Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
D I M I TA R H R I S T O F O R O V K O N D E V *
1. INTRODUCTION
* PhD Fellow at Aarhus University, Denmark and Senior Associate at Djingov, Gouginski, Kyutchukov
& Velichkov, Attorneys and Counsellors at law, Sofia, Bulgaria (www.dgkv.com). The author can be
contacted at dkondev@jura.ac.dk.
1
FIDIC is the French acronym of the International Federation of Consulting Engineers (www.fidic.
org). The FIDIC Contracts for Major Works referred to in this article include the Conditions of Contract
for Construction (or also known as Red Book), the Conditions of Contract for Plant and Design-Build (or
Yellow Book) and the Conditions of Contract for EPC/Turnkey Projects (or Silver Book). All references
in this article, unless explicitly indicated otherwise, are to the 1999 editions of these contracts.
2
For the purpose of convenience, I have used the names of the parties under the FIDIC Contracts in
the same way these parties are designated thereunder.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
Pt 3] Dispute Adjudication under FIDIC Contracts 257
3
This was the FIDIC Conditions of Contract for Design-Build and Turnkey Projects of 1995 (or also
called the Orange Book).
4
For more details about the history and nature of the DAB procedure, please see Jane Jenkins,
International Construction Arbitration Law, 2nd Edition. (Alphen aan den Rijn/Kluwer Law International,
2013), pp. 5664. See also Volker Mahnken, Why International Dispute Settlement Institutions should
offer ad hoc Dispute Board Rules [2006] ICLR 433, and Gtz-Sebastian Hk, Dispute Adjudication in
Civil Law Countries Phantom or Effective Dispute Resolution Method? [2011] ICLR 412.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
258 The International Construction Law Review [2014
employer which precluded him from making a fair and unbiased decision
on disputes5. Nowadays, the engineer is still involved in the dispute
settlement process at the stage when he has to make a determination on the
claims submitted by the parties6. However, once the claim crystallizes into
a dispute, i.e. the claim has been rejected by the engineer and the latters
rejection has also been rejected by the claiming party, then the role of the
DAB comes to the fore instead. The second reason for the introduction of
the DAB was to promote a new dispute avoidance mechanism. The dispute
avoidance function can be seen from the obligation of the DAB under the
Red Book to give opinions and recommendations if both parties jointly
require the DAB to do so7. In addition, the introduction of the DAB aimed
at decreasing the number of disputes which proceeded to arbitration by
creating a cheaper and faster way for resolution of construction disputes
while construction is still under way.
There are two types of DABs under the FIDIC Contracts8. Under the
Red Book, the DAB is a standing board which is constituted at the initial
stage of the construction project9. In contrast thereto, the DAB under the
Silver Book and the Yellow Book is an ad hoc board which is appointed
once the dispute has arisen10. As the reader will see in section 4.1 below,
the answer to the question posed in the title of this article depends on the
type of DAB which has been constituted.
Once seized with the dispute, the DAB should render its decision within
a term of 84 days and the party dissatisfied with the decision must serve
a notice of dissatisfaction if it is willing to pursue the dispute further11.
The decision is binding on the parties, unless, and until, it is revised in an
amicable settlement or an arbitral award12. If no notice of dissatisfaction
has been served against the decision, the dispute is deemed settled and the
decision becomes final. The notice of dissatisfaction triggers the next step
in the procedure.
5
This was due to the fact that the engineer was paid by the employer and, therefore, oftentimes
played to the tune of the employer. The engineer acted more as an employers agent and not as an
independent professional. For more details about the figure of the engineer under FIDIC Contracts
please see Ola Nisja, The Engineer in International Construction: Agent? Mediator? Adjudicator?
[2004] ICLR 230, and Helmut Kntges, International Dispute Adjudication Contractors Experiences
[2006] ICLR 306.
6
Sub-clause 3.5 FIDIC Contracts.
7
However, this function is envisaged under the Red Book only (sub-clause 20.2, paragraph 7). There
is no such a provision in the Yellow Book and the Silver Book.
8
As regards the pros and cons of the different types of boards, please see Christian Stubbe and
Michael Wietzorek, Making Dispute Boards Better with the One Plus One Model [2013] ICLR 4.
