Sei sulla pagina 1di 60

<LRH>Chapter Number (sentence case)

<RRH>Book Title (all caps)

<CN>CHAPTER

68

<CT>DesignESIGN ofOF IndianNDIAN

PressurizedRESSURIZED HeavyEAVY WaterATER

ReactorEACTOR ComponentsOMPONENTS

<CA>H.S. Kushwaha, K.K. Vaze, and K.B. Dixit

1 March 11, 2008


2 March 11, 2008
3 March 11, 2008
<H1>68.1 INTRODUCTION

The Nuclear Power Program in India at present is based mainly on a series of Pressurized Heavy Water Reactors (PHWRs).

Starting from Rajasthan Atomic Power Station, comprising of two units of 200 MWeMWe Canadian- designed PHWRs in 1973,

the program has come a long way with 15 PHWR units (which includes two 2 units of 540 MWe PHWRs) in operation and 3 units

under construction. Narora Atomic Power Station commissioned in 1991 marked major indigenization and standardization of

PHWR designs. The current design plans include 700 MWeMWe capacity units. The choice of PHWRs in the current stage of

India's Nuclear nuclear Power power Program program is based on long-term objectives to be achieved in the available uranium

resources and industrial infrastructure. These reactors use natural uranium as fuel and heavy water as moderator and coolant. The

nuclear power stations in India are generally planned as twin-unit modules, sharing common facilities such as service building,

control building, turbine building, spent fuel storage bay, etcand so on.

The Indian PHWR design has evolved through a series of improvements over the years in progressive projects. Such

improvements have been driven by, among others, evolution in technology, feedback from experience in India and abroad,

including lessons learnt from incidents and their precursors, evolving regulatory requirements, and cost considerations. Valuable

experience gained in design, manufacture, construction, operation, maintenance, and safety regulation has enabled continual

evolution, improvement, and refinement in the PHWR concept in a progressive manner.

In Indian PHWRs, the design, fabrication, testing, and inspection of all mechanical components basically follow the

requirements of appropriate Sections sections of the ASME Boiler & Pressure Vessel Code (ASME B&PV Code).

. Other international codes used are: (1) Canadian Code CAN/CSA N285.4-05 and IAEA Safety Guide 50-SG-02 for ISI, and (2)

French Code RCC-G for containment design. This chapter first provides a general overview of the Indian PHWR design and its

evolution. The design approach, material selection, and fabrication practices are described for major components such as the

calandria, headers, steam generators, and piping. Details are provided of the development and the use of leak-before-break (LBB)

criterion to eliminate the need for installation of pipe whip restraints. Results of experiments conducted to determine load-

carrying capacity of cracked pipes and the results of fatigue crack growth rate tests in support of LBB criteria are discussed. As a

further example of the research and development work conducted in India related to nuclear power plant applications, the

4 March 11, 2008


development of a modified B2 stress index (used in NB-3600- type stress analyses) for pipe elbows and curved pipes and,

quantification of additional safety factors to account cyclic tearing in LBB assessment , is are discussed.<!--<query>Please

check that intended meaning of the sentence "As a further.....discussed" is retained after modification

.</query>-->

<H1>68.2 INDIAN PHWR

<H2>68.2.1 Introduction to Indian PHWR [1]

The first PHWRs at Rajasthan Atomic Power Station #1 and 2 and Madras Atomic Power Station #1 and 2 were of Canadian

design (based on Douglas Point). When design work for the third PHWR station, Narora Atomic Power Station #1 and 2, was taken

up in the early 1970s, major modifications were incorporated with the objectives of upgrading the designs in line with the

internationally evolving safety standards, and to cater to the seismic loading. Narora Atomic Power Station design was the first

opportunity to apply India's operating experience with PHWRs, including aspects such as ease of maintenance, in-service

inspection (ISI) requirements, improved constructability, increased availability, and standardization of the unit. Some of the new

designs incorporated in In Narora Atomic Power Station, some of the new designs were incorporated with the objective to serve as

stepping stones for the design of subsequent larger 540 MWe PHWR.

Some of the significant design improvements made in Narora Atomic Power Station included adoption of an integral calandria

(reactor vessel) and end shields assembly, two independent fast acting reactor shutdown systems, a high- pressure Emergency Core

Cooling System, and a double containment with suppression pool.

Subsequent to Narora Atomic Power Station, Kakrapar Atomic Power Station #1 and 2, Kaiga Atomic Power Station #1 and 2 ,

and Rajasthan Atomic Power Station #3 and 4 saw further improvements leading to standardizations in design and layout for

220 MWe PHWRs. Table- 68.1 lists the design features of Indian standard 220 MWeMWe PHWR.

5 March 11, 2008


TableTABLE- 68.1: Design featuresDESIGN FEATURES: IPHWR 220 MWe MWe [1]

Design data
A. General
(i) Rated output thermal 756 MWt
(ii) Rated output electrical 220 MWe
(iii) Fuel Natural UO2
(iv) Moderator and reflector Heavy water
(v) Coolant Heavy water
(vi) Type Horizontal pressure tube

B. Reactor
(i) Calandria shell Horizontal stepped cylinder welded to extensions of end shield
(ii) Calandria shell material SS-304L
(iii) End shields Cylindrical box- type structure integral with calandria shell
(iv) End shield material SS-304L
(v) Calandria tubes
(a) Quantity 306
(b) Material Zircaloy-2
(vi) Coolant tubes
(a) Quantity 306
(b) Material Zirconium2.5% niobium alloy
C. Steam generators
(i) No. of steam generators 4
(ii) Type Vertical U- tube with integral steam drum (mushroom-shaped)
(iii) Material Incoloy-800
(iv) Steam pressure 3.923 MPa
(v) No. of tubes per SG 1834
(vi) Total steam flow to turbine 370 kg/s
(vii) Steam temperature 251 C
(viii) Maximum moisture content 0.25%

<H2>68.2.2 Description IPHWR

The reactor consists of a low-pressure horizontal reactor vessel (calandria) containing heavy water moderator at near ambient

pressure and temperature. The calandria (Fig. 68. 1) is pierced by a large number (306 in 220 MWe and 392 in 540 MWe PHWR) of

coolant tubes, which contain the fuel bundles, and through which pressurized heavy water coolant circulates. The calandria houses

all reactivity and reactor shutoff devices in the low-pressure, low- temperature environment.

The calandria is housed in a steel- lined vault filled with light water which that serves as shielding as well as provides cooling

to the calandria.

6 March 11, 2008


1. Calandria Shellshell 11. Main Shell shell

2. Over Pressure pressure Relief relief Assemblyassembly

Devicedevice(OPRD) 12. Tube Sheet sheet F/M Sideside

3. Shut Down down system #1 13. Tube Sheet sheet Calcal.

4. Shut Down down system #1 Sideside

5. Moderator Inletinlet 14. Lattice Tubetube

6. Moderator Outletoutlet 15. End Shield- shield Support

7. Vent Pipepipe support Plateplate

8. Coolant Channel channel 16. End Shield shield Cooling

Assemblyassembly ccooling Inlet inlet Pipespipes

9. End Shieldshield 17. End Fitting fitting

10. End Shield shield Support support Assemblyassembly

Structure structure assembly 18. Feeder Pipespipes

assy 19. Outer Shellshell

20. Support Luglug

Fig.FIG. 68. 1 Integral INTEGRAL assembly

ASSEMBLY of OF Calandria CALANDRIA And AND

End END Shield SHIELD (CUTCUT-Away View Of

ReactorAWAY VIEW OF REACTOR) [1]

TYPE SETTER

PLEASE SEE ATTACHED FILE FOR 'PHOTO

7 March 11, 2008


READY black & white PICTURE OF THIS FIGURE 1

THAT SHOULD BE INSERTED HERE". A suitable

enlarged size of this figure may be inserted at this

location of the chapter to make it legible for readers.

The Primary Heat Transport (PHT) system uses heavy water under forced circulation in a figure-of-eight loop. Figures 68. 2

and 68.3 show the schematic of the system.

The main circuit of 220 MWe units has four branches on each side.

Fig. 2 PHWR simplified flow diagram [1]FIG. 68. 2

PHWR SIMPLIFIED FLOW DIAGRAM [1]

8 March 11, 2008


Fig. 3 Perspective view of steam generator and

PHT system [1]

FIG. 68.3 PERSPECTIVE VIEW OF STEAM

GENERATOR AND PHT SYSTEM [1]

TYPE SETTER:

PLEASE SEE ATTACHED FILE FOR 'PHOTO

READY black & white PICTURE OF THIS FIGURE 3

THAT SHOULD BE INSERTED HERE". A suitable

enlarged size of this figure may be inserted at this

location of the chapter to make it legible for readers

9 March 11, 2008


For the latest 220 MWe units, PHT System system is valveless. Elimination of these valves along with general reduction in the

number of components has helped to decongest the layout in the pump room, facilitating better maintenance approachability, less

maintenance, and lesser manrem.

The primary heat transport system pressure control in 220 MWe units is based on the feed and bleed bleed concept. During

normal operation, the average pressure of both outlet headers is controlled at a set pressure of 8.53 MPa to keep the system

solid,, i.e.that is, no bulk boiling is permitted. Operational transients such as turbine trip, load rejection, boiler feed pump trip,

reactor power setback, etc.and so on, cause swell swell or shrinkage. The feed or bleed control valves actuate to counter

these swells/shrinkages. Though the system is solid there is some finite compressibility of the system, which keeps the pressure

changes within a fairly narrow band. The feed is provided by two feed control valves located on the discharge side of primary

pressurizing pumps, which take suction from storage tank. Two bleed control valves are connected to reactor inlet header. The hot

bleed is depressurized, cooled and returned back to storage tank via purification system.

In 540 MWe PHWR, a pressurizer has been introduced for primary heat transport system pressure control, while feed and

bleed is retained for inventory control.

Fig. 4 Containment Building [1]

FIG. 68. 4 CONTAINMENT BUILDING [1]

10 March 11, 2008


TYPE SETTER:

PLEASE SEE ATTACHED FILE FOR 'PHOTO

READY black & white PICTURE OF THIS FIGURE 4

THAT SHOULD BE INSERTED HERE". A suitable

enlarged size of this figure may be inserted at this

location of the chapter to make it legible for readers.

Current Indian PHWRs use a double containment principle. The annular space between the primary and secondary

containment envelopes is provided with a purging arrangement to maintain a negative pressure in the space. This arrangement

significantly reduces the ground- level releases to the environment during accidents involving radioactivity release into the primary

containment. Fig.ure 68. 4 shows the schematic of containment.

The containment structures are made of concrete. The primary containment is a pre-stressed concrete structure, consisting of a

perimeter wall topped by a pre-stressed concrete dome. The outer or secondary containment is a reinforced concrete cylindrical

wall topped by a reinforced concrete dome. The primary containment uses epoxy coating as liner on the inner surface for enhanced

leak-tightness and ease while decontamination. Because of the use of double containment, incorporation of a steel liner is not

considered necessary.

11 March 11, 2008


<H2>68.2.3 Design CodesDESIGN CODES

The design, fabrication, testing and inspection of all mechanical components are as per the appropriate sections of ASME

ASME B&PV CodeBoiler & Pressure Vessel Code [2, 3].

The design philosophy of the containment structure is based on limit state concept where the response of the structure under

load combinations pertaining to both limit state of serviceability and limit state of strength are is checked. The various limit states

specified in the French code Code RCC-G [4] along with the supporting documents BPEL [5] and BAEL [6] are adopted for

designing the structural elements of the inner and outer containment structures.

<H2>68.2.4 Regulatory Structure [7]

Atomic Energy Regulatory Board (AERB) is the national authority to ensure safety of Nuclear nuclear Power power

Plantsplants (NPPs). AERB fulfills its mission by stipulating and enforcing rules and regulations concerned with nuclear and

radiological safety. AERB has developed safety documents that lay down requirements for meeting safety criteria for activities

related to nuclear energy and provide guidance on methods for fulfilling the requirements.

Safety documents published by the International Atomic Energy Agency (IAEA) and regulatory bodies of other countries are

appropriately used as reference material for the purpose.

Safety Codes establish objectives and set minimum requirements that have to be fulfilled to provide adequate assurance for

safety in nuclear and radiation facilities. Safety Guides provide guidelines and indicate methods for implementing specific

requirements as prescribed in the codes, .

As on date, AERB has published 5 Safety Codes and 45 Safety Guides concerning various aspects of NPPs and 51 other safety

support documents. Several other documents are under various stages of preparation. All these safety documents are being

extensively utilized in developing designs, operating procedures and in regulation activities including safety reviews by AERB. A

short list of documents related to NPPs is given belowin Table 68.2.

For design of mechanical components such as vessels, pumps, and piping, use of appropriate ASME Codes is permitted.

