Sei sulla pagina 1di 186

Study on Economic Partnership Projects

In Developing Countries in FY2014

Study on the New Power Plant Project in Mawlamyaing,


Myanmar

Final Report

February 2015

Prepared for
Ministry of Economy, Trade and Industry
Ernst & Young Shin Nihon LLC
Japan External Trade Organization
Prepared by :
Mitsui & Co., Ltd.
Chubu Electric Power Co., Inc.
1

Reproduction prohibited

Preface

This report describes the outcomes of the Study on Economic Partnership Projects in Developing Countries
FY 2014 with which Mitsui & Co., Ltd. and Chubu Electric Power Co., Inc. were entrusted by the Ministry of
Economy, Trade and Industry.
In this report, Study on the New Power Plant Project in Mawlamyaing, Myanmar, an survey was made
for a coal-fired power plant construction project for the purpose of improving the power shortage issues in
Myanmar (the Project).

It is hoped that this report will contribute to the realization of the Project and also will serve as reference
information for those concerned in Myanmar and Japan.

Mitsui & Co., Ltd.


Chubu Electric Power Co., Inc.
February 2015

Project Map

Source: Data prepared by the Study team

Abbreviations

Words

Myanmar

Republic of the Union of Myanmar

MoEP

Ministry of Electric Power

MEPE

Myanma Electric Power Enterprise

DGSE

Department of Geological Survey and Mineral Exploration

MOI

Ministry of Industry

YESB

Yangon City Electricity Supply Board

ESE

Electric Supply Enterprise

DHPP

Department of hydropower Planning

DHPI

Department of hydropower Implementation

HPGE

Hydropower Generation Enterprise

DEP

Department of Electric Power

JICA

Japan International Cooperation Agency

Contents

Preface

Project map

Table of abbreviations

Contents

Executive Summary

(1) Project background

(2) Basic conditions of the Project

(3) Envisaged project outline

(4) Implementation schedule

(5) Request for Yen Loan and feasibility of the Project

(6) Superiority of Japanese enterprises in terms of technology etc. 10


(7) Schedule and issues to be concerned

10

(8) Envisaged project location

11

Chapter 1 Overview of the Host Country and Sectors

12

(1) Economic and financial situations of Myanmar

12

(2) Outlines of power sector

15

(3) Circumstances in power sector

18

Chapter 2 Study Methodology

27

(1) Description of study

27

(2) Study method

28

(3) study schedule

30

Chapter 3 Justification, Objectives and Technical Feasibility of the Project 32


(1) Project background

32

(2) Basic conditions of the Project

38

(3) Outline of the plan for the Project

41

(4) Plant Layout

45

(5) Power generation facilities

47

(6) Environmental treatment equipment and coal handling system


51
(7) Power transmission and substation equipment

91

(8)Others

98
6

Chapter 4 Evaluation of Environmental and Social Impacts 100


(1) Analysis of the environmental and social conditions at present 100
(2) Environmental improvement effects by the project 135
(3) Environmental and social impacts of the Project 136
(4) Outlines of the related laws and regulations for environmental impact assessment in Myanmar154
(5) Actions to be taken by the related authorities in Myanmar to realize the Project 167
169

Chapter 5 Financial and Economic Evaluation


(1) Cost estimation of the Project

169

(2) Preliminary financial and economic analyses

169

(3) Financial internal rate of return

172

(4) Economic internal rate of return

173

Chapter 6 Envisaged Project Schedule

175

Chapter 7 Implementing organizations

177

(1) Overview of the implementing organizations in Myanmar 177


(2) Organization for the implementation of the Project in MoEP 178
(3) Capability of the implementing organizations and countermeasures 180
182

Chapter 8 Technical Advantages of Japanese Companies

(1) Competitiveness of Japanese companies for the Project 182


(2) Expected Japanese contents

182

(3) Promotion of the Japanese Contents

183

Chapter 9 Expected fund source for the Project

184

(1) Direction of the fund sourcing by the Myanmar Government for the Project184
184