9
Sub-clause 20.2 Red Book.
10
Sub-clause 20.2 Yellow Book and Silver Book.
11
Sub-clause 20.4 FIDIC Contracts.
12
Sub-clause 20.4, paragraph 4 FIDIC Contracts.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
Pt 3] Dispute Adjudication under FIDIC Contracts 259
2.4. Arbitration
The final prong of the dispute settlement process under FIDIC Contracts is
arbitration under sub-clause 20.6. The arbitration clause proposed by FIDIC
is self-sufficient13. It contains reference to the ICC Rules of Arbitration and
envisages the composition of a three-member arbitral tribunal. The place
of arbitration can be chosen by the parties or determined by the tribunal in
case the contract is silent on this matter.
13
Christopher R. Seppl, The Arbitration Clause in FIDIC Contracts for Major Works [2005]
ICLR 4.
14
See Seppl, fn. 13 above, pp. 67. See also Dyal Jimnez Figueres, Multi-Tiered Dispute
Resolution Clauses in ICC Arbitration: Introduction and Commentary, in 14 ICC International Court of
Arbitration Bulletin, No 1 (2003), p. 71, Hk, fn. 4 above, pp. 422423, 426.
15
Please see Article 4 of the UNCITRAL Model Law in International Commercial Arbitration, available
at http://www.uncitral.org/pdf/english/texts/arbitration/ml-arb/07-86998_Ebook.pdf (Last accessed
22 April 2014), pursuant to which, the party who knows that any requirement under the arbitration agree-
ment was not complied with and yet proceeds with the application without stating its objection, shall be
deemed to have waived his right to object.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
260 The International Construction Law Review [2014
In these cases, parties should generally go through all the stages in sections
2.12.3 above16. This widespread opinion rests on three main arguments.
First of all, it is based on the interpretation of the FIDIC Contracts provisions.
Secondly, there are some arbitral awards which supposedly support the
opinion that dispute adjudication is a mandatory pre-arbitral step under
the FIDIC Contracts. And thirdly, the rationale for the introduction of the
DAB under the FIDIC Contracts further strengthens this argument. I will
now deal with each of these arguments below.
16
Seppl, fn. 13 above, pp. 67. As Christopher R Seppl has pointed out: The scope of the
arbitration clause is a narrow one as no dispute under the contracts may ordinarily go to arbitration
until it has run the gauntlet, so to speak, of clause 20. However, the author admits that the wording
under the 1999 Silver Book and 1999 Yellow Book is not satisfactory and might be interpreted in a way
which would allow the parties to by-pass the DAB phase of the dispute resolution process.
17
Pursuant to paragraph 5 of sub-clause 20.4, a notice of dissatisfaction should be given also in cases
where the DAB fails to give its decision within the prescribed period of time.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
Pt 3] Dispute Adjudication under FIDIC Contracts 261
18
For a detailed analysis about the topic see, for example, Christopher R Seppl, Enforcement by
an Arbitral Award of a Binding but not Final Engineers or DABs Decision under the FIDIC Conditions
[2009] ICLR 414. See also Gtz-Sebastian Hk, Dispute Adjudication Boards The International or
Third Dimension [2012] ICLR 420.
19
Seppl, fn. 13 above, pp. 67.
20
Seppl, fn. 13 above, pp. 67.
21
Excerpts from these awards have been published in the ICC International Court of Arbitration Bulletin
and have been commented on by Christopher R Seppl in a series of commentaries.
22
The awards deal with disputes that have arisen under the second (1969), third (1977) and fourth
(1987) Editions of the FIDIC Contracts.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
262 The International Construction Law Review [2014
23
Final Award in Case 6535 (Extract), in 9 ICC International Court of Arbitration Bulletin, No 2 (1992),
p. 60. The tribunal stated that: if the matters submitted to the Engineer are claims which have not
previously been rejected, they cannot be regarded as submitted under clause 67 whatever language is
used in the submission.
24
Partial Award in Cases 6276 and 6277 (Extract), in 9 ICC International Court of Arbitration Bulletin,
No 2 (1998), p. 58.