12 March 11, 2008


Table 2: Partial List of regulatory documents related to NPPs [7]TABLE 68.2 PARTIAL LIST OF REGULATORY

DOCUMENTS RELATED TO NUCLEAR POWER PLANTS [7]

S.
Title of Safety Document
noNo.

Code of practice on quality assurance for safety in


1.
Nuclear nuclear Power power Plantsplants
Code of practice on design for safety in Pressurized

2. pressurized Heavy heavy Water water Reactorreactor-

based Nuclear nuclear Power power Plantsplants


Code of practice on safety in Nuclear nuclear Power
3.
power Plant plant Operationoperation
Code of practice on safety in Nuclear nuclear Power
4.
power Plant plant siting
5. Code of regulation of nuclear and radiation facilities
Safety classification and seismic categorization of
6.
Structures, Systems, and Components (SSCs)
Design basis events for Pressurized pressurized Heavy
7.
heavy Water water Reactorsreactors
8. Primary Heat heat Transport transport system
Loss of coolant accident analysis for Pressurized
9.
pressurized Heavy heavy Water water Reactorsreactors
Safety guide for quality assurance in the design of
10.
Nuclear nuclear Power power Plantsplants
Safety Guide guide for seismic studies and design basis

11. ground motion for Nuclear nuclear Power power Plant

plant sites
Civil engineering structures important to safety of
12.
nuclear facilities
Design of concrete structures important to safety of
13.
nuclear facilities

13 March 11, 2008


S.
Title of Safety Document
noNo.

Design, fabrication, and erection of steel structures


14.
important to safety of nuclear facilities
Design, fabrication, and erection of embedded parts and
15.
penetrations important to safety of nuclear facilities

<H1>68.3 DESIGN OF INDIAN PRESSURISED PRESSURIZED HEAVY WATER REACTOR

COMPONETNSCOMPONENTS

<H2>68.3.1 Calandria- end End shield Shield assembly Assembly

The calandria- end shield assembly consists of calandria vessel with main shell and small shell connected by an annular plate.

The vessel houses 306 coolant tubes, reactivity mechanisms, and shutdown assemblies. At the two ends, the calandria vessel is

connected with end shields. The end shields limit the radiation dose in the fuelling machine vaults adjoining the calandria vault.

They also support and locate the calandria tubes and primary coolant channel assemblies in which the fuel resides. In the original

design of end shield (Rajasthan Atomic Power Station #1 and 2 and Madras Atomic Power Station #1), the end-shield material of

construction was 3.5% Ni-steel. However, it was found that Nil nil Ductility ductility Transition transition Temperature

temperature (NDTT) crossed the operating temperature within a short period of operation. While the stability of the end shields in

this condition is assessed in detail; from the second unit of Madras Atomic Power Station onwards, the end- shield material has

been changed to SS-304L, which is resistant to radiation embrittlement due to fast neutrons.

In the current design (Narora Atomic Power Station onwards) (Fig. 68.1), the calandria and two end shields constitute an

integral assembly, supported from the reactor vault walls, unlike earlier designs wherein the calandria and end shields were

separately suspended by support rods. This design allows common tube sheet between calandria and end shield. It also simplifies

alignment requirement between calandria tubes and end- shield lattice tubes, and is more suited to conditions at seismic site.

<H2>68.3.2 Main PHT System Components:

As described in section Section 1.0,<!--<query>Please check the section no. as no such section no.

exists in this chapter.</query>--> the main PHT system consists of steam generators, Primary primary circulating pumps,
pressurizer (for 540 MWeMWe PHWR), headers, feeders, and interconnecting piping.

14 March 11, 2008


68.3.2.1Steam Generator:

<H3>68.3.2.1 Steam Generator The Steam steam Generator generator (SG) design is of mushroom type. This design has
the advantage of a single integral unit with provisions of manholes on primary head to enable in-service inspection (ISI) of the

tubes. Four identical steam generators transfer heat from the heavy water reactor coolant on the primary side to the ordinary feed

water on the secondary side. The steam generators consist of an integral inverted vertical U-tube bundle in shell. Moisture

separators and driers are housed in the upper end of the shell.

The primary side of the steam generator consists of primary head, the primary side of the tube sheet and the primary side of the

tube bundle. A partition plate separates the inlet half of the primary head from the outlet half. The U-tubes are welded to the

primary side of the cladded carbon steel tube sheet and rolled into the tube sheet. The steam generator primary shell and head are

made of low alloy steel.

The secondary side of the steam generators consists of the shell, moisture separators and driers, the tube bundle shroud, the

secondary side of the tube sheet, the secondary side of the tube bundle, and tube support egg-crate grids. Low alloy carbon steel is

the principal material of construction.

The SG tubes are of 19-mm outer diameter (OD) and incoloy-800 material. The 19- mm tubes, when compared to 16-mm

tubes of 220 MWeMWe PHWR SG, offer advantages in ease of fabrication, reduction in manufacturing time and lower D 2O side

pressure drop. The shell of SG is provided with a man-way. Secondary side of the tube sheet is provided with suitable holes to

blow off and remove concentration of impurity in the secondary side water.

Both primary and secondary sides of the steam generators are designed and manufactured to the requirements of the ASME B&PV

Boiler and Pressure Vessel Code, Section III, subsection Subsection NB, Class-1 components.

15 March 11, 2008


68.3.2.2Primary Coolant Pumps

<H3>68.3.2.2 Primary Coolant Pumps The primary coolant pumps (PCP) are vertical, single stage, single suction, double
discharge, centrifugal pumps. Each pump is driven by a vertically, totally enclosed, air and water cooled, squirrel cage induction

motor.

A spacer type rigid coupling connects the pump shaft to the motor shaft. Each motor is supplied with a single piece flywheel

so that the total rotational energy of pump motor unit prolongs the operation of the pump after loss of motor power and the rate of

flow approximately matches the power run down following a reactor trip.

The pump has capability to operate without external injection (gland coolant external injection) but with process water

available from high pressureHP cooler. During hot standby condition when the pumps are unavailable, high pressureHP coolers

which are located at an elevation higher than the seal location provide necessary thermosyphon flow to ensure that temperature in

seal areas do not increase.

The pump casing design is in accordance with the requirements for class-1 components of ASME B&PVBoiler and Pressure

Vessel Code, Section III.

Primary circulating pump motor unit is a vertical assembly, with dead weight being supported at two locations; 80% on two

spring hangers located on boiler room floor and 20% on pump room floor through straight pipe piece attached to suction elbow. To

reduce stresses in heavy water pipes under operating conditions, sliding support has been provided at the bottom of pump suction

elbow. To mitigate large displacements of pump motor unit under earthquake, two horizontal snubbers each of 100 Te safe

shutdown earthquake (SSE) rating have been provided at pump motor C.G. location in two mutually perpendicular directions. The

pump bottom support is designed to resist vertical loads during the earthquake.

68.3.2.3 Pressurizer

<H3>68.3.2.3 Pressurizer In 500 MWeMWe PHWRs pressurizer is incorporated into the PHT main circuit to reduce
onerous demand on feed and bleed system to control inventory and pressure of the system. In these reactors, feed and bleed system

mainly acts as inventory control system and back-up for pressure control when pressurizer is not available. Pressurizer is connected

to Reactor Outlet Header (ROH) of each loop through one common isolation valve and two isolating valves, one for each loop. The

16 March 11, 2008


flow path is from ROH to steam generator to Primary Circulating Pump and then to Reactor Inlet Header (RIH). Pressurizer is

located in the pump room.

The heat transport medium is kept in a pressurized liquid state by a pressurizer (surge tank) backed- up by control valves,

which feed or bleed heavy water from the system including pressurizer.

Pressurizers are fabricated and machined from carbon steel forgings with non integral nozzles for piping connections. The

forgings of the vessel conform to SA 508 Cl.3 and in- house specification, and are made from vacuum degassed, Electro Slag

Remelted (ESR), killed fine grained steel. The forgings are delivered in normalized heat- treated and fully machined condition.

The in- house specification imposes special requirements on chemical composition and notch toughness for these forgings.

Pressurizer is in accordance with the requirements for Class-1 components of ASME B&PV Boiler & Pressure Vessel Code,

Section III, (Subsection NB).

Headers

<H3>68.3.2.4 Headers In 540- MWeMWe reactor there are four outlet headers, two in each loop of PHT main circuit.
Each outlet header receives flow from 98 outlet feeders and directs the flow to the steam generator via two inlet pipes. There are

also four inlet headers, two in each loop of PHT main circuit. Each inlet header receives flow from the Primary primary Coolant

coolant Pump pump and distributes the flow to 98 inlet feeders.

Headers in 540- MWeMWe PHWR are machined from single- piece carbon steel forgings with integral nozzles for feeders

and other piping connections, and the ends are closed by ellipsoidal caps. The single- piece forgings are made from the material

conforming to SA 350 LF2 and in- house specification. Also, these are made from vacuum degassed; , Bohler Electro Slag hot

topping process (BEST), killed, fine grained steel forgings and are delivered in normalized heat- treated and fully machined

condition. The in- house specification imposes special requirements on chemical composition and notch toughness for these

forgings. Reactor headers are designed to meet the requirements for Class-1 components of ASME B&PVBoiler and Pressure

Vessel Code, Section- III, Subsection NB.

In principle the reactor outlet headers are floating assemblies and govern the design/behavior of the rest of the circuit. Each

outlet header is mainly suspended through two steam generator inlet (SGI) lines connected to SGs inlet nozzle and resting on

sliding guide supports. Each of the reactor inlet headers is suspended through two pump discharge lines (PDL) connected to

discharge nozzles of main circulating pump.

17 March 11, 2008


To reduce large displacement due to inertial loading under earthquake, two snubbers each of 200 KN capacities have been

provided at each outlet header.

<H2>68.3.3 Feeders

There are total of 784 feeders in all, 392 at each end of the reactor, in 540- MWeMWe PHWR. The 392 feeders at each end of

the reactor run from the fuel channels vertically up the face of the reactor and there after horizontally across and above the fuelling

machine area to the reactor headers.

In order to achieve uniform outlet temperature, the feeders range in four sizes, viz. namely, 80-mm Nominal Bore (NB), 65-

mm NB, 50- mm NB, and 40- mm NB. These are inside diameter (I.D).- controlled pipes.

The feeders are of seamless carbon steel pipes conforming to SA 333 Gr.6 material and in accordance with the requirements

for Class-1 components of the ASME B&PV Boiler and Pressure Vessel Code, Section- III, Subsection NB.

The feeder pipes are arranged in banks, with a maximum of ten 10 feeders in a bank. The feeders are connected to end fittings

by high- pressure pipe couplings at lower end and are welded to header stubs at upper end. On the basis of analytical studies

carried out on feeders, it is observed that maximum stress occurs, in general, either at elbow after the coupling or at the pipe bend

location near header end. Thus, to take care of higher seismic load, the elbows at these ends have been strengthened by increasing

the wall thickness.

Piping<H2>68.3.4 Piping

All of the piping in the main primary heat transport system is of seamless carbon steel, ASME SA 333 Gr. 6, and designed and

fabricated in accordance with ASME B&PV Boiler and Pressure Vessel Code Section III, Subsection NB requirements. SA 333

Gr.6 seamless carbon steel pipes are intended even for the low- temperature application and have been preferred over SA 106 Gr. B

piping used in NAPP and earlier reactors because of inherent fracture toughness property.

In all standardized 220- MWeMWe and 540- MWe PHWRs, the three important segments of PHT piping are running from

ROH to SG inlet nozzle; SG outlet nozzle to suction nozzle of PCP, and from discharge nozzle of PCP to RIH. The dead weight of

outlet header, feeders, and heavy water SG inlet pipes would cause undue large moments on SG inlet nozzle because of off-set

between SG and outlet header along N-S axis. To reduce these moments, sliding guide supports resisting vertical loads have been

incorporated in heavy water pipes connecting outlet header to SG inlet nozzles.

18 March 11, 2008


68.3.4.1 Design Philosophy

<H3>68.3.4.1 Design Philosophy All the components of Main main PHT System system are categorized as class Class I
components and hence have been designed in accordance with ASME Section III, Division. I NB. Detailed design by analysis

approach has been adopted for all class Class I components. All the components have been designed for six sets of conditions.

These six service levels and the loads considered for each of them are summarized below:

Design Conditions

Design Conditions Internal pressure + Dead Weight weight (cold flooded)

Level A Service Loadings (Normal Operation)

Level A Service Loadings (Normal Operation) Internal Pressure pressure + Thermal Loads loads + Operating

Cyclescycles.

Level B Service Loadings (Up-set Condition)

Level B Service Loadings (Up-set Condition) Internal Pressure pressure + Thermal Loads loads + operation basis

earthquake (OBE) (inertial) + OBE (Seismic anchor movement) loads + operating cycles. Operation basis earthquake OBE inertial

and OBE seismic anchor movement loads have been combined on absolute sum basis.

Level C Service Loadings (Emergency Condition)

Level C Service Loadings (Emergency Condition) Internal Pressure pressure + Dead Weight weight

Level D Service Loadings (Faulted Condition)

Level D Service Loadings (Faulted Condition) Internal pressure + Dead weight + SSE Inertial Loadload.

