Sei sulla pagina 1di 13

Our ref : GOSB/GMB/PGFLS_1/14/FA/793

Your ref : GMB/GNID/IDS/L0371/2017

Date : 06 FEBUARY 2016

GAS MALAYSIA BERHAD


No. 5, Jalan Serendah 26/17,
Seksyen 26
40732 Shah Alam
Selangor Darul Ehsan

Attn: MR. K. SURESH


Project Manager
Gas Networks & Infrastructure Department

Dear Sir,

EPCC OF NGDS TO PASIR GUDANG FL STAGE 1/14


(PETROCHEMICALS) (793)
- REQUEST OF FINAL ACCEPTANCE

With reference to the above ,we would humbly request the issuance of Certificate of Final
Acceptance of the above project as the guarantee period of 12 months has ended.

For information, the Initial Acceptance was obtained on 14 November 2014.

We understand that , the Certificate of Final Acceptance will only be issued once the
relevant authorities have released the letter of satisfactory completion . However, we would
like to request to be exempted from the submission of the said letter since our guarantee
sum is still in the possession of the authorities.

Therefore , we will agree to undertake the following :

i. Perform any further obligation as and when required by the relevant


authorities in relation to the work at site of the above said contact and
ii. Compensate Gas Malaysia Berhad (GMB) for any losses arising from any
claim from authorities for any defects of work at site under the jurisdiction of
the said authorities for this project contract.

The issuance of this certificate shall not be construed as a waiver nor prejudice of Gas
Malaysias rights under the aforesaid contract.

Your approval on this matter is highly appreciated.

Thank you.

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
Yours faithfully,
GALAXY ONSHORE SDN BHD

Ir. AHMAD PAUZI ABDULLAH


Project Manager

Our ref : GOSB/GMB/PGDLS_1/15/FA/848

Your ref : GMB/GNID/IDS/L0371/2017

Date : 06 FEBUARY 2016

GAS MALAYSIA BERHAD


No. 5, Jalan Serendah 26/17,

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
Seksyen 26
40732 Shah Alam
Selangor Darul Ehsan

Attn: MR. K. SURESH


Project Manager
Gas Networks & Infrastructure Department

Dear Sir,

EPCC OF NGDS TO PASIR GUDANG DL STAGE 1/15


(CK GALVANIZINGSDN BHD)(848)
- REQUEST OF FINAL ACCEPTANCE

With reference to the above ,we would humbly request the issuance of Certificate of Final
Acceptance of the above project as the guarantee period of 12 months has ended.

We understand that , the Certificate of Final Acceptance will only be issued once the
relevant authorities have released the letter of satisfactory completion . However, we would
like to request to be exempted from the submission of the said letter since our guarantee
sum is still in the possession of the authorities.

Therefore , we will agree to undertake the following :

I. Perform any further obligation as and when required by the relevant


authorities in relation to the work at site of the above said contact and
ii. Compensate Gas Malaysia Berhad (GMB) for any losses arising from any
claim from authorities for any defects of work at site under the jurisdiction of
the said authorities for this project contract.

The issuance of this certificate shall not be construed as a waiver nor prejudice of Gas
Malaysias rights under the aforesaid contract.

Your approval on this matter is highly appreciated.

Thank you.

Yours faithfully,
GALAXY ONSHORE SDN BHD

Ir. AHMAD PAUZI ABDULLAH

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
Project Manager

Our ref : GOSB/GMB/PJDL_2/15/FA/819

Your ref : GMB/GNID/IDS/L0421/2017

Date : 06 FEBUARY 2016

GAS MALAYSIA BERHAD


No. 5, Jalan Serendah 26/17,
Seksyen 26
40732 Shah Alam
Selangor Darul Ehsan

Attn: MR. IR TAN CHYE HONG


Project Manager
Gas Networks & Infrastructure Department

Dear Sir,

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
EPCC OF NGDS TO PUTRAJAYA DL STAGE 2/15
(RESIDENTIAL PERCINT 12 & COMMERCIAL LOT P12) (819)
- REQUEST OF FINAL ACCEPTANCE

With reference to the above ,we would humbly request the issuance of Certificate of Final
Acceptance of the above project as the guarantee period of 12 months has ended.

