)

C OBRAS CIVILES 1,448,305.88


SUMINISTRO DE 4733.61 20,107.62 20,513.24
D COSTO DIRECTO (C.D.) 1,448,305.88 TRANSPORTE DE S 355.02 1,508.07 1,538.49
E GASTOS GENERALES 111,675.66
F UTILIDADES 1.00% 14,483.06 MONTAJE ELECT 4312.64 2,511.61 2,000.90
G VALORIZACION BRUTA FINAL 1,574,464.60 OBRAS CIVILES 1971.3 6187.67 9099.35
SUMINISTRO DE MATERIALES REUBICACION DE LINEA 33 SUMINISTRO DE MATERIALES REUBICACION DE LINEA 33
SUMINISTRO DE MATERIALES REUBICACIONES DE LNEAS 33 kV SUMINISTRO DE MATERIALES REUBICACION DE LINEA 33 kV
kV SOCABAYA - PARQUE INDUSTRIAL kV CHILINA -PARQUE INDUSTRIAL
(S/.) SOCABAYA -PAUCARPATA
(S/.) (S/.)
DESCRIPCIN DE TOTAL TOTAL TOTAL TOTAL
ITEM ITEM DESCRIPCIN DE PARTIDAS ITEM DESCRIPCIN DE PARTIDAS ITEM DESCRIPCIN DE PARTIDAS
PARTIDAS
SOLES (S/.) SOLES (S/.) SOLES (S/.) SOLES (S/.)
74639.2 A SUMINISTRO DE MATERIALES 588,195.63 588,195.63 A SUMINISTRO DE MATERIALES 61,389.47 A SUMINISTRO DE MATERIALES 260,772.84 A SUMINISTRO DE MATERIALES 266,033.32
D COSTO DIRECTO (C.D.) 588,195.63 588,195.63 D COSTO DIRECTO (C.D.) 61,389.47 D COSTO DIRECTO (C.D.) 260,772.84 D COSTO DIRECTO (C.D.) 266,033.32
E GASTOS GENERALES 45,354.46 45,354.47 E GASTOS GENERALES 4,733.61 E GASTOS GENERALES 20,107.62 E GASTOS GENERALES 20,513.24
F UTILIDADES 1.00% 5,881.96 5,881.95 F UTILIDADES 1.00% 613.89 F UTILIDADES 1.00% 2,607.73 F UTILIDADES 1.00% 2,660.33
G VALORIZACION BRUTA FINAL 639,432.05 639,432.05 G VALORIZACION BRUTA FINAL 66,736.97 G VALORIZACION BRUTA FINAL 283,488.19 G VALORIZACION BRUTA FINAL 289,206.89

TRANSPORTE DE MATERIALES REUBICACION DE LINEA 33 TRANSPORTE DE MATERIALES REUBICACION DE LINEA 33


TRANSPORTE DE MATERIALES REUBICACIONES DE LNEAS 33 kV TRANSPORTE DE MATERIALES REUBICACION DE LINEA 33 kV
kV SOCABAYA - PARQUE INDUSTRIAL kV CHILINA -PARQUE INDUSTRIAL
(S/.) SOCABAYA -PAUCARPATA
(S/.) (S/.)
DESCRIPCIN DE TOTAL TOTAL TOTAL TOTAL
ITEM ITEM DESCRIPCIN DE PARTIDAS ITEM DESCRIPCIN DE PARTIDAS ITEM DESCRIPCIN DE PARTIDAS
PARTIDAS
SOLES (S/.) SOLES (S/.) SOLES (S/.) SOLES (S/.)
A TRANSPORTE DE MATERIALES 44,114.67 44,114.67 A TRANSPORTE DE MATERIALES 4,604.21 A TRANSPORTE DE MATERIALES 19,557.96 A TRANSPORTE DE MATERIALES 19,952.50
D COSTO DIRECTO (C.D.) 44,114.67 44,114.67 D COSTO DIRECTO (C.D.) 4,604.21 D COSTO DIRECTO (C.D.) 19,557.96 D COSTO DIRECTO (C.D.) 19,952.50
E GASTOS GENERALES 3,401.58 3,401.58 E GASTOS GENERALES 355.02 E GASTOS GENERALES 1,508.07 E GASTOS GENERALES 1,538.49
F UTILIDADES 1.00% 441.15 441.15 F UTILIDADES 1.00% 46.04 F UTILIDADES 1.00% 195.58 F UTILIDADES 1.00% 199.53
G VALORIZACION BRUTA FINAL 47,957.40 47,957.40 G VALORIZACION BRUTA FINAL 5,005.27 G VALORIZACION BRUTA FINAL 21,261.61 G VALORIZACION BRUTA FINAL 21,690.52

MONTAJE ELECTROMECANICO REUBICACION DE LINEA 33 MONTAJE ELECTROMECANICO REUBICACION DE LINEA 33


MONTAJE ELECTROMECANICOREUBICACIONES DE LNEAS 33 kV MONTAJE ELECTROMECANICO REUBICACION DE LINEA 33
kV SOCABAYA - PARQUE INDUSTRIAL kV CHILINA -PARQUE INDUSTRIAL
(S/.) kV SOCABAYA -PAUCARPATA
(S/.) (S/.)
DESCRIPCIN DE TOTAL TOTAL TOTAL TOTAL
ITEM ITEM DESCRIPCIN DE PARTIDAS ITEM DESCRIPCIN DE PARTIDAS ITEM DESCRIPCIN DE PARTIDAS
PARTIDAS
SOLES (S/.) SOLES (S/.) SOLES (S/.) SOLES (S/.)
B MONTAJE ELECTROMECANICO 114,452.05 114,452.05 B MONTAJE ELECTROMECANICO 55,929.97 B MONTAJE ELECTROMECANICO 32,572.71 B MONTAJE ELECTROMECANICO 25,949.37
D COSTO DIRECTO (C.D.) 114,452.05 114,452.05 D COSTO DIRECTO (C.D.) 55,929.97 D COSTO DIRECTO (C.D.) 32,572.71 D COSTO DIRECTO (C.D.) 25,949.37
E GASTOS GENERALES 8,825.14 8,825.15 E GASTOS GENERALES 4,312.64 E GASTOS GENERALES 2,511.61 E GASTOS GENERALES 2,000.90
F UTILIDADES 1.00% 1,144.52 1,144.52 F UTILIDADES 1.00% 559.30 F UTILIDADES 1.00% 325.73 F UTILIDADES 1.00% 259.49
G VALORIZACION BRUTA FINAL 124,421.71 124,421.72 G VALORIZACION BRUTA FINAL 60,801.91 G VALORIZACION BRUTA FINAL 35,410.05 G VALORIZACION BRUTA FINAL 28,209.76

OBRAS CIVILES REUBICACION DE LINEA 33 kV SOCABAYA - OBRAS CIVILES REUBICACION DE LINEA 33 kV CHILINA
OBRAS CIVILES DE REUBICACIONES DE LNEAS 33 kV OBRAS CIVILES REUBICACION DE LINEA 33 kV SOCABAYA
PARQUE INDUSTRIAL -PARQUE INDUSTRIAL
(S/.) -PAUCARPATA
(S/.) (S/.)
DESCRIPCIN DE TOTAL TOTAL TOTAL TOTAL
ITEM ITEM DESCRIPCIN DE PARTIDAS ITEM DESCRIPCIN DE PARTIDAS ITEM DESCRIPCIN DE PARTIDAS
PARTIDAS
SOLES (S/.) SOLES (S/.) SOLES (S/.) SOLES (S/.)
C OBRAS CIVILES 223,820.86 223,820.86 C OBRAS CIVILES 25,565.55 C OBRAS CIVILES 80,247.07 C OBRAS CIVILES 118,008.24
D COSTO DIRECTO (C.D.) 223,820.86 223,820.86 D COSTO DIRECTO (C.D.) 25,565.55 D COSTO DIRECTO (C.D.) 80,247.07 D COSTO DIRECTO (C.D.) 118,008.24
E GASTOS GENERALES 17,258.33 17,258.32 E GASTOS GENERALES 1,971.30 E GASTOS GENERALES 6,187.67 E GASTOS GENERALES 9,099.35
F UTILIDADES 1.00% 2,238.21 2,238.21 F UTILIDADES 1.00% 255.66 F UTILIDADES 1.00% 802.47 F UTILIDADES 1.00% 1,180.08
G VALORIZACION BRUTA FINAL 243,317.40 243,317.39 G VALORIZACION BRUTA FINAL 27,792.51 G VALORIZACION BRUTA FINAL 87,237.21 G VALORIZACION BRUTA FINAL 128,287.67
SUMINISTRO DE MATERIALES S.E. SOCABAYA

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
A SUMINISTRO DE MATERIALES 1,078,716.88
D COSTO DIRECTO (C.D.) 1,078,716.88
E GASTOS GENERALES 83,177.47
F UTILIDADES 1.00% 10,787.17
G VALORIZACION BRUTA FINAL 1,172,681.52

TRANSPORTE DE MATERIALES S.E. SOCABAYA

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
A TRANSPORTE DE MATERIALES 52,400.00
D COSTO DIRECTO (C.D.) 52,400.00
E GASTOS GENERALES 4,040.45
F UTILIDADES 1.00% 524.00
G VALORIZACION BRUTA FINAL 56,964.45

MONTAJE ELECTROMECANICO S.E. SOCABAYA

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
B MONTAJE ELECTROMECANICO 157,830.95
D COSTO DIRECTO (C.D.) 157,830.95
E GASTOS GENERALES 12,169.99
F UTILIDADES 1.00% 1,578.31
G VALORIZACION BRUTA FINAL 171,579.25

OBRAS CIVILES S.E. SOCABAYA

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
C OBRAS CIVILES 63,066.77
D COSTO DIRECTO (C.D.) 63,066.77
E GASTOS GENERALES 4,862.94
F UTILIDADES 1.00% 630.67
G VALORIZACION BRUTA FINAL 68,560.38
SUMINISTRO DE MATERIALES S.E. PARQUE INDUSTRIAL

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
A SUMINISTRO DE MATERIALES 8,507,047.95
D COSTO DIRECTO (C.D.) 8,507,047.95
E GASTOS GENERALES 655,959.64
F UTILIDADES 1.00% 85,070.48
G VALORIZACION BRUTA FINAL 9,248,078.07

TRANSPORTE DE MATERIALES S.E. PARQUE INDUSTRIAL

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
A TRANSPORTE DE MATERIALES 119,900.00
D COSTO DIRECTO (C.D.) 119,900.00
E GASTOS GENERALES 9,245.22
F UTILIDADES 1.00% 1,199.00
G VALORIZACION BRUTA FINAL 130,344.22

MONTAJE ELECTROMECANICO S.E. PARQUE INDUSTRIAL

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
B MONTAJE ELECTROMECANICO 524,402.93
D COSTO DIRECTO (C.D.) 524,402.93
E GASTOS GENERALES 40,435.55
F UTILIDADES 1.00% 5,244.03
G VALORIZACION BRUTA FINAL 570,082.51

OBRAS CIVILES S.E. PARQUE INDUSTRIAL

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
C OBRAS CIVILES 322,496.24
D COSTO DIRECTO (C.D.) 322,496.24
E GASTOS GENERALES 24,866.97
F UTILIDADES 1.00% 3,224.96
G VALORIZACION BRUTA FINAL 350,588.17
SUMINISTRO DE MATERIALES TELECOMUNICACIO-NES Y SCADA

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
A SUMINISTRO DE MATERIALES 481,556.00
D COSTO DIRECTO (C.D.) 481,556.00
E GASTOS GENERALES 37,131.72
F UTILIDADES 1.00% 4,815.56
G VALORIZACION BRUTA FINAL 523,503.28

TRANSPORTE DE MATERIALES TELECOMUNICACIO-NES Y SCADA

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
A TRANSPORTE DE MATERIALES 25,600.00
D COSTO DIRECTO (C.D.) 25,600.00
E GASTOS GENERALES 1,973.96
F UTILIDADES 1.00% 256.00
G VALORIZACION BRUTA FINAL 27,829.96

MONTAJE ELECTROMECANICO TELECOMUNICACIO-NES Y SCADA

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
B MONTAJE ELECTROMECANICO 17,321.64
D COSTO DIRECTO (C.D.) 17,321.64
E GASTOS GENERALES 1,335.63
F UTILIDADES 1.00% 173.22
G VALORIZACION BRUTA FINAL 18,830.49

OBRAS CIVILES TELECOMUNICACIO-NES Y SCADA

DESCRIPCIN DE TOTAL
ITEM
PARTIDAS
SOLES (S/.)
C OBRAS CIVILES 0.00
D COSTO DIRECTO (C.D.) 0.00
E GASTOS GENERALES 0.00
F UTILIDADES 1.00% 0.00
G VALORIZACION BRUTA FINAL 0.00
ANLISIS DE COSTOS UNITARIOS
GASTOS GENERALES DIRECTO E INDIRECTOS DE OBRA
LINEA EN 138KV
SOCABAYA -PARQUE
PROYECTO:
INDUSTRIAL Y S.E.
ASOCIADAS

Departamento : AREQUI meses


Plazo de Obra : 15.5 meses /)