Test Conditions

Test Conditions Test pressure + Dead Weight weight

<H2>68.3.5 Coolant Channel Assembly

Coolant channel assemblies house the fuel bundles and contain the hot pressurized heavy water coolant flowing through them.

Each coolant channel assembly consists of a Zr-2.5% Nb coolant tube, two martensitic stainless steel end fittings one each at

either end, and associated hardware. The coolant tube is rolled to end fittings at both ends. Each coolant tube is thermally isolated

19 March 11, 2008


from cold heavy water present in the calandria vessel by a seamless- / or- seam- welded concentric Zircaloy-4 calandria tube,

which is rolled into the tube sheet of the end shield assembly at both ends.

Calandria tube envelops coolant tube forming an annulus space between the two tubes. Calandria tubes are manufactured out

of Zircaloy-4 material either by seamless route involving hot extrusion and cold pilgering or by seam welding cylindrically formed

tubes from strips. Both types of tubes would meet the specified longitudinal and transverse mechanical properties such as ultimate

tensile strength (UTS), yield strength (YS), and % Elongationelongation percentage. Calandria tubes are vacuum annealed to

minimize residual stresses.

Coolant tubes which that are the most important structural components in the reactor core are manufactured from Zr-2.5% Nb

alloy. Coolant tube is attached at either end to a stainless steel (type AISI-403 modified) end fitting by a roll- expanded joint. These

joints are of zero- clearance type and this feature helps in controlling the residual stresses in the joint region to a low level,

providing necessary safe-guard from delayed hydride cracking of coolant tube.

Coolant tubes are seamless tubes produced by hot extrusion and cold pilgering followed by stress relieving (autoclaving) in a

steam atmosphere. The ends of the coolant tubes require special finishing operations to obtain stringent dimensional control

necessary for zero- clearance rolled joints. The inlet and outlet end of coolant tube is roll expanded to end fittings made of

martensitic stainless steel (type 403 modified) solid forgings. End Fitting fitting is an open- ended tubular body of approximately

164 mm outside diameter and 2516 mm length. It has an integral side opening (feeder hub) to which the feeder pipe is attached.

Although zirconium alloys are not ASME Code approved materials, attempts have been made to follow all the requirements of

the ASME code Code for each component. Rolled joints are also not covered by ASME Code. However, detailed development

work and evaluation have been carried out to qualify these joints for reactor application and to establish that these joints satisfy all

design requirements.

68.3.5.1 Calandria Tube

<H3>68.3.5.1 Calandria Tube The ends of calandria tubes are joined with calandria side tube sheet of end shield
assembly by means of a special type of rolled joint called sandwich rolled joint. This joint is developed for a thin tube and low-

pressure conditions. If the calandria tube is directly rolled into a plain or grooved tube sheet, the joint would not develop the

required seating pressure and hence the required leak tightness. Due to this limitation, a sandwich type of joint is adopted where

calandria tube is squeezed (sandwiched) between an inner- landed sleeve insert of stainless steel type Type 410 in a full annealed

condition and the outer stainless steel tube sheet. The ends of the calandria tubes are flared to a larger diameter to accommodate

20 March 11, 2008


the landed sleeve insert and to provide design clearances between the coolant and calandria tubes anywhere along the channel axis.

Joint configuration with PIWR (percentage insert wall reduction) of 6.5 to 7.5 is selected after development work. Calandria tube

rolled joints have a minimum pullout load of 31 metric tons and a leak tightness of 3 x 10-6 cc cm3per /sec.

During normal operation, calandria tubes are subjected to a temperature of 75 o C, and maximum external pressure of 1.45

Kg/cm2, corresponding to the lower most row of calandria tubes in the calandria vessel (hydrostatic head of 0.85 Kg/cm 2 +

moderator helium cover gas pressure of 0.6 Kg/cm 2) . In addition, calandria tube is subjected to (i) Garter garter spring loads, (ii)

Buoyancy force, (iii) Direct direct pressure load on the tube sheets causing a tensile loading on all tubes, and iv) Stresses stresses

due to differential thermal expansion of calandria tubes and calandria shell.

Calandria Tube Collapse Pressure

Calandria Tube Collapse Pressure. The calandria tubes are designed on the basis of neutron economy and collapse due to

external pressure. The wall thickness is set at a minimum value, satisfying the requirement of stability against collapse pressure.

The design also caters for postulated accident conditions where overpressure of the calandria vessel is assumed. Calandria tube

collapse pressure works out to be 2.85 Kg/cm2.

68.3.5.2 Coolant Tube.

<H3>68.3.5.2 Coolant Tube The temperatures and pressures at the inlet and the outlet considered in design are as follows:

Coolant tube inlet pressure 124.18 Kg/ cm2

Coolant tube inlet temperature 260 o C

Coolant tube outlet pressure 115.82 Kg/cm2

Coolant tube outlet temperature 304 o C

Since the pressure and temperature vary along the length of the coolant tube, the design condition is established by evaluating

stresses at several locations along the length to determine which location requires the largest wall thickness. Minimum required

coolant tube wall thickness calculated on this basis works out to 4.3 mm, inclusive of corrosion and wear allowance of 0.2 mm,

with critical section of the tube being the inlet end.

Coolant tubes are designed in accordance with the intent of ASME Section III, Subsection NB requirements. As per ASME

codeCode, design stress intensity for coolant tubes should be the lowest of:

(a) 1/3 of the specified minimum ultimate tensile strength (UTS) at room temperature.,

(b) 1/3 of the UTS at temperature.,

21 March 11, 2008


(c) 2/3 of the specified minimum yield strength (YS) at room temperature., and

(d) 2/3 of the yield strength (YS) at temperature.

Out of Of the above criteria, the governing quantity deciding coolant tube design stress is the 1/3 UTS at operating

temperature.

Neutron- irradiation- enhanced creep deformation is one of the important factors deciding the life of coolant tube in PHWRs.

Based on the present level of understanding, the coolant tube is estimated to undergo a diametric creep strain of the order of 3%

and an axial elongation of 2.5% during the life of the reactor. The potential life limiting concerns due to creep are as follows:

(a) Diametral expansion causing bypass of coolant flow around the fuel bundles, and

(b) Relative sag between coolant tube and calandria tube causing possible contact.

Corrosion and Hydriding

Corrosion and Hydriding. Zr-2.5% Nb alloy has good corrosion resistance in high temperature water as long as oxygen

content is held extremely low. The predicted corrosion rate is expected to be about 0.1 mm over the operating life of the reactor. A

corrosion and wear allowance of 0.2 mm is provided on the coolant tube. More over, finished tubes are autoclaved in steam

atmosphere at 400 oC for 24 hours to form a protective layer on the tube surface. The presence of 1% oxygen in the circulating

annulus gas monitoring system helps in maintaining a constant oxide layer thickness at the tube O.D.

The more complex part of the corrosion reaction is the absorption of hydrogen evolved in the oxidation reaction of heavy

water with zirconium. Hydrogen is evolved in this reaction and a portion of this hydrogen is absorbed by the zirconium alloy ; and

this phenomenon is termed hydrogen pick-up by the alloy. If the hydrogen concentration in the tube exceeds the solubility limit,

then it precipitates as zirconium hydrides.

The solid solubility of hydrogen in zirconium alloys is very low below 150 o C. Hence, more zirconium hydrides will be

present at lower temperatures. Hydrogen when in solid solution in zirconium alloys can be driven in directions of thermal stress

and concentration gradients. Hydrogen in excess of solubility limits precipitates as zirconium hydrides. As zirconium hydrides are

brittle, this can lead to failure of coolant tube by initiation and propagation of a crack in the radial axial plane due to phenomenon

of delayed hydride cracking. Delayed hydride cracking is the process of formation of hydrides and their cracking aided by the

presence of tensile hoop stress (including residual stress) and defects in the tube.

22 March 11, 2008


Following remedial measures have been implemented in the design of a coolant tube against embrittlement effects and

hydriding:

(1) Zero- clearance rolled joints, which will significantly reduce the tensile residual stresses in the neighbourhood of rolled joint

region.

(2) Stringent Inspection And and Quality quality Controlcontrol, consisting of both, Angle angle beam and normal beam

ultrasonic examinations as well as a supplementary eddy current examination.

(3) Control of Impurities impurities, like such as Hydrogen hydrogen, Chlorine chlorine, Phosphorous phosphorous, and Carbon

carbon.

(4) Autoclaving of Coolant coolant Tubetube that which produces hard adherent oxide layer of about 1 mmicron thick on the

tubes, which acts as a barrier for hydrogen ingress from annulus gas side.

(5) Addition of Oxygen oxygen in the annulus gas to avoid deterioration of the oxide film.

(6) Avoidance of cold pressurization to improve the flaw tolerance at low system temperatures.

Leak-Before-Break Methodology

Leak-Before-Break Methodology. Achieving leak before break depends on the difference between the time available to

detect a leaking crack and time required to detect a leaking crack. The time available to detect a leak is estimated from:

Time available Ta Ta (in hours) is given by

(C 7W )
Ta
2V
where C is the critical crack length (CCL), 7 W is the leakage size crack and V is the delayed hydrogen cracking velocity in the

axial direction.

During service, CCL reduces and the DHC velocity increases and the time available to detect a leaking crack decreases. If

hydrides are present and a defect does initiate DHC, then the time available to detect the leak would be in the range of 11 to 12

hrs. Thus, a sensitive leak detection system called annulus gas monitoring system is implemented in the design which that enables

leak detection and safe shut down in less than 5 hours.

68.3.5.3 End Fittings.

23 March 11, 2008


<H3>68.3.5.3 End Fittings End fittings are manufactured out of AISI-403 (modified) stainless steel. Coolant coolant tube and

end fittings are connected by means of a rolled joint. To have a leak tight rolled joint at all temperatures , end fittings has need to

have coefficient of thermal expansion as close as possible to that of the coolant tube. End Fittings fittings also require comparable

values of mechanical properties like such as hardness with respect to coolant tube and liner tube for rolled joint integrity. AISI-403

(modified) material can be heat treated to attain the required mechanical properties.

Results of fast neutron irradiation damage on AISI 403 material at 304 o C shows that there is a change of NDTT (nil ductility

transition temperature) from 40 o C to about 100 o C during the life of the reactor. The presence of trace elements such as copper,

vanadium, antimony, aluminium, and arsenic can increase the shift in NDTT. Hence, these trace elements are controlled to the

extent possible in the end- fitting material. Presence of trace elements such as copper, vanadium, antimony, aluminium, and arsenic

are controlled to a maximum of 1450 ppm out of which copper alone is controlled to a maximum of 600 ppm.

End- fitting material is specified with the following impact properties:

Longitudinal: 2.8 Kg/.m (min) at 20 o C

Transverse: 2.1 Kg/.m (min) at 66 o C

<H1>68.4 DEVIATIONS FROM ASME CODE

All the Indian PHWR components are, in general, designed, fabricated, commissioned, and tested as per the ASME code Code

requirements. However, there are some areas in PHWRs where deviation from the ASME Code requirements is unavoidable due to

the basic design of the reactor. Still, in such areas, the basic intent of the ASME Code is maintained. The following are such areas:

<H2>68.4.1 CALANDRIACalandria

68.4.1.1 Material of Calandria Tubes:

<H3>68.4.1.1 Material of Calandria Tubes Material of calandria tubes is Zircaloy-2/ Zircaloy-4. This material has not been

approved by ASME Code Section III as Class I material. Since the calandria tubes are present in reactor core, due to neutron

economy, choice of material for calandria tubes is restricted to Zirconium alloys. ASME B&PVBoiler & Pressure Vessel Code,

Section. III has been developed for PWRs and boiling water reactors (BWRs) designed and built in the United States. These

reactors do not have calandria tubes. For heavy water reactors, calandria tubes are inherently present, and thus this violation of

code is unavoidable. However, the design, manufacturing, and inspection follow Section III, Class I philosophy.

24 March 11, 2008


68.4.1.2 Rolled Joints between Calandria Tubes and Calandria Side Tube Sheets:

<H3>68.4.1.2 Rolled Joints Between Calandria Tubes and Calandria Side Tube Sheets This type of joint is not approved

by ASME Code Section III for Class I components. The reason for using this type of joint is that Zircaloy-2 cannot be easily

welded to stainless steel. This violation of code also takes place due to presence of calandria tubes and thus is unavoidable.

However, this joint has been so developed that its pull out strength is at least equal to tensile strength of calandria tube. Moreover,

this joint is so designed that it is not falling on boundary of heavy water-light water. Moreover, this joint has been experimentally

proven satisfactory for strength and leak-tightness requirements.

68.4.1.3 Use of Rupture Disc for Over Pressure Relief:

<H3>68.4.1.3 Use of Rupture Disc for Overpressure Relief Over-pressure in calandria develops when rupture of a coolant

channel occurs in calandria vessel. During this condition, primary coolant which that operates at high temperature and high

pressure, gets liberated in moderator which that operates at low temperature and pressure. This results in pressurization of calandria

vessel. Four relief pipes having diameter of 500 mm are provided on calandria vessel for relieving the pressure. The ends of these

pipes are closed by rupture disc assemblies. In case of a coolant channel rupture in calandria, these rupture discs break open and

over-pressures in calandria are restricted.

