Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PIPELINE FEED
Constructability Study
DOCUMENT NO. OKGS-NF2-038-RPT-CS-00001
11 DEC 06
FW
JP
RJL/FW
29 NOV 06
FW
JP
RJL/FW
REV
DATE
ORIG
CHK
APPR
CONTRACTOR APPROVAL:
COMPANY APPROVAL:
DATE:
DATE:
COMPANY
Project
Contract
Originator
Type
Discipline
Seq. No.
OKGS
NF2
038
RPT
CS
00001
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Foreword
The purpose of this Constructability Study is to identify vessels and areas of
concern in conjunction with the installation of the export pipelines and infield
flowlines for the Olokola Gas Supply Project.
Page 2 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Table of Contents
Page
1.
Introduction ................................................................................................................... 4
1.1
Project Description ............................................................................................ 4
2.
Scope ............................................................................................................................ 4
3.
4.
5.
6.
7.
Vessel Matrix............................................................................................................... 18
Tables
Table 1.1: Pipelay Installation Contractors - Export Pipelines (Vessels over 200T Tension) 19
Table 1.2: Pipelay Installation Contractor Matrix - Infield Flowlines....................................... 20
Appendices
Appendix A Crossing MTO - Export Pipelines ....................................................................... 21
Appendix B Crossing MTO - Infield Flowlines........................................................................ 22
Page 3 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
1.
Introduction
1.1
Project Description
This document was developed during pipeline FEED for the Olokola Gas Supply
(OKGS) Project being executed by Chevron Nigeria Limited (CNL) offshore Nigeria in
the Western Delta region. This document applies to both the export pipeline system that
carries dehydrated gas and condensate from the Gas Production Platforms to the
Olokola Liquefied Natural Gas (LNG) Plant and the infield flowline system that carries
raw bulk flow between the Non-Associated Gas Wellhead Platforms and Gas Production
Platforms.
2.
Scope
The purpose of this Constructability Study is to evaluate the preliminary design of the
export pipelines and infield flowlines associated with the Olokola Gas Supply Project
(OKGS) to identify the type and capacity of the laybarge required for the project and also
identify vessels that might be available to perform the work. The plan is to split the
installation between export pipelines and in-field flowlines. The shallow water (63m to
shore) and the line sizes (48 to 8) eliminate considering J-lay; and limit the use of Reellay to the 8 produced water lines. The majority of the installation will be accomplished
by use of the S-Lay installation method.
3.
3.1
Summary
The Olokola Field construction requires the installation of:
30 risers, 64 pairs of various size flanges from 48 down to 8, 36 spool pieces and 2
wye assemblies to connect approximately 370 miles of 10 various diameter pipelines
to 2 production platforms, 10 each well head platforms and a riser platform and an
onshore LNG facility.
Water depth ranges from 0 to 63m (206); the majority in 6m (20) to 18m (60) of
water.
There will be two installation contractors, 1 laying the 48, 42 and 36 pipelines and
1 laying the pipelines 32 and less in diameter. There could be 2 or 3 dive boats to
provide inspection and installation services as the pipelines are being laid. A Dive
Page 4 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
crew set up with a Saturation diving spread will be required for the deeper
installations, over (200).
3.2
There are 70+ pipeline crossings and 9+ cable crossings that will require protection
with bridges, mattresses and/or sand/cement bags. The crossings will be installed
prior to pipelay.
Conclusions
3.2.1
3.2.2
Export Pipelines
The deep draft pipelay vessel with a static tensioning capacity of 275 to 325
metric tonnes (Te) and a stinger length between 67 to 109m is required for
laying the 48 pipeline coated with 121mm concrete coating in water depth
from 30 to 50m. This pipelay vessel with the above tensioning capacity and
stinger length is capable of installing all other smaller diameter export
pipelines.
It is desirable to route the 48 pipeline in water depth less than 40m to avoid
the scenario that only one or two pipelay vessels are capable of installing the
pipelines.
Infield Flowlines
Page 5 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
3.3
A shallow water pipelay vessel with static tensioning capacity of 100 Te and a
stinger length around 40m may be able to lay the 26 pipelines to an
intermediate water depth between 17m and 63m and the rest of the infield
flowlines.
Recommendations
The following are recommendations to the engineering efforts in the detailed design
phase:
Project specific seabed bathymetry and surface data along the pipeline/flowline
routes are required for a detailed installation design.
All export pipelines should be routed in water depth less than 40m to reduce the
requirements on installation vessel and to bring in more competition to the tendering
of installation work.