1.0 GASTOS GENERALES VARIABLES-GG DIRECTOS

1.1 Personal Profesional Principal


Descripcin Unidad Parcial
(S/.)
Ingeniero Gerente de la Obra Und. 193 750.00 ###
Ingeniero Residente de la Obra Und. 155 000.00 ###
Ing Asistente en Lneas de Transmisin Und. 39 200.00 ###
Ing Asistente en Subestaciones de Potencia Und. 86 800.00 ###
Ing de Seguridad Und. 93 000.00 ###

PARCIAL 1,1 374 000.00


Nota: El sueldo considerado por cada profesional incluye impuestos y leyes sociales

1.2 Personal de Auxiliar y Apoyo


Descripcin Und. Parcial
(S/.)
Administrador Und. 124 000.00 ###
Dibujante en Autocad y otros programas Und. 83 700.00 ###
Almacenero Und. 74 400.00 ###
Chofer Und. 93 000.00 ###
Seguridad en obra (Guardian) Und. 44 640.00 ###

PARCIAL 1,2 419 740.00


Nota: El sueldo considerado por trabajador incluye impuestos y leyes sociales

1.3 Hospedajes, Oficina, Campamentos, alimentacin y movilidad del personal principal, auxiliar y apoyo
Descripcin Und. Parcial
(S/.)
Alquiler de Oficina en Obra (Incluye agua y luz) Glb/mes 46 500.00
Alquiler de casas almacn (incluye agua y luz) Glb/mes 24 800.00
Comunicaciones: telefono, fax, internet, radio, etc. Glb/mes 16 740.00
Alimentacin Glb/mes 141 360.00
Pasajes Glb/mes 111 600.00

PARCIAL 1,3 341 000.00

1.4 Mobiliario, equipo, material de oficina y otros


Descripcin Und. Parcial
(S/.)
Mobiliario de oficina Glb/mes 1 395.00
Computadora Glb/mes 2 790.00
Impresora Glb/mes 930.00
tiles de Oficina Glb/mes 26 970.00
Camioneta pick up Glb/mes 33 131.25
Combustible Glb/mes 55 800.00
###
Mantenimiento Glb/mes 25 575.00

PARCIAL 1,4 146 591.25


Nota: El desgaste de los equipos ha sido calculado considerando una depreciacin lneal en 36 meses de vida til.
El desgaste de las camionetas ha sido calculado considerando una depreciacin lneal en 120 meses de vida til.

1.5 Gastos financieros y otros gastos


Descripcin Und. Parcial
S/.
Cartas fianza mes 8 137.19
Seguros Gbl 3 484.32

PARCIAL 1,5 11 621.51


PARCIAL GASTOS GENERALES VARIABLES (1) 1292 952.76
ANLISIS DE COSTOS UNITARIOS
GASTOS GENERALES DIRECTO E INDIRECTOS DE OBRA
LINEA EN 138KV
SOCABAYA -PARQUE
PROYECTO:
INDUSTRIAL Y S.E.
ASOCIADAS

Departamento : AREQUI meses


Plazo de Obra : 15.5 meses /)

2.0 GASTOS GENERALES FIJOS INDIRECTOS


2.1 Personal en la cede central de la Empresa
Descripcin Und. Total
S/.
Gerente Und. 58 125.00 ###
Ingeniero-Supervisin Tcnica Empresa Und. 46 500.00 ###
Contador Und. 18 600.00 ###
Auxiliar Contabilidad Und. 11 625.00 ###
Secretaria Und. 4 650.00 ###
Chofer Und. 6 200.00 ###
PARCIAL 2,1 145 700.00

2.2 Gastos de oficina principal y gastos varios


Descripcin Und. Total
S/.
Oficina (Incluye agua y luz) Und. 15 500.00
Comunicaciones: telef., fax, Internet, radio Glob 6 200.00
Material y Equipos de Oficina Glob 4 650.00
Mantenimiento y limpieza Glob 2 530.47
PARCIAL 2,2 28 880.47

2.3 Gastos de preparacin de oferta e imprevistos


Descripcin Und. Parcial
S/.
Elaboracin de propuesta Gbl 2 906.14
Imprevistos de obra y personal en oficina central Gbl 8 718.42
PARCIAL 2,3 11 624.56
PARCIAL GASTOS GENERALES FIJOS (2) 186 205.03

TOTAL GASTOS GENERALES (1)+(2) 1479 157.79

3.0 RESUMEN Costo Total US$


(S/.)
GASTOS GENERALES VARIABLES DIRECTOS ###
1292 952.76
GASTOS GENERALES FIJOS INDIRECTOS ###
186 205.03
TOTAL GASTOS GENERALES (1)+(2) ###
1479 157.79
SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 1.0 INGENIERA DE DETALLE DE LAS OBRAS ELECTROMECNICAS Y OBRAS CIVILES SEGN DETALLE
DESCRIPCIN:

1.01 INGENIERA DE DETALLE DE LAS OBRAS ELECTROMECNICAS Y OBRAS CIVILES (CONEXIONADO, PUESTA A TIERRA, COORDINACIN DE LAS PROTECCIONES,
SISTEMA DE COMUNICACIONES, ETC) NECESARIAS PARA EL CORRECTO DESARROLLO DE LA OBRA.

RENDIMIENTO : 0.011 Glb/da UNIDAD: Glb

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 192.50
Material consumible EST 1.00 192.50 192.50 192.500

MANO DE OBRA 71,307.50


Ingeniero electricista 0.50 h-h 349.72 52.50 18,360.20
Ingeniero de coordinacin de protecciones 0.50 h-h 349.72 85.00 29,726.03
Ingeniero especialista en cableado 0.15 h-h 104.92 50.00 5,245.77
Ingeniero de telecomunicaciones 0.15 h-h 104.92 80.00 8,393.23
Ingeniero Civil 0.10 h-h 69.94 80.00 5,595.49
Dibujante 0.50 h-h 349.72 11.40 3,986.79

MAQUINARIAS Y EQUIPOS 0.00

HERRAMIENTAS 0.00

COSTO DIRECTO TOTAL S/. 71,500.00

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.01 TRANSFORMADOR DE POTENCIA 138/33 KV 65MVA ONAN 80 MVA ONAF

RENDIMIENTO : 0.040 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 957.83
Material consumible EST 1.00 192.50 192.50 192.500
Pinza multimtrica Un. 1.00 1.93 1.93 1.925
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Escalera de aluminio de 6 m H-E 1.00 13.20 13.20 13.200
Petrleo gln 80.00 9.35 748.00 9.350

MANO DE OBRA 37,710.00


Ingeniero de seguridad 0.10 h-h 20.00 52.50 1,050.00 52.500
Capataz en trabajos elctricos 1.00 h-h 200.00 20.45 4,089.60 20.448
Operario en trabajos elctricos 2.00 h-h 400.00 17.24 6,897.60 17.244
Oficial en trabajos elctricos 2.00 h-h 400.00 15.13 6,052.80 15.132
Pen 4.00 h-h 800.00 11.40 9,120.00 11.400
Ingeniero electricista 1.00 h-h 200.00 52.50 10,500.00 52.500

MAQUINARIAS Y EQUIPOS 87,428.40


Prensa Hidrulica 0.50 h-m 100.00 5.50 550.00 5.500
Estuche de herramientas para mecnico 0.50 h-m 100.00 1.32 132.00 1.320
Camin gra de 5 TON 1.00 h-m 200.00 173.25 34,650.00 173.250
Camioneta pick up 4 x 2 d.cab. 1.00 h-m 200.00 45.42 9,084.00 45.420
Tirfor de 3 TON 1.00 h-m 200.00 2.88 576.40 2.882
Equipo de tratamiento de aceite 1.80 h-m 360.00 5.50 1,980.00 5.500
Espintermetro 1.00 h-m 200.00 38.50 7,700.00 38.500
Prtiga elctrica para montaje de transformadores 1.00 h-m 200.00 6.60 1,320.00 6.600
Equipo de medicin de humedad 0.10 h-m 20.00 3.30 66.00 3.300
Grupo Electrgeno de 50 kW 1.50 h-m 300.00 98.90 29,670.00 98.900
Megger 1.00 h-m 200.00 5.50 1,100.00 5.500
Taladro elctrico 1.00 h-m 200.00 3.00 600.00 3.000

HERRAMIENTAS 1,885.50
Herramientas manuales y equipos de proteccin % m-o 5.00 37,710.00 1,885.50

COSTO DIRECTO TOTAL S/. 127,981.73

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2,02 INTERRUPTOR TANQUE MUERTO 145 kV, 2000 A, 750 kV-BIL

RENDIMIENTO : 0.100 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 622.05
Material consumible EST 1.00 192.50 192.50 192.500
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Escalera de aluminio de 6 m H-E 0.50 13.20 6.60 13.200
Petrleo gln 45.00 9.35 420.75 9.350

MANO DE OBRA 9,152.40


Ingeniero de seguridad 0.10 h-h 8.00 52.50 420.00 52.500
Capataz en trabajos elctricos 1.00 h-h 80.00 20.45 1,635.84 20.448
Oficial en trabajos elctricos 1.00 h-h 80.00 15.13 1,210.56 15.132
Pen 3.00 h-h 240.00 11.40 2,736.00 11.400
Ingeniero electricista 0.75 h-h 60.00 52.50 3,150.00 52.500

MAQUINARIAS Y EQUIPOS 4,829.00


Estuche de herramientas para mecnico 1.00 h-m 80.00 1.32 105.60 1.320
Camin gra de 5 TON 0.25 h-m 20.00 173.25 3,465.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.25 h-m 20.00 45.42 908.40 45.420
Torqumetro 0.50 h-m 40.00 2.75 110.00 2.750
Taladro elctrico 1.00 h-m 80.00 3.00 240.00 3.000

HERRAMIENTAS 457.62
Herramientas manuales y equipos de proteccin % m-o 5.00 9,152.40 457.62

COSTO DIRECTO TOTAL S/. 15,061.07

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.03 SECCIONADOR DE LNEA DOBLE APERTURA 170 KV

RENDIMIENTO : 0.100 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 290.95
Material consumible EST 1.00 192.50 192.50 192.500
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 10.00 9.35 93.50 9.350

MANO DE OBRA 9,124.80


Ingeniero de seguridad 0.10 h-h 8.00 52.50 420.00 52.500
Capataz en trabajos elctricos 0.50 h-h 40.00 0.00 0.00
Operario en trabajos elctricos 2.00 h-h 160.00 20.45 3,271.68 20.448
Oficial en trabajos elctricos 2.00 h-h 160.00 15.13 2,421.12 15.132
Pen 1.00 h-h 80.00 11.40 912.00 11.400
Ingeniero electricista 0.50 h-h 40.00 52.50 2,100.00 52.500

MAQUINARIAS Y EQUIPOS 9,180.40


Estuche de herramientas para mecnico 1.00 h-m 80.00 1.32 105.60 1.320
Camin gra de 5 TON 0.50 h-m 40.00 173.25 6,930.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 40.00 45.42 1,816.80 45.420
Torqumetro 0.40 h-m 32.00 2.75 88.00 2.750
Taladro elctrico 1.00 h-m 80.00 3.00 240.00 3.000

HERRAMIENTAS 456.24
Herramientas manuales y equipos de proteccin % m-o 5.00 9,124.80 456.24

COSTO DIRECTO TOTAL S/. 19,052.39

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z CONSULTORES ASOCIADOS S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.04 TRANSFORMADORES DE TENSIN

RENDIMIENTO : 1.000 Un./da UNIDAD: Un.