(2) Surroundings for fund sourcing


(3) Expected fund source for the Project including yen loan

185

Chapter 10 Action plans for the request for yen loans

186

(1) Directions of the yen loan application to the Project

186
186

(2) Actions to be taken for the yen loan application

186

(3) Related issues for the yen loan application

Executive Summary
(1) Project background
The demand for power in Myanmar in 2030 is estimated to be about seven times that of today. To meet this
rapid increase in the demand for power and to supply power stably, a rapid development of power generating
facilities is necessary. In developing such power generating facilities, it is necessary to develop power generating
facilities using various power resources such as gas-fired power generation, coal-fired power generation,
hydropower generation, and renewable energy power generation using wind or solar energy.
In consideration of problems represented by the fact that the availability of power resources and the available
locations for hydropower generation are limited, however, it is important to develop well balanced portfolio of
various power resources with low generating cost.
Regarding gas-fired power generation, a demand for gas three times as large as the available domestic gas
supply is anticipated in 2030; for this reason, fuel must be imported with the possibility of importing liquid natural
gas (LNG) or of using a gas pipeline for transportation from the neighboring countries. But developing these
facilities takes costs and time.
Regarding hydropower generation, there are issues in developing large-scale hydropower generating facilities
such as the necessity of long development periods (10 years or more), the magnitude of environmental and
social impact (submergence of extensive land, relocation of inhabitants, and the like) depending on the location of
development and the difficulty of connecting to transmission lines depending on the location of development.
In addition, the available power generating capacity for hydropower varies from season to season, which poses the
problem of the power output lowering to 70% in the dry season from the full output in the rainy season.
A number of trial calculations on the power generating cost by kind of fuel resources in thermal power
generation have been performed, which show large variation; in general, however, the lowest of all power
generating costs is derived from coal-fired power generation.
After the Great East Japan Earthquake in March 2011, which caused the shutdown of nuclear power generation,
Japan managed to continue supplying power without a substantial hindrance to the supply of power by taking such
measures as increasing the import of LNG on an emergency basis to increase the LNG power generation and
restoring aged oil-fired power stations.
These examples show that diversifying the kinds of fuel resources, namely, developing gas-fired power
generation, coal-fired power generation, oil-fired power generation, and hydropower generation in a suitable
balance is extremely important in terms of security in the supply of power. To solve Myanmars energy problems,
the development of coal-fired power generation is an important means.

(2) Basic conditions of the project


In Myanmar, some coal mines produce sub-bituminous coal with properties suitable for power generation use.
But most of other coal mines produce brown coal and sub-bituminous coal with poor properties, for these reasons,
the present project presupposes the use of imported coal (bituminous coal) from coal exporting countries such as
8

Indonesia and Australia, adopting a design that is based on bituminous coal firing alone and the assumed heating
value is approximately 24,000 kJ/kg, the higher heating value in use.
The thermal efficiency of power generation is taken at 42% (HHV), which is on the same level as that of well
performed and reliable ultra supercritical pressure coal-fired plants that are operated as base-load plants in Japan.
The annual load factor and the availability are assumed in the same way as the thermal efficiency: an annual
load factor of 80%, an availability of 84%, and an operating mode as a base load power plant.

(3) Envisaged project overview


The site plan assumes that the site to be needed to construct a coal-fired power station with a generating output
of 600 MW, a coal storage yard, and a coal unloading facility is developed along the seashore nearby Mawlamyine,
the largest city in the Mon State.
With Mawlamyine connected to Yangon and to the trunk transmission system of

Myanmar with a 230-kV

transmission line, it is assumed that a transmission line is constructed from the site for the connection with the
trunk transmission system. With the site conceived facing the Andaman Sea, it is suitable as the base for ocean
transportation of imported coal. The site is also suitable to install limestone-gypsum desulphurization facilities
because limestone is mined in the nearby suburb.

(4) Execution schedule


This survey was positioned as the preliminary feasibility study that formed the premise of the feasibility study
associated with the construction of a coal-fired power station, ending in February 2015. After the Government of
Myanmar requests the Government of Japan to extend ODA of yen loan to the Project, the feasibility study
associated with the Project will be conducted, and the decision on the extension of yen loan will be notified to the
Government of Myanmar through the Japanese Embassy there; and when an agreement is reached between the
Governments of the two countries, the exchange of notes (EN) that concretely compiles the items agreed on will
be concluded between the two governments and the loan agreement (LA) between two governments will follow to
move into the execution stage.
It is envisaged that Construction of the plant will be started in 2018 and after a construction period of about five
years, commencement of the operation is scheduled in 2022.