Page 6 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
3.4
Area of Concerns
The following are areas of concern:
Shore pull tensions required for breakout under certain soil conditions should be
carefully considered at the design stage.
Previous experience has shown that buoyancy bags attached by steel bands to the
outside of the concrete coating sheared off not too far after touchdown as the pipe
was pulled across the seabed. Recommend that a groove be put in the concrete in
the coating yard when it is green and use 10mm steel cables instead of bands to
attach the buoyancy bags. Special attention should be paid to the groove so that the
cable can be pulled up tight, and hence not exposed to the stinger rollers and
seabed during pipe pull. A 1 x 1 groove shall be placed 1 meter from each end of
2325 joints of the line pipe to aid in attaching buoyancy to line pipe during shore pull.
Pipe lifting and movement are extremely dangerous operations, especially with large
diameter concrete weight coated (CWC) pipe.
It is imperative that all
lifting/movement procedures are reviewed and agreed upon to ensure that safe
methods are employed. Risk Assessments/Job Safety Analysis should be performed
by contractors supervisors/operators prior to start of work.
The cut back of the CWC needs to be 38cm (15in.) (-0/+1) to ensure the Automated
Ultrasonic Testing (AUT) equipment could fit to the pipe. The Fusion Bonded Epoxy
(FBE) cut back needs to be 23cm (9in) min.
For FBE corrosion coating, a rough coat is recommended in order to help bond the
concrete weight coating to the FBE.
Page 7 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Spool installation: confirm maximum length for spools - amount of platform overhang,
spreader bar design requirement, diving operation limits.
Anchor handling: identify the vessel position/lay tension variation when repositioning
anchors and the procedure to keep tension within the installation window. [Ref: 7].
4.
4.1
Acronyms
For the purposes of this report, the following acronyms are used:
Acronyms
A&R
AUT
CWC
DSV
FBE
MAWP
OKGS
OKLNG
SOW
Scope of Work
Te
Metric Tonne
WD
Water Depth
WT
5.
Reference Materials
5.1
Project Documents
1.
2.
3.
4.
5.
Page 8 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
6.
7.
6.
Installation Methodology
6.1
Shore Approach
A double row of sheet pilings will be driven from high water mark on the beach to
4~5 m water depth and the material between the pilings will be removed by landbased equipment. An access channel will be dredged to 6 ~7 m water depth to
allow shallow draft laybarge access to the cofferdam. A winch with sufficient
capacity to pull the 48 coated pipeline from the installation vessel will be located
onshore. The winch will be positioned to pull both pipelines without repositioning
the winch. The shallow draft laybarge will setup adjacent to the end of the sheet
piles, attach a pull-in wire to the pullhead and begin welding pipe with onshore
winch pulling each section toward shore. When the pipe end reaches selected
onshore location, the shallow draft laybarge will lay the 48 line to a water depth
of approximately 15m and install laydown head and abandon pipeline if needed.
The laybarge will move back to the sheet pile location, and duplicate pipe pull to
shore and lay procedure to deeper water and laydown the 2nd 48 pipeline in 20m
water depth if needed.
6.1.2
Constructability Study
OKGS-NF2-038-RPT-CS-00001
spool will be installed at a later date. After the desired tension is reached
additional joints of pipe will be welded on and the laybarge will move forward
following x-ray approval and field joint application. A previously established pipe
lay corridor for the placement of the flowline will be utilized to allow the flowline
route between platforms to be accomplished by changing laybarge heading within pre-determined radius curvature. No intermediate fittings will be placed along
the length of the pipeline. When the laybarge approaches the platform a laydown
head will be attached and the pipe end placed in its target box under tension.
The distance to the platform riser flange will be kept to a maximum length of 30m
(100ft).
6.1.3
42 and 36 Pipelines
The larger laybarge will install the 42 and 36 pipelines in a similar manner as stated
above.
6.2
6.3
Tie-In Spools
The installation of the tie-in spools will be carried out by the respective EPC Contractor.
All export pipelines and infield flowlines will have a tie-in spool connecting the riser to the
pipeline/flowline or wye.
For ease of installation, 2-swivel assemblies and 1misalignment swivel connection will be provided for each spool. This will allow for a
swivel assembly at the bottom of the riser, and a second approximately mid-point of the
spool. The misalignment swivel connection will be installed between the pipeline and
spool. All spools will be pre-commissioned onshore to include: flooding/cleaning,
gauging and hydrotest to 1.5 x design psig.