The use of rupture discs as the primary pressure relief device is not allowed by ASME B&PVBoiler and Pressure Vessel Code

Section III, Sub-section NB. As per this Ssub-section, the rupture disc may be used in conjunction with safety valves. However, for

the accident condition described above, the flow rate required for the pressure relief is so large that use of safety valves is not

adequate.

It may be mentioned here that the reactors which that are mainly addressed by ASME code Code are light water reactors

(LWRs). In these reactors, the functions of moderator and coolant are performed by the same fluid. There are no coolant channels

in these reactors, so that the type of accident which that is being considered for PHWR calandria, is not relevant for these reactors.

Over-pressures in the reactor vessels of these reactors occur mainly due to system transients, and these can be relieved using safety

valves and thus the use of rupture disc is not necessary in these reactors.

Normal operating pressure of the Helium helium cover gas which that is at the top of the calandria is low, i.e.that is, 0.3

kg/cm2 (g). There is a relief valve in the system, which opens when the system pressure rises above 0.5 kg/cm 2 (g). This relief

25 March 11, 2008


valve has a capacity of 2348 standard lpm, which is sufficient to take care of changes in volume of moderator due to swelling or

other minor causes. The rupture disc set pressure is 1.4 kg/cm 2 (g), which is not close to the relief valve setting.

So, the OPRDs come into action only when there is an accident involving coolant tube rupture. The size of opening is such

that one OPRD is sufficient to relieve the pressure in calandria in case of coolant tube rupture accident. For redundancy, four

identical rupture discs have been provided for each calandria.

The sample rupture disks are tested in shop for burst pressure & and cycle testing. The accepted range of burst pressure is 1.26

kg/ cm2 to 1.40 kg/ cm2 (g).

<H2>68.4.2 END SHIELDSEnd Shields

68.4.2.1 Tri-Junction Welds:

<H3>68.4.2.1 Tri-Junction Welds The design of end shield meets all requirements of ASME Code Section III, Class 2 in all

respects except for inspection of joint among lattice tubes, baffle plates, and calandria side tube sheet. However, ultrasonic

technique has been developed for this purpose. In addition to ultrasonic examination, dye penetrant (DP) examinations are carried

out after each welding pass. Mock-up weld passes are carried out everyday before start of welding to ensure good quality. These

mock-ups are sectioned and inspected if found necessary.

68.4.2.2 Monitoring of Intermetallic Joint (Diaphragm Plates):

<H3>68.4.2.2 Monitoring of Intermetallic Joint (Diaphragm Plates) Diaphragm plates are provided in the calandria side

tube sheet and the fuelling machine tube sheet. The diaphragm plates have lower thickness compared to the tube sheets to provide

the flexibility required to allow thermal expansion of the calandria tubes. There are weld joints between the diaphragm plates and

the tube sheets. Total thermal neutron flux at this joint is 1.08 E11 n/cm 2/sec. This is not expected to cause embrittlement of the

material over a period of 30 FPY. Stress analysis shows that stress level in this zone is very low. Quality control procedure assures

no defect in this joint (100% radiography in addition to root pass D. P.). Thus, no failure is expected during service. The water

level in expansion tank and makeup rate are monitored continuously.

<H2>68.4.3 COOLANT CHANNEL COMPONENTSCoolant Channel Components

Material of Coolant Tubes: . Zirconium - Niobium alloy has not been used as a material for the pressure- retaining components

in LWRs. Here also, the intent of ASME Code is followed in the design, manufacture, inspection, and testing of the tubes.

26 March 11, 2008


Rolled Joint between Between Coolant Tubes and End Fittings: . The reasons for using rolled joint here are same as those for

the joint between calandria tube and the calandria tube sheet.

Material of End Fitting: . Material of end fittings is Martensitic martensitic stainless steel AISI 403 (modified), hardened and

tempered. The essential elements of modification are: (i) controlled range of C and Cr to achieve consistent mechanical properties

with same heat treatment parameters and (ii) low level of residuals to reduce the shift in ductile to brittle transition temperature due

to irradiation.

This material has been approved by ASME, vide Code Case No. N-4-11 (approval date 13.7.81), as a pipe material, where the

toughness requirement as per NB-2332 applies. Accordingly, this material is required to exhibit a lateral expansion (LE) of 25 mils

(0.65 mm) minimum in a Cv test conducted at lowest service temperature (LST).

A series of tests were conducted jointly by Nuclear Power Corporation (NPC) and Indira Gandhi Centre for Atomic Research

(IGCAR) to obtain data on this aspect of unirradiated end fitting material. From the results, it is clear that this material is capable

of meeting this code requirement at temperatures above 60 C. Nil ductility transition NDT temperature of this material in

unirradiated condition corresponding to 15 ft. lb. absorbed energy in Cv test is 40 C. The shift in NDTT temperature due to

irradiation effect gets saturated at a fluence of about 6.5E19 n/ cm2. The maximum shift is about 55 C. Further, a test was

conducted at low temperature to simulate radiation damage, in which an artificially produced ([electrical discharge machining

(EDM)]<!--<query>Please check the full form of abbreviation "EDM" for correctness.</query>--> notch defect
in the highly stressed rolled joint area was extended by fatigue and the end fitting was tested up to burst. The end fitting could

withstand nearly three3 times the design pressure.

Therefore, end- fitting material is safe for all conditions of reactor operations, as it always operates at 265 CC. However, as a

precaution, hydro-test during manufacture and at pre-commissioning stage is conducted at a minimum temperature of 65 C and

also cold pressurisation pressurization is prohibited in the reactor, where during start-up, pressurisation pressurization starts at a

temperature of 130 C.

Inspection of End Fittings: . There are some areas of end fitting (at the top of the nozzle and some portion of side) which that are

not covered by bi-directional ultrasonic examination during manufacture. At these places only straight beam technique is used.

<H2>68.4.4 INACCESSIBILITY FOR IN-SERVICE INSPECTIONInaccessibility for In-Service Inspection

27 March 11, 2008


The reactor components like such as end shields and calandria are not accessible to periodic ISI. However, during design and

fabrication stage, all precautions are taken to see that no regular ISI is needed for this component. Stress analysis for all the

components has been done as required by the code.

<H1>68.5 Seismic Qualification, Leak-before-break, ISI, Containment DesignSEISMIC

QUALIFICATION, LEAK-BEFORE-BREAK, ISI, CONTAINMENT DESIGN

<H2>68.5.1 Seismic Qualification

The various structures, systems, and components in NPP are classified into three categories [8]. Category I systems are those

whose failure could lead to release of activity into containment or in the environment (e.g., reactor containment structure, PHT

system etc.and so on) and are designed for S1 (equivalent to OBE)- and S2 (equivalent to SSE)- level earthquakes [9]. Category II

structures (e.g., waste management building) are designed for S2- level earthquake and category Category III structures (e.g.,

turbine building, turbo-generator and so onetc.) are designed for earthquake resistance as per national practice [10].

Due to the numerical difficulties associated with use of plate/shell elements for complex geometries, the present practice is to

carry out separate analysis for the entire reactor building using 3D stick model, in which the inner containment (IC) is modeled

using a separate 3D stick connected to the Reactor reactor Building building raft. In this method, the structure is modeled using 3D

beam properties based on strain energy equivalence between 3D finite element model and 3D beam model. Lateral torsional

coupling and the effect of flexibility of floors, offset, and partial support of walls is are accounted for. In this method, the beams are

located at shear centers [11, 12] and the masses ate located at mass centers with a rigid link joining the two (Fig. 68. 5). Beam

models are used for obtaining the global seismic responses.

These are finally applied on the 3D finite element model for evaluating the design stresses. The seismic analysis model was

supplemented by an axi-symmetric model to evaluate the stresses at the shell/dome interface. In the current design being carried

out for 700 MWeMWe project, the seismic forces on the containment structure will be computed from a detailed 3D FE model

developed using beam/shell/solid elements.

For aspects such as soil-structure interaction, decoupling criteria, and damping in concrete structures; , guidelines of ASCE

are followed. The application of the decoupling criteria has resulted in a model of the Reactor reactor Containment containment

Building building, which includes beam elements representing calandria vault, calandria, and the end shields.

28 March 11, 2008


The application of the decoupling criterion to the complex structure such as containment structure is not straight forward.

Modifications have been suggested [13] that make the criteria applicable to the complex structure such as reactor containment

structure. This criterion is also not applicable for multi-connected equipment. A new criterion [14, 15] was developed that can be

used for checking the decoupling requirement of multi-connected equipment.

FigFIG. 68.5 Beam Model of PHWR


Building [12] BEAM MODEL OF PHWR
BUILDING Building
[12]BBBBBBBBBuilding [12]Building [12]
Building [12]
Beam Model of PHWR Building [12]

TYPE SETTER:

PLEASE SEE ATTACHED FILE FOR 'PHOTO READY black & white PICTURE OF THIS FIGURE 5 THAT SHOULD

BE INSERTED HERE". A suitable enlarged size of this figure may be inserted at this location of the chapter to make it

legible for readers.

29 March 11, 2008


For damping in piping, higher values such as the PVRC damping [16], as shown in Fig. 68. 6, are also used.

Fig. 6FIG. 68.6 Frequency Dependent Damping Values

(ASME Code Case N 411-1)FREQUENCY DEPENDENT DAMPING VALUES

(ASME CODE CASE N 411-1)

The floor- mounted equipment and piping are analysed analyzed using floor response spectra. For this purpose, time history of

the floor motion is generated by performing a time history analysis of the RCB. The resulting spectra are broadened + 15% for

use in equipment design.

For active equipment, such as electrical relays, switches, contacts, shut-off rod drives etc.and others, whose functioning solely

depends on the actuation of some parts within them, it is necessary to demonstrate their operability during an earthquake event by

testing on shake table. In addition, the equipment must withstand the effects of a number of OBEs prior to the SSE. The

procedures given in (IEEE-344, 1987) for the assessment of integrity and operability are adopted for testing. For heavy equipment

such as primary heat transport pumps, it is acceptable to qualify by detailed finite element analysis wherein the bearing stiffness,

gap between the casing and the impeller, and so on,etc. must be considered in a mathematical model.

<H2>68.5.2 IN-SERVICE INSPECTION PHILOSOPHY

In-Service Inspection Philosophy

As an integral part of quality assurance during operation, a periodic programme of in-service inspection has been instituted to

cover all critical items important to safety [17]. This programme has been formulated on the basis of guidelines given in IAEA

30 March 11, 2008


Safety Guide 50-SG-02 entitled In-service Inspection for Nuclear Power Plants [18] and the Canadian code Code CAN/CSA

N285.4-05 and 8-05 [19, 20].

In formulating this programme, the following special characteristics of PHWRs have been taken into consideration:

Use of a large number of coolant channel assemblies (306 nos. for 235 MWeMWe unit and 392 nos. for 500 MWe MWe

unit) in place of a reactor pressure vessel and leading to a multi-component primary cooling system.

Use of a variety of material requiring different kinds of examination techniques.

Strict requirements in limiting leakage of primary coolant from the point of view of safety and economy.

On-power refueling, which reduces the frequency of outages.

Examples of the components and methods of examination normally considered for the ISI programme are listed in Table

68.3.

The inspection areas and degree of inspection required for each system or component is are determined by the inspection

category, which in turn is based on two factors: stress intensity (SI) ratio (R s) and fatigue usage factor. There are three levels of

stress intensity, namely, high (2/3), medium, and low (1/3).

Calculated SI

SI Ratio (Rs) =

Allowable SI

Similarly, there are three levels of fatigue usage factor, viz. namely, low (0.01), medium, and high (0.1). Based on

different combinations of stress intensity ratio and fatigue usage factor, four levels of inspection categories A, B, C1 , and C2 in the

decreasing degree of examination requirements have been arrived at (Fig. 68.7).

31 March 11, 2008


TABLE 68.3: COMPONENTS AND METHODS OF EXAMINATION [17]

Items to be Examined Methods


Vessel and piping Visual, volumetric, and

Integrativeintegrative
Pump and valve

- weld Visual, volumetric, and

- interior surface Integrativeintegrative

Visual and surface (If if material is

subjected to stress corrosion or

erosion)
Support

- weld Visual, surface, and volumetric

- others Visual
Rotating Visual, surface, and volumetric

Machinerymachinery
Mechanical

Couplingscouplings
- Boltbolt Visual, surface, volumetric, and

- Studstud integrative

- Nutnut

All components

- Corrosioncorrosion UT Thickness gauging

- Erosionerosion
Heat

Exchangersexchangers/S

steam Generator Visual, surface, and volumetric

generator VolumetricVisual, surface and

- Shellshell volumetric

- Tubetube Volumetric

32 March 11, 2008


Items to be Examined Methods
Coolant Tubetube PT-CT Gap, Garter Spring spring

Locationlocation,

Volumetricvolumetric,

Dimensional dimensional, and

Hydrogen hydrogen Pickpick-up


Feeder pipe Visual, Feeder feeder Gapgap,

Volumetric volumetric, and

Thicknessthickness

Inspection category A requires examination of all welded points and adjacent base metal. Category B requires examination of

at least 1/3one-third of the inspection areas. For Category C1, no examination is required if the metal is ductile and creep resistant

and the effects of neutron irradiation are not significant. For category C2, no examination is required. The inspection methods are

of non-destructive type like such as visual, dye penetrant, ultrasonic, radiography, acoustic emission, and hydro and leak testing.

