Construction
Please careful read the special manuals:
In connection with a delivery, the erection of the supplied equipment is a very important
function.
The erection can be carried out in various ways dependent on local conditions, however,
irrespective of local conditions, it is of utmost importance always strictly to follow
the instructions in the enclosed drawings and manuals in order to obtain an optimum result.
Subsequent are shown a number of main actions and sequences occurring during erection of an
electrostatic precipitator. Type E is mainly used at illustrations, but the procedure is nearly
the same for type F and C

Type C

Type E

Type F

Electrostatic Precipitator
Construction Foundation for pendular support

Check that the recessed foundation have been made correctly


in accordance with the load and assembly drawings.
Check the position of the foundation in relation to buildings
connected with the ESP.

Foundation example
Support
Non shrinkage
mortar
Concrete to
be cast after
positioning
of anchor bolts
Reinforced
concrete
Anchor bolts
Screed

Electrostatic Precipitator
Construction Pendular support
Temporary stiffening, if necessary, to be mounted for provisional
stabilization of the columns.

Temporary stiffening
Welding of diagonally bracing
to column

Pre-assembling and pre-welding of support

Electrostatic Precipitator
Construction Prendular support, principle
To enable unrestrained heat expansion of the ESP, it is necessary to use flexible columns

ESP
Direction of motion
Fixed point

Guide ring

Spherical top
(To be cut
away after
mounting)

Concrete
Guide ring
Foundation bolt
Spherical top

Electrostatic Precipitator
Construction Hopper, pre-assembly on ground

Temporary placement of hoppers


between support columns

Pyramid hopper

Longitudinal hopper
Pre-assembling and welding of hopper

Electrostatic Precipitator
Construction Casing, pre-assembly on ground

Welding of frames
Pictures shows frames for ESP type F

Firm base and block up to make


columns and roof beams in level

Pre-assembling and welding of frames

Electrostatic Precipitator
Construction Casing placement on support

Temporary stiffening
between frames
Temporary wire
for the first frame

Picture shows frames for ESP type E

Picture shows frames for ESP type F

Pre-assembled frames to be lifted in place

Electrostatic Precipitator
Construction Casing plate work

Gas tight welding to be executed

Picture shows plate work for ESP type F

Scaffold for welding

Casing plate work to be lifted in place


Picture shows plate work for ESP type E

Electrostatic Precipitator
Construction

Hopper, in-and outlet

Hopper to be lifted
and welded to casing

Hoppers
Picture shows hoppers for ESP type F

Pre-assembled inlet
Pre-assembling and welding of in-and outlet

Electrostatic Precipitator
Construction

Gas distribution
After welding of hoppers all temporary stiffening
can be removed

Pre-assembled screens

Screen details
Pre-assembling of gas distribution screens

Electrostatic Precipitator
Construction In-and outlet mounting
Gas distribution screens have been mounted
in the in-and outlets before lifting in place

Inlet inclusive gas distribution

Holes for inspection doorways to be cut out


Mounting of outlet inclusive gas distribution

Electrostatic Precipitator
Construction Internals

Discharge electrodes and collecting plates supply

Pre-assembling of discharge electrode system and


collecting plates
Pre-assembling of discharge frames and
collecting plates in a firm base

Electrostatic Precipitator
Construction Internals, collecting plates and discharge frames

Rows of plates and frames

Discharge frame

Collecting plates
Temporary support

Casing

Collecting plates
Discharge frame

Lifting pre- assembled discharge frames and


collecting plates in place

Electrostatic Precipitator
Construction Internals, rapping systems
Discharge rapping systems
Collecting rapping systems

Discharge frame
Supporting beam
Rapping systems
Supporting beam

Discharge frames to
be connected to
support beam

Lifting pre- assembled rapping systems in place

Electrostatic Precipitator
Construction Internals, connection to insulators
Supporting rod to be connected to
the supporting beam.
The complete system to be
suspended in the insulators.

Supporting insulator
Adapter (Not shown)
Supporting insulator
Supporting rod

Temporary support
can now be removed

Lifting roof plates for insulators in place

Electrostatic Precipitator
Construction Auxiliary equipment

Insulator chamber

Drive station
Gear motor

Lifting insulator chambers and drive stations in place

Electrostatic Precipitator
Construction Outer roof

Support for plate work

Insulation of inner roof

Inner inspection
doorways to be
welded to casing
Tear plate chequered plate cover
Lifting parts for outer roof in place

Electrostatic Precipitator
Construction Insulation
The ESP have to be insulated and with thickness and
types depending of the process

Insulation of casing side walls

Insulator chamber
have to be insulated

Mounting of weather
protection door
Lifting insulation materials in place

Electrostatic Precipitator
Construction Access facilities
Stair case tower designed after DIN standard

Pre-assembled stair case tower to be lifted in place

Electrostatic Precipitator
Construction Electrical equipment
High tension equipment, heating elements
and control units

Rectifier

Control units

Heating elements and Pt 100 sensors


Rectifier to be lifted in place

Electrostatic Precipitator
Construction Dust extraction

Dust extraction can be by means of drag chain,


screw conveyor or air lock

Air locks and screw conveyor

Drag chain and air lock


Dust extraction to be lifted in place

Electrostatic Precipitator
Construction Finishing

Control and final straightening of internal equipment


and control of all high tension distances

Electrostatic Precipitator
Construction Finished