At the riser end or Subsea wye, diver will take a measurement between each tie-in
flange including the angle of the face of each flange. This metrology will be used to
fabricate the spool piece that will be installed between the riser and the pipeline, flowline
or wye. Fabrication/testing of the spools will be performed onshore. Pipeline mattresses
and/or sand/cement bags should be placed under the riser tube turn for support and
over top of the tube turn after tie-in to the pipeline and out from the platform
approximately 15m (50ft) for protection from dropped objects. This distance may vary
depending on the size of the riser tube turn.
Page 10 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
6.3.1
Option
If the tie-in spool lengths can be reduced to a maximum length of 25 to 30m, they
could be installed in one piece thereby reducing the number of flanges required
and also reduce the installation time.
6.4
Wye Assembly
The two wye assemblies weigh approximately 136 Te each, and will be placed by one of
the installation vessels qualified in the weight range for the offshore lift. The installation
vessel, with survey equipment onboard, will locate target box for the installation of the
wye assemble and the vessel will be positioned with the crane in the optimum position
for lift. Divers will perform pre-installation bottom survey and site preparation activities to
ensure that the seabed in the area of the installation is clear and free of obstructions.
The diver will also confirm that any existing pipelines in the vicinity are located. It is
envisioned that the wye assemblies will be placed on piles due to the instability of the
bottom soils.
Vessel crane, with spreader bar and slings of pre-determined lengths, will place the pile
template on the seabed. Piles will be driven to support penetration and the template will
be removed. Elevation collars for positioning the wyes @ their desired elevation will be
attached to each pile and tightened. Crane, with spreader bar and slings of predetermined lengths be attached to the wye assembly and the structure will be set over
the piles and lowered to rest on the collars. If the bottom was found to be too soft to
support the connecting spools, mattresses will have been placed to provide support.
Divers will complete a bottom search and clear any installation devices, etc. Location
and orientation will be confirmed by survey for the As-built final positioning of the Wye
which will also include a video.
6.5
Page 11 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Throughout the flooding and pigging operation the following minimum parameters
would be recorded:
Page 12 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Upon confirmation of the pig train reception the test end receiver would be
removed and lifted to the surface, where the pigs would be removed and the
gauge plate inspected. After confirmation of the integrity of the pigs and Gauge
Plate are acceptable, the test end would be refitted subsea in preparation for the
hydrotest. Photographic records would be taken of all received pigs.
Consideration should be given to the provision of a Geometry-Caliper Pig Survey
contingency, should a gauge plate be received damaged.
6.6.2
Hydrotesting
Upon achieving the required test pressure the system would be allowed to
stabilize to achieve temperature equilibrium within the test water. When the
system is stabilized the test pressure will be re-established, and the test hold
period commence. Pressures would be recorded every 10 minutes, along with
pipe, ambient, and subsea temperatures. Upon successful completion of the test
hold period, the respective pipeline would be depressurized. [Ref.5]. Upon
completion of all hydrotesting the Pipelay Contractor would then commence the
riser spool and wye piece tie-in program.
6.6.3
Leak Testing
Upon completion of the tie-ins the topsides, risers, and spools would be toped up
with inhibited seawater. All trapped air would be removed from the high points,
and then pressurization would commence to achieve a test pressure of 1.1 x
MAWP. Following the stabilization period the 8 hour test period would
commence. Pressures would be recorded every 10 minutes along with pipe,
ambient, and subsea temperatures. Upon successful completion of the Leak
Test hold period the respective pipeline would be depressurized at a rate no
greater than 2 barg per minute until zero pressure is achieved. [Ref 6].
6.6.4
Bulk Dewatering
It is proposed to dewater the two 48 x 124.7km Okan GPP-OKLNG pipelines
from onshore. For the 42 EARP-B and the 36 Funiwa GPP EARP-B pipelines
the optimum direction for dewatering would be from Okan GPP and Funiwa GPP
respectively.
From a pre-commissioning perspective the air-nitrogen spread would be located
on the two main platforms, i.e., Okan GPP and the Funiwa GPP. The footprint
required for this equipment is approximately 18m x 15m. This would be for all
offshore dewatering, drying and nitrogen operations, but this may not be practical
due to lack of space. If this is achievable it would eliminate the need for hose
Page 13 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
transfers from the Vessel and the weather dependency of this operation. This
would also make the operation more efficient by allowing the routing of air from a
single static source to the respective main platform pipelines. The exceptions
being the Meji and Sonam pipelines which would need to be dewatered from the
satellites to accommodate the wye piece geometry. The bulk dewatering for the
export pipelines would be achieved by the introduction of the following eight (8)
pig train, which would be propelled at a velocity greater than 0.3 m/s.