The procedures adopted are generally in conformance with ASME Section V and XI Codes.

The results of the Ppre-Service service Inspection inspection (PSI) of the components prior to the start of operation of the

plant establish the base line data required for comparison during subsequent ISI. This examination is carried out using the same

methods and techniques and types of inspection instruments as those, which are planned to be used for in-service inspection. In

the case of many components and systems, the inspection data collected during manufacture serve s as baseline data. PSI is

performed either:

(a) After after the hydrostatic pressure test but before start up of the reactor; or

(b) Before before the hydrostatic pressure test provided that a confirmatory examination is performed after the

component hydrostatic pressure test and the results indicate no significant change.

Low Medium High

Fatigue Fatigue Fatigue

Factor Factor Factor

33 March 11, 2008


Stress Intensity Ratio, RS

High Stress

Intensity
C1 B A

Medium

C1 B B Stress

Intensity
Low Stress

Intensity
C2 C1 C1
1
2/3
1/3
0

0 0.01 0.1 1.0

Fatigue Usage Factor

FIG. 68. 7: DETERMINATION OF INSPECTION CATEGORY [17]

In order to minimize the radiation exposure of inspection personnel and keeping in view the fact that a large number of

components used are identical, a sampling approach has been taken for working out the inspection programme. For identical

welds of identical components, the number of welds to be inspected may be reduced to FA. The value is FA is taken from Fig. 68.8.

34 March 11, 2008


Fig. 8: Inspection Sample for Identical Components/

Welds [17]FIG. 68.8 INSPECTION SAMPLE FOR

IDENTICAL COMPONENTS/ WELDS [17]

The in-service inspection intervals are chosen such that any deterioration occurring in systems and components are is detected well

before any failure takes place. The first inspection is carried out commencing from the end of the first year to the end of the fifth

year after going into commercial operation with the examinations spread as evenly as practicable over the period. The subsequent

in-service inspections are scheduled at intervals of 10 years (Table 68.4).

Table 4: Inspection Schedule for Pressurised Heavy Water ReactorTABLE 68. 4 INSPECTION SCHEDULE FOR

PRESSURIZED HEAVY WATER REACTOR

Inspe Inspection period Minimum % Maximum

ction indicated as percentage of percentage

Interv calendar year of examinations of %

al plant service required to be examinati

from completed ons

commencement credited

of operation
1st (5 0-2 16 34

years) 2-5 100 100


2nd 5-8 16 34

(10 8-12 50 67

35 March 11, 2008


years) 12-15 100 100
3rd 15-18 16 34

(10 18-22 50 67

years) 22-25 100 100


4th 25-28 16 34

(10 28-32 50 100

years) 32-35 100 100


Note: Plant life is assumed to be 40 years.

Acceptance standards for visual, surface and volumetric examinations are same as those in ASME Code Sec. XI.

Acceptance Standards for Visual, Surface, and Volumetric Examinations are Same as Those in ASME Code Section XI.

While the components of primary heat transport system do receive the inspection commensurate with their importance, the major

challenges faced by the Indian PHWRs are (i) Life management of coolant channels, and (ii) thinning of feeders and secondary

side piping due to Flow flow Aaccelerated Corrosion corrosion (FAC). These challenges have been successfully met through ISI

and maintenance/replacement strategies. The Coolant coolant channels suffer from degradation due to irradiation creep resulting in

increase in diameter and sag; deuterium pickup resulting from corrosion reaction and leading to loss of fracture toughness. The ISI

programme for coolant channels consists of the following:

(a) Non-destructive examination for flaws including flaws in the rolled joint region.

(b) Channel CT-PT gap, wall thickness, axial elongation, channel sag, etcand so on.

(c) Eddy- current detection for location of garter springs.

(d) Measurement of gap between coolant tube and calandria tube.

(e) Sliver sampling for measurement of hydrogen content.

BARC in-service inspection system (BARCIS)<!--<query>Please check the full form of BARCIS for

correctness.</query>--> and Sliver sliver sampling scraping tools are some of the important tools developed for ISI of coolant
channels.

Flow accelerated corrosion FAC has become another focused area following some recent incidents. Thickness measurement is

regularly carried out at a large number of locations.

As far as replacement is concerned, India has successfully completed en- masse coolant channel replacement in four reactors

where Zzircalloy-2 pressure tubes were used. Also, feeder replacement has been successfully completed in three reactors.

36 March 11, 2008


<H2>68.5.3 Leak-beforeBefore-breakBreak

Leak-before-break LBB approach has been applied to primary heat transport (PHT) system piping of 500- MWeMWe Indian

PHWR as per NUREG-CR-1061, Vol.3 [21], and IAEA TECDOC-710 [22]. Parallel to these analyses, a comprehensive

Component Integrity Test Program has been initiated to address some of the issues in the fatigue and fracture analyses. These

issues include the transferability of the specimen fracture parameters to the component level, the effect of cyclic/dynamic load (that

may occur during an earthquake) on fracture properties, the effect of system compliance on the load- bearing capacity of piping

components etcand so on. For in-depth understanding of these issues, 70 fatigue/fracture tests have been conducted so far on full-

scale piping components. Apart from these, probabilistic methodology has also been used to address the uncertainty associated with

the input parameters used in the LBB analysis. The present paper discusses the LBB qualification of PHT system piping of 500

MWeMWe Indian PHWR and addresses some of the issues not considered in LBB concepts by above standards.

The LBB concept is basically demonstrated through fracture mechanics analysis that there is negligible chance of catastrophic

break of PHT pipes without giving prior indication of leakage. This involves detailed fracture mechanics studies of different piping

components such as straight pipe, elbow and branch tee. Leak-before-break LBB is ensured by demonstrating three levels of safety

assessment against sudden double- ended guillotine break (DEGB). Level 1 is inherent in the design philosophy of ASME Code

Sec. Section III [2], which is normally followed in piping design. Ductile and tough materials are widely used in nuclear power

plant piping due to their high resistance against non-ductile rupture. The design is done with a well-defined factor of safety on of

code- specified 95% exceedance probability on strength. It does not permit the presence of any defect larger in size than allowed

in ASME Code Section Sec. III for girth welds. The demonstration of Level 2 safety consists of postulating a surface crack mostly

in the weld, which may go undetected during the non-destructive examination. It is then shown that there is insignificant crack

growth of this surface crack during the entire life period of the reactor. In this crack growth study, one should consider all the

possible crack growth mechanisms such as corrosion, erosion, fatigue, creep, flow- induced vibration, etc.and so on, whichever

may be operative for the particular piping system. From the operating experience of various PHWRs, it has been observed that

under the controlled environment of PHT piping system, fatigue is the only crack growth mechanism which cannot be totally ruled

out. Hence, one should perform the fatigue crack growth study of the postulated surface flaw in the PHT pipes. In the Level 3

safety assessment, a through- wall crack is postulated at the maximum stress location with the worst material properties. The size

of the crack is chosen so as to ensure the predicted leakage is detected by the leak monitoring devices. Finally, it is shown that this

crack will withstand the maximum credible load that may act during a safe shutdown earthquake (SSE).

68.5.3.1 Fatigue crack growth Tests

37 March 11, 2008


<H3>68.5.3.1 Fatigue Crack Growth Tests Fatigue crack growth tests [23] have been conducted on pipes till the crack

depth has reached through-wall. During the tests, crack depth and number of cycles have been recorded. Maximum crack depth and

number of cycles for given stress ratio (R) and initial crack depth in pipes have been shown in Fig. 68.Figure 9. Maximum crack

depth and number of cycles calculated analytically have also been shown in figure Fig. 68.9 and shows a good comparison. Figure

68.10 shows that crack growth in depth direction is more rapid compared to with circumferential direction and the limiting value of

the aspect ratio is between 2.5-and 5. This is essential for verification of Level 2 LBB.

Figure 9: Maximum crack depth vs. number of cycles

for different initial crack depth and R = 0.5 [23]

FIG. 68. 9 MAXIMUM CRACK DEPTH VERSUS

NUMBER OF CYCLES FOR DIFFERENT INITIAL

CRACK DEPTH AND R = 0.5 [23]

TYPE SETTER:

PLEASE SEE ATTACHED FILE FOR 'PHOTO

READY black & white PICTURE OF THIS FIGURE 9

THAT SHOULD BE INSERTED HERE". A suitable

enlarged size of this figure may be inserted at this

location of the chapter to make it legible for readers.

38 March 11, 2008


Figure 10: Variation in aspect ratio with crack growth

for 324 mm outer diameter pipe [23]FIG. 68. 10

VARIATION IN ASPECT RATIO WITH CRACK

GROWTH

FOR 324-MM OUTER DIAMETER PIPE [23]

TYPE SETTER:

PLEASE SEE ATTACHED FILE FOR 'PHOTO

READY black & white PICTURE OF THIS FIGURE 10

39 March 11, 2008


THAT SHOULD BE INSERTED HERE". A suitable

enlarged size of this figure may be inserted at this

location of the chapter to make it legible for readers.

68.5.3.2 The cyclic loading effect on load carrying capacity of piping components

<H3>68.5.3.2 The Cyclic Loading Effect on Load-Carrying Capacity of Piping Components Leak- before- Break break

(LBB) assessment is based primarily on the monotonic fracture tearing instability. The effect of cyclic loading has generally not

been considered in the fracture assessment of nuclear power plant piping. The pipe fracture analysis used in present LBB considers

the seismic loading as a one- time applied load of magnitude equal to peak load at the postulated flaw location during the

earthquake event. The assessment of pipe with flaw (or crack) is based on the monotonic tearing instability or Net Section Collapse

(NSC). There is no explicit consideration of the cyclic damage or the number of applied load cycles during earthquake event.

An experimental and analytical investigation [24] was carried out in by conducting tests on full- scale circumferential through-

wall cracked pipe under reversible cyclic loading conditions. The experiments covers a wide range of pipe sizes (NPS: 6, 8,

12, 16), crack sizes (2 : 60o, 90o, 120o), material (Low low Carbon carbon manganese steel, Stainless stainless steel), crack

location (base, weld), loading mode (load controlled, displacement controlled), and loading parameters (load ratio, load amplitude,

displacement increment etc.). The cyclic test results have been compared with the corresponding monotonic pipe fracture test

results to quantify the damage (loss in load- carrying capacity) due to cyclic loading as a function of number of load cycles, and a

simplified master curve has been generated to include the cyclic tearing damage in LBB assessment. The master curve is a plot of

the cyclic load amplitude (given as % percent of maximum load recorded in corresponding monotonic fracture test) versus number

of load cycles to failure (Nf) and has been as shown in Figure Fig. 68.11. Few available results on similar tests (on 4- pipe,

STS410 Japanese carbon Steelsteel) from literature, of Central Research Institute of Electric Power Industry (CRIEPI), Japan [25]

have also been plotted in the master curve and are in good agreement with the results of the present tests series. The curve is

independent of crack sizes as well as pipe sizes since all experiment data lie with in a narrow scatter band.

40 March 11, 2008


This curve gives the load reduction factor as a function of number of load cycles and is applied on the monotonic critical load.

The curve suggests an additional safety factor cc of 4/3 for SSE loading and 3/2 for OBE loading over the monotonic critical

load, for LLB assessment. For an OBE, the factor is relatively higher in view of its higher frequency of occurrence than a SSE.

Fig. 11: Master Curve for Cyclic Tearing Assessment

[24]

FIG. 68.11 MASTER CURVE FOR CYCLIC

TEARING ASSESSMENT [24]

EDITOR:

PLEASE SEE ATTACHED FILE FOR 'PHOTO

READY black & white PICTURE OF THIS FIGURE 11

THAT SHOULD BE INSERTED HERE". A suitable

enlarged size of this figure may be inserted at this

location of the chapter to make it legible for readers.

