Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
UAE UNIVERSITY
(KFM-016-2016)
1. TITLE
2. SCOPE OF WORK
This statement is to define the Supply and installation of Painting Works in UAE University.
2. SCOPE OF WORK
The scope of this method statement is to define the general procedure that will be
followed for the Supply and installation of Painting Works in various areas (as follows,
Vacuum Cleaner
Mobile Scaffolds
Ladder
PPE
Access routes: Use and follow the defined routes to the UAE University and relevant
work Permits from M/s. KHADAMAT.
Communication at site shall be effected through Mobile phone & land lines.
Toolboxes and safety awareness talks shall be observed at site before
Initiating critical activities to properly communicate to the working level all
The hazards involved.
By Phones:
Before commencing the work have to take necessary permission from the authority
(M/s KHADAMAT)
Locating the work area under the supervision of the authority
Storage of Material
These are properly labeled on both the material and the storage area to indicate
the material status at all times.
Store material in a cool, well ventilated and dry place, away from direct sunlight.
Ensure adequate ventilated application.
Avoid contact with skin or eyes. Any skin or eye contamination should be washed
immediately with plenty of water and seek medical treatment.
All materials are under the responsibility of the material controller and the
supervisor on duty at each of the floor level.
Handling of Materials
All equipment and materials will be handled in such a manner as not to damage
the item and hence its performance.
This will allow materials and equipment to be marshaled just in time for the
installation commencement of these phases, maximizing efficiency of delivering
and minimizing storage equipment.
All materials delivery will be carefully supervised and coordinated and proper
documentation will be kept throughout the contract period. Such deliveries will
be arranged in conjunction with site requirements and programs need.
All materials will be checked against specifications and expiry dates verified.
Shifting skates/rollers and a small bottle jack may be required for final
positioning. Care will be taken when towing equipment on rollers.
Painting
The Site Engineer/ Supervisor inspects the surface is ready to receive the
paint coat.
Work will be done in proper illuminated areas.
Thinning or any mixing will be as per manufacturer recommendation.
Primers to be applied to thickness as specified
First coat of paint is applied following suitable application medium
(brush/roller) and to required thickness as per manufacturer
recommendations.
Additional coat will be applied on repaired crack areas if any.
Additional Coats of paint applied allowing for sufficient time in between each
coat for curing.
Care will be taken to avoid any paint splashes, brush marks etc. and will be
cleaned as necessary to obtain quality finishing.
Engineers approval will be taken.
2.6 RESPONSIBILITY
Responsibility:
Responsibility:
Responsible for scheduling day to day activities at site Ensure that the work is
executed as per contract specification.
Responsible for the follow up and updating of work schedule
Responsible for material requisition
Responsible for coordination with quality and HSE engineers
Ensure the welfare and safety of the personnel working under him.
Emergency Procedures
RISK ASSESSMENT
Initial Risk Rating Resultant Risk Rating
S/N Hazard Potential ES&H Effects Proposed Control Measures
S L R S L R
" Use of PPE including hard hat, high visibility vest, safety glasses,
safety boots, gloves, appropriate work clothing and hearing
protection if necessary. " All personnel will be site safety inducted.
1 General Work Injury to personnel 3 3 9 3 1 3
"First aid available on site. "Emergency evacuation plan highlighted
to site personnel, and where assembly point is located. " STARRT
Talks.
Wear cotton clothing underneath the coveralls
2 Heat stress Fatigue / Dehydration 4 4 16 Avoid exposure to peak mid day sunlight 2 1 2
Provide drinking water and frequent breaks
Wherever possible mechanical handling devices shall be used.
Size of load shall be reduced when it is necessary to walk
considerable distance in confined areas.
3 Manual lifting Muscular skeletal injuries. 3 3 9 2 1 2
Heavy load shall be assessed before lifting and help obtained from
other members of the site team.
Inspect the ladder at the start of every day. Ensure the base of
ladder is on solid level surface. Tie of the top of the ladder.
Make sure the ladder extends at least 3 feet above the
surface. Always maintain a three point contact while on the
Falls, cuts, abrasions,
4 Ladders 5 4 20 ladder. Never use a metal / aluminum ladder when working 2 2 4
broken bones and death
around electricity. Use full body harness and hook off. Have
one person spotting the foot of the ladder, Conduct a tool box
talk and start card talk. Be sure that all the ladder you use is
color coded for that quarter.
Work access area shall be maintained in a neat & tidy condition, free
of debris &material that will pose a
Hazard
All crafts need to clean up daily in their area, dispose of and remove
10 Housekeeping Slip, trip and falls 2 3 6 unused materials.Starrt talk conducted with site personnel on 2 1 2
housekeeping issues.
RISKMATRIX
RiskRatingTable 1 2 3 4 5
1 1 2 3 4 5
2 2 4 6 8 10
Severityof
3 3 6 9 12 15
Hazard
4 4 8 12 16 20
5 5 10 15 20 25
RiskRatingTable
Rating ProcessRequirements