Documentations and other work requirements for the approval of the SEPCiN
PTW shall be complied with.
Reasons for Step Night work (22:00 06:00hrs) is required to successfully complete
Out: mechanical and system integration/upgrade tie-in works during the Soku Gas
Plant shutdown window. Details of the tasks to be carried out and justification
for same are included in the table below.
2
2. Egunatum Uche - Project Engineer (SPDC)
3. Bola Duyilemi - Senior QA/QC Rep (SPDC)
4. Kunle Hamzat - Site Mechanical Site Rep (SPDC)
5. Bagshaw Somiari - Site Civil Site Rep (SPDC)
6. Ellis Bubu - Site PACO Site Rep (SPDC)
7. Abiola Busari - Contractor Project Engineer (Steve Integrated Tech
Services Ltd)
8. Elliot Ifidon - Contractor HSE rep (Steve Integrated Tech Services
Ltd)
9. Jude Odionye - SPDC HSE site rep
Notes:
1. Working alone is not allowed, buddy system shall be maintained throughout the HSE STEP OUT
duration
2. There should be clear communication protocol at night between the project and Asset teams
3. The requirements of this HSE step out must be communicated at tool box meetings before
commencement of work
4. Asset team to provide all necessary emergency cover in accordance with project E.R plan.
We confirm that the activities in the contract covered by this step-out application will be executed in a
safe, healthy, and environmentally responsible manner.
Contractors will be required to confirm their understanding and commitment to comply with these
controls in writing as a requirement to be considered for the implementation of this waiver. Approved
security plan for activity available.