25
The tribunal stated that: the claimant was under a duty to put the defendant (Employer) on
notice to indicate to it the name of the Engineer to whom the dispute could be submitted. It was only
if it had met with a refusal or in the event of the failure to reply on the part of the defendant that the
claimant could have been dispensed from complying with this pre-arbitral phase.
26
Cited by Christopher R Seppl, International Construction Contract Disputes: Third
Commentary on ICC Awards, in 23 ICC International Court of Arbitration Bulletin, No 2 (2012), p. 27. The
tribunal concluded: before such claims may be referred to arbitration they must in the first place,
be referred in writing to the Engineer Pursuant to the express terms of clause 67, therefore, this
Arbitral Tribunal has no jurisdiction to consider any claims that have not been so referred.
27
Final Award in Case 8677 (Extract), in 19 ICC International Court of Arbitration Bulletin, No 2
(2008), p. 71.
28
See Christopher R Seppl, International Construction Contract Disputes: Second Commentary
on ICC Awards, in 19 ICC International Court of Arbitration Bulletin, No 2 (2008), p. 63.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
Pt 3] Dispute Adjudication under FIDIC Contracts 263
As already stated in section 3.1 above, the general rule under FIDIC
Contracts is that a dispute should go through the review of a DAB and an
attempt to settle the dispute amicably before being referred to arbitration.
Sub-clause 20.8 is one of the exceptions to this rule, since it allows either
party to refer disputes directly to arbitration without having to comply with
the two pre-arbitral steps described above, provided that the conditions for
application of sub-clause 20.8 are fulfilled. These conditions will now be
examined in some more detail.
(a) Sub-clause 20.4. [Obtaining Dispute Adjudication Boards Decision] and sub-
clause 20.5 [Amicable Settlement] shall not apply, and
(b) the dispute may be referred directly to arbitration under sub-clause 20.6
[Arbitration].
On its face, it seems that sub-clause 20.8, which bears the sub-title
Expiry of Dispute Adjudication Boards Appointment, will apply only in cases
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
264 The International Construction Law Review [2014
where a DAB has been appointed and its mandate has expired. In cases
where the DAB is a standing board, as under the Red Book, this approach
is understandable. The standing DAB is appointed at the beginning of
the project and its mandate expires after its completion and the issuance
of the performance certificate under sub-clause 11.9 which certifies
the completion of contractors obligations under the contract29. It
cannot be expected from a DAB to stand for an indefinite period of time
after the project completion. The appointment of the engineer would
probably also have expired by that time. Therefore, in these cases, FIDIC
introduces a less stringent dispute settlement procedure which allows
either party to refer disputes directly to arbitration.
However, under the FIDIC Yellow Book and Silver Book, the DABs are
ad hoc boards. Pursuant to sub-clause 20.2 thereunder, the respective
DAB is appointed when a dispute has arisen and its appointment
expires once the DAB has given its decision on the dispute. If any other
disputes are submitted to the DAB by the date it has given its decision
on the first dispute, then its mandate shall expire on the date when
it has also given its decision on these other disputes30. Thus, there is
a gap in respect of all disputes submitted for review after the date of
DABs decision. In practice, these disputes may arise well before the
completion of the project. Read in conjunction with sub-clause 20.8,
the wording of sub-clause 20.2 creates the impression that the parties
do not have to submit these disputes to a DAB31. Moreover, they do not
have the obligation to try to reach an amicable settlement. Thus, it turns
out that disputes under the Yellow Book and Silver Book are treated
differently regardless of the phase of completion of the project. The
criterion for the differentiation seems to be temporal, i.e. whether the
dispute in question has been referred before the date when the DAB has
taken its decision on previous disputes or afterwards. Such a difference
in the treatment of disputes could hardly be justified but, unfortunately,
it is rooted in the contractual provisions.
29
More precisely, under the last paragraph of sub-clause 20.2 the appointment of the DAB shall
expire when the discharge under sub-clause 14.12 becomes effective, unless otherwise agreed between
the parties. The discharge is provided by the contractor after the issuance of the performance certificate
for the works and in the discharge the contractor acknowledges that the amounts indicated in his
application for a final payment certificate are all the amounts due to the contractor under the contract.
