Tetrapods North
the Arctic Circle
By SVERRE KJELSTRUP, Chief Engineer,
Norwegian Ports Authority, Sth Distrct-Tromss
Historical
Berlevaag is a small fishing port of some
1,500 inhabitants, situated on the Nor
Wwegian coast inside the Aretie Circle, mid
way between the North Cape and the port
of Vard6, which is not far from the Russian
order. ‘The climate is harsh and fishing
is the sole means of livelihood. For over
a century, however, the rich bounty of the
sea, which hardly varies from year to year,
has assured the prosperity of the coastal
population in this province of Finnmarken,
Which is exposed co winds of gale force.
There are few good harbours in this
region. There is also a lack of natural
‘tection in the form of reefs and islets
4 the Arctic Ocean can on occasion dis-
play a savage power. Berlevaag is par-
ticularly vulnerable to storms from N. to
E. The only other harbour of any size in
the area is Baatsfjord where the annual
catch, in the region of 28,000 tons, is
larger than any other brought in on Nor-
way's northern seaboard.
Harbour improvement at Berlevaag
started at the beginning of the 20th Cen-
tury with the deepening of the natural
harbour basin of “Vagen” which consti-
tutes the port proper, In 1909, however, a
large number of the ‘raft in this harbour
were destroyed by a nor’ nor’ easterly
storm, As a resul:, the Varnes breakwater
was built, being finished in 1926. °
‘A scheme involving the construction of
two new breakwaters was drawn up to
extend. the area of available calm water
inside the harbour. The Svartoksen break-
water, the most westerly one, was begun
towards 1920. The structure’ was of the
‘Sle mound embankment type. The
awerry was five kilometres east of the bar-
Dour and the link was provided by the
railway line, but the rock fill available was
ff very poor quality and therefore a great
deal had to be quarried before blocks of
the size required for the facing could be
obtained. Nevertheless work was able to
proceed at a steady pace until, in 1932, @
violent north-easterly gale destroyed the
structure, It was then decided to rebuild
and reinforce the breakwater, whilst retain
jing a rock fill facing. By 1940, the struc-
ture was still not complete and the con-
S struction work was very much slowed,
“down during the war. After being bombed
by the Russians Berlevaag was set on fire
of
by the Germans during their retreat in
1944 and the whole area was destroyed,
including the port installations
The first necessity was to rebuild houses,
next, to put the fishing harbour back int
working order. It was not until somewhere
around 1950 that work could be restarted
on the breakwater. By 1958, the structure
ARCTIC OCEAN
Syartoksen mole (cenpit
Brief Survey of Local Conditions
Before proceeding with a detailed
examination of the problems raised by the
use of Tetrapods in Arctic waters, some
account of the particular conditions at
Berlevaag may not be out of place,
The tide range is relatively large, rea:
ing 3.60 m. for spring tides, whilst the
average range is 2.50 m, The summer is
short but on occasions temperatures may
be very high, e.g, temperatures of over
30°C. have been recorded but they did not
last more than a few weeks. Winter sem-
eratures can be as low as - 20°C. and
en ~25°C, generally accompanied by
strong winds.” This means that the break-
water is covered with a thick layer of ice
jn winter but on the other hand the sea
never freezes over at Berlevaeg and the
i983)
Revnes mole (under censircion)
ov 100 2000 2s0m
ee
‘ie plan of Berlevaag Horbour, Finnmark
was within 50 metres of completion. The
facing on the seaward side was built up
from 15 ton conerete cubes. On the 6th
of January, 1959, however, another fierce
gale, this time from the E.N-E., wrecked the
seaward end of the breakwater along some
90 metres and all the concrete blocks were
washed down on to the harbour side.
Although the damage was less than in
1932 the breakwater tip had to be rebuilt
again. In 1959, after much theoretical and
scale model design research, it was decided
to use Tetrapods in the facing
breakwater is therefose free from damage
caused by ice pressure, Sea temperatures
remain above freezing and the concrete
structures affected by the tide range are
subjected to freeze and thaw twice daily
These conditions call for the use of excep-
tionally high quality concrete,
Breakwater Profile Design Stwi
Before the work of rebuilding the sea
ward end of the Svartoksen breakwater
could be undertaken it was essential to
carry out design work and scale model
tests to find the optimum profil./ —Teirspod armour om Svartoksen Mole
The first necessity was to determine the
characteristics of the waves which had
destroved the structure in January 1959
The meteorological charts for this period
were analysed and from the fetch, dura
n und strength of the wind it was possi-
ble to determine the wave amplitude. The
observed damage was then reconstructed
by means of stability tests on a scale model
at the Maritime Section of the Technical
University of Trondheim. An identical
model cross-section of the breakwater was
built to represent the structure before its
destruction and subjected to waves of
reasing amplitude, There was complete
‘eement between the results of both the
eorologicsl study and the wave fume
sts and it was therefore possible to estab-
ish the amplitude of the highest waves of
the storm at approximately & metres,
Design studies were then carried out to
Jetermine the final profile to be adopted
che rebuilt structure, The model tesfs
were carried out in Grenoble in the labora-
~ f
Messrs. Sogreah (the Societé
Grenobloise d'Etudes et 4'Applicarions
Hydrauliques) on behalf of Sotramer
Grenoble (the Société d’Exploitation de
revets pour Travaux a la Mer). An essen:
dition was the need to re-use the
g 15-ton blocks stored
nd those which had been washed away
by the storm, which could
covered.
