60 long Cut off wall and Rubble packing at spill way


A B

1
A B
PLAN
IRRIGATION DEPARTMENT -NP Project:- Provincial Specific Development Grant IE's OFFICE DDI's OFFICE
Scheme :- Madawalasingam Tank LEVELED & CAD CHECKED SUBMITTED CHECKED DESIGN CHECKED APPROVED
MULLAITIVU RANGE Structure :- Construction of 98.60m long Cut off wall and Rubble packing between
Spill cushion to newly constructing Cutoff wall area
Location : CO Spill way at Madawalasingam Tank
MUTHUIYANKADDU DIVISION Drg.NO :- PSDG/MIK/MAD/SPILL/01 SHEET NO :- 01 OF 02 DATE :- 13.01.2016 V.Vasanthakumar, T.O T.Thayananthan, D'man Eng.N.Vijayaravi, I.E P.Yogachandran, D'man Eng.(Mrs.)M.Joyeskumar, I.E Eng.N.Sriskandarajah, D.D.I
D = 540
Section B-B

2
D = 540
Section A-A
IRRIGATION DEPARTMENT -NP Project:- Provincial Specific Development Grant IE's OFFICE DDI's OFFICE
Scheme :- Madawalasingam Tank LEVELED & CAD CHECKED SUBMITTED CHECKED DESIGN CHECKED APPROVED
MULLAITIVU RANGE Structure :- Construction of 98.60m long Cut off wall and Rubble packing
between CO Spill cushion to newly constructing Cutoff wall area
Location :- CO Spill way at Madawalasingam Tank
MUTHUIYANKADDU DIVISION Drg.NO :- PSDG/MIK/MAD/SPILL/01 SHEET NO :- 02 of 02 DATE :- 13.01.2016 V.Vasanthakumar, TO T.Thayananthan, D'man Eng.N.Vijayaravi, I.E P.Yogachandran, D'man Eng.(Mrs.)M.Joyeskumar, I.E Eng.N.Sriskandarajah, D.D.I
Estimate for the expenses necessary to be incurred for Improvements of Spill way at Madawalasingam tank,
Muththuiyankaddu Division, Mullaitivu Range under PSDG-2016.

Specific This estimate provides for all labour, material transport, tools and equipments necessary to be incurred for the construction of above work at
ation Mullaitivu District as per plan and items of the body of the estimate and the instruction given by the officer supervising the work

S.I Description Qty Unit Rate Amount Total


Preliminaries
Provision for the cost of construction and maintenance of a temporary sheds to
accommodate the Contractor's staff and workmen at the site during the contract
A Item Allow P.sum 7,500.00
period.(After completion of construction paid each materials to be handover to
MIK IE's Office).
Sub Total 7,500.00
Construction of 98.60m long Cut off wall and Rubble packing between Spill
1
cushion to newly constructing Cutoff wall area
1.1 Site Clearing for spill way rehabilitation. Item Allow Sum 1,500.00
Earth excavation in foundation & part refill manually and balance disposed as 3
1.2 44.40 m 1,175.00 52,170.00
directed.
Supplying & Laying of 1:3:6(38 mm) cement concrete without form work for
1.3 21.40 m3 12,220.00 261,508.00
cutoff wall construction.
Supplying & Laying of 1:3:6(38 mm) cement concrete with form work for cutoff
1.4 39.95 m3 12,950.00 517,352.50
wall construction.

Approved Earth filling inside of cut off wall, layer thickness of 100mm to 150mm 3
1.5 130.00 m 335.00 43,550.00
watered, rammed & well consolidated (Earth to be taken from tank bed)

Approved Gravel filling inside of cut off wall, layer thickness of 100mm to
1.6 55.00 m3 590.00 32,450.00
150mm watered, rammed & well consolidated(Gravel to be taken from tank bed)

Supplying and placing 450 x 600 mm size Random rubbles with packing inside of 3
1.7 171.00 m 2,660.00 454,860.00
cut off wall.

3
S.I Description Qty Unit Rate Amount Total
Supplying and pitching 150 x 225 mm size Random rubbles for side wall
1.8 11.00 m3 6,410.00 70,510.00
construction.
1.9 Tidying up site after construction Item Allow Sum 40.94
Sub Total 1,433,941.44
Total Civil Cost 1,441,441.44
VAT 11% 158,558.56
Grand Total 1,600,000.00
At IE's OFFICE At DDI's OFFICE
Prepared By:- Checked by :-
V.Vasanthakumar, TO P.Yogachandran, D'man

Checked By:- Reviewed & Passed by :-


T.Thayananthan,D'Man Eng.(Mrs).M.Joyeskumar,
Irrigation Engineer

Submitted by :- Approved by :
Eng.N.Vijayaravi Eng.N.Sriskandarajah
Irrigation Engineer, Deputy Director of Irrigation
Muthuiyankaddu Division. Mullaitivu Range

4
Rehabilitation of Spill way at Madawalasingam tank, Muththuiyankaddu Division, Mullaitivu Range

T D S Description
Construction of 98.60m long Cut off wall and Rubble packing between
Spill cushion to newly constructing Cutoff wall area
1 1.000 1.000 1.1 Site Clearing for spill way rehabilitation.
Item- Allow
Earth excavation in foundation & part refill manually and balance
1.2
1 98.600 disposed as directed.
0.600
0.750 44.370 Say = 44.40 m
Supplying & Laying of 1:3:6(38 mm) cement concrete without form work
1.3
1 98.600 for cutoff wall construction.
0.600
0.150 8.874
1 38.000
0.600
0.550 12.540
21.414 Say = 21.40 m
Supplying & Laying of 1:3:6(38 mm) cement concrete with form work for
1.4
1 98.600 cutoff wall construction.
0.450
0.600 26.622
1 98.600
0.300
0.450 13.311
39.933 Say = 39.95 m
Approved Earth filling inside of cut off wall, layer thicknes of 100mm to
1.5 150mm watered, rammed & well consolidated(Earth to be taken from
tank bed)
1 38.000
3.000
1.140 129.960 Say =130.00m
Approved Gravel filling inside of cut off wall, layer thicknes of 100mm to
1.6 150mm watered, rammed & well consolidated(Gravel to be taken from
1 96.600 tank bed)
3.800
0.150 55.062 Say = 55.0 m
Supplying and placing 450 x 600 mm size Random rubbles with packing
1.7
1 96.600 inside of cut off wall.
3.950
0.450 171.707 Say = 171.00 m
Supplying and pitching 150 x 225 mm size Random rubbles for side wall
1.8
construction.
2 3.950
1.200
1.000 9.480
2/(1/ 3.950
0.375
1.000 1.481
5
T D S Description
10.961
1.000 Less Cutoff wall portion
0.300
0.150 0.045
1.000
0.150
0.600 0.090
(0.135)
10.826
10.820 Say = 11.00 m
1.9 Tidying up site after construction
Item - Allow
Prepared By:- Checked By:-
V.Vasanthakumar, TO. T.Thayananthan, D'man.