Sei sulla pagina 1di 18

GAS INSULATED SUBSTATIONS

SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016

METHOD STATEMENT for INTERVENTION :


REPLACEMENT OF IFES Q8 ON BAY 08 + 09 phase R + bay 06

ZAKHER (EAU )
SUBSTATION B105-6
BHT CONTRACT N : AH71
RDS 0006

DISTRIBUTION : After Sales dept., Site erection dept., Quality control site dept., Quality dept.

D 24/01/2017 Add HV test


C 15/12/2016 Add IFES bay 06
B 08/12/2016 Add detail of operation
A 22/11/2016 Original issue
Revision Date Modifications

Established by : R. ASSIER
Checked by : C. CARLE Page : 1/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016

SUMMARY

1- FIELD OF APPLICATION

2- GENERAL

3- GLOSSARY

4- LISTING OF REFERENCE DOCUMENTS

5- MAIN HAZARD IDENTIFICATION, RISK ASSESSMENT & ACCESS FOR INTERVENTION

6- STAFF / EQUIPMENT / CONSUMABLE

7- SUPERVISOR COMPETENCES

8- DETAILED CHART FOR ACTIVITIES & FOR CONTROLS OPERATIONS

Established by : R. ASSIER
Checked by : C. CARLE Page : 2/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016

1- FIELD OF APPLICATION

The Quality plan is a document of quality insurance which defines: tasks, responsibilities, and documents attached to the substation erection or
maintenance, inspection and test operations.

2- GENERAL

The Quality plan is conform to the Environment & Quality Manual (MQ2000) and more precisely to the 2.2.3 Installation on site, work & site tests. It
precise the responsibilities about the quality, the documentation, the site training, the inspections and test. The treatment of non-conformities and the
corrective actions.

3- GLOSSARY

Abbreviation list

FAQ : Quality insurance document


MPR : Montage Problem Report
FG : Operational instruction
DRC : Site test and control report
PTW : Permit to work
VT : Voltage transformer
CT : Current transformer
TA : Bushing
NOT : Manual of switcher substation
NA : Not applicable
1-2-3 : Level of qualification
AC : Self-control
ICC : Inspection by supervisor

Established by : R. ASSIER
Checked by : C. CARLE Page : 3/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016

4 LISTING OF REFERENCES DOCUMENTS


List of quality document referring to the quality plan and used during site erection.
N Update DESIGNATION
SPP / A Safety and prevention plan
WINVAX / AH71 A Software of substation parts list
MANUAL / AH71 A Manual of maintenance of substation
Site documentation :
F06A000722 12 GIS - Single line diagram
F06A000723 14 GIS - Layout
Appendix 1 Electrical lockout & gas treatment for intervention
Appendix 2 Procedure for earthing switch removing

DRC/ AH71 Site test and control report


FG 40 002 O Supervisor manual instruction
FG40 010 C Safety Instruction
FG40 011 A EHS rules applicable during gas treatments on site
FG37571 A Assembly on site
FG40011 A EHS rules during gas treatment

Established by : R. ASSIER
Checked by : C. CARLE Page : 4/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
4 LISTING OF REFERENCES DOCUMENTS
List of quality document referring to the quality plan and used during site erection.

N Update DESIGNATION
29/09/11
SOFTWARE ON LINE
Manual on supervisor data base
Chapter 1 :
Site Opening
Chapter 2 :
Assembly preparation
Chapter 3 :
GIS Assembly
Chapter 4 :
Preparation for Assembly of Gas Insulated Bus (GIB)
Chapter 5 :
Assembly of Gas Insulated Bus (GIB)
Chapter 6 :
Particular assembly procedure
Chapter 7 :
Gas treatment
Chapter 8 :
Cable path and earth circuit
Chapter 9 :
Assembly of low voltage
Chapter 10 :
Commissioning
Chapter 11 :
Dielectric tests + Checking of surge arresters
Chapter 12 :
Cable box and liaison transformer connections
Chapter 13 :
Site closing

Established by : R. ASSIER
Checked by : C. CARLE Page : 5/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
5 MAIN HAZARD IDENTIFICATION & RISK ASSESSMENT FOR INTERVENTION (1/2)

ITEM DESCRIPTION OF TASKS REFERENCE DOCUMENTS HAZARDS / PREVENTION MEASURES

Overall hazard for intervention FDPEHS 40004 : Safety during GIS operations
FG40010 : Safety instructions

Intervention on dismantling FG40010 item 7.2: Prior to remove the conductor makes sure that the
conductor conductors supports are earthed at both sides.
Intervention on cable box In case of cable box link dismantling, the cable must be
earthed at the closest from the dismantling link => cable
bushing on the cable box side.
Intervention on live substation : TEX N52 checked and formalized by supervisor & Lockout Tagout : individual padlocks & tags mandatory
Overhead energized lines. customer Wear PPE (helmet with face protection, gloves, insulation mat
LV Commissioning FG27025 :Rules for electrical operations & tools)
5min Safety : V.A.V. kit Working area delimited with Physical barriers
5min Safety : safety during LV commissioning Tags warnings the presence of danger.

Work at height FG27016 Work at height Full harness.