(5) Request for Yen Loan and feasibility of the project


In Myanmar, power stations have been built and operated by means of its own funds or of the offering of gratis
fund aids or they have been built and operated as IPP business operations by private power generating operators,
while few power stations have been built by means of loan fund aids in recent years. Due to the past
circumstances, Myanmar may not positively desire the offering of loan fund. On the other hand, two reasons, (1)
the underdeveloped state of laws necessary to organize project finance and (2) the inability of national guarantee
of investment, prevent the development of large-scale power stations requiring with project financing while the
9

condition of supply and demand of power is increasingly stringent.


It is understood that the Government of Myanmar expresses a certain level of understanding of the necessity of
yen loan for the construction of power stations through the meeting with high officials of MoEP, MEPE, and other
offices during the study.

(6) Superiority of Japanese enterprises in the technical and other aspects


The only coal-fired power station operating in Myanmar now is Tigyit Power Station with two 60 MW units.
The power station was commissioned in cooperation with the Government of China in 2004. It is said, however,
that the availability of the power station remains around 30% due to troubles of facilities and that troubles in the
exhaust gas system have caused environmental problems due to flue-gas.
Under these circumstances, high hopes are placed on a high-efficiency and environment-friendly coal-fired
power station based on advanced technologies of Japanese manufacturers. The integrated approach with the
Japanese government and private companies to combines the export of experienced operating know-how of
Japanese utility companies, the capability of project development and finance arrangement of Japanese trading
houses, and ODA, financial assistance and technical support by the Government of Japan will contribute to the
enhancement of more business opportunities for the related industries for Japanese companies and also to the
facilitation of appropriate economic development in Myanmar
For an ultra supercritical pressure power plant, major equipment such as the boiler, a steam turbine, and a
generator are expected to be manufactured in Japan or by Japanese companies. Furthermore, technical assistance
in operation and maintenance of the coal-fired power station after its commissioning for well managed operation
at high efficiency can be provided to the power plant in Myanmar by Japanese utility companies and the
technological transfer can also be expected for a long run perspective.

(7) Issues to be concerned


With the further feasibility study of the Project following this study, it is expected that the Myanmar
Government and the Japanese Government will agree that the Project would be financially supported by yen loan
by the Japanese Government. Since there is an opinion to hesitate to utilize a loan for a project in the Myanmar
Government, it is important for the Government to recognize the benefit of the appropriate loan for a project and
request the Japanese Government for the yen loan for the Project.
There is a strong perception in Myanmar that coal-fired power generation is considered to be highly
environment-burdening as a result of NGO activities and of great environmental impacts inflicted by existing
coal-fired power stations in Myanmar because of their inefficiency and lack of environmental treatment. In order
to promote the Project, it is necessary for the Myanmar Government and also Japanese Government to make it
widely known to the public that the environmental-friendly coal-fired power generation is achievable by
introducing environmental treatment system for removal of toxic substances such as desulphurization equipment
to remove sulfur oxides, selective catalytic reduction facility to remove nitrogen oxides and dry dust collector to
remove dust.
10