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL
MATERIALES 174.90
Material consumible EST 0.50 192.50 96.25 192.500
Mesa de trabajo Pza. 0.50 2.20 1.10 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 8.00 9.35 74.80 9.350

MANO DE OBRA 663.89


Ingeniero de seguridad 0.10 h-h 0.80 52.50 42.00 52.500
Capataz en trabajos elctricos 1.00 h-h 8.00 20.45 163.58 20.448
Operario en trabajos elctricos 2.00 h-h 16.00 17.24 275.90 17.244
Pen 2.00 h-h 16.00 11.40 182.40 11.400

MAQUINARIAS Y EQUIPOS 809.56


Estuche de herramientas para mecnico 1.00 h-m 8.00 1.32 10.56 1.320
Camin gra de 5 TON 0.50 h-m 4.00 173.25 693.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 4.00 15.00 60.00 45.420
Torqumetro 1.00 h-m 8.00 2.75 22.00 2.750
Taladro elctrico 1.00 h-m 8.00 3.00 24.00 3.000

HERRAMIENTAS 33.19
Herramientas manuales y equipos de proteccin % m-o 5.00 663.89 33.19

COSTO DIRECTO TOTAL S/. 1,681.54

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.05 TRAMPA DE ONDA PORTADORA 0,5 mH, Rb 600 ohm, 1000 A, 31,5 kA

RENDIMIENTO : 1.000 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 156.20
Material consumible EST 0.50 192.50 96.25 192.500
Mesa de trabajo Pza. 0.50 2.20 1.10 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 6.00 9.35 56.10 9.350

MANO DE OBRA 525.94


Ingeniero de seguridad 0.10 h-h 0.80 52.50 42.00 52.500
Capataz en trabajos elctricos 1.00 h-h 8.00 20.45 163.58 20.448
Operario en trabajos elctricos 1.00 h-h 8.00 17.24 137.95 17.244
Pen 2.00 h-h 16.00 11.40 182.40 11.400

MAQUINARIAS Y EQUIPOS 493.90


Estuche de herramientas para mecnico 1.00 h-m 8.00 1.32 10.56 1.320
Camin gra de 5 TON 0.25 h-m 2.00 173.25 346.50 173.250
Camioneta pick up 4 x 2 d.cab. 0.25 h-m 2.00 45.42 90.84 45.420
Torqumetro 1.00 h-m 8.00 2.75 22.00 2.750
Taladro elctrico 1.00 h-m 8.00 3.00 24.00 3.000

HERRAMIENTAS 26.30
Herramientas manuales y equipos de proteccin % m-o 5.00 525.94 26.30

COSTO DIRECTO TOTAL S/. 1,202.34

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.06 PARARRAYOS DE XIDO DE ZINC CON CONTADOR DE DESCARGA 120 kV, 10kA

RENDIMIENTO : 2.000 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 174.90
Material consumible EST 0.50 192.50 96.25 192.500
Mesa de trabajo Pza. 0.50 2.20 1.10 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 8.00 9.35 74.80 9.350

MANO DE OBRA 331.94


Ingeniero de seguridad 0.10 h-h 0.40 52.50 21.00 52.500

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
Capataz en trabajos elctricos 1.00 h-h 4.00 20.45 81.79 20.448
Operario en trabajos elctricos 2.00 h-h 8.00 17.24 137.95 17.244
Pen 2.00 h-h 8.00 11.40 91.20 11.400

MAQUINARIAS Y EQUIPOS 420.20


Estuche de herramientas para mecnico 1.00 h-m 4.00 1.32 5.28 1.320
Camin gra de 5 TON 0.50 h-m 2.00 173.25 346.50 173.250
Camioneta pick up 4 x 2 d.cab. 0.25 h-m 1.00 45.42 45.42 45.420
Torqumetro 1.00 h-m 4.00 2.75 11.00 2.750
Taladro elctrico 1.00 h-m 4.00 3.00 12.00 3.000

HERRAMIENTAS 16.60
Herramientas manuales y equipos de proteccin % m-o 5.00 331.94 16.60

COSTO DIRECTO TOTAL S/. 943.64

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.07 PRTICOS METLICOS 138 KV

RENDIMIENTO : 0.190 Glb./da UNIDAD: Glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 300.99
Material consumible EST 0.10 192.50 19.25 192.500
Mesa de trabajo Pza. 0.25 2.20 0.55 2.200
Escalera de madera de 4 m H-E 0.25 2.75 0.69 2.750
Petrleo gln 30.00 9.35 280.50 9.350

MANO DE OBRA 5,393.68


Ingeniero de seguridad 0.10 h-h 4.21 52.50 221.05 52.500
Capataz en trabajos elctricos 1.00 h-h 42.11 20.45 860.97 20.448
Operario en trabajos elctricos 2.00 h-h 84.21 17.24 1,452.13 17.244
Oficial en trabajos elctricos 2.00 h-h 84.21 15.13 1,274.27 15.132
Pen 1.00 h-h 42.11 11.40 480.00 11.400
Ingeniero electricista 0.50 h-h 21.05 52.50 1,105.26 52.500

MAQUINARIAS Y EQUIPOS 5,260.21


Estuche de herramientas para mecnico 0.50 h-m 21.05 1.32 27.79 1.320
Camin gra de 5 TON 0.50 h-m 21.05 173.25 3,647.37 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 21.05 45.42 956.21 45.420
Equipo de corte y soldadura 0.50 h-m 21.05 2.75 57.89 2.750
Esmeril 0.50 h-m 21.05 1.32 27.79 1.320
Mquina soldadora 0.50 h-m 21.05 8.80 185.26 8.800
Torqumetro 2.00 h-m 84.21 2.75 231.58 2.750
Taladro elctrico 1.00 h-m 42.11 3.00 126.32 3.000

HERRAMIENTAS 269.68
Herramientas manuales y equipos de proteccin % m-o 5.00 5,393.68 269.68

COSTO DIRECTO TOTAL S/. 11,224.56

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 3.00 MONTAJE DE EQUIPOS Y MATERIALES 33 kV


DESCRIPCIN: 3.01 PARARRAYOS OXIDO DE ZINC CON CONTADOR DE DESCARGA 36 kV, 10kA

RENDIMIENTO : 4.000 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 49.36
Material consumible EST 0.25 192.50 48.13 192.500
Mesa de trabajo Pza. 0.25 2.20 0.55 2.200
Escalera de madera de 4 m H-E 0.25 2.75 0.69 2.750

MANO DE OBRA 67.79


Ingeniero de seguridad 0.10 h-h 0.20 52.50 10.50 52.500
Operario en trabajos elctricos 1.00 h-h 2.00 17.24 34.49 17.244
Pen 1.00 h-h 2.00 11.40 22.80 11.400

MAQUINARIAS Y EQUIPOS 4.32


Estuche de herramientas para mecnico 0.50 h-m 1.00 1.32 1.32 1.320
Taladro elctrico 0.50 h-m 1.00 3.00 3.00 3.000

HERRAMIENTAS 3.39
Herramientas manuales y equipos de proteccin % m-o 5.00 67.79 3.39

COSTO DIRECTO TOTAL S/. 124.86

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 3.00 MONTAJE DE EQUIPOS Y MATERIALES 33 kV


DESCRIPCIN: 3.02 CELDA METAL-CLAD DE LLEGADA DE TRANSFORMADOR EN 36 KV
3.03 CELDA METAL-CLAD DE LLEGADA DE TRANSFORMADOR EN 36 KV
3.04 CELDA METAL-CLAD DE LLEGADA EN 36 KV
3.05 CELDA METAL-CLAD DE SALIDA EN 36 KV
RENDIMIENTO : 0.190 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 664.13
Material consumible EST 1.00 192.50 192.50 192.500
Pinza multimtrica Un. 1.00 1.93 1.93 1.925
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Petrleo gln 50.00 9.35 467.50 9.350

MANO DE OBRA 4,567.71


Ingeniero de seguridad 0.10 h-h 4.21 52.50 221.05 52.500
Capataz en trabajos elctricos 0.50 h-h 21.05 20.45 430.48 20.448
Operario en trabajos elctricos 2.00 h-h 84.21 17.24 1,452.13 17.244
Oficial en trabajos elctricos 3.00 h-h 126.32 15.13 1,911.41 15.132
Ingeniero electricista 0.25 h-h 10.53 52.50 552.63 52.500

MAQUINARIAS Y EQUIPOS 4,953.89


Estuche de herramientas para mecnico 1.00 h-m 42.11 1.32 55.58 1.320
Camin gra de 5 TON 0.50 h-m 21.05 173.25 3,647.37 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 21.05 45.42 956.21 45.420
Megger 1.00 h-m 42.11 5.50 231.58 5.500
Taladro elctrico 0.50 h-m 21.05 3.00 63.16 3.000

HERRAMIENTAS 228.39
Herramientas manuales y equipos de proteccin % m-o 5.00 4,567.71 228.39

COSTO DIRECTO TOTAL S/. 10,414.12

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 4.00 MONTAJE DE CABLES DE ENERGA, CONTROL Y TERMINALES


DESCRIPCIN: 4.01 CABLE DE ENERGA N2XSY 35 KV 1X400 MM2
4.02 CABLE DE ENERGA N2XSY 35 KV 1X240 MM2
4.03 CABLE DE ENERGA N2XSY 35 KV 1X120 MM2
4.04CABLES DE CONTROL, PROTECCIN Y MEDICION
RENDIMIENTO : 0.090 global/da UNIDAD: glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 66.70
Material consumible EST 0.10 192.50 19.25 192.500
Pinza multimtrica Un. 0.25 1.93 0.48 1.925
Mesa de trabajo Pza. 0.10 2.20 0.22 2.200
Petrleo gln 5.00 9.35 46.75 9.350

MANO DE OBRA 8,647.73


Ingeniero de seguridad 0.10 h-h 8.89 52.50 466.67 52.500
Capataz en trabajos elctricos 0.50 h-h 44.44 20.45 908.80 20.448
Operario en trabajos elctricos 2.00 h-h 177.78 17.24 3,065.60 17.244
Pen 3.00 h-h 266.67 11.40 3,040.00 11.400
Ingeniero electricista 0.25 h-h 22.22 52.50 1,166.67 52.500

MAQUINARIAS Y EQUIPOS 2,714.84


Estuche de herramientas para mecnico 0.25 h-m 22.22 1.32 29.33 1.320
Camin gra de 5 TON 0.10 h-m 8.89 173.25 1,540.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 8.89 45.42 403.73 45.420
Caballete alzabobina 0.10 h-m 8.89 62.20 552.89 62.200
Megger 0.25 h-m 22.22 5.50 122.22 5.500
Taladro elctrico 0.25 h-m 22.22 3.00 66.67 3.000

HERRAMIENTAS 432.39
Herramientas manuales y equipos de proteccin % m-o 5.00 8,647.73 432.39

COSTO DIRECTO TOTAL S/. 11,861.66

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 4.00 MONTAJE DE CABLES DE ENERGA, CONTROL Y TERMINALES


DESCRIPCIN: 4.05 CONJUNTO DE TERMINALES TERMOCONTRAIBLES PARA CABLE DE 300mm; 35kV (3unidades)
4.06 CONJUNTO DE TERMINALES TERMOCONTRAIBLES PARA CABLE DE240mm; 35kV (3unidades)
4.07 CONJUNTO DE TERMINALES TERMOCONTRAIBLES PARA CABLE DE 120mm; 35kV (3 unidades)
RENDIMIENTO : 3.000 Cjto./da UNIDAD: Cjto

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 19.95
Material consumible EST 0.10 192.50 19.25 192.500
Pinza multimtrica Un. 0.25 1.93 0.48 1.925
Mesa de trabajo Pza. 0.10 2.20 0.22 2.200

MANO DE OBRA 291.30


Ingeniero de seguridad 0.10 h-h 0.27 52.50 14.00 52.500
Capataz en trabajos elctricos 1.00 h-h 2.67 20.45 54.53 20.448
Operario en trabajos elctricos 2.00 h-h 5.33 17.24 91.97 17.244
Pen 2.00 h-h 5.33 11.40 60.80 11.400
Ingeniero electricista 0.50 h-h 1.33 52.50 70.00 52.500

MAQUINARIAS Y EQUIPOS 54.56


Estuche de herramientas para mecnico 0.50 h-m 1.33 1.32 1.76 1.320
Caballete alzabobina 0.25 h-m 0.67 62.20 41.47 62.200
Megger 0.50 h-m 1.33 5.50 7.33 5.500
Taladro elctrico 0.50 h-m 1.33 3.00 4.00 3.000

HERRAMIENTAS 14.57
Herramientas manuales y equipos de proteccin % m-o 5.00 291.300 14.57

COSTO DIRECTO TOTAL S/. 380.38

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 5.00 DESMONTAJE TABLEROS EXISTENTES


DESCRIPCIN: 5.01 TABLEROS: REGULADOR DE TENSIN, TABLERO RTU, TABLERO DE MEDICIN, TABLERO DE COMUNICACIN,
TABLERO DE SSAA, TABLERO RECTIFICADOR
RENDIMIENTO : 0.500 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 243.38
Material consumible EST 1.00 192.50 192.50 192.500
Pinza multimtrica Un. 1.00 1.93 1.93 1.925
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Petrleo gln 5.00 9.35 46.75 9.350

MANO DE OBRA 1,493.62


Ingeniero de seguridad 0.10 h-h 1.60 52.50 84.00 52.500
Capataz en trabajos elctricos 0.50 h-h 8.00 20.45 163.58 20.448
Operario en trabajos elctricos 2.00 h-h 32.00 17.24 551.81 17.244
Oficial en trabajos elctricos 2.00 h-h 32.00 15.13 484.22 15.132
Ingeniero electricista 0.25 h-h 4.00 52.50 210.00 52.500

MAQUINARIAS Y EQUIPOS 503.00


Estuche de herramientas para mecnico 1.00 h-m 16.00 1.32 21.12 1.320
Camin gra de 5 TON 0.10 h-m 1.60 173.25 277.20 173.250
Camioneta pick up 4 x 2 d.cab. 0.25 h-m 4.00 45.42 181.68 45.420
Equipo de corte y soldadura 0.25 h-m 4.00 2.75 11.00 2.750
Megger 0.25 h-m 4.00 0.00 0.00 0.000
Taladro elctrico 0.25 h-m 4.00 3.00 12.00 3.000

HERRAMIENTAS 74.68
Herramientas manuales y equipos de proteccin % m-o 5.00 1,493.62 74.68

COSTO DIRECTO TOTAL S/. 2,314.68

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 6.00 TABLEROS DE CONTROL, PROTECCIN Y MEDICIN


DESCRIPCIN: 6.01 Tableros existentes
6.02 Tablero de control, proteccin, medicin y controlador de baha de la Lnea 138 kV
6.03 Tablero de equipos registradores de fallas para la Lnea 138 kV

RENDIMIENTO : 0.250 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 243.38
Material consumible EST 1.00 192.50 192.50 192.500
Pinza multimtrica Un. 1.00 1.93 1.93 1.925
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Petrleo gln 5.00 9.35 46.75 9.350