5min Safety : Work at height Scaffolding with tags for compliance
Operator trained for mobile platform

Lifting operations FG27028 Lifting manual Operator must be trained & competent
5min safety slinging recommendations Lifting plan for particular slinging (hooking points, weight to
be lifted)

Vehicle movement ALSTOM EHS 009 Circulation of mobile equipment & pedestrian must be
5min safety Vehicle movement separated (2m)
High visibility jacket for vehicle drivers & on construction
forklift & trucks maneuvering areas
Installation of traffic signs

Established by : R. ASSIER
Checked by : C. CARLE Page : 6/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016

5 MAIN HAZARD IDENTIFICATION & RISK ASSESSMENT FOR INTERVENTION (2/2)

ITEM DESCRIPTION OF TASKS REFERENCE DOCUMENTS HAZARDS / PREVENTION MEASURES

Gas treatment FG40011 : EHS rules applicable during gas Operator trained for gas treatment (SF6 & pressure)
treatments on site Visible Tags on compartments
Work being closed insulator need factory approval
FG40118 : Treatment of compartment on site
FG27027 Pressure safety
5min safety 10 main safety rules


Polluted SF6 FG40011 : EHS rules applicable during gas Compartment must be identified
treatments on site PPE during removal of the polluted compartment :
FG40042 : compartments which can contains Gloves
polluted SF6. Cartridge mask ABEKP
5min safety Polluted SF6 Disposable coverall

Machine safety (safety) : FG27025 : Rules for electrical & mechanical CB mechanism out of voltage and spring is discharge
Hydraulic intervention operations
CB Mechanism 5min safety FK Mechanism

Other : 5min EHS Chemical Hazard Wear PPE defined by the safety data sheet.
Chemical products - asbestos 5min safety : rupture disk with asbestos
Confined spaces FG28018 confined spaces
Excavation works 5min EHS protection of floor opening

In addition, TEX N52 data sheet MUST be completed before intervention

Established by : R. ASSIER
Checked by : C. CARLE Page : 7/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
5 ACCESS ON SUBSTATION

IFES Q8 which must be


replaced
on bay 08 R phase
B105-EF6 / 10 / AH71

on bay 09 R phase
B105-EF6 / 13 / AH71

on bay 06
B105-EF6 / 4 / AH71

Established by : R. ASSIER
Checked by : C. CARLE Page : 8/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
2 -Dismantle the operating
mechanism
3 -Dismantle the support

1 -Dismantle the linkage

Established by : R. ASSIER
Checked by : C. CARLE Page : 9/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016

6 STAFF / EQUIPMENT / CONSUMABLE

STAFF PER TEAM :

1 ALSTOM supervisor 1 ALSTOM HV Tester


CONSUMABLE :
1 gasman, Cleaning paper,
1 fitters, Isopropyl alcohol,
XX electrician Gasket for cover and moisture absorber,
. Gas label for compartment identification
Grease
CONTRACTOR EQUIPMENT NEEDED FOR INTERVENTION: (Non exhaustive list to PPE for working with polluted SF6
be consolidated prior to intervention with site team)

Overhead crane with valid test load certificate


Mobile crane with valid test load certificate SPARE PARTS :
Power supply for Vacuum pump 380V AC 32 A
Power supply for DILO group 380V AC 63 5pinsA Interface, gasket, bolts
FES
1SF6 empty containers for polluted SF6
1SF6 empty containers
New SF6 gas

1 Pallet truck
Scaffolding
1 mobile access platform

BHT TOOLS:

Refer to additional tool list

Established by : R. ASSIER
Checked by : C. CARLE Page : 10/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
7 SUPERVISOR COMPETENCES

ITEM DESCRIPTION OF TASKS REFERENCE DOCUMENTS HAZARDS / PREVENTION MEASURES

0 SITE PREPARATION IN FACTORY


Safety Specific training for intervention
Electrical Risk (NFC C18-510)
Overhead crane
Mobile access platform
Forklift

Material Specific training for intervention


B
T

Established by : R. ASSIER
Checked by : C. CARLE Page : 11/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
8 DETAILED CHART FOR ACTIVITIES & FOR CONTROLS OPERATIONS

DAY / REFERENCE DOCUMENTS REFERENCE DOCUMENTS


DESCRIPTION OF TASKS HAZARDS / PREVENTION MEASURES
bay FOR SUPERVISOR FOR CUSTOMER

FES REPLACEMENT

1 Electrical Lockout Appendix 1 M.S

CUSTOMER SCOPE
1 Checking of Electrical Lockout Appendix 1 M.S TEX N52 checked and TEX N52 checked and formalized by
formalized by supervisor & supervisor & customer
customer

1 CB in opened position Appendix 1 M.S TEX N52 checked and formalized by


CB mechanism out of voltage and spring is discharge Moisture content NOT 200.4052 supervisor & customer
Checking of filling pressure NOT
200.4060

1 Pressure, Temperature, Moisture content & % SF6 Appendix 1 M.S


gas measurement for all treated compartments Moisture content NOT 200.4052
Checking of filling pressure NOT
200.4060