(8) Envisaged project location

11

Chapter 1 Overview of the Host Country and Sectors


(1) Economic and financial situations of Myanmar
1) Political situation in Myanmar
Due to the coup d tat staged by the national armed forces in 1962, military administration continued for a long
period of time. In 2003, however, the 7-stage Roadmap for Democratization was formulated. As a result of the
general election held in November 2011, President Thein Sein took office on February 4, 2011. After assuming the
office, he dissolved the State Peace Development Council (SPDC), which had been in charge of the military junta.
He then successively worked out the following items: democratization under the initiative of the new government,
national reconciliation (promotion of peace negotiations with ethnic minorities and of cease-fire agreement), and
activities aimed at economic reforms. In such a flow of major reforms, people who had been imprisoned as
political criminals due to democratization movements were released. Furthermore, democratization activists who
had emigrated to foreign countries because of the inability to carry out political activities in Myanmar were
requested by the president himself to participate in the creation of a new country. Many competent persons who
accepted his request have returned to Myanmar. In August 2011, a dialogue between the president and Ms. Aung
San Suu Kyi, the leader of the National League for Democracy (NLD), which is the largest opposition party, was
realized. An agreement was reached that they would cooperate with each other for the purpose of the development
of the country. Ms. Aung San Suu Kyi highly evaluates President Thein Sein as a trustworthy person.
In conjunction with the progress of democratization and national reconciliation, the United States lifted the
embargo on Myanmarese products except some jewelry items in November 2012. Furthermore, in April 2013, the
EU lifted economic sanctions on Myanmar except for the embargo on weapons. Thus economic sanctions by
European and North American countries were relaxed. In Myanmar, the national armed forces participate in
national administration even now under the provisions of the constitution. However, the national armed forces
have declared their intention to support the political and economic reform line of the current regime. The
possibility is low that democratization will be made to backslide by the national armed forces.
Incidentally, the military is currently authorized to hold 25% of the parliamentary seats. Against this
background, Global Insight, which is an investigating and rating company, is of the view that if a candidate of the
NLD is selected as President as a result of the general election scheduled for 2015, the following will be the case:
It is considered that progress will not be easily made in a constitution amendment aimed at reforming the issue of,
or abolishing, the above-mentioned military parliamentary seats; it cannot be denied that temporary political
tension will occur; the NLD highly evaluates President Thein Seins current economic policies and efforts in
democratization; Thus measures will be taken so that losses will be compensated for in the unlikely event that
Myanmar will fall into a state of civil war around the time of the general election in 2015, or that the government
forcibly expropriates the power plant.

2) Economic situation in Myanmar


Ratings pertaining to Myanmar are follows: The rating by three major rating companies is NR; the rating by
Global Insight, which is the only rating company that has given a rating to Myanmar, is B-. The real GDP
12

growth rates were, according to IMF estimates, 5.5% in FY 2010, 5.9% in FY 2011, 6.3% in FY 2012, and 6.8%
in FY 2013. It is predicted that the growth rate in FY 2014 will also be approximately 7%, and that this growth
rate level will continue thereafter until 2018. Thus it is expected that stable growth will continue in the future also.
The GDP per capita is 855 dollars (in 2013), which is at the lowest level in the ASEAN. In Yangon, however, the
GDP per capita is said to be 1,800 dollars. That is, the purchasing power of the intermediate and high income
classes is higher than is imagined.
The trade balance was such that surpluses of 2.4 billion dollars were posted in 2010. However, in 2011,
surpluses of 1 billion dollars were posted. That is, imports and exports were approximately balanced. In 2012,
Myanmar fell into a state of trade deficit. The greatest reason for the reduced trade surplus is a rapid increase in
imported used cars. However, the export of natural gas to Thailand, which currently accounts for 40% of the total
export, remains in a favorable condition. Furthermore, the pipeline for export to China was opened in September
2013. For this reason, gas export to china is expected to increase. Thus it is estimated that the trade balance will
improve. The current-account balance is such that some deficit amount was posted. However, an amount of 7
billion dollars, which is equivalent to 9 months worth of total export, is secured as foreign currency reserves.
Direct investments increased rapidly in and after FY 2010. There were inflows of 20 billion dollars in FY 2010
and 4.6 billion dollars in FY 2011. Main countries are not only China and Thailand, which are neighboring
countries, but also ASEAN countries. The main field is energy, including electric power, petroleum, and gas.
Meanwhile, in and after FY 2012, there were increases in investments in manufacturing industries. It is true that
the money amount per item is low, but the number of investment items account for 80% of the number of direct
investment items.
As regards the fiscal balance, a financial deficit of about 1.5 trillion kyat (about 2 billion dollars) (in FY 2009)
has continued. In this respect, under the guidance of the IMF, the financial deficit is controlled in such a way as to
be within 5% of the GDP as a rough target. Deficits are covered by the issuance of government bonds. Private
monetary institutions in Myanmar act as main purchasers. Government bonds that have been issued are controlled
within 5% of the GDP. Thus government bonds can be stably consumed in Myanmar. Foreign debts as of the end
of March, 2012, were 13.7 billion dollars, out of which the delinquent debt balance was 4.8 dollars. In FY 2012,
Japanese and international organizations (including the World Bank and the ADB) exempted/dissolved delinquent
debts, with the result that foreign debts were reduced to half of the amount as it was at the end of FY 2011. In
January 2013, the Myanmarese Government held consultations, in the Paris Club, with the member nations of this
club, and reached an agreement that half of the debts would be exempted in two stages. It was decided that the
remaining debts be deferred for 15 years. Currently, the IMF is monitoring the process of the debt reduction
measures. In January 2014, the IMF sent an study team. The results of the investigation were satisfactory. It is
expected that in the future, resumption of loans can be newly realized. The JBIC is expected to send its study team
in concert with the equivalents of other countries, and to start to newly extend credit in May or later this year.
At present, interest rates in Myanmar are as follows: The deposit interest rate is 8%; the official discount rate is
10%; the lending interest rate is 13%. By way of recent news, an interest rate reduction of 2% was carried out in
September 2011, and the same reduction was performed again in January 2012. Since the interest rate level is
higher than in neighboring countries, the Central Bank is considering a further interest rate reduction. In this
connection, the Central Bank used to be under the umbrella of the Ministry of Financial Revenue. However, an
13