41 March 11, 2008


Figure 12 Comparison of component and system load

displacement behaviour (Po refers to limit load of un-

cracked component/system)FIG. 68. 12 COMPARISON

OF COMPONENT AND SYSTEM LOAD

DISPLACEMENT BEHAVIOUR (Po REFERS TO

LIMIT LOAD OF UNCRACKED

COMPONENT/SYSTEM)

68.5.3.3 Compliance effect on load carrying capacity of piping components

<H3>68.5.3.3 Compliance Effect on Load Carrying Capacity of Piping Components A phenomenon mitigating

the effect described in the preceding section is the role of system compliance. It means the stiffening effect of the connected piping

on the cracked section is negligible. Moreover, in these analyses the LBB assessment is based on the maximum load, irrespective

of the location at which they are acting. However, in the real situation, the local compliance of the cracked section and the global

residual compliance of the piping system may have significant effect on the load- carrying capacity of the cracked pipe. These

compliance effects must be included while evaluating the safety margins. This is due to the fact that the load acting on the cracked

section changes, during crack growth, due to because of indeterminacy of the piping system. Thus, a purely load-controlled

condition, representing the case of a piping system with infinite compliance, changes into a mixed mode , that is, partly load-

controlled and partly displacement-controlled. As a result the crack section sheds some of the load during the crack growth, and

42 March 11, 2008


this load is picked up by the connecting piping system. The load redistribution may increase safety margin. For simplified fracture

mechanics calculation, an analytical expression is proposed [26, 27] to evaluate actual moment at the cracked section in a 3-D

piping system equation:

L
M u 1 c
Leff
Mc
Lc I
1
Leff I eff Here Mu is the un-cracked moment and Mc is the actual moment at the cracked section. Lc and Ieff

are the length and effective moment of inertia of the equivalent piping element used to simulate crack. The Leff is the

equivalent length of the pipe modeled with fixed- end conditions, which simulates piping system compliance at the crack

element. The I is moment of inertia of the pipe.

Actual tests were performed on reactor grade pipes to validate theoretical studies regarding the effects of system compliance

on fracture integrity. Seven fracture tests have been conducted in which system compliance was simulated by fixed ends and it was

varied in terms of L/R parameters. The main conclusions of this experimental study can be summarized as follows:

Fracture load of a piping system having even very large crack size is very near the collapse load of an un-cracked piping

system (as shown in Figure Fig.68.12), thereby proving that large plastic straining occur at un-cracked ends before the system

collapse.

A large margin was observed between crack initiation load and the maximum load that the piping system has sustained. It is

worth to note noting that in conventional fracture tests (infinite compliance), crack initiation load is usually very near to the

maximum collapse load.

68.5.3.4 LBB Assessment of 500 MWe PHWR Piping;

Fatigue crack growth analysis of 500 MWe TAPP 3 & 4 PHT piping (Level 2)

<H3>68.5.3.4 LBB ASSESSMENT of 500 MWe PHWR PIPING

Fatigue Crack Growth Analysis of 500 MWe TAPP 3&4 PHT Piping (Level 2). A part-through semi-elliptical circumferential

flaw at the inside surface of pipe is postulated. The depth of flaw is conservatively assumed to be 25% of wall thickness of pipe

based on ASME Code Sec.Section III, Appendix G recommendation. The flaw aspect ratio is assumed to be 6 six, that which is

representative of typical flaw found in service. Cyclic loading due to normal operating condition (service Service level Levels A

and B) is considered to calculate the fatigue crack growth. Paris power law as given in ASME Section Sec. XI [3] is used. Table

43 March 11, 2008


68. 5 shows the various transient events and the number of excursions of each event postulated for the entire design life period of

the reactor. It was seen that the fatigue crack growth is very small (original crack depth of 25% increased to 27 %) over the entire

design life period of the reactor.

44 March 11, 2008


TABLE 68. 5 VARIOUS TRANSIENT EVENTS POSTULATED FOR ENTIRE DESIGN LIFE OF 500 MWeMWE TAPP

3&4

Sl. Event No. of cycles

No.
1 Operation basis earthquake (OBE) 50 (5 events, each causing 10

cycles)
2 Heat-up from cold shutdown to hot stand-by 1000
3 Start-up from hot stand-by to full power 3500
4 Power maneuvering 15,000

at full power

Fracture Assessment (Level 3)

Fracture Assessment (Level 3). The fracture assessment of PHT system pipes, with postulated through-wall circumferential and

axial flaws, was carried out using the concept of a two-criteria Failure failure Assessment assessment Diagram diagram (FAD)

[28], which describes the interaction between fracture and collapse and is documented as the R-6 procedure. The results obtained

have been used to qualify Leak leak-Before before-Breakbreak criteria of PHT pipes. The R-6 method was also used to perform

sensitivity analysis for reserve margins with respect to different input parameters such as material properties, material test

temperature, initial crack length etcand so on.

The margins (FL = critical load/applied load) obtained for the different piping segments using R-6 method and accounting for the

cyclic loading effect, range from 1.7-to3.4 against a minimum required value of 2.

68.5.3.5 General Limit Load and B2 Stress Index Equation for Pipe Bends under In Plane Bending

<H3>68.5.3.5 General Limit Load and B2 Stress Index Equation for Pipe Bends under In-Plane Bending The limit

load assessment is essential to prevent the pipe or pipe bends to fail by excessive deformation or collapse. Currently available limit

load equations have a limited range of applicability and do not cover the wide range of bend geometries that are used in power

plant piping. Ideally, the elbow limit load equation should approach straight pipe limit load with increasing pipe bend radius.

Keeping this fact in mind, finite element analyses of around 65 elbows having different geometric parameters were performed. The

45 March 11, 2008


parameters considered were elbow bend radius (rb) to mean radius (R) ratio (2, 3, 6, 9, 12, and 18) and pipe radius (R) to thickness

(t) ratio (5, 7.5, 10, 15, 20, and 30).

One quarter of elbow was modeled using three- dimensional 20 nodded brick elements and elastic perfectly and a plastic

analysis was performed, which included the geometric nonlinearity. The analyses have been carried out for both in-plane closing

and opening bending, and limit load for each case was determined using the twice elastic slope method. A relational study was

performed to understand the dependence of limit load on the R/t, rb/R and elbow characteristic h. The study addressed the

weakening factor (Wf), i.ethat is,. the normalized limit loads (ratio of limit load of elbow to limit load of corresponding pipe). A

simple expression for weakening factor (or limit load) is proposed [29] for closing bending bending, which covers the entire

domain of the parameters and provides a good prediction of limit load for non standard elbows. A margin consistent definition [30]

for B2 index defines it as the ratio of the pipe collapse load to the collapse load of corresponding elbow.

Elbow Pipe 2
M W M W (4 R t )
L f L f o

Limit moment of an equivalent pipe 1 0.2 (68.1)


B = 1
2 Limit moment of the elbow Wf 1.028 0.095 rb / R
h

The Section III of ASME B&PVBoiler and Pressure Vessel Code allows for design by simplified analysis (NB-3600)

using stress indices. The B2 index is used for calculating the primary stress intensity due to bending load.

Using margin consistent definition, the ASME Code Expression expression for B2 can easily deduced as 1.3 3 from the lower
2

0.6 Pipe
bound in-plane limit moment expression for the elbow as 0.8 M L given by Spence and Findlay [31]. However, The ASME

Code has typically defined B2 as 2/3rdtwo-third of C2 index. Thus, the stress index value of 1.3 for B2 in the ASME Code is equal to

2/3 of 1.95. The ASME Code C2 index is based on Dodge and Moore [32] investigations on the stress intensities in curved pipe

under combinations of in-plane, out-of-plane, and torsional moments. He found that a C2 index of 1.95/(h2/3) would conservatively

predict the maximum stress intensity for any resultant moment.

ASME B2 index is found to be in good agreement for extra large bend- radius elbows. However it is very conservative for

standard elbows (rb/R = 2 and 3). Based on these investigations, a new B2 index (Eq. 68.1) is proposed, which eliminates

undesirable conservatism in the present ASME B2 index equation and it can be used for elbows of any bend radius. Following

figure Figure 68.13 shows the conservatism of present B 2 index equation as well as compares the limit load equation with other

literature equations as Caladine [33], Touboul [34], Chattopadhyay [35], and Kim [36].

46 March 11, 2008


Similar equations are also proposed for opening bending, closing, and opening bending for elbow with circumferential

through- wall crack.

Fig. 13: Comparison of FEM and Proposed equation with the literature equations [29]FIG. 68.13 COMPARISON

OF FEM AND PROPOSED EQUATION WITH THE LITERATURE EQUATIONS [29]

Type Setter:

PLEASE SEE ATTACHED FILE FOR 'PHOTO READY black & white PICTURE OF THIS FIGURE 13 THAT SHOULD

BE INSERTED HERE". A suitable enlarged size of this figure may be inserted at this location of the chapter to make it

legible for readers.

<H2>68.5.4 Containment Design

The containment design has evolved from single containment in Rajasthan Atomic Power Station to full double containment in

all the current designs with the provision of openings in the dome of reactor building for erection of steam generator. The design

follows the guidelines of French design Design code Code RCC-G [4].

68.5.4.1 Design against Membrane Stresses

<H3>68.5.4.1 Design Against Membrane Stresses The major loads considered for the design of containment structure are

dead load, prestress loads with appropriate losses, internal pressure on account- postulated design basis accident scenario,

47 March 11, 2008


temperature loads under test, normal operating and design basis accident conditions, environmental loads, viz.namely, seismic

(both operating basis earthquake and safe shut down earthquake) and wind loads. Appropriate live loads under normal operating

condition as well as during construction process are also considered while carrying out the design of containment structure.

The prestress loads which that are imparted on the structure to counter the tensile stresses generated during design basis

accident condition, vary both spatially as well as in time domain on account of short - term and long- term losses. The short-term

losses are due to friction and wobble effect, anchorage draw-in, and elastic shortening of concrete structure due to stage wise

stressing of cables during the process of prestressing. Shrinkage and creep of concrete and relaxation (creep) of prestressing steel

contribute towards the long-term losses of prestress loads.

Finite element analysis is carried out in order to evaluate the membrane forces due to various types of loads , for the inner

containment structure. Normally, the IC structure can be modeled using thick shell elements, which can take care of the shear

deformation. In order to obtain the stresses in the discontinuity areas more accurately due to irregular geometry and also due to the

discrete anchorage forces due tobecause of prestress cable, the IC ring beam is modeled using 8-noded 3D solid brick elements.

The effect of the duct openings and the reinforcing/prestressing steel is accounted for appropriately at the design stage.

The design of the prestressed concrete inner containment structure is checked both under limit state of serviceability as well as

under limit state of strength (also called as ultimate limit state) as per the provisions of RCC-G. It is ensured that a membrane

compressive stress of at least 1 MPa is available under accident condition. Presence of voids in the concrete section due to cable

duct openings led to development of special computer programs for carrying out the design check under limit state of serviceability

and limit state of strength.

The entire inner containment is checked against the requirement of Limit limit State state of Strengthstrength. In general, the load

factor for the permanent loads is 1.35 and that for the variable loads is 1.5.

68.5.4.2 Design against Radial Stress in IC Dome

<H3>68.5.4.2 Design Against Radial Stress in IC Dome The normal stress in the thickness direction, also called as radial

stress, is generated in the inner containment structure due to (i) Curvature effect, in which the curved prestressed cables embedded

inside the concrete exert pressure towards the center of curvature at the bottom of the cable sheath leading to development of radial

stress, (ii) transition Transition effect, arising at locations where the shell thickness changes rapidly within a short distance, and

(iii) Stress concentration effect, in which the in-plane membrane compressive stresses in the IC dome also generate radial tensile

stress around the cable duct openings.

48 March 11, 2008


Normally, the radial stresses in the prestressed concrete inner containment structure are maximum during the construction

period since the prestress forces are maximum. With time, long- term losses take place and thus, the residual prestress is reduced.

In view of this, the design against radial stress is carried out for the loads under construction stage. Working stress method of

design is adopted for this.

In order to control cracking of concrete, the radial stresses are limited to 0.67 times the tensile strength of concrete. The

allowable radial tensile stress is further reduced in order to take into account the effect of membrane compressive stress field. The

radial tensile stress generated due to all the phenomena are considered for limiting the concrete tensile stress except that due to the

effect of stress concentration, since the radial stress generated due to this phenomenon is secondary in nature and is balanced by the

adjacent compressive stress field.

The radial reinforcements in the IC dome are designed to carry the radial tensile force resulting from the curvature effect and

transition effect where the cable spacing is sufficiently large. However, where the cable spacing is close, reinforcements are

provided to take care of the local tensile force due to stress concentration effect also.

A reduced value of permissible stress is considered while designing the reinforcements to limit cracking in the concrete. The

deflection and strains at certain locations in the IC are recorded during proof testing mainly to compare the deflection as well as

strains obtained from analytical study. The strain measurements are also necessary to monitor the development of stresses in the IC

structure at different stages of prestressing during construction.

The strains are measured using vibrating wire strain gauges (VWSG) connected to automatic data-logger at locations covering

the entire IC in order to capture both membrane as well as radial stresses. Based on the recorded data the stresses developed in the

IC are compared with the specified allowable stress limits of the design code RCC-G.

