ACTIVIDAD PRECEDENCIA TO TM

A _ 5 6
B A 7 9
C A 15 17
D B 9 11
E B 6 7
F C 13 16
G E 8 10
H D 11 12
I H,G 1 2
J F 6 7

HOLGURA DE ACTIVIDADES = TU-(IP+ TP)


HB= 7
HD= 7
HE= 12.5
HH= 7
HG= 12.5
HI= 7

RUTA CRITICA= A-C-F-J

DURACION DEL PROYECTO= 48


TP T PROMEDIO
8 6.17
13 9.33
21 17.33
16 11.50 TU= TERMINACION ULTIMA O TIEMPO MAS TA
15 8.17 IP= INICIACIN PRIMERA O TIEMPO MAS TEMP
21 16.33
11 9.83
13 12.00
3 2.00
15 8.17

DIAS
N DE EVENTO
T.U. I.P.
N ULTIMA O TIEMPO MAS TARDE POSIBLE
RIMERA O TIEMPO MAS TEMPRANO POSIBLE
B(9.33
)
A(6.17)
1 2
0 0 6.17 6.17

C(17.33)
4
D(11.50) 3 27
4

3
22. 15.5
5
E(8.17 36.1
5

)
23.67
7

F(16.33
17.33)

8
23.5 23.5
H(12)
I(2)
6 7
46 3 4
9 8

G(9.83
)

9
39.83 39.83
J(8.17)
F(16.33)
7

f(0)
4
1

10
4 48
8

J(8.17)