ID Task Name Duration start finish

1 Overall Project Schedule 2/11/2017 3/22/2017


2 Delivery Milestones for KOD vessel 2/11/2017 3/22/2017
3 KOD Vessel 3/22/2017 3/22/2017
4 Order Receipt 2/11/2017 2/11/2017

5 Submission/ Approval project control documents 2/14/2017 2/19/2017


6 L4 Activity Schedule 2/14/2017 2/19/2017
7 Submission for review to CCED
8 Comments from CCED
9 Submission for approval/comments to CCED
10 Comments from CCED
11 document register 2/12/2017 2/19/2017
12 Submission for review to CCED
13 Comments from CCED
14 Submission for approval/comments to CCED
15 approval from CCCED
16 Engineering 2/11/2017 2/19/2017
17 Design Calculations 2/15/2017 2/19/2017
18 Issued for comments to CCED
19 Comments from CCED
20 Issued for Approval to CCED
21 Approval from CCED
22 Issued for Const.
23 GA Drawing 2/16/2017 2/19/2017
24 Issued for comments to CCED
25 Comments from CCED
26 Issued for Approval to CCED
27 approval from CCED
28 issued for const.
29 Changes in Design submission for approval
30 comments and approval from CCED
31 issue for construction
32 surface preparation and painting 2/13/2017 2/19/2017
33 Issued for comments to CCED
34 Comments from CCED
35 Issued for Approval to CCED
36 approval from CCED
37 Quality 2/11/2017 2/19/2017
38 Quality Control Plan/ Stage Inspection Schedule 2/14/2017 2/19/2017
39 Issued for comments to CCED
40 Comments from CCED
41 Issued for Approval to CCED
42 approval from CCED

43 Method Statement for Modification of KOD vessel 2/14/2017 2/19/2017


44 Issued for comments to CCED
45 Comments from CCED
46 Issued for Approval to CCED
47 approval from CCED

Welding Procedure specification & Welding


48 Procedure 2/13/2017 2/19/2017
49 Issued for comments to CCED
50 Comments from CCED
51 Issued for Approval to CCED
52 approval from CCED
53 issued for const.
54 Welder Performance Qualification 2/13/2017 2/19/2017
55 Issued for comments to CCED
56 Comments from CCED
57 Issued for Approval to CCED
58 approval from CCED
59 Issued for Const.
60 Welding Repair Procedure 2/14/2017 2/19/2017
61 Issued for comments to CCED
62 Comments from CCED
63 Issued for Approval to CCED
64 approval from CCED
65 Radiography Procedure 2/16/2017 2/19/2017
66 Issued for comments to CCED
67 Comments from CCED
68 Issued for Approval to CCED
69 approval from CCED
70 Magnetic Particle inspection Procedure 2/16/2017 2/19/2017
71 Issued for comments to CCED
72 Comments from CCED
73 Issued for Approval to CCED
74 approval from CCED
75 Pressure Test Procedure 2/14/2017 2/19/2017
76 Issued for comments to CCED
77 Comments from CCED
78 Issued for Approval to CCED
79 approval from CCED
80 Quality Dossier Index 2/15/2017 2/19/2017
81 Issued for comments to CCED
82 Comments from CCED
83 Issued for Approval to CCED
84 approval from CCED
85 Material Procurement & Delivery to Shop 2/19/2017 2/19/2017
86 Plates for Flush Patches 2/19/2017 2/19/2017
87 Shortlisting Vendors
88 Enquiries to shortlisted Vendors
89 Reciept of quotation from sub vendors
90 Technical and commercial bid evaluation
91 final negotiation with approved vendor
92 Placement of Purchase order
93 Delivery to Shop
94 Modification of KOD 2/19/2017 3/22/2017
95 Vessel No. (MFME-PE-1006A) & (MFME-PE-1006B)
96 Removal of Platform and Ladder 2/20/2017 2/20/2017
97 Surface weld build up 2/20/2017 2/20/2017
98 MPI of surface build up 2/21/2017 2/21/2017
99 Machining and Forming Curvature 2/22/2017 2/22/2017
100 Cutting of Nozzles and Fit up of Flush Plate 2/22/2017 2/22/2017
101 Welding of Flush patch plate 2/23/2017 2/23/2017
102 Radiographic testing 2/23/2017 2/24/2017
103 Internal cleat welding @ painting touch up 2/23/2017 2/23/2017
104 Hydrotest 2/26/2017 2/26/2017
105 blasting 2/27/2017 2/27/2017
106 Primer coat painting 2/28/2017 2/28/2017
107 Mid coat painting 3/1/2017 3/1/2017
108 Final Coat painting 3/2/2017 3/2/2017
109 curing time 2/9/2017 2/9/2017
110 Installation of Anode 2/9/2017 2/9/2017
111 Final Inspection 2/9/2017 2/9/2017
112 Packing 2/10/2017 2/10/2017
113
114 Vessel No. (MFME-PE-1006C) & (MFME-PE-1006D)
115 Removal of Platform and Ladder 2/20/2017 2/20/2017
116 Surface weld build up 2/20/2017 2/20/2017
117 MPI of surface build up 2/21/2017 2/21/2017
118 Machining and Forming Curvature 2/22/2017 2/22/2017
119 Cutting of Nozzles and Fit up of Flush Plate 2/22/2017 2/22/2017
120 Welding of Flush patch plate 2/23/2017 2/23/2017
121 Radiographic testing 2/23/2017 2/24/2017
122 Internal cleat welding @ painting touch up 2/23/2017 2/23/2017
123 Hydrotest 2/26/2017 2/26/2017
124 blasting 3/11/2017 3/11/2017
125 Primer coat painting 3/11/2017 3/11/2017
126 Mid coat painting 3/12/2017 3/12/2017
127 Final Coat painting 3/13/2017 3/13/2017
128 curing time 3/20/2017 3/20/2017
129 Installation of Anode 3/20/2017 3/20/2017
130 Final Inspection 3/21/2017 3/21/2017
131 Packing 3/22/2017 3/22/2017
132 Compilation of QC Dossier 3/23/2017 3/23/2017
133 End of Project 3/23/2017 3/23/2017
Predecessor Successor

133

8
9
10

16
13
14
15

26
19
20
21
22

94

105

94
97

97

94

102

96

104

112

94
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112