68.5.4.3 Equivalence Study with Respect to ASME, Sec-III, Div-2

<H3>68.5.4.3 Equivalence Study with Respect to ASME Code Section III, Division 2 As discussed in the preceding

sections, the design of containment structures of Indian PHWRs has been based on the methodology evolved considering the

Indian construction practices. The design methodology is mainly based on the principles of the French code Code RCC-G as the

containment system adopted for the Indian PHWRs is a double containment without metallic liner, similar to the one adopted in the

French containments of PWRs. However, an attempt has been made to study the equivalence of the various provisions of design of

primary (Innerinner) containment structure being followed in India with respect to those adopted in various international standards

in order to assess the level of its safety under design basis accident scenario. The study has been carried out to establish the

equivalent partial safety factor for accident pressure (Pa) in factored load combination under limit state of strength. For this

49 March 11, 2008


purpose, a detailed design check has been carried out for some typical elements located in different regions of Inner inner

Containment containment structure, such as, (i) IC dome thickened area near SG Openingopening, (ii) IC dome general area, (iii)

IC wall Raft raft junction, (iv) IC wall general area, and (v) IC dome springing area under accidental load combination as per the

provisions of various international standards, viz.namely, Canadian Standard, ASME, Section- III, Division- 2 and RCC-G.

Based on the equivalence study, the following conclusions are drawn:

(i) Though the design philosophy and partial safety factors for material and loads, pre-stress loss computation, etc and others

are different in various international standards (such as Canadian, ASME and RCC-G), the design provisions and the

associated design parameters suggested by various International international codes pertaining to design of containment

structure are laid down in such a balanced way that the final design lies in the same range.

(ii) In general, it is noticed that the load combination involving accident pressure along with the design philosophy suggested

in RCC-G is equivalent to the design provisions adopted in the Canadian standard as well as the ASME Code.

<H1>68.6 Organization of Design, Fabrication, Construction, Operation, and ISI of NPPs in India

<H2>68.6.1 Design:

India started its nuclear power programme with two BWRs, which were constructed on turn-key basis by General Electric,

USA in 1969. Later on, India had collaboration with Canada for two 220 MWeMWe PHWRs. First PHWR was designed and

constructed by Canadians. However, during the construction of second reactor, the collaboration ended and India took over the

remaining construction work. Subsequent to the end of collaboration with Canada, India has built 11 x 220 MWe MWe PHWRs

and 2 x 540 MWeMWe PHWRs. Three more 220 MWeMWe PHWRs are in the final stages of completion. Design,

construction and operation of all these reactors are totally done in India. All the PHWRs are being designed, constructed, and

operated by Nuclear Power Corporation of India Limited (NPCIL), a Government of India Enterprise, under the Department of

Atomic Energy. Civil structures design is by consultants like such as M/s. STUP, Development Consultants Private Limited, Tata

Consulting Engineers, etc.and others and quality assessment is done by NPCIL.

NPCIL has developed a very high expertise in design of small- and medium- sized PHWRs. It has its own R&D facilities

where new and innovative designs are developed and tested. Besides this, NPCIL gets support from its sister concerns like such as

Bhabha Atomic Research Centre (BARC), Indira Gandhi Centre for Atomic Research (IGCAR), and Raja Ramanna Centre for

Advanced Technology (RRCAT) in the field of research and development. It has a strong team of design engineers who look after

all the design aspects starting from conceptual design to detailed structural design and analysis, process design, and electrical, civil,

50 March 11, 2008


and instrumentation design of NPPs. International codes such aslike ASME, IEEE, and RCC, etc and others are followed for

design of nuclear power plants. Further, safety codes and guides issued by IAEA, USNRC, and AERB are also followed.

Design of Fast fast Breeder breeder Reactors reactors (FBRs) is done by IGCAR. They have all the facilities for design,

analysis and R&D of FBRs. FBRs are totally looked after by IGCAR with the help of other sister organizations like such as

BARC, NPCIL, RRCAT etcand others. One Fast fast Breeder breeder Test test Reactor reactor is under operation. One Prototype

Fast Breeder Reactor of 500 MWeMWe capacity is under construction by Bhartiya Vidyut Nigam (BHAVINI).

Design and development of thorium- based reactors, including all the engineering, analysis, and related R&D activities, is

done by BARC. A 300- MWeMWe Advanced Heavy Water Reactor (AHWR) is being designed by BARC.

<H2>68.6.2 Fabrication:

India is one of the few countries in the world that has acquired expertise in the entire range of nuclear fuel cycle activities. As

these activities are of special nature and did not form a part of the general industrial domain of the country, Department of Atomic

Energy (DAE) established facilities for carrying them out in a proper phased manner. Over the years, significant efforts were put by

DAE/NPCIL to develop indigenous manufacturing capability to fabricate various equipment / components conforming to stringent

quality standard of nuclear power plants. Indigenous industrial infrastructure for nuclear power plants is well developed. Indian

industry has gained valuable experience and reached a stage of maturity in manufacturing components for these reactors. Indian

industries are fully capable of manufacturing all the components, including large- size components like such as calandria, end-

shields, steam generators, turbine, condenser, etcand others. These Indian industries have developed capabilities to manufacture all

the nuclear as well as secondary side components. All the class Class I, II, and III nuclear components are fabricated, inspected,

and tested as per applicable ASME codesCodes. Raw materials are procured to meet the ASME specifications. Inspection is done

by the Quality Assurance Group of these industries. NPCIL has its own QA Groupgroup, which does the surveillance job at the

shops of manufacturers. Expertise for carrying out all the Non nondestructive examinations has been developed by NPCIL as well

as the manufacturers.

<H2>68.6.3 Construction:

Over the years, India has developed expertise in the construction of Nuclear nuclear Power power Plants plants (NPPs). At

present India is constructing nuclear power plants in less than five years. Advanced project management techniques are being

51 March 11, 2008


followed to cut down the gestation period. Further, the following improvements have been made in the construction methodology

to cut down the gestation period.

Concept of mega packages has been introduced.

Vendors participation in analysis and decision making has been increased.

Integrated action plans are evolved to resolve issues related to design, material, and construction activities.

Targets and expectations are fully defined.

Open top construction, increased mechanization, and parallel civil and mechanical erection are implemented.

Round the clock construction work is practiced.

Use of project management tools, increased use of information technology for prompt decision making and timely mid-

course corrections and revision of construction sequence have been successfully implemented.

There are a large number of civil construction companies in India, which take care of full construction of civil structures.

Prominent amongst them are M/s. Engineering Construction and Contracts (ECC), M/s. Gammon India Ltd., M/s Hindustan

Construction Co., etcand others. In the early reactors, mechanical erection was done by NPCIL. But now there are many

companies which that undertake Engineeringengineering, Procurement procurement, and Construction construction (EPC)

contracts. Now, the construction of NPPs is being carried out through mega packages. On the secondary side, mostly, there are

EPC packages. On the nuclear side, there are PC packages. This has reduced the construction time drastically.

<H2>68.6.4 Operation:

At present India has 2 x 200 MWeMWe BWRs, 13 x 220 MWeMWe PHWRs, and 2 x 540 PHWR NPPs in operation.

All operations are done indigenously by NPCIL. Each twin station unit has around 600 operating manpower, including Operation

and Maintenance (O&M) personnel. At each station, there are four operating crews, one for each operating shift and one extra

crew for exigencies. All the engineers are trained and licensed and their licenses are periodically updated. All the reactors are

operated as per their operating technical specifications, which cover all the operating limits as per IAEA safety standards. The

technical specifications are duly reviewed and approved by Atomic Energy Regulatory Board (AERB).

NPCIL is a member of World Association of Nuclear Operators (WANO), CANDU Owners Group (COG) , and International

Atomic Energy Agency (IAEA). The peer reviews by expert teams of WANO has been recognized internationally as major tool for

sharing the best practices in operation and performance improvement. Such reviews have been completed for all the reactors. These

52 March 11, 2008


reviews indicate that the condition and performance of stations matched with those at the world level. WANO members regularly

visit our plants and review the operation and safety aspects. In the recent reactors, even pre -operation reviews have been carried

out by WANO before the criticality of newly constructed reactors. Regular seminars / meetings are held among members of COG,

during which the challenges faced in various PHWRs are shared and discussed. This helps in upgrading the safety standards

further.

India has experience of 265 reactor operating years. Till now there has not been any significant event wherein radioactivity is

released to the public domain and no nuclear accident, as defined by International Nuclear Event Scale (INES) of IAEA, has

occurred.

Indian PHWRs have very high availability factor over the entire lifetime. This is made possible by strict scheduled outage for

maintenance and in-service inspections. Biennial shutdown is taken only for 18 to 20 days. All the in-service inspections, and

containment testing, etc.and so on are done within this time. Unscheduled outages have totally reduced and downtime is very much

controlled. On redundant systems, preventive maintenance is performed on power. Radiological protection is enhanced by

choosing Cobalt cobalt-free materials, providing adequate shielding thickness, and by optimized design and layout of components

and systems.

A comprehensive radiological surveillance programme around each NPP is pursued by well- equipped Environmental

environmental Survey survey Laboratorieslaboratories (ESLs). The basic objective of these laboratories is to assess the radiation

doses to the public due to operation of NPPs and to demonstrate the compliance with the applicable regulatory limits set by

national and international authorities.

The Environmental environmental Survey survey Laboratories laboratories (ESL) at site periodically collect and analyse

analyze various environmental matrices, including dietary items such as water, cereals, pulses, meat, fish, milk, eggs etc.and others

for their radioactivity contents. Environmental samples are collected on regular basis from various locations surrounding the

nuclear facility up to a distance of 30 km. The sampling locations are selected on the basis of wind pattern, utilization of

environment, and population clusters around the facility. The type of samples are selected on the basis of potential pathways to

man. Annually about 2500 environmental samples are being collected and analysed analyzed by ESL at each nuclear site. The

samples are analysed analyzed for various biologically important radionuclides. The data thus obtained are processed statistically

and used to evaluate the dose annually to the members of public residing around NPPs.

The well- defined and executed environmental radiological surveillance programme around each nuclear power plant shows

that radioactive contamination is insignificant. It also demonstrates that the NPP releases are well within the prescribed regulatory

53 March 11, 2008


limits. It is observed that the annual radiation doses at the site boundary of the respective nuclear power plant are less than 7 % of

the annual regulatory limit of 1000 Sv during the period of operations. On comparing with the naturally occurring background

radiation of 2400 Sv/year yr, it is almost negligible.

The release of radioactivity to environment from the nuclear power stations is in very small quantities and in any case well

within the limits stipulated by AERB. For monitoring the compliance to the prescribed regulatory requirements, environmental

survey and meteorological laboratories are set up at each plant site. These laboratories analyze samples of food, air, water,and so

on etc. up to an area of 30- km radius from the plant to assure environmental security.

<H2>68.6.5 In- Service Inspection (ISI):

In- Service service Inspection at all the operating plants is carried out periodically as per station ISI program. ISI program is

finalized based Based on ISI documents, ISI program is finalized, which meet the intent of ASME section Section XI. India has

developed all the special tools required for ISI of coolant channels and steam generators. BARCIS and Sliver Sliver sampling

scraping tools are some of the important tools developed for ISI for pressure tubes. Life management of coolant channels, Flow

flow Accelerated accelerated Corrosion corrosion (FAC) mainly on secondary side, and feeder thinning are the major challenges

faced by the Indian PHWRs. These challenges have been successfully met through ISI and maintenance.

India has successfully completed en- masse coolant channel replacement in four reactors where zircalloyZircaloy-2 pressure

tubes were used. All the tools and techniques were developed indigenously. Also, feeder replacement has been successfully

completed in three reactors.

During the evolution of main circuit design, effort has been made at minimizing the weld joints and in turn the in-service

requirement of such joints. This has been achieved by adopting integral forging for the headers with pull out nozzles, main circuit

piping with hockey stick combination for large pipe spools. The Steam steam Generator generator shells have also been specified

as ring forging to eliminate longitudinal joints.

Development of Codes, Guides and Standards

<H2>68.6.6 Development of Codes, Guides, and Standards In order to fulfill its mission of stipulating and enforcing rules and

regulations concerned with nuclear and radiological safety, AERB is in the process of developing codes and guides for various

54 March 11, 2008


aspects of nuclear reactor design. These guides will borrow appropriate elements from ASME, ASCE, ACI, Canadian and French

Codes and incorporate Indias experience in their usage, Indian materials, and construction practices. One such is effort aims at

developing a safety standard for Design of Nuclear Power Plant Containment Structures and is currently in draft stage [37]. This

is based on ASME CodeSec Section III, Div.Division 2 [38], ACI 349 [39], RCC-G [4], CSA-N287.3 [40], and the Indian code

Code IS 456 [41]. Another guide in draft stage is the one for Seismic Qualification of Structures, Systems and Components of

Pressurised Heavy Water Reactors [42]. This guide builds on the Indian experience gained during seismic design of reactor

structures and is based on ASCE [43], IEEE [44] JAEG 4601 [45], IAEA NS-G-1.6 [46], and IS 1893 [10].