1 Gas recovery from GIS compartments. Appendix 1 M.S FG40011 : EHS rules applicable during gas
FG40118. treatments on site

1 RDC Measurement. NOT 730.4010 : RDC measurement


Note values on DRC Record values on DRC

Established by : R. ASSIER
Checked by : C. CARLE Page : 12/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
DAY / REFERENCE DOCUMENTS REFERENCE DOCUMENTS
DESCRIPTION OF TASKS HAZARDS / PREVENTION MEASURES
bay FOR SUPERVISOR FOR CUSTOMER

1 Disconnect the equipment between GIS and HV


cable
2 Fast Earthing Switch in closed position (spring F140687
discharged)
Dismantle the IFES linkage
Dismantle the operating mechanism
Dismantle the support
Dismantle the fast earthing switch reference
hereunder
B105-EF6 / 10 / AH71
B105-EF6 / 13 / AH71
B105-EF6 / 4 / AH71

2 Installation of the new IFES F140687


Adjust the earthing rod with the fixed contact on the
disconnector active part and tight the scew with the
correct torque.
Closed the cable box compartment
Replacement of the absorber
Installation of the IFES linkage
2 Commissioning of the FES according to the DRC Make proof earthing switch NOT
request (Motor consumption, operating time, Auxiliary 733.8030
switch operating time ) DRC
Visual check of the position indicator
Control the clamping of the rod system .

2 RDC Measurement. NOT 400 4010 : RDC measurement Record values on DRC
Note values on DRC Record values on DRC

3 Re-filling of SF6 on GIS compartments FG40118 FG40011 : EHS rules applicable during gas
Filling SF6 NOT 200.4021 treatments on site

Established by : R. ASSIER
Checked by : C. CARLE Page : 13/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
DAY / REFERENCE DOCUMENTS REFERENCE DOCUMENTS
DESCRIPTION OF TASKS HAZARDS / PREVENTION MEASURES
bay FOR SUPERVISOR FOR CUSTOMER

3 Pressure, Temperature, Moisture content & % SF6 Moisture content SF6 NOT FG40011 : EHS rules applicable during gas
gas measurement 200.4052 treatments on site
Checking of filling pressure NOT
200.4060

CONSIGNATION for HV Test Appendix 2

CUSTOMER SCOPE

4 Checking of Electrical Lockout Appendix 3 TEX N52 checked and TEX N52 checked and formalized by
formalized by supervisor & supervisor & customer
customer

4-5-6 HV test FG46005 & FG46243

6 Gas recovery from GIS compartments. Appendix 1 M.S FG40011 : EHS rules applicable during gas
FG40118. treatments on site

7 Reconnect the equipment between GIS and HV


cable

7 Re-filling of SF6 on GIS compartments FG40118 FG40011 : EHS rules applicable during gas
Filling SF6 NOT 200.4021 treatments on site

Established by : R. ASSIER
Checked by : C. CARLE Page : 14/15
MS 3014
Approved by : JC. BORNAND
GAS INSULATED SUBSTATIONS
SERVICES DEPARTMENT
Grid Solutions a GE and Alstom joint venture
Rev: 19/01/2016
DAY / REFERENCE DOCUMENTS REFERENCE DOCUMENTS
DESCRIPTION OF TASKS HAZARDS / PREVENTION MEASURES
bay FOR SUPERVISOR FOR CUSTOMER

8 Pressure, Temperature, Moisture content & % SF6 Moisture content SF6 NOT FG40011 : EHS rules applicable during gas
gas measurement 200.4052 treatments on site
Checking of filling pressure NOT
200.4060

8 Cancellation of PTW Intervention report TEX N09 to be Intervention report TEX N09 to
signed by client be signed by client
Site test results (DRC) to be signed Site test results (DRC) to be
by client signed by client

Established by : R. ASSIER
Checked by : C. CARLE Page : 15/15
MS 3014
Approved by : JC. BORNAND
Apparatus locked in closed position Compartment at reduced pressure SF6 (< 0,3b rel)
Appendix 1 MS 3014
Fast Earthing Switch Apparatus locked in open position Compartment opened to the atmosphere
BAY : 08+09 Comp: G4 Phase : R Earth Mandatory Compartment at nominal pressure of SF6

OUTAGE OF BAY 08 + 09 Contact Resistance measurement

FES which must be replaced

B105-EF6 / 10 / AH71
B105-EF6 / 13 / AH71
Apparatus locked in closed position Compartment at reduced pressure SF6 (< 0,3b rel)
Appendix 1 MS 3014
Fast Earthing Switch Apparatus locked in open position Compartment opened to the atmosphere
BAY : 06 Comp: G4 Phase : ? Earth Mandatory Compartment at nominal pressure of SF6

OUTAGE OF BAY 06 Contact Resistance measurement

FES which must be replaced

B105-EF6 / 4 / AH71
Apparatus locked in closed position HV Test section
Appendix 3 MS 3014
Consignation & Gas treatment for HV test Apparatus locked in open position Earth section
Fast Earthing Switch Earth Mandatory
BAY : 08+09 Comp: G4 Phase : R Injection point

OUTAGE OF BB 1A-2A

For dielectric test