We understand that , the Certificate of Final Acceptance will only be issued once the
relevant authorities have released the letter of satisfactory completion . However, we would
like to request to be exempted from the submission of the said letter since our guarantee
sum is still in the possession of the authorities.

Therefore , we will agree to undertake the following :

i. Perform any further obligation as and when required by the relevant


authorities in relation to the work at site of the above said contact and
ii. Compensate Gas Malaysia Berhad (GMB) for any losses arising from any
claim from authorities for any defects of work at site under the jurisdiction of
the said authorities for this project contract.

The issuance of this certificate shall not be construed as a waiver nor prejudice of Gas
Malaysias rights under the aforesaid contract.

Your approval on this matter is highly appreciated.

Thank you.

Yours faithfully,
GALAXY ONSHORE SDN BHD

Ir. AHMAD PAUZI ABDULLAH


Project Manager

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
Our ref : GOSB/GMB/KMFLS_3/14/FA/812

Your ref : GMB/GNID/IDS/L0421/2017

Date : 06 FEBUARY 2016

GAS MALAYSIA BERHAD


No. 5, Jalan Serendah 26/17,
Seksyen 26
40732 Shah Alam
Selangor Darul Ehsan

Attn: MR. IR TAN CHYE HONG


Project Manager
Gas Networks & Infrastructure Department

Dear Sir,

EPCC OF NGDS TO KAMUNTING FL STAGE 3/14


(PROFESSIONAL LATEX SDN BHD) (812)
- REQUEST OF FINAL ACCEPTANCE

With reference to the above ,we would humbly request the issuance of Certificate of Final
Acceptance of the above project as the guarantee period of 12 months has ended.

For information, the Initial Acceptance was obtained on 27 MAY 2015.

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
We understand that , the Certificate of Final Acceptance will only be issued once the
relevant authorities have released the letter of satisfactory completion . However, we would
like to request to be exempted from the submission of the said letter since our guarantee
sum is still in the possession of the authorities.

Therefore , we will agree to undertake the following :

i. Perform any further obligation as and when required by the relevant


authorities in relation to the work at site of the above said contact and
ii. Compensate Gas Malaysia Berhad (GMB) for any losses arising from any
claim from authorities for any defects of work at site under the jurisdiction of
the said authorities for this project contract.

The issuance of this certificate shall not be construed as a waiver nor prejudice of Gas
Malaysias rights under the aforesaid contract.

Your approval on this matter is highly appreciated.

Thank you.

Yours faithfully,
GALAXY ONSHORE SDN BHD

Ir. AHMAD PAUZI ABDULLAH


Project Manager

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
Our ref : GOSB/GMB/PDLS_1/14/FA/811

Your ref : GMB/GNID/IDS/L0421/2017

Date : 06 FEBUARY 2016

GAS MALAYSIA BERHAD


No. 5, Jalan Serendah 26/17,
Seksyen 26
40732 Shah Alam
Selangor Darul Ehsan

Attn: MR. IR TAN CHYE HONG


Project Manager
Gas Networks & Infrastructure Department

Dear Sir,

EPCC OF NGDS TO PRAI DL STAGE 1/14


(FUJISASH (M) SDN BHD) (811)
- REQUEST OF FINAL ACCEPTANCE

With reference to the above ,we would humbly request the issuance of Certificate of Final
Acceptance of the above project as the guarantee period of 12 months has ended.

For information, the Initial Acceptance was obtained on 02 APRIL 2015.

We understand that , the Certificate of Final Acceptance will only be issued once the
relevant authorities have released the letter of satisfactory completion . However, we would
like to request to be exempted from the submission of the said letter since our guarantee
sum is still in the possession of the authorities.

Therefore , we will agree to undertake the following :

i. Perform any further obligation as and when required by the relevant


authorities in relation to the work at site of the above said contact and
ii. Compensate Gas Malaysia Berhad (GMB) for any losses arising from any

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
claim from authorities for any defects of work at site under the jurisdiction of
the said authorities for this project contract.

