FIELD COATING OF STEEL BRIDGE (As of date 28 Dec 15)

Date

Location

Activity

31/10/15

BR. 9 CG 101-104, MG 101-104, MG201-204

Bresle Test and Mist Coat

01/11/15

BR. 9 CG-105-108, MG105-108, MG205-208

Bresle Test and Mist Coat

02/11/15

BR. 9 CG 127-130, MG127-131, MG227-231

Bresle Test and Mist Coat

03/11/15

BR. 9 CG 119-126, MG119-126, MG219-226

Bresle Test and Mist Coat

04/11/15

BR. 9 CG116-118, MG116-118, MG216-218

Bresle Test and Mist Coat

05/11/15

BR. 9 CG 109-115, MG 109-115, MG 209-215

Bresle Test and Mist Coat

06/11/15

BR. 9 CG101-130, MG101-130 (Inner Web),


MG201-130 (Inner Web)

Final Coat Application

07/11/15

BR. 9 CG101-112, MG201-212

Surface Preparation and Inspection


prior to Final Coat

08/11/15

BR. 9 CG101-130, MG201-231

Final Coating Application

09/11/15

BR. 9 MG101-131 (Bottom)

Final Coat Application

10/11/15

BR. 9 CG101-130 (East Wing side),


MG101-131 (Outer Web)

Surface Preparation Prior to final


Coating

11/11/15

12/11/15

Br. 8 MG 120-134

Water Jet washing and repairing

13/11/15

BR. 8 MG 220-234

Water Jet washing and repairing

BR. 8 MG 201-219

Water Jet washing and repairing

Br. 8 CG122-134 Bottom, MG122-134 (Bottom)

Bresle Test and Mist Coat

Br. 8 CG122-134, MG122-134


(Outer Web & Wing side)

Bresle Test and Mist Coat

Br.8 CG 122-134, MG 222-234

Bresle Test and Mist Coat

14/11/15

15/11/15

16/11/15

Br. 8 CG118-133, MG218-234


(Outer Web & Wing side)

Bresle Test and Mist Coat

17/11/15
18/11/15
19/11/15
20/11/15
21/11/15
22/11/15
23/11/15
24/11/15 to
9/12/15
10/12/2015

Br.8 CG109-122, MG209-222


(Bottom, Outer Web, Wing Area)
Br. 8 CG101-108, MG 201-208
(Bottom, Outer Web, Wing Area)
Br. 8 CG111-121, MG 111-121
(Bottom, Outer Web, Wing Area)
Friday
Br. 8 CG101-110, MG 101-110
(Bottom, Outer Web, Wing Area)
Br. 8 CG 111-115 (B&C),
MG 111-115 (Inner Web), MG 211-215 (Inner Web)
Br. 8 CG 117-118 (B&C), CG 132-133 (Center)
MG 117-118 (Inner Web), MG132-133 (Inner Web)
MG 216-218 (Inner Web), MG 232-233 (Inner Web)
Bridge 8

Bresle Test and Mist Coat


Bresle Test and Mist Coat
Bresle Test and Mist Coat
Weekend
Bresle Test and Mist Coat
Bresle Test and Mist Coat
Bresle Test and Mist Coat
Repairing, Cleaning, Surface
preparations & quality checking

Br. 8 CG 101-108 (Center), MG 101-109 (Inner Web), MG


201-209 (Inner Web)

Bresle Test & Surface Inspection Prior


to mist coat
Br. 8 CG 119-131 (Center), MG 119-131(Inner Web), MG219231 (Inner Web)

11/12/2015

Br. 8 CG 101-108 (Center), MG 101-109 (Inner Web), MG


201-209 (Inner Web)
Br. 8 CG 119-131 (Center), MG 119-131(Inner Web), MG219231 (Inner Web)

Mist coat

12/12/2015

Br 8. CG 101-116, MG 201-216 (Bottom, Outer Web, Wing)

Final Coat Application

13/12/2015

Br. 8 CG117-133, MG 217-233 (Bottom, Outer Web, Wing)

Final Coat Application

14/12/2015

Br. 8 CG117-133, MG 117-133 (Bottom, Outer Web, Wing)

Final Coat Application

15/12/2015

Br 8. CG 101-116, MG 101-116 (Bottom, Outer Web, Wing)

Final Coat Application

16/12/2015

Br. 8 CG 116-133 (Center), MG 116-134(Inner Web), MG216234 (Inner Web)

Final Coat Application

17/12/2015

20-28/12/2015

Br. 8 CG 101-108 (Center), MG 101-109 (Inner Web), MG


201-209 (Inner Web)

Final Coat Application

Br. 8 CG 111-114 (Center), MG 111-114 (Inner Web), MG


211-214 (Inner Web)

Final Coat Application

Br. 8 & Br. 9

Br 8 - Top Coat Inspection & Repairing


of Top coat defects
Br. 9 Preparation for Final Coating

Bridge 9 Steel Coating


Mist Coat -All Mist Coat Finish on Br.9
Final Coat

Bridge 8 Steel Coating


Water Jet (washing)

Surface Preparation/ Repairing

Mist Coat -All Mist Coat Finish on Br. 8

Final Coat

Remarks : Bridge 8 Top/Final Coat Completed and Inspected except:


(1) CG 101-108 & CG 117-134 Center Top side.
(2) CG 100 & 134
(3) Temporary Support Areas.

5)
Remarks

Weather condition is not


stable.
Center Area MS & SS

Center Area MS & SS


(Friday)

MS Center Area

SS Center Area
Pylon Center Area
Bridge 8 All Top coat Finish
inspection.