MANO DE OBRA 2,987.23


Ingeniero de seguridad 0.10 h-h 3.20 52.50 168.00 52.500
Capataz en trabajos elctricos 0.50 h-h 16.00 20.45 327.17 20.448
Operario en trabajos elctricos 2.00 h-h 64.00 17.24 1,103.62 17.244
Oficial en trabajos elctricos 2.00 h-h 64.00 15.13 968.45 15.132
Ingeniero electricista 0.25 h-h 8.00 52.50 420.00 52.500

MAQUINARIAS Y EQUIPOS 1,626.16


Estuche de herramientas para mecnico 1.00 h-m 32.00 1.32 42.24 1.320
Camin gra de 5 TON 0.10 h-m 3.20 173.25 554.40 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 16.00 45.42 726.72 45.420
Equipo de corte y soldadura 0.35 h-m 11.20 2.75 30.80 2.750
Megger 1.00 h-m 32.00 5.50 176.00 5.500
Taladro elctrico 1.00 h-m 32.00 3.00 96.00 3.000

HERRAMIENTAS 149.36
Herramientas manuales y equipos de proteccin % m-o 5.00 2,987.23 149.36

COSTO DIRECTO TOTAL S/. 5,006.13

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 7.00 SISTEMA DE PUESTA A TIERRA


DESCRIPCIN: 7.01 SISTEMA DE PUESTA A TIERRA PROFUNDA
7.02 SISTEMA DE PUESTA A TIERRA SUPERFICIAL
RENDIMIENTO : 0.120 global/da UNIDAD: glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 113.45
Material consumible EST 0.10 192.50 19.25 192.500
Pinza multimtrica Un. 0.25 1.93 0.48 1.925
Mesa de trabajo Pza. 0.10 2.20 0.22 2.200
Petrleo gln 10.00 9.35 93.50 9.350

MANO DE OBRA 10,552.40


Ingeniero de seguridad 0.10 h-h 6.67 52.50 350.00 52.500
Capataz en trabajos elctricos 1.00 h-h 66.67 20.45 1,363.20 20.448
Operario en trabajos elctricos 2.00 h-h 133.33 17.24 2,299.20 17.244
Pen 4.00 h-h 266.67 11.40 3,040.00 11.400
Ingeniero electricista 1.00 h-h 66.67 52.50 3,500.00 52.500

MAQUINARIAS Y EQUIPOS 2,058.13


Estuche de herramientas para mecnico 0.50 h-m 33.33 1.32 44.00 1.320
Camin gra de 5 TON 0.10 h-m 6.67 173.25 1,155.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 6.67 45.42 302.80 45.420
Caballete alzabobina 0.10 h-m 6.67 62.20 414.67 62.200
Megger 0.25 h-m 16.67 5.50 91.67 5.500
Taladro elctrico 0.25 h-m 16.67 3.00 50.00 3.000

HERRAMIENTAS 527.62
Herramientas manuales y equipos de proteccin % m-o 5.00 10,552.40 527.62

COSTO DIRECTO TOTAL S/. 13,251.60

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 8.00 FERRETERA Y OTROS ACCESORIOS


DESCRIPCIN: 8.01 CONECTORES, CONDUCTORES, AISLADORES, FERRETERA, BANDEJAS

RENDIMIENTO : 0.120 global/da UNIDAD: glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 112.97
Material consumible EST 0.10 192.50 19.25 192.500
Mesa de trabajo Pza. 0.10 2.20 0.22 2.200
Petrleo gln 10.00 9.35 93.50 9.350

MANO DE OBRA 5,725.80


Ingeniero de seguridad 0.10 h-h 6.67 52.50 350.00 52.500
Capataz en trabajos elctricos 0.50 h-h 33.33 20.45 681.60 20.448
Operario en trabajos elctricos 2.00 h-h 133.33 17.24 2,299.20 17.244
Pen 2.00 h-h 133.33 11.40 1,520.00 11.400
Ingeniero electricista 0.25 h-h 16.67 52.50 875.00 52.500

MAQUINARIAS Y EQUIPOS 1,643.47


Estuche de herramientas para mecnico 0.50 h-m 33.33 1.32 44.00 1.320
Camin gra de 5 TON 0.10 h-m 6.67 173.25 1,155.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 6.67 45.42 302.80 45.420
Megger 0.25 h-m 16.67 5.50 91.67 5.500
Taladro elctrico 0.25 h-m 16.67 3.00 50.00 3.000

HERRAMIENTAS 286.29
Herramientas manuales y equipos de proteccin % m-o 5.00 5,725.80 286.29

COSTO DIRECTO TOTAL S/. 7,768.53

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. PARQUE INDUSTRIAL

PARTIDA : 9.00 SISTEMA DE ILUMICACIN Y FUERZA


DESCRIPCIN: 9.01 INSTALACIONES ELCTRICAS EXTERIORES

RENDIMIENTO : 0.200 global/da UNIDAD: glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 77.43
Material consumible EST 0.10 192.50 19.25 192.500
Pinza multimtrica Un. 0.25 1.93 0.48 1.925
Mesa de trabajo Pza. 0.10 2.20 0.22 2.200
Escalera de madera de 4 m H-E 0.50 2.75 1.38 2.750
Petrleo gln 6.00 9.35 56.10 9.350

MANO DE OBRA 3,734.04


Ingeniero de seguridad 0.10 h-h 4.00 52.50 210.00 52.500
Capataz en trabajos elctricos 0.50 h-h 20.00 20.45 408.96 20.448
Operario en trabajos elctricos 2.00 h-h 80.00 17.24 1,379.52 17.244
Oficial en trabajos elctricos 2.00 h-h 80.00 15.13 1,210.56 15.132
Ingeniero electricista 0.25 h-h 10.00 52.50 525.00 52.500

MAQUINARIAS Y EQUIPOS 293.08


Estuche de herramientas para mecnico 0.50 h-m 20.00 1.32 26.40 1.320
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 4.00 45.42 181.68 45.420
Megger 0.25 h-m 10.00 5.50 55.00 5.500
Taladro elctrico 0.25 h-m 10.00 3.00 30.00 3.000

HERRAMIENTAS 186.70
Herramientas manuales y equipos de proteccin % m-o 5.00 3,734.04 186.70

COSTO DIRECTO TOTAL S/. 4,291.25

SZ-04-207/005 C:\Anaid\SZ-04-207\VOLUMEN3\PRESUP.xls
SUBESTACION PARQUE INDUSTRIAL 138/33 KV t.c
SUMINISTRO DE EQUIPOS Y MATERIALES 2.62

Precio Precio
Precio Total (S/.) Precio Total (S/.)
ITEM. DESCRIPCIN Unidad Cantidad Total Total
Equipo Nacional Equipo Importado
(S/.) (S/.)

I SUMINISTRO DE EQUIPOS Y MATERIALES

1.00 SUMINISTRO DE EQUIPOS Y MATERIALES 138 KV

Transformador de Potencia 138/33 kV 60 MVA ONAN; 75 MVA ONAF, inc T.C. en bushings, tablero de
1.01 Un 1.00 3,736,120.00 3,736,120.00 3,736,120.00
regulacin automtica y tablero de medicin y proteccin.
Interruptor tanque muerto 170 kV, 2000 A con TC's en los bushings 170 kV, 750 kV BIL, incluye estructura
1.02 Un 1.00 445,400.00 445,400.00 445,400.00
soporte.
Seccionador de lnea doble apertura, 170 kV, 1250 A, 750 kV BIL, incluye cuchilla de puesta a tierra, con
1.03 Un 1.00 77,552.00 77,552.00 77,552.00
mecanismo de operacin manual y elctrica.
1.04 Transformador de tensin 138/, 170 kV, 750 kV-BIL, incluye estructura soporte* Un 3.00 103,123.20 103,123.20 103,123.20
1.05 Trampa de onda portadora 0,5 mH, Rb 600 ohm, 1000 A, 31,5 kA** Un 1.00 18,078.00 18,078.00 18,078.00
Pararrayos de xido de Zinc con contador de descarga 120 kV, incluye estructura soporte para tres
1.06 Un 6.00 58,950.00 58,950.00 58,950.00
unidades
1.07 Prticos metlicos 138 kV Glb 1.00 52,400.00 52,400.00 52,400.00
Sub-Total: 52,400.00 4,439,223.20 4,491,623.20 4,491,623.20

2.00 SUMINISTRO DE EQUIPOS Y MATERIALES 33 KV


2.01 Pararrayos de xido de Zinc con contador de descarga 30 kV Un 3.00 3,144.00 3,144.00 3,144.00

Celda Metal clad de llegada de transformador en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia
2.02 2000 A, transformador de corriente 1600-800/5/5/5 A, 2x10 VA 5P20, 10 VA cl 0.2, rel de proteccin contra Un 1.00 262,000.00 262,000.00 262,000.00
sobre corriente, rel diferencial y medidor multifuncin (para transformador 138/33 kV).

Celda Metal clad de salida al transformador en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia
2.03 1250 A, transformador de corriente 800-400/5/5/5 A, 2x10 VA 5P20, 10 VA cl 0.2, rel de proteccin contra Un 2.00 524,000.00 524,000.00 524,000.00
sobre corriente, rel diferencial y medidor multifuncin (para transformadores existentes).

Celda Metal clad de llegada en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia 1250 A,
2.04 transformador de tensin 33/3; 0.10/3; 0.10/3, 10 VA 3P, 10 VA cl 0.2, transformador de corriente 800- Un 4.00 995,600.00 995,600.00 995,600.00
400/5/5/5 A, 2x10 VA 5P20, 10 VA cl 0.2, rel de proteccin multifuncin y medidor multifuncin.

Celda Metal clad de salida en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia 1250 A,
2.05 transformador de tensin 33/3; 0.10/3; 0.10/3, 10 VA 3P, 10 VA cl 0.2, transformador de corriente 400- Un 4.00 995,600.00 995,600.00 995,600.00
200/5/5/5 A, 2x10 VA 5P20, 10 VA cl 0.2, rel de proteccin multifuncin y medidor multifuncin.

Celda Metal clad de medicin en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia 1250 A,
2.05 Un 1.00 235,800.00 235,800.00 235,800.00
transformador de tensin 33/3; 0.10/3; 0.10/3, 10 VA 3P, 10 VA cl 0.2.

Sub-Total: 3,016,144.00 0.00 3,016,144.00 3,016,144.00

3.00 CABLES DE ENERGA, CONTROL Y TERMINALES


3.01 Cable de energa N2XSY 35 kV; 1x300mm m 750.00 90,982.50 90,982.50 90,982.50
3.02 Cable de energa N2XSY 35 kV; 1x240mm m 1,600.00 158,464.00 158,464.00 158,464.00
3.03 Cable de energa N2XSY 35 kV; 1x120mm m 3,200.00 227,200.00 227,200.00 227,200.00
3.04 Cables de control, proteccin y medicin Glb 1.00 15,720.00 15,720.00 15,720.00
3.05 Conjunto de terminales autocontrables para cable de 300mm; 35kV (3unidades) Cjto 4.00 17,501.60 17,501.60 17,501.60
3.06 Conjunto de terminales autocontrables para cable de 240mm; 35kV (3unidades) Cjto 8.00 21,735.52 21,735.52 21,735.52
3.07 Conjunto de terminales autocontrables para cable de 120mm; 35kV (3 unidades) Cjto 14.00 21,641.20 21,641.20 21,641.20
Sub-Total: 76,598.32 476,646.50 553,244.82 553,244.82

4.00 TABLEROS DE CONTROL, PROTECCIN Y MEDICIN


4.01 Tablero de control, proteccin, medicin y controlador de baha de la Lnea 138 kV U 1.00 170,300.00 170,300.00 170,300.00
4.02 Tablero de equipos registradores de fallas para la Lnea 138 kV U 1.00 175,540.00 175,540.00 175,540.00
Sub-Total: 345,840.00 0.00 345,840.00 345,840.00
5.00 SISTEMA DE PUESTA A TIERRA
5.01 Sistema de puesta a tierra profunda, conductor de cobre de 185mm m 700.00 44,016.00 44,016.00 44,016.00
5.02 Bentonita, bolsa de 30 kg blsa 450.00 17,451.00 17,451.00 17,451.00
5.03 Soldadura exotrmica u 140.00 1,764.00 1,764.00 1,764.00
5.04 Varilla de cobre de 3/4 16 mm x 2,40 m con conector u 17.00 612.85 612.85 612.85
5.05 Tapa de registro para puesta a tierra u 6.00 149.52 149.52 149.52
5.06 Sistema de puesta a tierra superficial, conductor de cobre de 120 mm2 glb 1.00 14,980.56 14,980.56 14,980.56
Sub-Total: 78,973.93 0.00 78,973.93 78,973.93
6.00 FERRETERA Y OTROS ACCESORIOS
6.01 Conectores, conductores, aisladores, ferretera, bandejas glb. 1.00 13,100.00 13,100.00 13,100.00
Sub-Total: 13,100.00 0.00 13,100.00 13,100.00
7.00 INSTALACIONES ELCTRICAS
7.01 Instalaciones Elctricas exteriores glb 1.00 8,122.00 8,122.00 8,122.00
Sub-Total: 8,122.00 0.00 8,122.00 8,122.00

COSTO TOTAL DE SUMINISTRO EQUIPOS Y MATERIALES 3,591,178.25 4,915,869.70 8,507,047.95 8,507,047.95

* Un transformador de tensin previsto para montaje de onda portadora


** Trampa de onda portadora para montaje sobre transformador de tensin
SUBESTACION PARQUE INDUSTRIAL 138/33 KV
MONTAJE DE EQUIPOS Y MATERIALES

Costo
ITEM. DESCRIPCIN Unidad Cantidad Total
(S/.)