organizational reform was carried out in July 2013 for the purpose of securing independence in accordance with
the international standard. In April 2012, foreign exchange rates were integrated, and a transition was made to a
floating exchange rate system. Subsequently, foreign exchange rates have been decided at auctions conducted by
monetary institutions that are authorized to perform exchange transactions. Immediately after the transition, the
foreign exchange rate dropped to 900 kyat/dollar. Recently, however, foreign exchange rates stably remain
between approximately 900 kyat/dollar and 950 kyat/dollar.

14

(2) Outlines of power sector


Changes in electric power sectors in Myanmar are shown in Table 1-1 .
The origin of the electric power business in Myanmar dates back to the fact that in 1908, Anglo Burma
Company started to supply electric power in Rangoon City. Large numbers of small-scale electric power
enterprises were founded in various places. The total number of such enterprises amounted to a maximum of 120.
Subsequently, reorganizations of electric power enterprises were repeated up to now, until the Ministry of
Electricity Power under the current setup was founded in September 2012.

Table 1-1
Period

Event
Anglo Burma Company started to supply electric power in Rangoon City.

1908

Subsequently, small-scale electric power enterprises were founded, until the number of such
enterprises amounted to a maximum of 102.

1947

The Electricity Department was established in the Ministry of Industry (MOI).

1948

The Electricity Supply Act No. 69 was enacted, and the electric power business was nationalized.

1951

The Electricity Supply Board (ESB) was established, and nationalization was promoted.

1960
1972
1974
1988
1994
1997
1999
2002
2005

Baluchung No. 2 Hydropower Station was completed within the framework of Japans reparation
aid.
The Electricity Power Corporation (EPC), into which the electric power enterprises in Myanmar
were consolidated, was established.
Baluchung No. 2 Hydropower Station was enlarged.
The Electricity Power Corporation (EPC) was renamed the Myanma Electric Power Enterprise
(MEPE).
The Foreign Investment Law was amended, and the purchase of IPPs and electric power facilities
was started.
The electric power organizations that were under the umbrella of the Ministry of Energy became
independent, and the Ministry of Electric Power (MOEP) was established.
Operation of combined cycle power stations was started in Ahlone and Hlawga.
The Department of Hydropower was established under the umbrella of the Ministry of Electric
Power (MOEP).
Operation of a coal-fired power station was started in Tigyit.
The MOEP was divided into the MOEP 1 and the MOEP 2.
The HPGE (Hydropower Generation Enterprise), the YESB (Yangon City Electricity Supply Board),

2006

and the ESE (Electric Supply Enterprise) became independent of the MEPE.
The whole business was divided into electric power generation, electric power transmission, and
electric power distribution.

2012

The MOEP 1 and the MOEP 2 were integrated into the MOEP.
Source: Data prepared by the Study team

15

The Ministry of Electric Power (MOEP) consists of three departments and four enterprises, and takes
charge of the following work. Furthermore, the organization of the Ministry of Electric Power is shown in
Figure1-1. Policies related to coal fired power plant are made at DHPP, DHPI and HPGE.