The entry into force of the discharge may be made conditional upon the return of the performance
certificate and the payment of any outstanding amounts to the contractor.
30
Last paragraph of sub-clause 20.2 Silver Book and Yellow Book.
31
The problematic wording of sub-clause 20.8 under the FIDIC Yellow and Silver Books has been
noticed by Christopher R Seppl. See Seppl, fn. 13 above, p. 13 (fn. 21). The author commented
that: the language is unsatisfactory as it could be interpreted as entitling a party to go directly to
arbitration and bypass the DAB, which was certainly not the intention.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
Pt 3] Dispute Adjudication under FIDIC Contracts 265
32
Axel-Volkmar Jaeger and Gtz-Sebastian Hk, FIDIC: A Guide for Practitioners, (New York, 2009),
pp. 407409. Pursuant to sub-clause 20.2, such a tripartite agreement shall incorporate by reference the
General Conditions of Dispute Adjudication Agreement which are contained in the Appendix to the
FIDIC Contract. Therefore, the lack of such a tripartite agreement will actually mean that these General
Conditions will not enter into force.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
266 The International Construction Law Review [2014
can replace the member who is unable to act33. If the parties fail to agree
on a replacement, then the fall-back provision of sub-clause 20.3 comes
into play. It envisages that the appointing authority or the official named
in the Appendix of Tender (under the Red Book and the Yellow Book)
or the Particular Conditions (under the Silver Book) will appoint the
replacement in parties stead34. However, this mechanism will not always
lead to the desired result. It will not be possible to appoint a replacement
person if the parties have not specified an appointing authority in the
FIDIC Contract or if the specified authority has failed to act35. These
circumstances may be considered as stumbling-blocks for the continuation
of the work of the initially appointed DAB which may be overcome only
by agreement between the parties as regards the appointment of the
replacement member. If the parties fail to co-operate, the only way forward
seems to be the application of the exception under sub-clause 20.8 which
will open the way to arbitration.
It follows that the vague wording of sub-clause 20.8 gives some leeway
for the parties to assert that they are not obliged to use the services of the
DAB. This makes it possible for the arbitral tribunal reviewing the dispute
to reach the conclusion that the DAB and the attempts for amicable
settlement are non-mandatory phases of the dispute resolution under
the FIDIC Contracts. Anecdotal information suggests that in Central and
Eastern Europe claimants in arbitration proceedings have often relied on
this interpretation of sub-clause 20.8 in order to have their disputes reviewed
directly by arbitration. The reasons for such an approach could be varied.
One of them is the fear of the unknown. In Central and Eastern Europe,
dispute adjudication is still not well comprehended, despite the widespread
use of the FIDIC Conditions in these countries. The review of construction
disputes by a DAB is often perceived as a procedure which increases the
costs and prolongs the time for dispute resolution. Claimants reluctance
to use DABs can be further explained by the uncertainties related to the
enforcement of a DABs decision which has not been complied with by the
defaulting party36. Further anecdotal evidence suggests that, when faced
33
Pursuant to sub-clause 20.2, the parties may at any time appoint a replacement person. The
appointment of such a person will come into effect if a DAB member declines to act or is unable to
act as a result of death, disability, resignation or termination of appointment. However, if any of these
circumstances occurs and no replacement is available, the replacement should be appointed in the
same manner as the replaced person was required to have been nominated or agreed upon.
34
FIDIC has suggested that the functions of the appointing authority may be exercised by the
president of FIDIC or a person appointed by the president but in practice the parties often modify the
default provision and specify another person or legal entity to act as an appointing authority.
35
I have seen several FIDIC Contracts concerning projects in Central and Eastern Europe where the
engineer or another person related to the employer was designated to act as an appointing authority
for the purposes of sub-clause 20.3. In these cases, the employer might try to persuade the appointing
authority to refrain from appointing a replacement member of the DAB if the employer wants to avoid
the continuation of the dispute adjudication and refer its dispute with the contractor to arbitration.