II MONTAJE ELECTROMECNICO

1.00 INGENIERIA DE DETALLE DE LAS OBRAS ELECTROMECANICAS Y OBRAS CIVILES

Ingeniera de detalle de las obras electromecnicas y obras civiles (Conexionado, puesta a tierra,
1.01 coordinacin de las protecciones, sistema de comunicaciones, etc) necesarias para el correcto desarrollo de Glb 1.00 71,500.00
la obra.
Sub-Total: 71,500.00

2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 KV

Transformador de Potencia 138/33 kV 60 MVA ONAN; 75 MVA ONAF, inc T.C. en bushings, tablero de
2.01 Un 1.00 127,981.73
regulacin automtica y tablero de medicin y proteccin.
Interruptor tanque muerto 170 kV, 2000 A con TC's en los bushings 170 kV, 750 kV BIL, incluye estructura
2.02 Un 1.00 15,061.07
soporte.
Seccionador de lnea doble apertura, 170 kV, 1250 A, 750 kV BIL, incluye cuchilla de puesta a tierra, con
2.03 Un 1.00 19,052.39
mecanismo de operacin manual y elctrica.
2.04 Transformador de tensin 138/, 170 kV, 750 kV-BIL, incluye estructura soporte Un 3.00 5,044.62
2.05 Trampa de onda portadora 0,5 mH, Rb 600 ohm, 1000 A, 31,5 kA Un 1.00 1,202.34

2.06 Pararrayos de xido de Zinc con contador de descarga 120 kV, incluye estructura soporte para tres unidades Un 6.00 5,661.84

2.07 Prticos metlicos 138 kV Glb 1.00 11,224.56


Sub-Total: 185,228.55

3.00 MONTAJE DE EQUIPOS Y MATERIALES 33 KV


3.01 Pararrayos de xido de Zinc con contador de descarga 30 kV Un 3.00 374.58

Celda Metal clad de llegada de transformador en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia
3.02 2000 A, transformador de corriente 1600-800/5/5/5 A, 2x10 VA 5P20, 10 VA cl 0.2, rel de proteccin contra Un 1.00 10,414.12
sobre corriente, rel diferencial y medidor multifuncin (para transformador 138/33 kV).

Celda Metal clad de salida al transformador en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia
3.03 1250 A, transformador de corriente 800-400/5/5/5 A, 2x10 VA 5P20, 10 VA cl 0.2, rel de proteccin contra Un 2.00 20,828.24
sobre corriente, rel diferencial y medidor multifuncin (para transformadores existentes).

Celda Metal clad de llegada en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia 1250 A,
3.04 transformador de tensin 33/3; 0.10/3; 0.10/3, 10 VA 3P, 10 VA cl 0.2, transformador de corriente 800- Un 4.00 41,656.48
400/5/5/5 A, 2x10 VA 5P20, 10 VA cl 0.2, rel de proteccin multifuncin y medidor multifuncin.

Celda Metal clad de salida en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia 1250 A,
transformador de tensin 33/3; 0.10/3; 0.10/3, 10 VA 3P, 10 VA cl 0.2, transformador de corriente 400- Un 4.00 41,656.48
200/5/5/5 A, 2x10 VA 5P20, 10 VA cl 0.2, rel de proteccin multifuncin y medidor multifuncin.

Celda Metal clad de medicin en 36 kV; 170 kV-BIL, 3000 A, 31,5 kA, interruptor de potencia 1250 A,
3.05 Un 1.00 10,414.12
transformador de tensin 33/3; 0.10/3; 0.10/3, 10 VA 3P, 10 VA cl 0.2.

Sub-Total: 125,344.02

4.00 MONTAJE DE CABLES DE ENERGA, CONTROL Y TERMINALES


4.01 Cable de energa N2XSY 35 kV; 1x300mm Glb 0.25 2,965.42
4.02 Cable de energa N2XSY 35 kV; 1x240mm Glb 0.50 5,930.83
4.03 Cable de energa N2XSY 35 kV; 1x120mm Glb 1.00 11,861.66
4.04 Cables de control, proteccin y medicin Glb 1.00 11,861.66
4.05 Conjunto de terminales termocontraibles para cable de 300mm; 35kV (3unidades) Cjto 4.00 1,521.52
4.06 Conjunto de terminales termocontraibles para cable de 240mm; 35kV (3unidades) Cjto 8.00 3,043.04
4.07 Conjunto de terminales termocontraibles para cable de 120mm; 35kV (3 unidades) Cjto 14.00 5,325.32
Sub-Total: 42,509.45

5.00 DESMONTAJE DE TABLEROS EXISTENTES


Tableros: regulador de tensin de transformador, tablero RTU, tablero de medicin, tablero de comunicacin,
5.01 Un 7.00 16,202.76
tablero de SSAA. Tablero rectificador.
Sub-Total: 16,202.76

6.00 MONTAJE TABLEROS DE CONTROL, PROTECCIN Y MEDICIN


6.01 Tableros existentes Un 7.00 35,042.91
6.02 Tablero de control, proteccin, medicin y controlador de baha de la Lnea 138 kV Un 1.00 5,006.13
6.03 Tablero de equipos registradores de fallas para la Lnea 138 kV Un 1.00 5,006.13
Sub-Total: 45,055.17
7.00 SISTEMA DE PUESTA A TIERRA
7.01 Sistema de puesta a tierra profunda, conductor de cobre de 185mm Glb 1.00 13,251.60
7.02 Sistema de puesta a tierra superficial, conductor de cobre de 120 mm2 Glb 1.00 13,251.60
Sub-Total: 26,503.20
8.00 FERRETERA Y OTROS ACCESORIOS
8.01 Conectores, conductores, aisladores, ferretera, bandejas Glb 1.00 7,768.53
Sub-Total: 7,768.53
9.00 SISTEMA DE ILUMINACIN Y FUERZA
9.01 Alumbrado exterior (patio de llaves) Glb 1.00 4,291.25
Sub-Total: 4,291.25

COSTO TOTAL DE MONTAJE ELECTROMECNICO 524,402.93


Tipo de cambio 2.75
SUBESTACION PARQUE INDUSTRIAL 138/33 KV
OBRAS CIVILES

Costo Costo
ITEM. DESCRIPCIN Unidad Cantidad Unitario Total
(S/.) (S/.)

III OBRAS CIVILES AGREGADO GRUESO DLAR CEMENTO PORTLAND TIPOMADERA TERCIADA PARA ACERO DE CONSTRUCCIO PERFIL DE ACERO INDICE GENERAL DE PREC MAQUINARIA Y EQUIPO N MANO DE OBRA

1.0 OBRAS PRELIMINARES


1.01 MOVILIZACIN Y DESMOVILIZACIN DE EQUIPOS glb 1.00 10,000.00 10,000.00 10000 10,000.00
1.02 DEMOLICIN DE PISOS m2 1,255.00 17.18 21,560.90 21563.6068 8297.96 13265.65
1.03 DEMOLICIN DE ESTRUCTURAS DE CONCRETO m3 27.00 311.61 8,413.47 8413.3593 4175.4933 4237.866
1.04 DEMOLICIN DE MUROS DE ALBAILERA m2 21.00 27.24 572.04 572.0946 27.2426 544.852
1.05 OBRAS DE DESMANTELAMIENTO m2 387.00 28.15 10,894.05 10895.3813 518.82768 10376.5536
1.06 MONTAJE Y DESMONTAJE DE PORTN METLICO glb 1.00 4,000.00 4,000.00 4000 4000
1.07 DESMONTAJE DE TORRE EXISTENTE glb 1.00 8,200.00 8,200.00 8200 8200
Sub-Total: 63,640.46 0
0
2.0 MOVIMIENTO DE TIERRAS 0
2.01 EXCAVACION MANUAL EN MATERIAL SUELTO m3 290.00 44.55 12,919.50 12920.892 845.292 12075.6
2.02 RELLENO COMPACTADO MANUAL CON MATERIAL PROPIO m3 65.00 33.60 2,184.00 2184.02049 13.65 1888.6313962616 281.739092376
2.03 ELIMINACIN DE MATERIAL EXCEDENTE m3 300.00 10.87 3,261.00 3259.55246 3028.6861714286 230.8662857143
2.04 COLOCACION DE MATERIAL GRAVA m2 580.00 110.94 64,345.20 64345.2 39985.2 24360
Sub-Total: 82,709.70 0
0
3.0 OBRAS DE CONCRETO 0
3.01 CONCRETO f'c= 100 kg/cm2 m2 180.00 34.63 6,233.40 6233.36962 780.39 460.368 1108.08 32.4 452.262816 3399.8688
3.02 CONCRETO f'c= 140 kg/cm2 m2 27.00 298.59 8,061.93 8062.02956 1161.459 66.48318 3744.09 50.603778 378.5616 2660.832
3.03 CONCRETO f'c = 210 kg/cm2 m3 110.00 323.79 35,616.90 35616.4351 4664 577.0974 18810 722.403 1525.2013333333 9317.7333333333
3.04 ENCOFRADO Y DESENCOFRADO RECTO m2 445.00 74.55 33,174.75 33174.6239 9692.1 1805.03125 2776.266 1718.2933333333 17182.9333333333
3.05 ACERO DE REFUERZO fy = 4200 kg/cm2 kg 6,800.00 5.82 39,576.00 39607.9034 22633.8 2539.8 944.300224 13490.0032
Sub-Total: 122,662.98 0
0
4.0 MISCELNEOS 0
4.01 SUMIN. E INSTAL. DE RIEL m 20.00 140.25 2,805.00 2847.0816 1653 165.3 48.9896 979.792
4.02 CERCO DE MALLA METLICA m2 160.00 90.00 14,400.00 14400 14400
4.03 MURO DE ALBAILERA m2 20.00 62.33 1,246.60 1246.69608 17.0995 572.94824 29.822 3.4756 29.6833684211 593.6673684211
4.04 SUMIN. DE TUBERA PVC SAL D=6" m 280.00 39.00 10,920.00 10920 10920
4.05 SUMINISTRO DE TUBO DE FF D 8" m 3.00 115.50 346.50 346.5 346.5
4.06 DRENAJE EN CANALETAS m 60.00 29.39 1,763.40 1763.4132 360 428.4 46.4292 928.584
4.07 COLOCACIN DE PAVIMENTO m2 448.00 37.95 17,001.60 17001.6 17001.6
4.08 ACABADOS VARIOS m2 1.00 5,000.00 5,000.00 5000 5000
Sub-Total: 53,483.10 0
0 AGREGADO GRUESO DLAR CEMENTO PORTLAND TIPOMADERA TERCIADA PARA ACERO DE CONSTRUCCIO PERFIL DE ACERO INDICE GENERAL DE PREC MAQUINARIA Y EQUIPO N MANO DE OBRA
COSTO TOTAL DE OBRAS CIVILES 322,496.24 0
322573.759 46968.1485 1103.94858 24235.11824 9721.922 22633.8 3458.03125 17998.798378 23925.8502067778 172528.142213178
0
-77.52
0
322496.24 46890.63 1103.95 24235.12 9721.92 22633.8 3458.03 17998.8 23925.85 172528.14
0
FORMULA POLINOMICA - SUMINISTRO Y TRANSPORTE DE MATERIALES TELECOMUNICACIONES Y SCADA
PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 551,333.24
FECHA : Diciembre - 2012
TR EQN EQI GG U
K = 0.046 ---- + 0.000 ---- +0.873 ---- + 0.071------+0.009-------
TRo EQNo EQIo GGo U

Incidencia Base(Octubre-2012)
INDICE SIMB. DESCRIPCION MONTO COEF.
100(%)
Coef. Indice

49 EQI Materiales y Equipos Importados 481,556.00 87.34% 100.00% 0.873 227.56

48 EQN Materiales y Equipos Nacionales 0.00 0.00% 100.00% 0.000 324.30

32 TR Transporte de Suministro 25,600.00 4.64% 100.00% 0.046 450.67

INDICE UNIFICADO 481,556.00 87.34%

39 GG Gastos Generales 39,105.68 7.09% 100.00% 0.071 380.86

39 U Utilidades 5,071.56 0.92% 100.00% 0.009 380.86

Ko1 = 1.000 1.000

FORMULA POLINOMICA MONTAJE ELECTROMECANICO - TELECOMUNICACIONES Y SCADA


PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 18,830.49
FECHA : Diciembre - 2012
MO EyM GG U
K = 0.752 ---- + 0.168 ---- +0.071------+0.009-------
MOo EyMo GGo Uo

Incidencia Base(Octubre-2012)
INDICE SIMB. DESCRIPCION MONTO COEF.
100(%)
Coef. Indice

47 MO Mano de Obra 14,157.44 75.18% 100.00% 0.752 470.79

49 EyM Equipos y Materiales 3,164.20 16.80% 100.00% 0.168 227.56

INDICE UNIFICADO 17,321.64 91.99%

39 GG Gastos Generales 1,335.63 7.09% 100.00% 0.071 380.86

39 U Utilidades 173.22 0.92% 100.00% 0.009 380.86

Ko1 = 1.000 1.000

FORMULA POLINOMICA OBRAS CIVILES - TELECOMUNICACIONES Y SCADA


PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 350,588.17 322,496.24
FECHA : Diciembre - 2012

