Sei sulla pagina 1di 18

01/16/201707:37:51

TIMESHEET RECORD
Company Name (if not KC): Konecranes Indonesia

Name of Employee: Galang Pandusatya

Working Week No: 48

Job Number : PS006805

Start
Time

End
Time

Monday

08.00

17.00

Tuesday

08.00

17.00

Wednesday

08.00

17.00

Day

Date

Job Description, Location Comments, Crane Details

Thursday

12/1/2016

08.00

17.00

Knowing about cranes and part of cranes,ROS,E-Room & Server Room

Friday

12/2/2016

08.00

17.00

Knowing about preventive actifity & Learn to collect report from cms

Saturday

Day Of

Sunday

Day Of
Total Worked Hours

Notes:
1 daily worked hours = start time to end less 1 hour for breaks
2 Enter worked hours under SGA unless otherwise instructed
3 GA = General Activities; OP = Open Points; WA = Warranty
4 O/T - overtime hours are subject to individual contract arrangements with employer - KCI or Harbarindo

Galang Pandusatya

Date: 05/12/2016

01/16/201707:37:51

01/16/201707:37:51

Cost Codes
N41637
GA

OP

WA

Incs
O/T
Hours

Total
Worked
Hours

O/T

16

16

Tommi Manninen

Date : 05/12/2016

01/16/201707:37:51

01/16/201707:37:51

TIMESHEET RECORD
Company Name (if not KC): Konecranes Indonesia

Name of Employee: Galang Pandusatya

Working Week No: 49

Job Number : PS006805

Date

Start
Time

End
Time

Job Description, Location Comments, Crane Details

Monday

05/12/2016

08.00

17.00

Automation Support PM & Make a report to harbarindo (CMS Based)

Tuesday

06/12/2016

08.00

17.00

Knowing the automation system on cranes & ROS system

Wednesday 07/12/2016 08.00

17.00

Read an electrical drawing (Block & wiring Diagram)

Thursday

08/12/2016

08.00

17.00

Automation Support PM ARTG 8,10,11 & Support Laser Calibration

Friday

09/12/2016

08.00

17.00

Automation Support PM Artg 1,3,5

Day

Saturday

Day Of

Sunday

Day Of
Total Worked Hours

Notes:
1 daily worked hours = start time to end less 1 hour for breaks
2 Enter worked hours under SGA unless otherwise instructed
3 GA = General Activities; OP = Open Points; WA = Warranty
4 O/T - overtime hours are subject to individual contract arrangements with employer - KCI or Harbarindo

Galang Pandusatya

Date: 09/12/2016

01/16/201707:37:51

01/16/201707:37:51

Cost Codes
N41637
GA

OP

WA

Incs
O/T
Hours

Total
Worked
Hours

O/T

40

40

Tommi Manninen

Date : 09/12/2016

01/16/201707:37:51

01/16/201707:37:51

TIMESHEET RECORD
Company Name (if not KC): Konecranes Indonesia

Name of Employee: Galang Pandusatya

Working Week No: 50

Job Number : PS006805

Day

Date

Start
Time

End
Time

Job Description, Location Comments, Crane Details

Monday

Day Of (National Holiday)

Tuesday

12/13/2016

08.00

17.00

Support PM (Artg 07 & 09)

Wednesday

12/14/2016

08.00

17.00

Automation Support PM (Artg 2,4,6) & Collect inverter service info

Thursday

12/15/2016

08.00

17.00

Automation Support PM (Artg 8,10) & Update CMS Registry

Friday

12/16/2016

08.00

17.00

Automation Support PM (Artg 5,11)

Saturday

Day Of

Sunday

Day Of
Total Worked Hours

Notes:
1 daily worked hours = start time to end less 1 hour for breaks
2 Enter worked hours under SGA unless otherwise instructed
3 GA = General Activities; OP = Open Points; WA = Warranty
4 O/T - overtime hours are subject to individual contract arrangements with employer - KCI or Harbarindo

Galang Pandusatya

Date: 16/12/2016

01/16/201707:37:51

Incs
O/T
Hours

Cost Codes
N41637
GA

OP

WA

Total
Worked
Hours

O/T

32

32

Tommi Manninen

Date : 16/12/2016

01/16/201707:37:51

TIMESHEET RECORD
Company Name (if not KC): Konecranes Indonesia

Name of Employee: Galang Pandusatya

Working Week No: 51

Job Number : PS006805


Start
Time

End
Time

Job Description, Location Comments, Crane Details

Monday

12/19/2016 08.00

17.00

Automation Support PM (ARTG 03 & 05) & Knowing Yard Tool

Tuesday

12/20/2016 08.00

17.00

Support PM (ARTG 07 & 09)

Wednesday 12/21/2016 08.00

17.00

Automation Support PM (ARTG 02,04,06) & Setting Bracket Position Laser Gantry

Thursday

12/22/2016 08.00

17.00

Automation Support PM (Artg 08,10) & Restart Position Laser Gantry

Friday

12/23/2016 08.00

13.00

Automation Support PM (Artg 11 ,01)

Day

Date

Saturday

Day Of

Sunday

Day Of
Total Worked Hours

Notes:
1 daily worked hours = start time to end less 1 hour for breaks
2 Enter worked hours under SGA unless otherwise instructed
3 GA = General Activities; OP = Open Points; WA = Warranty
4 O/T - overtime hours are subject to individual contract arrangements with employer - KCI or Harbarindo

Galang Pandusatya

Date: 23/12/2016

01/16/201707:37:51

01/16/201707:37:51

Cost Codes
N41637
GA

OP

WA

Incs
O/T
Hours

Total
Worked
Hours

O/T

37

37

Tommi Manninen

Date : 23/12/2016

01/16/201707:37:51

01/16/201707:37:51

TIMESHEET RECORD
Company Name (if not KC): Konecranes Indonesia

Name of Employee: Galang Pandusatya

Working Week No: 52

Job Number : PS006805

Date

Start
Time

End
Time

Job Description, Location Comments, Crane Details

Monday

12/26/2016

08.00

17.00

Day Of (National Leave)

Tuesday

12/27/2016

08.00

17.00

Day Of (KCI Calendar)

Wednesday 12/28/2016

08.00

17.00

Automation Support PM (Artg 7,9) Centering Spreader Camera (Artg 7)

Thursday

12/29/2016

08.00

17.00

Automation Support PM(Artg 2,4,6) & Install Stopper Remote I/O

Friday

12/30/2016

08.00

13.00

Day

Saturday

Day Of

Sunday

Day Of
Total Worked Hours

Notes:
1 daily worked hours = start time to end less 1 hour for breaks
2 Enter worked hours under SGA unless otherwise instructed
3 GA = General Activities; OP = Open Points; WA = Warranty
4 O/T - overtime hours are subject to individual contract arrangements with employer - KCI or Harbarindo

Galang Pandusatya

Date: 30/12/2016

01/16/201707:37:51

01/16/201707:37:52

Cost Codes
N41637
GA

OP

WA

Incs
O/T
Hours

Total
Worked
Hours

O/T

21

21

Tommi Manninen

Date : 30/12/2016

01/16/201707:37:52