The issuance of this certificate shall not be construed as a waiver nor prejudice of Gas
Malaysias rights under the aforesaid contract.

Your approval on this matter is highly appreciated.

Thank you.

Yours faithfully,
GALAXY ONSHORE SDN BHD

Ir. AHMAD PAUZI ABDULLAH


Project Manager

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
Our ref : GOSB/GMB/NTDS_1/14/FA/807

Your ref : GMB/GNID/IDS/L0421/2017

Date : 06 FEBUARY 2016

GAS MALAYSIA BERHAD


No. 5, Jalan Serendah 26/17,
Seksyen 26
40732 Shah Alam
Selangor Darul Ehsan

Attn: MR. IR TAN CHYE HONG


Project Manager
Gas Networks & Infrastructure Department

Dear Sir,

EPCC OF NGDS TO NIBONG TEBAL DL STAGE 1/14


(CENTURY MOVE FIBRE ) (807)
- REQUEST OF FINAL ACCEPTANCE

With reference to the above ,we would humbly request the issuance of Certificate of Final
Acceptance of the above project as the guarantee period of 12 months has ended.

We understand that , the Certificate of Final Acceptance will only be issued once the
relevant authorities have released the letter of satisfactory completion . However, we would
like to request to be exempted from the submission of the said letter since our guarantee
sum is still in the possession of the authorities.

Therefore , we will agree to undertake the following :

i. Perform any further obligation as and when required by the relevant


authorities in relation to the work at site of the above said contact and
ii. Compensate Gas Malaysia Berhad (GMB) for any losses arising from any
claim from authorities for any defects of work at site under the jurisdiction of
the said authorities for this project contract.

The issuance of this certificate shall not be construed as a waiver nor prejudice of Gas
Malaysias rights under the aforesaid contract.

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
Your approval on this matter is highly appreciated.

Thank you.

Yours faithfully,
GALAXY ONSHORE SDN BHD

Ir. AHMAD PAUZI ABDULLAH


Project Manager

Our ref : GOSB/GMB/KMFLS_3/14/FA/001

Your ref : TBA

Date : 06 FEBUARY 2016

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
GAS MALAYSIA BERHAD
No. 5, Jalan Serendah 26/17,
Seksyen 26
40732 Shah Alam
Selangor Darul Ehsan

Attn: MR. IR TAN CHYE HONG


Project Manager
Gas Networks & Infrastructure Department

Dear Sir,

EPCC OF NGDS KUALA LUMPUR DL ST 1/12 KUALA LUMPUR


(PARK ROYAL HOTEL)
- REQUEST OF FINAL ACCEPTANCE

With reference to the above ,we would humbly request the issuance of Certificate of Final
Acceptance of the above project as the guarantee period of 12 months has ended.

For information, the Initial Acceptance was obtained on 04 SEPTEMBER 2012.

We understand that , the Certificate of Final Acceptance will only be issued once the
relevant authorities have released the letter of satisfactory completion . However, we would
like to request to be exempted from the submission of the said letter since our guarantee
sum is still in the possession of the authorities.

Therefore , we will agree to undertake the following :

i. Perform any further obligation as and when required by the relevant


authorities in relation to the work at site of the above said contact and
ii. Compensate Gas Malaysia Berhad (GMB) for any losses arising from any
claim from authorities for any defects of work at site under the jurisdiction of
the said authorities for this project contract.

The issuance of this certificate shall not be construed as a waiver nor prejudice of Gas
Malaysias rights under the aforesaid contract.

Your approval on this matter is highly appreciated.

Thank you.

Yours faithfully,

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com
GALAXY ONSHORE SDN BHD

Ir. AHMAD PAUZI ABDULLAH


Project Manager

GALAXY ONSHORE SDN BHD ( CO. REG. 543608-H)


No. 15 Jalan Putra Perdana 2/2, Taman Putra Perdana, 47130 Puchong, Selangor Darul Ehsan.
Telephone : 6 03 8325 1210 Fax : 6 03 8325 1209 Email : gosb.admin@gmail.com

Potrebbero piacerti anche