<H1>68.7 Conclusions

1. Design of Indian PHWRs is based on ASME B&PV code Code Section. III.

2. In those cases where the code rules could not be met in letter, they have been met in spirit by carrying out the required

material characterization and component qualification tests.

3. Indian PHWR programme depends on Leakleak-before-break criterion for eliminating pipe whip restraints. Leak-before-

breakLBB has been demonstrated by carrying out extensive tests on specimens, pipes, and elbows.

4. The tests have demonstrated adequate margins with respect to failure by fracture even when leakage size crack is present.

5. The R&D programme has explored effects of cyclic loading and presence of connected piping on fracture behaviour of

piping.

6. A new B2 index is proposed which eliminates undesirable conservatism in the present ASME B2 index equation and it can

be used for elbows of any bend radius.

7. In-service programme follows a combined philosophy of ASME Code Section. XI and the Canadian Code CSA/N281.5-

05.

8. Design of concrete containment is based on French Ccode RCC-G.

9. In order to avoid a mixture of codes, a need has been felt to write our own codes and a beginning has been made in this

respect. AERB has published 5 Safety Codes and 45 Safety Guides concerning various aspects of NPPs and 51 other

safety support documents. A few others are in various stages of preparation.

<H1>68.8 Acknowledgment ACKNOWLEDGMENTS

55 March 11, 2008


The authors gratefully acknowledge the contribution of Shri Vivek Bhasin, Shri Rohit Rastogi, Shri P.K. Singh, Shri Suneel K.

Gupta, and Shri Imran Ali Khan of Reactor Safety Division of BARC, and Shri K.P. Dwivedi, Shri A.G. Chhatre, Shri Raghupati

Roy, and Shri Santosh Kumar of Nuclear Power Corporation (NPC).

<H1>68.9 REFERENCES

1 S.S. Bajaj, S.S. and A.R. Gore, A.R., The Indian PHWR, Nuclear Engineering and Design, Volume Vol. 236, Issues

Nos 7-8, April 2006, Pages pp. 701-722, April 2006.

2 ASME Boiler and & Pressure Vessel Code, Section. III; also,, American Society of Mechanical Engineers, 1995 ASME

Boiler and Pressure Vessel Code, Sec. III, Appendix G, American Society of Mechanical Engineers, 1995.

3 ASME Boiler and & Pressure Vessel Code, Section. XI, American Society of Mechanical Engineers, 1995.

4 RCC-G (English Translation), Vols .-I & II, Design and Construction Rules for Civil Works of PWR Nuclear Islands,

Drawn-up by Electricite De France (EDF), July 1988.

5 BPEL-83 (English Translation), Technical Rules for the Design of Prestressed Concrete Structure using Using the Limit

State Method.<!--<query>Reference details appear incomplete, please check. </query>-->

6 BAEL-83 (English Translation), Technical Rules for the Design and Calculation of Reinforced Concrete Structures and

Buildings using Using Limit State Method. <!--<query>Reference details appear incomplete, please check. </query>-->

7 Jaharlal Koley, J., Harikumar, S., Ashraf, S.A.H., Chande, S.K., and Sharma, S.K., et al; Regulatory practices Practices for

nuclear Nuclear power Power plants Plants in India, Nuclear Engineering and Design, Volume Vol. 236, Issues Nos 7-8,

April 2006, Pages pp. 894-913, April 2006.

8 AERB/SG/D-1,. 2000. Safety classification Classification and seismic Seismic categorization Categorization for pressurized

Pressurized heavy Heavy water Water reactorsReactors,. Atomic Regulatory Board, Mumbai, India, 2000.

9 AERB/SG/S-11,. 1990. Seismic studies Studies and design Design basis Basis ground Ground motion Motion for nuclear

Nuclear power Power plants Plants sitesSites,. Atomic Regulatory Board, Mumbai, India,1990.

10 IS: 1893,. 1984. Criteria for earthquake Earthquake resistance Resistance design Design of structuresStructures. , BIS,

New Delhi., 1984.

56 March 11, 2008


11 Reddy, G.R., Kushwaha, H.S., and Kakodkar, A.; ., Seismic Analysis of Calandria End shield Assembly of 500 MWe

Pressurised Water Reactor, Proc. eedings of ASME Pressure Vessel and Piping conferenceConference. , Vol. 237: , pp.

115-120.(,1992.)

12 G.R. Reddy, G.R., H.S. Kushwaha, H.S., S.C. Mahajan, S.C., S.P. Kelkar, S.P., G.V. and Karandikar; G.V., Development

of 3-D beam Beam model Model for seismic Seismic analysis Analysis of 500 MWeMWe reactor Reactor

buildingBuilding, BARC/1996/I/004, 1996.

13 Reddy, G.R., Vaze, K.K., Kushwaha, H.S., Tandale, J.V., Subramanian, K.V., and Kelkar, S.P.; ., Procedure of Applying

Decoupling Criteria for a Complex Primary and Secondary System, Proc. eedings of ASME Pressure Vessel and Piping

conferenceConference, Vol.. 272-, No.1, pp.: 129-139, (1994).

14 Neelwarne, A., Kushwaha, H.S, and Kakodkar, A.,; Seismic Qualification of Nuclear Equipment under Multiple Support

Excitations, Proceedings. of 11th SMiRT, Japan, 1991.

15 Reddy, G.R., Kohei, S.uzuki, Kushwaha, H.S., and Mahajan, S.C.; ., Decoupling Criteria for Multi-Connected

equipmentEquipment, Journal of Pressure Vessel Technology, Vol.120: , pp. 93-98, (1999).

16 ASME Boiler and & Pressure Vessel Code, Code Case N-411-1, Alternative Damping Values for Response Spectra Analysis

of Class 1, 2 and 3 Piping, Section III, Division 1, American Society of Mechanical Engineers, New York, New York,

February 20, 1986.

17 AERB Safety Guide AERB/SG/O-2, In-Service Inspection of Nuclear Power Plants.

18 IAEA Safety Guide 50-SG-02 entitled In-service Service Inspection for Nuclear Power Plants.

19 CAN/CSA N285.4-05, Periodic Inspection of CANDU Nuclear Power Plant Components, Canadian Standard Association,

.2005.

20 CAN/CSA N285.8-05, Technical Requirements for In-Service Evaluation of Zirconium Alloy Pressure Tubes in CANDU

Reactors, Canadian Standard Association, 2005.

21 Report of the United States Nuclear Regulatory Commission Piping Review Committee, Evaluation of Potential for Pipe

Breaks, NUREG/CR-1061, Vol.3, 1984.

22 International Atomic Energy Agency, Applicability of Leak-Before-Break Concept, Report of the IAEA Extra budgetary

Budgetary programme Programme on the safety Safety of WWER-440 Model 230 Nuclear Plants, IAEA TECDOC-710,

1993.

57 March 11, 2008


23 P.K. Singh, P.K., K.K. Vaze, K.K., V. Bhasin, V., H.S. Kushwaha, H.S., P. Gandhi, P., and D.S.R. Murthy, D.S.R., Crack

Initiation and Growth Behaviour of Circumferentially Cracked Pipes Under under Cyclic and Monotonic Loading,

International Journal of Pressure Vessel and Piping, Vol. 80, Issue No. 9, pp. 629640, September, 2003., pp. 629-640.

24 Suneel K. Gupta, S.K., Vivek Bhasin, V., K. K. Vaze, K.K., A.K. Ghosh, A.K., and H. S. Kushwaha, H.S., Experimental

Investigations on Effects of Simulated Seismic Loading on LBB Assessment of High Energy Piping ,, ASME-Journal of

Pressure Vessel and Technology, Vol.-129, February 2007.

25 Miura, N., Fujioka, T., Kashima, K., Kanno, S., Hayashi, M., Ishiwata, M., and Gotohm, N., 1994, Low Cycle Fatigue and

Ductile Fracture for Japanese Carbon Steel under Dynamic Loading, Nuclear Engineering and Design, Vol.153, pp. 57-

69, 1994..

26 Suneel K. Gupta, S.K., V. Bhasin, V., Vaze, K. K., Vaze and H. S. Kushwaha, H.S., Ductile Fracture Assessment of Piping

Systems Including the Compliance Effects , Paper # 1427, SMiRT 16, Washington DC, August 2001 Transactions., Paper #

1427

27 I.A. Khan, I.A., Bhasin, V., Bhasin,Vaze, K.K., Vaze, A.K. Ghosh, and A.K., Kushwaha, H.S., Kushwaha, Significance of

Finite Compliance of a Connected Piping System on Fracture Integrity Assessment, American Society of Engineering

Pressure Vessel and Piping Conference (ASME-PVP-2005), Colorado, USA, July, 2005.

28 Rastogi, R., Bhasin, V., and Kushwaha H. S., Qualification of PHT piping Piping of Indian 500MW PHWR for LBB, using

Using R-6 method , Bhabha Atomic Research Centre, External Report, BARC/1997/E/026, India, 1997.

29 Suneel K. Gupta, S.K., Vivek Bhasin, V., K. K. Vaze, K.K, A.K. Ghosh, A.K., H. S.and Kushwaha, H.S., General Limit

Load and B2 Stress Index Equation for Pipe Bends under In- Plane Bending, Paper # B04/5, SMiRT-19, Toronto, Canada,

August 12-17, 2007, . Paper # B04/5

30 Tan, Y., Experimental and nonlinear Nonlinear FEA Investigation of elbow Elbow leading Leading to a new definition of

the B2 Stress Index, [PhD Thesis, with Vernon C. Matzen], Civil Engg.ineering Department, North Carolina State

University, Raleigh, 2001.

31 Spence, J. and Findley, G. E., (1976). Limit load Load for pipe Pipe bend Bends under inIn-plane Plane bendingBending

Proceedings., of 2nd International Conference on Pressure Vessel Technology, San Antonio, Texas, pp. 393-399,1976.

32 Dodge, W.G. and Moore, S.E., Stress Indices and Flexibility Factors for Moment Loadings on Elbows and Curved Pipes,

Welding Research Council Bulletin No. 179, December 1972.

58 March 11, 2008


33 Caladine, C. R., (1974) Limit analysis Analysis of curved Curved tubesTubes, Journal of Mechanical Engineering

Science, J. Mech. Eng. Sci. vol Vol. 16, pp. 85-87,1974.

34 Touboul, F., Ben Djedidia, M., and Acker, D.,et. al. (1989) Design criteria Criteria for piping Piping component

Component against Against plastic Plastic collapseCollapse: Application to pipe Pipe bend Bend experimentsExperiments,

Proc.,eedings of 6th International Conference on Pressure Vessel Technology, Beijing, China, pp.73-84,1989.

35 Chattopadhyay, J., Tomar, A.K.S., Dutta, B.K., and Kushwaha, H.S., et. al. (2004) Closed form Form collapse Collapse

moment Moment equation Equation of through Through wall Wall circumferentially Circumferentially cracked Cracked

elbows Elbows subjected Subjected to inIn-plane Plane bending Bending momentMoment , ASME Journal. of Pressure

Vessel Technology, Vol.126, pp. 307-317,2004.

36 Kim, Y. J. and Chang, S. O., (2006). Closed form Form plastic Plastic collapse Collapse loads Loads of pipe Pipe bends

Bends under combined Combined pressure Pressure and inIn-plane Plane bendingBending, J. ournal of Engineering

fracture Fracture Mechanics., Article in Press.<!--<query>Please update.</query>-->

37 AERB/SS/CSE-3, Design of Nuclear Power Plant Containment Structures (draft).

38 ASME Code Section III, Div. ision 2.

39 ACI 349, Code Requirements for Nuclear Safety Related Concrete Structures. (ACI 349)

40 CSA-N287.3-1983,; Design Requirements for Concrete Containment Structures for CANDU Nuclear Power Plant; ,

Canadian Standard Association.

41 IS 456-2000, Plain and Reinforced Concrete - Code of Practice.

42 AERB Safety Guide No. AERB/SG/D-23, Seismic Qualification of Structures, Systems and Components of Pressurised

Heavy Water Reactors (draft).

43 AMERICAN SOCIETY OF CIVIL ENGINEERS,American Society of Civil Engineers, Seismic Analysis of Safety-Related

Nuclear Structures and Commentary; , ASCE 4-98, Virginia, USA, 2000.

44 IEEE, Standard 344-1987, 1987. IEEE Recommended Practice for Seismic Qualification of Class 1E Equipment for

Nuclear Generating Stations,1987.

45 JAPAN ELECTRIC ASSOCIATIONJapan Electric Association, Technical Guidelines for Aseismic Design ofTechnical

Guidelines for Nuclear Power Plants; , JAEGJEAG-4601, 1987.<!--<query>Please check the changes for

correctness. </query>-->

59 March 11, 2008


46 INTERNATIONAL ATOMIC ENERGY AGENCY,International Atomic Energy Agency, Seismic Design and Component

Qualification for Nuclear Power Plants; , IAEA Safety Guide NS-G-1.6, Vienna, Austria, 2003.

60 March 11, 2008

Potrebbero piacerti anche