36
See Seppl, fn. 18 above, pp. 414427. See also Hk, fn. 4 above, pp. 435437.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
Pt 3] Dispute Adjudication under FIDIC Contracts 267
with premature requests for arbitration of disputes which have not gone
to a DAB, arbitral tribunals in Central and Eastern Europe are inclined
to adopt the interpretation of sub-clause 20.8 posed above. Frequently, in
such cases the respondents will raise a jurisdictional objection claiming
that the pre-arbitral phases of the dispute settlement process have not been
exhausted and that the tribunal does not have jurisdiction to review the
dispute. However, when faced with such objections the arbitral tribunals
often confirm their jurisdiction by leaning on the word otherwise in
sub-clause 20.8. How local courts in these countries would decide on the
jurisdictional objection if seized with it remains to be seen. In the cases
under both section 4.1 and section 4.2 above, it can be easily seen how the
general rule regarding the preconditions to arbitration may be defeated
by the exception provided in sub-clause 20.8. The exception creates broad
opportunities for the parties to by-pass the pre-arbitral stages of dispute
resolution under the FIDIC Contracts. Most likely, the arbitral awards
mentioned in section 3.2 above would not limit the established practice
in Central and Eastern Europe to evade DABs. It is true that an arbitral
tribunal acting under the auspices of the ICC International Court of
Arbitration might be influenced by the content of these awards. However,
they do not have the value of precedents. Their influence is even less
certain when it comes to disputes reviewed by ad hoc arbitral tribunals
or tribunals acting under the auspices of other arbitration institutions.
Moreover, as mentioned earlier, these awards dealt with disputes based on
earlier editions of the FIDIC Contracts in which the engineer fulfilled the
role of the DAB. However, under these editions there were no exceptions
similar to sub-clause 20.8 which allowed parties to by-pass the review of the
dispute by the engineer. Therefore, the considerations underlying these
awards could not be directly transposed to the question discussed in the
present article.
5. GOVERNING LAW
It is beyond any doubt that the dispute resolution mechanism under FIDIC
Conditions can be significantly affected by the law governing the respective
contract. It is outside the scope of this article to provide an overview of
statutory provisions in different countries that may influence the settlement
of construction disputes based on FIDIC Contracts. However, two cases can
be mentioned here. They are of direct relevance to the question posed in
the title of this article and have an impact on the sequence and character of
the contractually agreed dispute settlement procedures. First of all, dispute
adjudication of construction claims under certain types of contract and
project in Great Britain is mandatory under the provisions of the Housing
Grants, Construction and Regeneration Act 1996. Obviously, in these cases
parties have to allow their disputes to be adjudicated whatever the contract
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256
268 The International Construction Law Review [2014
may have said. There are also other countries which have introduced
statutory adjudication in their legislation37. On the other hand, there are
some states where the jurisdiction of arbitral institutions over disputes is
conferred by law. As a result, courts have held that the respective arbitration
institution may assume jurisdiction over disputes even though the parties
have agreed to follow certain pre-arbitration steps which they have not
complied with. The Supreme Court of Manila has followed this approach
in a recent case38.
However, it is argued that states which recognise the principle of
contractual freedom typically do not adopt legislation which affects
contractually agreed pre-arbitral phases of dispute resolution39. The issue
discussed in this article may well be relevant in all these states.
6. CONCLUSION
37
This is the case, for example, with Singapore (see Chapter 30B of the Building and Construction
Industry Security of Payment Act), New Zealand (New Zealand Construction Contracts Bill), Malaysia
(Construction Industry Payment and Adjudication Act 2012) and some jurisdictions in Australia.
38
Hutama-RSEA Joint Operations Inc v Citra Metro Manila Tollways Corp, GR No 180640, 24 April 2009,
cited by Hk, fn. 18 above, pp. 422423. The court held:
It is true that clause 20.4 of [FIDIC] states that a dispute between petitioner and respondent as
regards the contract shall be initially referred to the DAB for decision, and only when the parties
are dissatisfied with the decision of the DAB should arbitration commence. This does not mean,
however, that the CIAC is barred from assuming jurisdiction over the dispute if such clause was
not complied with.
39
Hk, fn. 18 above, p. 423.
Informa plc 2014. This article first appeared in the International Construction Law Review Part 3 July 2014 [2014] ICLR 256