The fresh water would be introduced to act as a flush to remove the salt content
of the seawater to an acceptable level < 200 ppm.
The bulk dewatering of the Infield flowlines would be achieved by the introduction
of the following six (6) pig train.
Page 14 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
The pipeline test water would be offloaded overboard via an installed fabricated
dumpline. The minimum size required would be a minimum of 8 diameter for the
export system, and 6 for the In-field pipeline system. Upon reception of the
dewatering pig train, the pigs would be removed in batches as dictated by the
size of the pig receiver. Upon recovery of the pigs they would be inspected for
wear and condition. Photographic records would be taken of all received pigs.
Throughout all pigging operation the following minimum parameters would be
recorded:
Air flow
Pipeline temperature
When the complete pig train has been removed the pipeline would be vented
down to zero pressure via installed temporary silenced vents, located at each
end of the pipeline.
6.6.5
Final Dewatering
When each export pipeline has been depressurized, a second eight (8) pig train
would be loaded and propelled through the pipeline at a velocity of between 0.5
1.0 m/s. The pig train will be as follows:
Constructability Study
OKGS-NF2-038-RPT-CS-00001
When each infield flowline has been depressurized, a second six (6) pig train
would be loaded and propelled through the flowline at a velocity of between 0.5
1.0 mls. The pig train would be as follows:
Upon reception of the final dewatering pig train, the pigs would be removed in
batches as dictated by the size of the pig receiver. Upon recovery of the pigs
they would be inspected for wear and condition and reported upon. Photographic
records would be taken of all received pigs.
Throughout all pigging operation the following minimum parameters would be
recorded:
Air flow
Pipeline temperature
Constructability Study
OKGS-NF2-038-RPT-CS-00001
When the complete pig train has been removed the pipeline would be vented
down to zero pressure in preparation for commissioning.
6.7
Commissioning
Commissioning activities will include both the export pipelines and infield flowlines and
be included in the contract for the each installation.
6.7.1
6.7.2
Page 17 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
7.
Vessel Matrix
Communications with Installation Contractors have identified various installation
vessel(s) for the pipelay operation that are capable of performing the installation of the
pipelines/flowlines. The 12, 8 and 6 flowlines could be installed by reel method, but at
this stage none were offered.
Offshore Contractors is a Nigerian contractor with equipment that appears suitable for
the installation.
Some of the contractors contacted have vessels that are capable of installing some/all
the lines but are not interested in participating in the Project. Their comments as follows:
McDermott We are aware of the Olokola Project however we are not currently active
in the Niger Delta area and our strategic plans do not envision establishing a marine
construction presence there in the near future.
Heerema No, we dont do that type of work with our current equipment pool. We are
limited to J-lay at the moment with 32 max and in deeper water segment only.
Subsea 7 Thank you; however at this time Subsea 7 would have to decline.
Horizon Our lay barge departed for Singapore last month so we have nothing to take
on another job with. 48" is a little out of our range anyway.
Page 18 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Table 1.1: Pipelay Installation Contractors - Export Pipelines (Vessels over 200T Tension)
GLOBAL
Contact Information
Jim Gallagher
ACERGY
ALLSEAS
HYUNDAI
SAIPEM (SONSUB)
HYUNDAI
jimg@globalind.com
Barbara Thompson
barbara.thompson@acergy-group.com
Johan Drost
jdr@allseas.com
Clyde Evons
clyde.evons@saipemamerica.com
K.S. Won
kswon@hhi.co.kr
K.S. Won
kswon@hhi.co.kr
Installation Vessel
Hercules
Seaway Polaris
Solitaire
Castoro Sei
HD-2500
HD-60
Dimensions(ft)
DP System
DPS-2
BV DY.MSA.MA.TA.RS- Class 3
N/A
N/A
Anchor Spread
N/A
Diameter Capacity
S-Lay to 60-inches
Reel lay to 18-inches
S-Lay to 60-inches
J-Lay to 20-inches
S-Lay to 60-inches
S-lay to
S-Lay to 60-inches
S-Lay to 60-inches
Tensioner Capacity
544T
3 = 204T total
3 x 350T=1050T
3 = 330T
2 + 1 =226T
3 = 245T
500T
150T
420T
330T
250T
300T
Crane Capacity
1800T fixed
1450T revolving
1,500T fixed
1,100T revolving
300T
2 x 134T ea
2,268T fixed
1,000T revolving
1,633T fixed
1,579T revolving
Stinger Configuration
52m
95m 3 sections
83m 1 section
Lay-ramp Location
Stb.
