Scope of Activity
Substation Tendering
Engineering Tools Development
3D modeling of EHV AIS
Activities
Scope of Activity.
Scope of Work.
400kV AIS, 1 & Breaker Scheme, 2 Complete Dia and 1 Tie
with Line Bay
8 Nos. of SF6 CB, and All the Switchyard Equipment including
Control Control & Relay Panel
500kV Switchyard at SIAM Energy Thailand: SLD & Top View
Scope of Work.
500kV AIS, with Single Bus Scheme, and Two Power Block
2 Nos. of SF6 CB, and All the Switchyard Equipment including
Control Control & Relay Panel
220kV Switchyard at Dhuvaran III: SLD, Section & top View
Scope of Work.
220kV AIS, With Two Main and One Transfer Scheme.
7 Nos. of SF6 CB, All the Switchyard Equipment including
Control Control & Relay Panel
Rehabilitation and Extension of SCADA at Banglade
Scope of Work.
Supply and Installation of RTU, Controller and Radio Link
Communication
Laying and Termination of Control Cable between Equipment
and RTU
Conventional Contract
Substation Engineering
SLD
Tier - 1
Tier -
Protection Engineering
To Site
Erection Key Diagram
Specification &
Purchase Datasheet 3D Modeling with all
To Customer for Approval
2D Representation of GA
Engg. Data(Elect., & Section Drawing
Structural, etc). Tier - 2
Protection Engg.
Tendering Stage
Technical BOQ Estimation
Commercial Price Back up and discount measurement
Engineering
Engineering Hours Calculation and Design
Detail Engineering
General Arrangement Engineering from 2- D
drawing
Structure Engineering Weight of civil
structures
Cable Engineering - Estimation of power and
control cables
Project Management
Client Claim End client Claim Handling process
Supplier Claim Handling Process
Project Closing Process
Reduction and Mitigation plan with Smart Substation
Engineering
Tendering Stage
What is D.S.L.P.?
How it is achieved?
It can be achieved by
providing
Lightning Mast
Shield Wire
Combination of above
DSLP Calculation Tools
Based on IEEE-998 by
using Rolling Sphere
method, High Voltage Engg.
By Prof. Razevig
Gives the flexibility to
choose height of LM and
height of equipment to be
protected and it will
calculate the protection
area
It will Generate the
Drawing in 3-D view as
well as generate a report
in Excel file
Short Circuit Forces Calculation Tool