K= 0.0*(AGr / AGo) + 0.0*(Dr / Do) + 0.0*(EQr / EQo) + 0.0*(MCr / MCo) + 0.0*(Mr / Mo) + 0.0*(MOr / MOo) + 0.0*(PAr / PAo) + 0.0*(UGr/UGo)

Incidencia Base(Octubre-2012)
INDICE Simb. Descripcin MONTO COEF.
100(%) Coef Indice
5 AG AGREGADO GRUESO 0.00% 100.00% 0.000 610.17
30 D DLAR 0.00% 100.00% 0.000 348.90
48 EQ MAQUINARIA Y EQUIPO NACIONAL 0.00% 100.00% 0.000 324.30
21 MC CEMENTO PORTLAND 0.00% 100.00% 0.000 423.60
M MADERA TERCIADA PARA
45
ENCOFRADO
0.00% 100.00% 0.000 313.39
47 MO MANO DE OBRA 0.00% 100.00% 0.000 470.79
ACERO DE CONSTRUCCION
3 PA
CORRUGADO
0.00% 100.00% 0.000 427.77
51 PERFIL DE ACERO 0.00% 280.76
INDICE GENERAL DE PRECIOS AL
39 UG
CONSUMIDOR
0.00% 100.00% 0.000 380.86

Ko1 = 0.000 0.000


FORMULA POLINOMICA - SUMINISTRO Y TRANSPORTE SUBESTACION PARQUE INDUSTRIAL
PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 9,378,422.29
FECHA : Diciembre - 2012
TR EQN EQI GG U
K = 0.013 ---- + 0.383 ---- +0.524 ---- + 0.071------+0.009-------
TRo EQNo EQIo GGo U

Incidencia Base(Octubre-2012)
INDICE SIMB. DESCRIPCION MONTO COEF.
100(%)
Coef. Indice

49 EQI Materiales y Equipos Importados 4,915,869.70 52.42% 100.00% 0.524 227.56

48 EQN Materiales y Equipos Nacionales 3,591,178.25 38.29% 100.00% 0.383 324.30

32 TR Transporte de Suministro 119,900.00 1.28% 100.00% 0.013 450.67

INDICE UNIFICADO 8,507,047.95 90.71%

39 GG Gastos Generales 665,204.86 7.09% 100.00% 0.071 380.86

39 U Utilidades 86,269.48 0.92% 100.00% 0.009 380.86

Ko1 = 1.000 1.000

FORMULA POLINOMICA - MONTAJE SUBESTACION PARQUE INDUSTRIAL


PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 570,082.51
FECHA : Diciembre - 2012
MO EyM GG U
K = 0.511 ---- + 0.409 ---- +0.071------+0.009-------
MOo EyMo GGo Uo

Incidencia Base(Octubre-2012)
INDICE SIMB. DESCRIPCION MONTO COEF.
100(%)
Coef. Indice

47 MO Mano de Obra 291,473.73 51.13% 100.00% 0.511 470.79

49 EyM Equipos y Materiales 232,929.20 40.86% 100.00% 0.409 227.56

INDICE UNIFICADO 524,402.93 91.99%

39 GG Gastos Generales 40,435.55 7.09% 100.00% 0.071 380.86

39 U Utilidades 5,244.03 0.92% 100.00% 0.009 380.86

Ko1 = 1.000 1.000

FORMULA POLINOMICA - OBRAS CIVILES SUBESTACION PARQUE INDUSTRIAL


PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 350,588.17 322,496.24
FECHA : Diciembre - 2012

K= 0.145*(AGr / AGo) + 0.003*(Dr / Do) + 0.074*(EQr / EQo) + 0.075*(MCr / MCo) + 0.030*(Mr / Mo) + 0.535*(MOr / MOo) + 0.081*(PAr / PAo)

Incidencia Base(Octubre-2012)
INDICE Simb. Descripcin MONTO COEF.
100(%) Coef Indice
5 AG AGREGADO GRUESO 46890.63 14.54% 100.00% 0.145 610.17
30 D DLAR 1103.95 0.34% 100.00% 0.003 348.90
48 EQ MAQUINARIA Y EQUIPO NACIONAL 23925.85 7.42% 100.00% 0.074 324.30
21 MC CEMENTO PORTLAND 24235.12 7.51% 100.00% 0.075 423.60
M MADERA TERCIADA PARA 9721.92
45
ENCOFRADO
3.01% 100.00% 0.030 313.39
47 MO MANO DE OBRA 172528.14 53.50% 100.00% 0.535 470.79
ACERO DE CONSTRUCCION 22633.80
3 PA
CORRUGADO
7.02% 86.75% 0.081 427.77
51 PERFIL DE ACERO 3458.03 1.07% 13.25% 280.76
INDICE GENERAL DE PRECIOS AL 17998.80
39 UG
CONSUMIDOR
5.58% 100.00% 0.056 380.86

Ko1 = 1.000 1.000


SUBESTACION SOCABAYA 138 KV T.C.

SUMINISTRO DE EQUIPOS Y MATERIALES 2.62

Precio
Precio Total (S/.) Equipo Precio Total (S/.) Equipo
ITEM. DESCRIPCIN Unidad Total
Nacional Importado
(S/.)

I SUMINISTRO DE EQUIPOS Y MATERIALES

1.00 SUMINISTRO DE EQUIPOS Y MATERIALES 138 KV

1.01 Seccionadores de barra tipo Pantgrafo 170 kV, 750 kV-BIL, 1250 A, incluye estructura soporte Un 137,288.00 137,288.00
Interruptor de potencia con accionamiento unitripolar 170 kV, 750 kV-BIL, 1250 A, 31 kA, incluye estructura
1.02 Un 250,079.00 250,079.00
soporte
1.03 Transformador de corriente 600-300/1/1/1/1 A, 170 kV, 750 kV-BIL, incluye estructura soporte Un 93,534.00 93,534.00
1.04 Transformador de tensin 138/, 170 kV, 750 kV-BIL, incluye estructura soporte Un 75,770.40 75,770.40
Seccionador de lnea con cuchilla de puesta a tierra, 170 kV, 750 kV-BIL, 1250 A, 31 kA, incluye estructura
1.05 Un 35,815.40 35,815.40
soporte
1.06 Pararrayos de xido de Zinc con contador de descarga 120 kV, incluye estructura soporte Un 23,344.20 23,344.20
1.07 Aisladores soporte 170 kV, incluye soporte metlico Un 5,512.48 5,512.48
1.08 Trampa de onda portadora 0,5 mH, Rb 600 ohm, 1000 A, 31,5 kA Un 18,078.00 18,078.00
1.09 Cadena de aisladores de suspensin, incluye acccesorios Un 707.40 707.40
1.10 Prticos metlicos 138 kV Glb 31,440.00 31,440.00
Sub-Total: 31,440.00 640,128.88 671,568.88

2.00 CABLES DE CONTROL


2.01 Cables de control, proteccin y medicin Glb 15,720.00 15,720.00
Sub-Total: 15,720.00 0.00 15,720.00

3.00 TABLEROS DE CONTROL, PROTECCIN Y MEDICIN


3.01 Tablero de control, proteccin, medicin y controlador de baha de la Lnea 138 kV U 170,300.00 170,300.00
3.02 Tablero de equipos registradores de fallas para la Lnea 138 kV U 175,540.00 175,540.00
Sub-Total: 345,840.00 0.00 345,840.00
4.00 FERRETERA Y OTROS ACCESORIOS
4.01 Conectores, ferretera, bandejas Glb 31,440.00 31,440.00
Sub-Total: 31,440.00 0.00 31,440.00
5.00 SISTEMA DE PUESTA A TIERRA
5.01 Sistema de puesta a tierra superficial, conductor de cobre de 120 mm2 glb. 11,266.00 11,266.00
Sub-Total: 11,266.00 0.00 11,266.00
6.00 INSTALACIONES ELCTRICAS
6.01 Instalaciones Elctricas exteriores glb 2,882.00 2,882.00
Sub-Total: 2,882.00 0.00 2,882.00

COSTO TOTAL DE SUMINISTRO EQUIPOS Y MATERIALES 438,588.00 640,128.88 1,078,716.88


FORMULA POLINOMICA - SUMINISTRO Y TRANSPORTE LINEA 33KV PAUCARPATA
PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 71,742.24
FECHA : Apr-13
TR EQN EQI GG U
K = 0.064 ---- + 0.856 ---- +0.000 ---- + 0.071------+0.009-------
TRo EQNo EQIo GGo U

BASE (Indice de precios a la fecha de


Incidencia presupuesto base)
INDICE SIMB. DESCRIPCION MONTO COEF.
100(%)
Coef. Indice

48 EQN Materiales y Equipos Nacionales 61,389.47 85.57% 100.00% 0.856

32 TR Transporte de Suministro 4,604.21 6.42% 100.00% 0.064

39 GG Gastos Generales 5,088.63 7.09% 100.00% 0.071

39 U Utilidades 659.93 0.92% 100.00% 0.009

Ko1 = 1.000 1.000

FORMULA POLINOMICA - MONTAJE LINEA 33KV PAUCARPATA


PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 60,801.91
FECHA : Apr-13
MO EyM GG U
K = 0.610 ---- + 0.310 ---- +0.071------+0.009-------
MOo EyMo GGo Uo

BASE (Indice de precios a la fecha de


Incidencia
INDICE SIMB. DESCRIPCION MONTO COEF. presupuesto base)
100(%)
Coef. Indice

47 MO Mano de Obra 37,073.83 60.97% 100.00% 0.610

49 EyM Equipos y Materiales 18,856.14 31.01% 100.00% 0.310

INDICE UNIFICADO 55,929.97 91.99%

39 GG Gastos Generales 4,312.64 7.09% 100.00% 0.071

39 U Utilidades 559.30 0.92% 100.00% 0.009

Ko1 = 1.000 1.000

FORMULA POLINOMICA - OBRAS CIVILES LINEA 33KV PAUCARPATA


PROYECTO : INGENIERA DEFINITIVA DE LA LNEA DE TRANSMISIN EN 138 kV
SOCABAYA PARQUE INDUSTRIAL Y SUBESTACIONES ASOCIADAS
UBICACION : AREQUIPA
MONTO S/.: 27,792.51 25,565.55
FECHA : Apr-13

K= 0.062*(AGr / AGo) + 0.0*(TPr / TPo) + 0.099*(EQr / EQo) + 0.217*(MCr / MCo) + 0.078*(Mr / Mo) + 0.396*(MOr / MOo) + 0.103*(PAr / PAo) + 0.046*(UGr/UGo)

BASE (Indice de precios a la fecha de


Incidencia presupuesto base)
INDICE Simb. Descripcin MONTO COEF.
100(%)
Coef Indice
5 AG AGREGADO GRUESO 1579.08 6.18% 100.00% 0.062
72 TP TUBERIA DE PVC 0.00% 100.00% 0.000
48 EQ MAQUINARIA Y EQUIPO NACIONAL 2532.89 9.91% 100.00% 0.099
21 MC CEMENTO PORTLAND TIPO I 5543.30 21.68% 100.00% 0.217
45 M MADERA TERCIADA PARA ENCOFRADO 1983.29 7.76% 100.00% 0.078
47 MO MANO DE OBRA 10116.85 39.57% 100.00% 0.396
3 PA ACERO DE CONSTRUCCION CORRUGADO 2645.29 10.35% 100.00% 0.103
39 UG INDICE GENERAL DE PRECIOS AL CONSUMIDOR 1164.85 4.56% 100.00% 0.046

Ko1 = 1.000 1.000


SUBESTACION SOCABAYA 138 KV
MONTAJE DE EQUIPOS Y MATERIALES

Precio Precio
ITEM. DESCRIPCIN Unidad Cantidad Unitario Total
(S/.) (S/.)