Center Slot
Center Slot
Stb.
Center Slot
Receive Pipe
Port
Port Or Stb.
Port Or Stb.
Port
Port
24,000 tons
NO
NO
YES
YES
NO
YES
Welding System
Automatic
Automatic
Semi-automatic
Automatic
Working Draft
4.9m
4.8m to 5.8m
(9.5m DP)
9.23m
10 14.5m
5.5m
8.5 10m
Page 19 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Contact Information
Jim Gallagher
jimg@globalind.com
Jim Gallagher
jimg@globalind.com
Barbara Thompson
barbara.thompson@acergygroup.com
Clyde Evons
clyde.evons@saipemamerica
.com
Johan Drost
jdr@allseas.com
Henk Vastenholt
henk.vastenholt@offcon.nl
Henk Vastenholt
henk.vastenholt@offcon.nl
Roy Sijthoff
rsijthoff@HelixESG.com
Installation Vessel
DLB Iroquois
DLB Comanche
Seaway Orion
S 355
Tog Mor
Jascon 30
Jascon 25
Deepwater Caesar
Dimensions(ft)
DP System
None
None
None
None
None
DP-3
DP-Class 3
DPNMD Class 2
Anchor Spread
N/A
N/A
N/A
Diameter Capacity
S-Lay to 48-inches
S-Lay to 60-inches
S-Lay to 42-inches
S-Lay to 48-inches
S-Lay to 60-inches
S-Lay to 60-inches
S-Lay
S-lay to 42 inches
Tensioner Capacity
2= 200T total
1 x 75T
2 = 36T total
2 = 100T total
1 x 100T
1 x 100T
2 x 60T
3 x 137T
=405T total
200T total
79T
50T
110T
1 x 175T
100T
Crane Capacity
907T fixed
748T revolving
165T revolving
590T fixed
500T revolving
300T
300T
30.5m + 4-section
pontoons
Single Section
Single Section
43m
55m
90m
Stb.
Center Slot
Port
Stb.
Stb.
Receive Pipe
Port
SAIPEM (SONSUB)
ALLSEAS
OFFSHORE
CONTRACTORS
GLOBAL
Stinger Configuration
ACERGY
OFFSHORE
CONTRACTORS
GLOBAL
Port
HELIX
2 x 225T
800T
300T
10,000T
NO
NO
NO
NO
NO
NO
NO
Welding System
Manual
Manual
Manual
Manual-Automatic (Optional)
Automatic
Manual
Automatic
Working Draft
4.3m
4.3m to 5.8m
3.3m
2.6m to 4.8m
3.15m
5m
6m
7.8m to 9m
Page 20 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Appendix A
Crossing MTO - Export Pipelines
Item
Nominal
Diameter
Location
Number of Crossings
Pipelines
Cables
Crossing
Length
(m)
Mattresses (1)
M1
48
10
152
M2
48
10
152
M3
42
48
M4
32
30
M5
Subtotal
382
Spares (10%)
38
Totals
---
30
Comments
420
Note:
1. Mattress dimensions: 5m x 2m x 150 mm thick, SG 2.2, articulated in all directions, with double width and/or high density (SG ~3.0) edge blocks. Alternatively, 8x20x9;
weights typically circa 5000 kg in air and circa 2700 kg submerged.
Page 21 of 22
Constructability Study
OKGS-NF2-038-RPT-CS-00001
Appendix B
Crossing MTO - Infield Flowlines
Item
Nominal
Diameter
Location
Number of Crossings
Pipelines
Cables
Crossing
Length
(m)
Mattresses (1)
M1
24
30
M2
20
15
M3
18
15
M4
18
45
M5
24
105
M6
20
15
M7
20
45
M8
26
105
M9
105
M10
M11
32
Subtotal
512
Spares (10%)
51
Totals
---
34
Comments
563
Note:
2. Mattress dimensions: 5m x 2m x 150 mm thick, SG 2.2, articulated in all directions, with double width and/or high density (SG ~3.0) edge blocks. Alternatively, 8x20x9;
weights typically circa 5000 kg in air and circa 2700 kg submerged.
Page 22 of 22