I. EARTH WORK:
a. Excavation- 182 to 2.89 man hours / cu.m.
b. Back Fill- 132 man hours/ cu.m
II. FORMWORK:
a. Footing, grade, column -2.5 man hours/ sq. m.
b. Beams, bond beams, floor slab 2.8 man hours/ sq. m.
c. Roof beams and bond beams 3.01 man hours/ sq. m.
d. Roof slabs 3.34 man hours / sq. m.
e. Retaining Walls 2.4 man hours / sq. m
f. Stairs and landing 2.48 man hours/ sq. m.
g. Form oil application 6.0 man hours/ sq. m.
III. REINFORCEMENT:
CAPABILITIES OF EQUIPMENT
(DI READABLE!) Type of Work Capability
1. (eto din!) a. clearing 500sq. m./ hr.
b. stripping 200 sq. m./hr.
c. excavation 25 cu. m./ hr.
d. quarrying 50 cu. m./ hr.
e. pushing 3 sq. m. /hr.
5 cmpt
1 metric ton of asphalt conc. covers 8 sq. of pavement 0.05 m. thick or 0.43 cu.m. of asphalt
concrete.
2. SUSPENDED MEMBER
Formwork _____________ 3.28 MH/M
Concreting _____________ 16.70 MH/M3
Rebars Work _____________ 0.08 MH/KG
Finishing _____________ 0.80 MH/M2
ARCHITECTURAL SPECIALTIES
TRUSSES
Truss Fabrication ------------ 46 BF / md
Truss Erection ------------ 40 BF /md
Posts ------------ 60-90 BF / md
Girts ------------ 50-75 BF / md
Plates ------------ 90-120 BF /md
Purlins ------------ 40-60 BF/ md
Facia Boards ------------ 25-35 BF / md
CABINETS
Framing ------------ 30-60 BF / md
Boarding ------------ 40-80 BF/ md
Plywood Sheating ------------ 75-150 ft2 / md
Cabinet & Doors ------------ 40-80 ft2 / md
EXCAVATION
Hand Excavation
Soil Excavation Man Hours /Cu.M.
/
Soft Clay Dry 2.50
cu.m.
/
Wet 3.51
cu.m.
/
Hard Medium Dry 4.90
cu.m.
/
Wet 8.50
cu.m.
/
Hard Adobe Dry 13.50
cu.m.
/
Wet 13.50
cu.m.
BACKFILL
Unit Man Hours
Labor Optr Oil Total
GRAVEL FILL
SELECTED FILL
ITEM MANHOURS
Unit Laborer Airtool Total
ELEVATED SLABS
With Pneumatic Breaker cu.m. 3.28 2.72 6.00
By Hand With Sledge cu.m. 16.24 16.24
CONCRETE WALLS
With Pneumatic Breaker cu.m. 1.03 2.06 3.09
By Hand With Sledge cu.m. 14.41 14.41
FORMWORKS
MANHOURS PER SQUARE METER
ITEMS MANHOURS
Carpenter Laborer Total
1 Continuous Wall Type (CHB) 0.70 0.40 1.10
2 Foundation of Pile Caps 1.50 0.65 2.15
3 Grade Beam or FTB 0.75 0.40 1.15
4 Walls Ground to 8 high 1.10 0.72 2.92
5 Walls 8 to 16 high 1.21 0.78 1.99
6 Walls 16 to 20 high 1.35 0.90 2.25
7 Columns 1.22 0.80 2.02
8 Beams and Girders 1.90 1.22 3.12
9 Elevated Slabs (Word Shores) 1.15 1.16 2.31
10 Elevated Slabs (Adjusted Shores) 0.70 0.90 1.60
SCAFFOLDING
LENGTH MANHOURS PER SECTION
1 or 2 Section High More Than 2 Section High
Erect Dismantl Total Erect Dismantl Total
e e
1 to 2 Section Long 1.20 0.35 2.05 1.40 1.00 2.40
3 to 5 Section Long 0.75 0.50 1.25 0.85 0.60 1.45
6 Section or more long 0.65 0.35 0.95 0.75 0.40 1.15
RE-USE FACTORS
CONCRETING
Item MANHOURS
Laborer Carpenter Operator Oiler Total
Continuous Wall Type Footings
Job Mix 5.10 0.05 0.05 5.20
Chute 0.75 0.05 0.80
Buggies 0.98 0.98
Spread Type Footings
Job Mix 5.10 0.05 0.05 5.20
Chute 0.86 0.07 0.93
Buggies 1.14 1.14
Footing Tie Beam
Job Mix 5.10 0.05 0.05 5.20
Chute 0.90 0.07 0.97
Buggies 1.48 1.48
Foundation or Basement Walls
Job Mix 5.10 0.05 0.05 5.20
Chute 0.90 0.07 0.97
Buggies 1.48 1.48
Columns
By Hand and Pulley 8.51 8.51
Porta-Lift 6.35 0.08 0.08 6.51
Crane, Bucket and 2.02 0.16 0.16 2.34
Buggies
Retaining Wall to 10 High
By Hand and Pulley 12.71 12.71
Porta-Lift 10.60 0.08 0.08 10.76
Tooled Joint Finish 3.67 1.22 4.89
Plain Cement Finish 4.00 0.47 4.47
(Louvre Blocks)
Glazed Tiles 6.38 2.13 8.51
Rubbed Concrete 4.27 0.11 4.38
LOADING DOCKS:
Carpenter Laborer Total
SUB-FLOORING:
NOTE:
1,000 foot board
measure
WALL COVERINGS:
INTERIOR TRIM: