Topic 2

Taking Off Quantities for Building and Civil Engineering


Works
- Foundation-

Prepared By: Pn Asmawati Che Hasan


Room: No 38, Level 5, FKA
UiTM Pasir Gudang
CO2 : Prepare taking Off Sheet, bill of quantities and
estimate the total cost of building and civil
engineering works in accordance to SMMM and
CESMM

PO3: Ability to identify, formulate and solve


engineering problems using thinking skills and
engineering reasoning
Lesson Outcome

2.1 Prepare the taking off sheet and bill of quantities


for concrete, reinforcement and formwork for;
Beam
Foundation
Stump/column
Slab
Example 1
Figure 1 shows the detailing of pad footing and stump to be constructed. Carry out the
calculation for quantities of material for the formwork, concrete and reinforcement bar for
the stump and pad footing. Given the concrete cover for pad footing and stump is 30 mm and
sawn timber used is 25 mm thick. Concrete grade25 is used for the pad footing and stump.

L1 L2 H Ties

1500 1500 450 T20


1800

4T16
R8-150 8T20

8T20

Figure 1
Times Dim Qtt Description Timesi Dim Qtt Description
ing ng
Excavation Concrete
Pad Footing
Excavation of top soil
1/ 1.500 1.5 x 1.5 x0.45
1.500
2.250 1/ 1.500
2.250 m2 top soil
1.500
0.450 1.012
1.012 m3 concrete
Excavation of depth of trench <1.5
Stump
Depth 1.8
Depth 1.800
(-) top soil 0.15 (-) Pad footing 0.450
1.65 (-) Ground beam 0.450
1/ 1.500 (+) lean concrete 0.05 0.900
1.500 1.70 1/ 0.125
1.500 3.375 0.450 0.051 m3 concrete
0.900 0.051
3.375 m3 Lean Concrete
lean concrete thickness = 0.05
Excavation of depth of trench >1.5 1/ 1.500
Depth 1.8 1.500 0.113 m3 lean concrete
(-) top soil 0.15 0.05 0.113
1/ 1.500 1.65 Reinforcement
1.500 (+) l.c 0.05
0.200 1.70 Pad Footing (8T20 B/W)
0.450
(-) trench 1.500
Length = 1.500
0.200 (-) 2cover = 0.060
1.44
1/2/8/ 1.660 26.560 (+) 2 bend
0.450 m3 (2)(5.5)(0.02) = 0.22
1.66
26.560m T20
Times Dim Qtt Description Timesi Dim Qtt Description
ing ng
Ties Link
Length = 1.500
(-) 2 cover 450 R8
2(0.030) = 0.060
1.440
1.440 (4 sides) = 5.760
Length = 0.125
(-) 2 cover
(+) anchorage =
2(15)(0.020) = 0.600 2(0.030) = 0.060
6.360 0.065
(0.065 ) x 2 sides = 0.130
1/1/ 6.360 6.360
6.360 m T20 Length = 0.450
2(0.030) = 0.060
0.390
Stump
(0.39) x 2 sides = 0.780
Length = 1.800 (+) anchorage, 24d
(-) cover = 0.030 24(0.008) = 0.192
1.770 1.102
(-) 2T20 = 0.040
= 1.730 No of Stirrups
(+) lapping Length = 1.800
40(0.016) = 0.64 (-) cover = 0.030
2.370 1.770
(+) bend (-) 2T20 = 0.040
5.5 (0.016) = 0.088 = 1.730
2.458 (-) Ground beam = 0.450
1.280
1/4/
2.458 1/10/ 1.102
9.832 9.832m T16 (1.280/150)+1 = 9.53
11.020
Say, 10

11.020 m R8
Time Dim Qtt Description Timesi Dim Qtt Description
sing ng
Formwork

Pad Footing
Length = 1.5

height = 0.45
+ lean concrete = 0.05
0.500
1/4/ 1.500
0.500 3.000 3.00 m2 sawn timber 25mm thick

Stump

Length = 1.800
(-) Ground beam = 0.450
1.350
(-) Pad Footing = 0.450
0.900
1/2/ 0.125
0.90 0.113 0.113 m2 sawn timber 25mm thick

1/2/ 0.450
0.90 0.81 0.810 m2 sawn timber 25mm thick
Bill of Quantity
Item
Description Quantity Unit Rate RM
No.
Excavation
1 Excavation of top soil, 150mm 2.250 Sq.m
Excavation of trench depth not exceeding
2 3.375 Cu.m
1.5m
Excavation of trench depth exceeding 1.5m
3 but not exceeding 3.0m 0.450 Cu.m

Concrete
Concrete Grade 25
4 1.063 Cu.m
1.012+0.051

5 Lean concrete
0.013 Cu.m
Reinforcement
6
T20,
6.36+26.560 = 32.920m 81.196 Kg
(3.14x0.0102x32.920x7850)
7 T16, (3.14x0.0082x9.832x7850) 15.520 kg

8 R 8, 11.020m (3.14x0.0042x11.020x7850) 4.349 kg


(Density of steel bar, assume = 7850kg/m3)

8 Sawn Timber 25mm thick


3.923 Sq.m
3.000+0.113+0.81

Total Bill RM