twas thought
Sogreah
design @ profile around crest
these blocks,
works built of
The final design is shown in Fig. 1. The
breakwater armour is built of 15-ton (63
cu. m.) Tetrapods with two rows of 15-
ton cubic blocks forming a platform for
the mobile crane operat he (+6.20)
level. The crest. works between the
(6.20) and the (+8.00) levels consist of
four 15-ton cubic blocks placed from the
breakwater head after the main work had
been completed and just before crane was
This runni jon was designed to
resist storms producing waves of up to
9 metres amplitude without serious
age. For the more
water head, however,
ction was necessary. After further wave
tank tests in Grenoble it was decided to
uuse 25-ton (10 cu, m.) Tetrapods on a trun:
sted cone shaped breakwater head, the
stability of which was practically the same
as that of the running section. As the
vulnerable break:
2€ effective pro
The model breakwoter heed in a wave tank,
ships of this tonnage cannot
hat Berlevaag and must anchor in the
stead, being loaded and unloaded by
lighters and bar
the same direction, an even stronger design
would be a square breakwater head faced
with 25-ton (10 cu, m.) Tetrapods, but ia
this case the safety factor would be higher
than that of the running section, which is
unnecessary, especially as it would also be
more expensive,
Other thkee dimensional experimental
studies, toa scale of 1:110, were carried
cout in the Trondheim laboratory to investi-
te methods of countering waves from the
‘open sea and to find out how the waves
are damped inside the harbour. The
object of these tests was to the
layout and exact lengih of the second,
breakwater to be built on
eastern side and to find the best site for
a quay for ocean going vessels. At the
Revnes,
The Works
The west or Svartoksen breakwater has
now been completed, Construction work
the final breakwarer head protected by
25-ton Tetrapods is still going on and the
Taising of the crest werks between the
(46.20) and (+8.00) levels will be finished
during the summer of 1968. Owing to the
inlavourable climate it has not been possi-
ble to maintain a very rapid rate of con:
struction, The winter lasts until May and
the site is unworkable before the end of
‘hat month, Thus only some four months
are available for construction work, since
the equinoetial gales start at the end of
September or during October. A_t
porary breakwater head of 15-ton Tetza
pods must therefore be built early in
Tetraped facing on Svartoksen Mole
The model breakwater profile in @ wave flumeautumn every year in the hope that it will
afford sufficient protection until the fol
lowing spring.
Special care must be taken with the
nerere, In view of the risk of frost
lamage, especially in the area affected by
the tide range, the conerete used for the
Tetrapods contains 400 kg. of cement per
fe metre, craining agent in
the form of a resinous oil is added and the
mix, which must be as dry as possible
(watercement ratio below 0.45) must. be
efully vibrated.
Specimens are taken
egularly for compression the
laboratory and the mean compressive
strength after 28 days has always been
over 300 kg./sa. em.
The majority of the blocks are provided
ng eye for easier removal each
rapid positioning if a storm
1r as possible, however, the
1B eyes has been kept to a
ninimum, since they represent a source
of corrosion. Wherever possible slings
have been used to place the Tetrapods.
With a view to obtaining precise data on
wave periods and amplitudes during
storms, the Norwegian Port Authority
has been operating a wave recorder for
the past three years some 400 metres out
to sea from the Svarioksen breakwater.
‘The pressure variations on the sea bed are
relayed 10 the shore station by cable and
jn this way a continuous record can be
Kept of the waves during storms.
Preporing 10 pour concrete in Tetrepod.
Results Obtained
Several storms occurred during the
winter of 1961-1962 and wave amplitudes
of some six metres were observed,
A certain limited amount of settling
took place on the temporary breakwater
head, faced with 63 cu. m. Tetrapods, and
some blocks broke away from the main
‘mass during the winter of 1961-1962 but
no serious damage was observed. During
the north-easterly gale of 10th December,
1962, on the other hand, when the maxi-
mum amplitude was 7.44 m. for a period
of 12 seconds, no damage was suffered by
the breakwater,
Work Still to be Done
If the port of Berlevaag is to be com
pletely protected against storms the second
(Revnes) breakwater must be built, The
layout has been chosen but certain details
of the profile have still to be determined.
The first 200° metres have already been
built and protected by means of @ rubble
armour. As this part of the breakwater
lies in shallow water a lightly-built steuc~
re was acceptable. The rest of the break-
fer on the other hand will be subjected
to the same conditions as the Svartoksen
one and the present intention is t0 build
4 very similar type of construction, with
aan identical breakwater head.
Conclusions
‘The improvement of Berlevaag harbour
is a problem of great importance for this
locality. The town was linked to the State
road network in 1959 but the new road
is impassable during the winter owing to
the heavy snowfall. Thus for half the year
the only access to Berlevaag is by ‘sea,
which is moreover the source of livelihood
of the inhabitants: the harbour is there-
fore the corner stone of their existence
The total cost of the work on this har-
bour between 1903 and 1959 amounts to
16 million Kroner, i.e. over 10 million
francs. The final cost, including the work
of reinforcing the Svartoksen breakwater
carried out since 1959 and the work of
building the Revnes breakwater, still to be
done, will amount to 31 million Kroner
(over 20 million franes)
‘The manufacture and use of TETRAPODS are pyiented in over 60 countries, exclusive licensing rights being held by
SOTRAMER, B.P.52, GRENOBLE, France (Gram:
SOTRAMER — Telex No. 31.050 — Phone: 44.55-30).
SOTRAMER is represented in 36 countries, with main Agents in the following cities:-
LONDON
Vauxhall Bridge Road, $.W.1
Grams: AFTRADERS
Phone:- ViCtoria 0231
Telex:- No. 25.398
NEW YORK
NEYRPIC I
375 Park Avenue, N.Y. 22
Grams:- NEYRPICAM
Phone:- Plaza 1.1820
PARIS
SOTRAMER
8, rue Bellini, XVIe
Phone:- PASsy 51.09
Telex:- 27.963
Descriptive literature and a preliminary design are available to prospective Tetrapod users free and without obligation on request.