Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Revision 3.0
SOURCE OF DATA
The following source codes are used to reference the origin of each criterion:
Ref
CCC Supplied Data 1
Calculation 2
Outotec Supplied Data 3
Orway Mineral Consultants (OMC) Report 4
Vendor Supplied Data 5
Assumption 6
Mass Balance 7
Ammtec Supplied Testwork results 8
Page 1
REV3.0
1 General ROM Ore Characteristics
Value Data
Criteria Units
Expected Design Source
Volcanic % 50 5010 1
Expected Ore Split
Diorite % 50 5010 1
Page 2
REV3.0
2 Primary Milling Circuit Area 210
Value Data
Criteria Units
Expected Design Source
Configuration Wet, open circuit Ball Milling.
Utilisation % 95 90 1
Annual operating
hours 8322 7884 2
time
Mill Feed Rate Nom.dry t/h 2632 2778 1
Page 3
REV3.0
Utilisation % 95 90 1
Annual operating
hours 8322 7884 1
time
Mill Feed Rate Nom.dry t/h 2632 2778 1
Page 4
REV3.0
Cyclone Feed 8&9 Pump Solids (w/w) 58 60 7
Pressure kPa 50 70 70 5
Utilisation % 95 95 1
Annual operating
hours 8322 8322 1
time
ix
Mill Feed Rate Nom.dry t/h 257 257 1
Page 5
REV3.0
Circulating Load % 150 200 7
Utilisation % 95 95 1
Froth Height % ~ 3% 3
Page 6
REV3.0
Froth Factor Concentrate Pump 1.25 1.5 6
Concentrate Sump Residence
100% level secs 30 30 6
Time
Ph of Slurry pulp Ph 9.5 9.50.5 1
Utilisation % 95 95 1
HG Cleaner Bank 1
Page 7
REV3.0
HG Cleaner Bank 2
HG Cleaner Bank 3
Utilisation % 95 95 1
Page 8
REV3.0
Thickener Feed % Solids % 10.1 10.1 7
2
Solids Loading t/m h 0.25 0.25 3
xv
Flocculant Addition g/t 2.0 2.0 3
71
Underflow % Solids (w/w) % 68 3
(achievable)
Utilisation % 95 95 1
Page 9
REV3.0
Thickener Diameter Required Option 1 m 2 x 39 3
62
Underflow % Solids (w/w) % 55 3
(achievable)
Utilisation % 95 95 1
Page 10
REV3.0
Filtration Rate 2 230 3
kg D.S. /m h
2
Filter Area Required Option 2 2 1 x 198m 3
m
Solids content in the Cake (w/w) % 90 90 1
If the plant tonnage is kept at 60KTPD, the estimated rougher flotation feed increases to P80 >
260m. The consequence is that there is a potential for lower copper recovery values i.e. < 85%.
Ammtec testwork undertaken on the Diorite and Volcanic ore types indicated regrinding of both the
rougher and scavenger concentrate was necessary to achieve the final product grade close to the
target value of 26.5% Cu. Under these conditions the regrind mill feed rate will increase and the
estimated cleaner flotation feed increases to a P80 >125m. The consequence is that the final
copper product is likely to reduce in both Cu grade and recovery.
x
The predicted cleaner flotation feed P80 is based on both Regrind mills operating as duty mills in
parallel feed configuration. Thus, CCC current flexibility of a duty/standby regrind milling circuit will be
removed. The consequence is that during Regrind mill maintenance or breakdowns, the plant tonnage
will need to be reduced to 40KTPD to maintain final product grade / recovery.
Page 11
REV3.0
In addition, the design regrind P80 of 86 m is based on historical performance of the Carmen ore
through the existing plant. Ammtec laboratory testwork on the Diorite and Volcanic composites
suggests a requirement for a significantly finer regrind P80 of <40 m to target the final product grade
of 26.5% Cu. Thus, the current regrind mills (both operating as duty) at the design plant tonnage
(60KTPD) may not be suitable to achieve the target final product grade.
It is estimated that with the current regrind mills, the plant tonnage will need to be reduced to
<30KTPD to achieve the Ammtec P80 of <40 m.
To operate the plant at the design tonnage (60KTPD) and achieve a regrind P80 of <40 m, a new
regrind mill will be required i.e. an Inert Stirred mill with an estimated 4.5MW installed power.
xi
The design BWi is based on OMC database of similar ore types. It is recommended by OMC that
fine grinding test work be undertaken on the rougher and scavenger concentrates to validate this
prediction. If the BWi value is higher than predicted, the consequence is that the cleaner flotation
feed P80 will be coarser and it is likely that the final copper product will reduce in both Cu grade and
recovery.
xiii
The HG Cleaner circuit has been designed with three stages of cleaning. In the current cleaner
circuit, the rougher concentrate bypasses the regrind mill and undergoes three stages of cleaning.
Thus, the design is based on the expectation that the new Carmen ore will behave similarly to the
Lutopan ore. If this proves incorrect, the consequence is that additional cleaner banks may be
required to achieve the target product grade.
Page 12
REV3.0
xvii
Client Comment Eventually this could be the specification, in the interim, CCC will
purchase short term solution.
Page 13