(As per para-2a (ii) of Annexure-1 of G.O. Ms.No.94 I & CAD Dept., dated 1.7.2003.)

Name of work:- Widening and Strengthening the road from Km 43/0 - 44/4
of Nandayal(Gadivemula-Midthur)Nandikotkur Road in
Kurnool District

***

Certified that the stage-1 approval is not required as detailed investigation completed.

Land acquisition and shifting of utilities are not required for taking up the subject work

without interruption.

Assist.Exe. Engineer, Dy. Executive Engineer, Executive Engineer,


(R&B) Section-II,Kurnool (R&B) Sub-division, Kurnool. (R&B) Division, Kurnool.

Superintending Engineer,
(R&B) Circle, Kurnool.
CHECK SLIP ACCOMPANYING THE ROAD WORK PROPOSALS UNDER
PLAN TO GOVERNMENT

NAME OF WORK:- Widening and Strengthening the road from Km 43/0 - 44/4 of
Nandayal(Gadivemula-Midthur)Nandikotkur Road in Kurnool District
1 Budget Eligibility ::

a. Budget provision during the year 2013-14 under PLAN ::


(MDR)
b. Commitments on hand under the head (spill over works as ::
on 1st April + sanctions accorded during the year)
c. Balance available ::
2 Whether detailed investigation conducted. Department to :: Yes
certify that investigation is done properly.
3 Whether designs have been approved by the competent :: -
authority
4 Whether Hydrological clearance is obtained, where ever :: -
required
5 It the work is for new formation or up-gradation of a road, :: Yes
the proposal should be substantiated with reference to
traffic census.
6 In case the proposal is against the provisions of SCP/TSP, :: Not applicable
whether the guidelines prescribed have been satisfied.
7 Whether any Land Acquisition involved. If so, the details :: Not required
viz., Govt. land, Private land, Forest land etc., and the
realistic costs thereon and the stage of acquisition.
8 Whether the land is free from litigation. :: Yes
9 Whether the work requires two stage Administrative :: No
Sanction, as investigated in G.O.Ms.No.94 I & CAD
Department, dated.1.7.2003 (Applicable to all Engineering
departments)
a. If the land acquisition or any other clearances are involved, :: No
the department may propose invariably for Stage-I sanction
only.
b. In case the department satisfies that all the above :: Certificate is
requirements are full-filled and there are no hurdles to go enclosed
ahead with the work, the department should append a
certificate from the Engineer-in-Chief/Chief Engineer to
that effect as required under Para 2 a (ii) of Annexure-1 of
G.O.Ms.No.94 I & CAD Department, dated.1.7.2003.
10 Detailed estimate prepared has been checked with reference :: Yes
to the Codal Rules and Govt. Orders issued periodically.
11 Any other requirement not covered above. :: Nil
12 Remarks of the Administrative Department. ::
Executive Engineer Dy. Executive Engineer, Asst.Exe. Engineer,
(R&B) Division, Kurnool (R&B) Sub-division, Kurnool (R&B) Section-II, Kurnool.

Superintending Engineer,
(R&B) Circle, Kurnool.