II MONTAJE ELECTROMECNICO

1.00 INGENIERIA DE DETALLE DE LAS OBRAS ELECTROMECANICAS Y OBRAS CIVILES


Ingeniera de detalle de las obras electromecnicas y obras civiles (Conexionado, puesta a tierra,
1.01 coordinacin de las protecciones, sistema de comunicaciones, etc) necesarias para el correcto desarrollo de Glb 1.00 55,350.00 55,350.00
la obra. Sub-Total: 55,350.00

2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 KV

2.01 Seccionadores de barra tipo Pantgrafo 170 kV, 750 kV-BIL, 1250 A, incluye estructura soporte Un 2.00 5,061.45 10,122.90
Interruptor de potencia con accionamiento unitripolar 170 kV, 750 kV-BIL, 1250 A, 31 kA, incluye estructura
2.02 Un 1.00 10,676.27 10,676.27
soporte
2.03 Transformador de corriente 600-300/1/1/1/1 A, 170 kV, 750 kV-BIL, incluye estructura soporte Un 3.00 1,803.22 5,409.66
2.04 Transformador de tensin 138/, 170 kV, 750 kV-BIL, incluye estructura soporte Un 3.00 1,803.22 5,409.66
Seccionador de lnea con cuchilla de puesta a tierra, 170 kV, 750 kV-BIL, 1250 A, 31,5 kA, incluye estructura
2.05 Un 1.00 4,240.05 4,240.05
soporte
2.06 Pararrayos de xido de Zinc con contador de descarga 120 kV, incluye estructura soporte Un 3.00 943.64 2,830.92
2.07 Aisladores soporte 170 kV, incluye soporte metlico Un 4.00 214.70 858.80
2.08 Trampa de onda portadora 0,5 mH, Rb 600 ohm, 1000 A, 31,5 kA Un 1.00 1,202.34 1,202.34
2.09 Cadena de aisladores de suspensin, incluye acccesorios Un 2.00 81.31 162.62
2.10 Prticos metlicos 138 kV Glb 1.00 11,226.62 11,226.62
Sub-Total: 52,139.84

3.00 CABLES DE CONTROL


3.01 Cables de control, proteccin y medicin Glb 1.00 10,327.56 10,327.56
Sub-Total: 10,327.56

4.00 TABLEROS DE CONTROL, PROTECCIN Y MEDICIN


4.01 Tablero de control, proteccin, medicin y controlador de baha de la Lnea 138 kV Un 1.00 5,006.13 5,006.13
4.02 Tablero de equipos registradores de fallas para la Lnea 138 kV Un 1.00 5,006.13 5,006.13
Sub-Total: 10,012.26
5.00 FERRETERA Y OTROS ACCESORIOS
5.01 Conectores, ferretera, bandejas Glb 1.00 12,458.44 12,458.44
Sub-Total: 12,458.44
6.00 SISTEMA DE PUESTA A TIERRA
6.01 Sistema de puesta a tierra superficial, conductor de cobre de 120 mm2 Glb 1.00 13,251.60 13,251.60
Sub-Total: 13,251.60
7.00 INSTALACIONES ELCTRICAS
7.01 Instalaciones Elctricas exteriores Glb 1.00 4,291.25 4,291.25
Sub-Total: 4,291.25

COSTO TOTAL DE MONTAJE ELECTROMECNICO 157,830.95


Tipo de cambio 2.75
SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 1.0 INGENIERA DE DETALLE DE LAS OBRAS ELECTROMECNICAS Y OBRAS CIVILES SEGN DETALLE
DESCRIPCIN:

1.01 INGENIERA DE DETALLE DE LAS OBRAS ELECTROMECNICAS Y OBRAS CIVILES (CONEXIONADO, PUESTA A TIERRA, COORDINACIN DE LAS PROTECCIONES,
SISTEMA DE COMUNICACIONES, ETC) NECESARIAS PARA EL CORRECTO DESARROLLO DE LA OBRA.

RENDIMIENTO : 0.015 Glb/da UNIDAD: Glb

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 192.50
Material consumible EST 1.00 192.50 192.50 192.500

MANO DE OBRA 55,157.50


Ingeniero electricista 0.50 h-h 270.51 52.50 14,201.91
Ingeniero de coordinacin de protecciones 0.50 h-h 270.51 85.00 22,993.56
Ingeniero especialista en cableado 0.15 h-h 81.15 50.00 4,057.69
Ingeniero de telecomunicaciones 0.15 h-h 81.15 80.00 6,492.30
Ingeniero Civil 0.10 h-h 54.10 80.00 4,328.20
Dibujante 0.50 h-h 270.51 11.40 3,083.84

MAQUINARIAS Y EQUIPOS 0.00

HERRAMIENTAS 0.00

COSTO DIRECTO TOTAL S/. 55,350.00

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.01 SECCIONADOR DE BARRA TIPO SEMIPANTOGRAFO 138 KV

RENDIMIENTO : 0.400 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 290.95
Material consumible EST 1.00 192.50 192.50 192.500
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 10.00 9.35 93.50 9.350

MANO DE OBRA 2,357.52


Ingeniero de seguridad 0.10 h-h 2.00 52.50 105.00 52.500
Capataz en trabajos elctricos 0.50 h-h 10.00 20.45 204.48 20.448
Operario en trabajos elctricos 2.00 h-h 40.00 17.24 689.76 17.244
Oficial en trabajos elctricos 2.00 h-h 40.00 15.13 605.28 15.132
Pen 1.00 h-h 20.00 11.40 228.00 11.400
Ingeniero electricista 0.50 h-h 10.00 52.50 525.00 52.500

MAQUINARIAS Y EQUIPOS 2,295.10


Estuche de herramientas para mecnico 1.00 h-m 20.00 1.32 26.40 1.320
Camin gra de 5 TON 0.50 h-m 10.00 173.25 1,732.50 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 10.00 45.42 454.20 45.420
Torqumetro 0.40 h-m 8.00 2.75 22.00 2.750
Taladro elctrico 1.00 h-m 20.00 3.00 60.00 3.000

HERRAMIENTAS 117.88
Herramientas manuales y equipos de proteccin % m-o 5.00 2,357.52 117.88

COSTO DIRECTO TOTAL S/. 5,061.45

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.02 INTERRUPTOR DE POTENCIA CON ACCIONAMIENTO UNITRIPOLAR 138 KV

RENDIMIENTO : 0.100 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 622.05
Material consumible EST 1.00 192.50 192.50 192.500
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Escalera de aluminio de 6 m H-E 0.50 13.20 6.60 13.200
Petrleo gln 45.00 9.35 420.75 9.350

MANO DE OBRA 5,636.40


Ingeniero de seguridad 0.10 h-h 8.00 52.50 420.00 52.500
Capataz en trabajos elctricos 1.00 h-h 80.00 20.45 1,635.84 20.448
Oficial en trabajos elctricos 1.00 h-h 80.00 15.13 1,210.56 15.132
Pen 2.00 h-h 160.00 11.40 1,824.00 11.400
Ingeniero electricista 0.13 h-h 10.40 52.50 546.00 52.500

MAQUINARIAS Y EQUIPOS 4,136.00


Estuche de herramientas para mecnico 1.00 h-m 80.00 1.32 105.60 1.320
Camin gra de 5 TON 0.20 h-m 16.00 173.25 2,772.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.25 h-m 20.00 45.42 908.40 45.420
Torqumetro 0.50 h-m 40.00 2.75 110.00 2.750
Taladro elctrico 1.00 h-m 80.00 3.00 240.00 3.000

HERRAMIENTAS 281.82
Herramientas manuales y equipos de proteccin % m-o 5.00 5,636.40 281.82

COSTO DIRECTO TOTAL S/. 10,676.27


SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.03 TRANSFORMADORES DE CORRIENTE
2.04 TRANSFORMADORES DE TENSIN
RENDIMIENTO : 1.000 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 174.90
Material consumible EST 0.50 192.50 96.25 192.500
Mesa de trabajo Pza. 0.50 2.20 1.10 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 8.00 9.35 74.80 9.350

MANO DE OBRA 663.89


Ingeniero de seguridad 0.10 h-h 0.80 52.50 42.00 52.500
Capataz en trabajos elctricos 1.00 h-h 8.00 20.45 163.58 20.448
Operario en trabajos elctricos 2.00 h-h 16.00 17.24 275.90 17.244
Pen 2.00 h-h 16.00 11.40 182.40 11.400

MAQUINARIAS Y EQUIPOS 931.24


Estuche de herramientas para mecnico 1.00 h-m 8.00 1.32 10.56 1.320
Camin gra de 5 TON 0.50 h-m 4.00 173.25 693.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 4.00 45.42 181.68 45.420
Torqumetro 1.00 h-m 8.00 2.75 22.00 2.750
Taladro elctrico 1.00 h-m 8.00 3.00 24.00 3.000

HERRAMIENTAS 33.19
Herramientas manuales y equipos de proteccin % m-o 5.00 663.89 33.19

COSTO DIRECTO TOTAL S/. 1,803.22

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.05 SECCIONADOR DE LINEA C/CUCHILLA DE PUESTA A TIERRA 138 kV, 1250 A750 kV BIL

RENDIMIENTO : 0.400 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 290.95
Material consumible EST 1.00 192.50 192.50 192.500
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 10.00 9.35 93.50 9.350

MANO DE OBRA 1,575.24


Ingeniero de seguridad 0.10 h-h 2.00 52.50 105.00 52.500
Capataz en trabajos elctricos 1.00 h-h 20.00 20.45 408.96 20.448
Oficial en trabajos elctricos 2.00 h-h 40.00 15.13 605.28 15.132
Pen 2.00 h-h 40.00 11.40 456.00 11.400

MAQUINARIAS Y EQUIPOS 2,295.10


Estuche de herramientas para mecnico 1.00 h-m 20.00 1.32 26.40 1.320
Camin gra de 5 TON 0.50 h-m 10.00 173.25 1,732.50 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 10.00 45.42 454.20 45.420
Torqumetro 0.40 h-m 8.00 2.75 22.00 2.750
Taladro elctrico 1.00 h-m 20.00 3.00 60.00 3.000

HERRAMIENTAS 78.76
Herramientas manuales y equipos de proteccin % m-o 5.00 1,575.24 78.76

COSTO DIRECTO TOTAL S/. 4,240.05


SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.06 PARARRAYOS DE OXIDO DE ZINC CON CONTADOR DE DESCARGA 120 Kv

RENDIMIENTO : 2.000 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 174.90
Material consumible EST 0.50 192.50 96.25 192.500
Mesa de trabajo Pza. 0.50 2.20 1.10 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 8.00 9.35 74.80 9.350

MANO DE OBRA 331.94


Ingeniero de seguridad 0.10 h-h 0.40 52.50 21.00 52.500
Capataz en trabajos elctricos 1.00 h-h 4.00 20.45 81.79 20.448
Operario en trabajos elctricos 2.00 h-h 8.00 17.24 137.95 17.244
Pen 2.00 h-h 8.00 11.40 91.20 11.400

MAQUINARIAS Y EQUIPOS 420.20


Estuche de herramientas para mecnico 1.00 h-m 4.00 1.32 5.28 1.320
Camin gra de 5 TON 0.50 h-m 2.00 173.25 346.50 173.250
Camioneta pick up 4 x 2 d.cab. 0.25 h-m 1.00 45.42 45.42 45.420
Torqumetro 1.00 h-m 4.00 2.75 11.00 2.750
Taladro elctrico 1.00 h-m 4.00 3.00 12.00 3.000

HERRAMIENTAS 16.60
Herramientas manuales y equipos de proteccin % m-o 5.00 331.94 16.60

COSTO DIRECTO TOTAL S/. 943.64

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.07 AISLADORES SOPORTE 138 kV

RENDIMIENTO : 4.000 Un/da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 3.30
Mesa de trabajo Pza. 0.25 2.20 0.55 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750

MANO DE OBRA 86.36


Ingeniero de seguridad 0.10 h-h 0.20 52.50 10.50 52.500
Oficial en trabajos elctricos 1.00 h-h 2.00 15.13 30.26 15.132
Pen 2.00 h-h 4.00 11.40 45.60 11.400

MAQUINARIAS Y EQUIPOS 120.73


Estuche de herramientas para mecnico 1.00 h-m 2.00 1.32 2.64 1.320
Camin gra de 5 TON 0.25 h-m 0.50 173.25 86.63 173.250
Camioneta pick up 4 x 2 d.cab. 0.25 h-m 0.50 45.42 22.71 45.420
Torqumetro 0.50 h-m 1.00 2.75 2.75 2.750
Taladro elctrico 1.00 h-m 2.00 3.00 6.00 3.000

HERRAMIENTAS 4.32
Herramientas manuales y equipos de proteccin % m-o 5.00 86.36 4.32

COSTO DIRECTO TOTAL S/. 214.70

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.08 TRAMPA DE ONDA PORTADORA 0,5 mH, Rb 600 ohm, 1000 A, 31,5 kA

RENDIMIENTO : 1.000 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 156.20
Material consumible EST 0.50 192.50 96.25 192.500
Mesa de trabajo Pza. 0.50 2.20 1.10 2.200
Escalera de madera de 4 m H-E 1.00 2.75 2.75 2.750
Petrleo gln 6.00 9.35 56.10 9.350

MANO DE OBRA 525.94


Ingeniero de seguridad 0.10 h-h 0.80 52.50 42.00 52.500
Capataz en trabajos elctricos 1.00 h-h 8.00 20.45 163.58 20.448
Operario en trabajos elctricos 1.00 h-h 8.00 17.24 137.95 17.244
Pen 2.00 h-h 16.00 11.40 182.40 11.400

MAQUINARIAS Y EQUIPOS 493.90


Estuche de herramientas para mecnico 1.00 h-m 8.00 1.32 10.56 1.320
Camin gra de 5 TON 0.25 h-m 2.00 173.25 346.50 173.250
Camioneta pick up 4 x 2 d.cab. 0.25 h-m 2.00 45.42 90.84 45.420
Torqumetro 1.00 h-m 8.00 2.75 22.00 2.750
Taladro elctrico 1.00 h-m 8.00 3.00 24.00 3.000

HERRAMIENTAS 26.30
Herramientas manuales y equipos de proteccin % m-o 5.00 525.94 26.30

COSTO DIRECTO TOTAL S/. 1,202.34

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL S&Z Consultores Asociados S.A.

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.09 CADENA DE AISLADORES DE SUSPENSIN, INCLUYE ACCESORIOS

RENDIMIENTO : 12.000 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 29.10
Material consumible EST 0.10 192.50 19.25 192.500
Mesa de trabajo Pza. 0.10 2.20 0.22 2.200
Escalera de madera de 4 m H-E 0.10 2.75 0.28 2.750
Petrleo gln 1.00 9.35 9.35 9.350

MANO DE OBRA 23.66


Ingeniero de seguridad 0.10 h-h 0.07 52.50 3.50 52.500
Capataz en trabajos elctricos 0.50 h-h 0.33 20.45 6.82 20.448
Operario en trabajos elctricos 0.50 h-h 0.33 17.24 5.75 17.244
Pen 1.00 h-h 0.67 11.40 7.60 11.400

MAQUINARIAS Y EQUIPOS 27.37


Estuche de herramientas para mecnico 1.00 h-m 0.67 1.32 0.88 1.320
Camin gra de 5 TON 0.20 h-m 0.13 173.25 23.10 173.250
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 0.07 45.42 3.03 45.420
Torqumetro 0.20 h-m 0.13 2.75 0.37 2.750

HERRAMIENTAS 1.18
Herramientas manuales y equipos de proteccin % m-o 5.00 23.66 1.18

COSTO DIRECTO TOTAL S/. 81.31

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 2.00 MONTAJE DE EQUIPOS Y MATERIALES 138 kV


DESCRIPCIN: 2.10 PRTICOS METLICOS

RENDIMIENTO : 0.190 Glb./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 303.05
Material consumible EST 0.10 192.50 19.25 192.500
Mesa de trabajo Pza. 0.25 2.20 0.55 2.200
Escalera de aluminio de 4 m H-E 0.25 11.00 2.75 11.000
Petrleo gln 30.00 9.35 280.50 9.350

MANO DE OBRA 5,393.68


Ingeniero de seguridad 0.10 h-h 4.21 52.50 221.05 52.500
Capataz en trabajos elctricos 1.00 h-h 42.11 20.45 860.97 20.448
Operario en trabajos elctricos 2.00 h-h 84.21 17.24 1,452.13 17.244
Oficial en trabajos elctricos 2.00 h-h 84.21 15.13 1,274.27 15.132
Pen 1.00 h-h 42.11 11.40 480.00 11.400
Ingeniero electricista 0.50 h-h 21.05 52.50 1,105.26 52.500

MAQUINARIAS Y EQUIPOS 5,260.21


Estuche de herramientas para mecnico 0.50 h-m 21.05 1.32 27.79 1.320
Camin gra de 5 TON 0.50 h-m 21.05 173.25 3,647.37 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 21.05 45.42 956.21 45.420
Equipo de corte y soldadura 0.50 h-m 21.05 2.75 57.89 2.750
Esmeril 0.50 h-m 21.05 1.32 27.79 1.320
Mquina soldadora 0.50 h-m 21.05 8.80 185.26 8.800
Torqumetro 2.00 h-m 84.21 2.75 231.58 2.750
Taladro elctrico 1.00 h-m 42.11 3.00 126.32 3.000

HERRAMIENTAS 269.68
Herramientas manuales y equipos de proteccin % m-o 5.00 5,393.68 269.68

COSTO DIRECTO TOTAL S/. 11,226.62


SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 3.00 CABLES DE CONTROL


DESCRIPCIN: 3.01 CABLES DE CONTROL, PROTECCIN Y MEDICION

RENDIMIENTO : 0.090 global/da UNIDAD: glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 290.13
Material consumible EST 1.00 192.50 192.50 192.500
Pinza multimtrica Un. 1.00 1.93 1.93 1.925
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Petrleo gln 10.00 9.35 93.50 9.350

MANO DE OBRA 6,350.40


Ingeniero de seguridad 0.10 h-h 8.89 52.50 466.67 52.500
Capataz en trabajos elctricos 1.00 h-h 88.89 20.45 1,817.60 20.448
Operario en trabajos elctricos 1.00 h-h 88.89 17.24 1,532.80 17.244
Pen 2.50 h-h 222.22 11.40 2,533.33 11.400

MAQUINARIAS Y EQUIPOS 3,369.51


Estuche de herramientas para mecnico 1.00 h-m 88.89 1.32 117.33 1.320
Camin gra de 5 TON 0.10 h-m 8.89 173.25 1,540.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 8.89 45.42 403.73 45.420
Caballete alzabobina 0.10 h-m 8.89 62.20 552.89 62.200
Megger 1.00 h-m 88.89 5.50 488.89 5.500
Taladro elctrico 1.00 h-m 88.89 3.00 266.67 3.000

HERRAMIENTAS 317.52
Herramientas manuales y equipos de proteccin % m-o 5.00 6,350.40 317.52

COSTO DIRECTO TOTAL S/. 10,327.56

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 4.00 TABLEROS DE CONTROL, PROTECCIN Y MEDICIN


DESCRIPCIN: 4.01 Tablero de control, proteccin, medicin y controlador de baha de la Lnea 138 kV
4.02 Tablero de equipos registradores de fallas para la Lnea 138 kV
RENDIMIENTO : 0.250 Un./da UNIDAD: Un.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 243.38
Material consumible EST 1.00 192.50 192.50 192.500
Pinza multimtrica Un. 1.00 1.93 1.93 1.925
Mesa de trabajo Pza. 1.00 2.20 2.20 2.200
Petrleo gln 5.00 9.35 46.75 9.350

MANO DE OBRA 2,987.23


Ingeniero de seguridad 0.10 h-h 3.20 52.50 168.00 52.500
Capataz en trabajos elctricos 0.50 h-h 16.00 20.45 327.17 20.448
Operario en trabajos elctricos 2.00 h-h 64.00 17.24 1,103.62 17.244
Oficial en trabajos elctricos 2.00 h-h 64.00 15.13 968.45 15.132
Ingeniero electricista 0.25 h-h 8.00 52.50 420.00 52.500

MAQUINARIAS Y EQUIPOS 1,626.16


Estuche de herramientas para mecnico 1.00 h-m 32.00 1.32 42.24 1.320
Camin gra de 5 TON 0.10 h-m 3.20 173.25 554.40 173.250
Camioneta pick up 4 x 2 d.cab. 0.50 h-m 16.00 45.42 726.72 45.420
Equipo de corte y soldadura 0.35 h-m 11.20 2.75 30.80 2.750
Megger 1.00 h-m 32.00 5.50 176.00 5.500
Taladro elctrico 1.00 h-m 32.00 3.00 96.00 3.000

HERRAMIENTAS 149.36
Herramientas manuales y equipos de proteccin % m-o 5.00 2,987.23 149.36

COSTO DIRECTO TOTAL S/. 5,006.13


SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 5.00 FERRETERA Y OTROS ACCESORIOS


DESCRIPCIN: 5.01 SISTEMA DE BARRAS, CONECTORES, AISLADORES, FERRETERA, BANDEJAS Y CANALETAS

RENDIMIENTO : 0.120 global/da UNIDAD: glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 236.23
Material consumible EST 0.25 192.50 48.13 192.500
Mesa de trabajo Pza. 0.50 2.20 1.10 2.200
Petrleo gln 20.00 9.35 187.00 9.350

MANO DE OBRA 8,425.00


Ingeniero de seguridad 0.10 h-h 6.67 52.50 350.00 52.500
Capataz en trabajos elctricos 1.00 h-h 66.67 20.45 1,363.20 20.448
Operario en trabajos elctricos 2.00 h-h 133.33 17.24 2,299.20 17.244
Oficial en trabajos elctricos 2.00 h-h 133.33 15.13 2,017.60 15.132
Pen 2.00 h-h 133.33 11.40 1,520.00 11.400
Ingeniero electricista 0.25 h-h 16.67 52.50 875.00 52.500

MAQUINARIAS Y EQUIPOS 3,375.97


Estuche de herramientas para mecnico 0.50 h-m 33.33 1.32 44.00 1.320
Camin gra de 5 TON 0.25 h-m 16.67 173.25 2,887.50 173.250
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 6.67 45.42 302.80 45.420
Megger 0.25 h-m 16.67 5.50 91.67 5.500
Taladro elctrico 0.25 h-m 16.67 3.00 50.00 3.000

HERRAMIENTAS 421.25
Herramientas manuales y equipos de proteccin % m-o 5.00 8,425.00 421.25

COSTO DIRECTO TOTAL S/. 12,458.44

SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 6.00 SISTEMA DE PUESTA A TIERRA


DESCRIPCIN: 6.01 SISTEMA DE PUESTA A TIERRA SUPERFICIAL

RENDIMIENTO : 0.120 global/da UNIDAD: glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 113.45
Material consumible EST 0.10 192.50 19.25 192.500
Pinza multimtrica Un. 0.25 1.93 0.48 1.925
Mesa de trabajo Pza. 0.10 2.20 0.22 2.200
Petrleo gln 10.00 9.35 93.50 9.350

MANO DE OBRA 10,552.40


Ingeniero de seguridad 0.10 h-h 6.67 52.50 350.00 52.500
Capataz en trabajos elctricos 1.00 h-h 66.67 20.45 1,363.20 20.448
Operario en trabajos elctricos 2.00 h-h 133.33 17.24 2,299.20 17.244
Pen 4.00 h-h 266.67 11.40 3,040.00 11.400
Ingeniero electricista 1.00 h-h 66.67 52.50 3,500.00 52.500

MAQUINARIAS Y EQUIPOS 2,058.13


Estuche de herramientas para mecnico 0.50 h-m 33.33 1.32 44.00 1.320
Camin gra de 5 TON 0.10 h-m 6.67 173.25 1,155.00 173.250
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 6.67 45.42 302.80 45.420
Caballete alzabobina 0.10 h-m 6.67 62.20 414.67 62.200
Megger 0.25 h-m 16.67 5.50 91.67 5.500
Taladro elctrico 0.25 h-m 16.67 3.00 50.00 3.000

HERRAMIENTAS 527.62
Herramientas manuales y equipos de proteccin % m-o 5.00 10,552.40 527.62

COSTO DIRECTO TOTAL S/. 13,251.60


SOCIEDAD ELCTRICA DEL SUR OESTE S.A. SEAL

ANLISIS DE COSTOS UNITARIOS DE LAS OBRAS ELECTROMECNICAS DE LA S.E. PARQUE INDUSTRIAL 138/33 KV

PROYECTO: LINEA DE TRANSMISION 138KV SOCABAYA - PARQUE INDUSTRIAL: S.E. SOCABAYA

PARTIDA : 8.00 INSTALACIONES ELCTRICAS


DESCRIPCIN: 8.01 INSTALACIONES ELCTRICAS EXTERIORES

RENDIMIENTO : 0.200 global/da UNIDAD: glb.

DESIGNACIN CUAD. UNID. APORTE COSTO U. C. PARCIAL SUB TOTAL


MATERIALES 77.43
Material consumible EST 0.10 192.50 19.25 192.500
Pinza multimtrica Un. 0.25 1.93 0.48 1.925
Mesa de trabajo Pza. 0.10 2.20 0.22 2.200
Escalera de madera de 4 m H-E 0.50 2.75 1.38 2.750
Petrleo gln 6.00 9.35 56.10 9.350

MANO DE OBRA 3,734.04


Ingeniero de seguridad 0.10 h-h 4.00 52.50 210.00 52.500
Capataz en trabajos elctricos 0.50 h-h 20.00 20.45 408.96 20.448
Operario en trabajos elctricos 2.00 h-h 80.00 17.24 1,379.52 17.244
Oficial en trabajos elctricos 2.00 h-h 80.00 15.13 1,210.56 15.132
Ingeniero electricista 0.25 h-h 10.00 52.50 525.00 52.500

MAQUINARIAS Y EQUIPOS 293.08


Estuche de herramientas para mecnico 0.50 h-m 20.00 1.32 26.40 1.320
Camioneta pick up 4 x 2 d.cab. 0.10 h-m 4.00 45.42 181.68 45.420
Megger 0.25 h-m 10.00 5.50 55.00 5.500
Taladro elctrico 0.25 h-m 10.00 3.00 30.00 3.000

HERRAMIENTAS 186.70
Herramientas manuales y equipos de proteccin % m-o 5.00 3,734.04 186.70

COSTO DIRECTO TOTAL S/. 4,291.25


Unidad p.u. (US$) p.u. (S/.)
Capataz h-h 6.78
Oficial h-h 6.15 12.06
Operario h-h 5.44 13.62
Pen h-h 4.39 10.89
Tcnico Elctricista I h-h 8.78
Tcnico Elctricista II h-h 7.02
Tcnico Elctricista III h-h 6.15
Ingeniero Elctricista h-h 14.04
Equipos
Equipo de tratamiento de aceite h-m 121.329
Equipos de Medicion h-m 26.442
Equipos de pruebas y puesta en servicio h-m 35.256
Montacargas 3Tn h-m 40.287 90.06
Montacargas 5 Tn h-m 51.298 114.66
Montacargas 7,5Tn h-m 62.972 140.76
Caja de herramientas h-m 2.847
Gra 20 Tn h-m 95.472 213.41
Camin gra de 6 Tn h-m 43.446
Camin plataforma 4x2, 122 HP, 8 Tn h-m 49.907
Camin Plataforma de 8 Tn h-m 49.907
Camioneta 4x4, doble cabina h-m 34.632 77.41
Materiales 0
Riel 60 lbs/yd m 121.641
Soldadura cellocord kg 5.291
Electrobomba de 1/2 HP u