Department of Hydropower Planning (DHPP)


Drafting of hydropower development plans and management of ministerial organizations related to
hydropower, as well as communication and coordination

Department of Hydropower Implementation (DHPI)


Implementation of design and construction of hydropower plants, procurement of materials and
equipment, and maintenance and repair of existing power plants

Hydropower Generation Enterprise (HPGE)


Operation of hydropower plants and coal-fired power plants

Department of Electric Power (DEP)


Consolidation of systems and management of organizations other than those related to hydropower and
coal coal-fired power, as well as communication and coordination

Myanma Electric Power Enterprise (MEPE)


Electric power transmission system operation work and operation of thermal power plants (except for
coal-fired power)

Yangon City Electricity Supply Board (YESB)


Supply of electric power to places in the Yangon region

Electric Supply Enterprise (ESE)


Supply of electric power to regions other than the Yangon region

Figure1-1 Setup chart of the Ministry of Electric Power (MoEP)


Minister

Vice-Minister

Department of Department of
Hydropower
Hydropower
Planning
Implementation
(DHPP)
(DHPI)

Vice-Minister

Hydropower
Generation
Enterprise
(HPGE)

Department of
Electric
Power
(DEP)

Myanma
Electric
Power
Enterprise
(MEPE)

Source: Data prepared by the Study team


16

Yangon City
Electricity
Supply Board
(YESB)

Electric
Supply
Enterprise
(ESE)

As shown in Figure1-2 , the current supply setup in electricity business in Myanmar is divided into power
generation business, power transmission business, and power distribution business.

Power
generation

Figure1-2
Hydroelectric power plants
and coal-fired power plants
of Hydropower Generation
Enterprise (HPGE)

Hydroelectric power plants


and thermal power plants
that are Independent Power
Producers (IPPs)

Thermal power plants of


Myanma Electric Power

Electric power Electric power


distribution
transmission

Enterprise (MEPE)
Myanma Electric Power Enterprise
(MEPE)

Yangon City Electricity Supply Board


(YESB):
Supply area: Yangon region

Electric Supply Enterprise (ESE):


Supply area: regions other than the
Yangon region

Source: Data prepared by the Study team

17

(3) Circumstances in power sector


1) Energy situation
Myanmar is blessed with resources such as hydropower, petroleum, natural gas, and coal. Particularly, it can be
said that hydropower and natural gas resources are abundant. Economically developable hydropower resources are
estimated to be 48.5 GW. However, the actual amount developed is no more than 3.0 GW (6.2%). Meanwhile, the
history of development of petroleum and natural gas is so old as to date back to the days of Burmese Petroleum
Corporation during the British rule. At the beginning, development of small-scale oil fields and gas fields were
pushed forward on land. However, in the 1970s, seabed surveys were started, with the result that the development
of large-scale gas fields has been carried out. About 80% of the amount of natural gas mined is exported. The
resulting annual income is 3.3 billion dollars, which accounts for 20% of the annual revenue of the country (in
2013). In the case of the coal resources, neither reserves nor properties are correctly grasped. However, reserves
are estimated to be 460 million tons.

Figure1-3

Main energy resources

Resource
Hydropower

Resource amount
108 GW (Theoretical potential
hydropower)
48.5 GW (Economically developable
potential hydropower)

Petroleum

2,100 million bbl

Natural gas

25,000,000 MMcf

Coal

460 million tons (estimate)

Oil shale

720 3,300 million bbl (estimate)


Source: Data prepared by the Study team

2) Energy supply and demand situation


The energy supply and demand balance in 2010 is shown in Figure1-4 . The amount of energy produced in the
country is estimated to be 22,530,000 ton (oil equivalent). About 50% is commercial energy. Natural gas accounts
for 80% or more of the above-mentioned 50%. In this connection, 80% or more of the natural gas is exported.
Domestic demands for natural gas not only for power generation but also for other industries are high. Priority is
desired to be given to domestic demands as regards the gas fields to be developed from now on. However, no
prospect has been obtained for such supply.

18

Figure1-4
Unit: Thousand oil equivalent
Other
Domestic product(22,530)
(108)

Import
(239)

Natural gas

Oil
product
(239)
Hydro power Coal
(409)
(439)
Coal
(409)
Oil product
(390)
Hydro power
(439)

Uncommercial

(10,211)

energy(10,535)

Oil
(935)
Domestic supply(13,997)
Uncommercial
energy(10,535)

Oil
(892)

(8879)
Natural gas(8,879)

(8879)
Export(8,879)
Natural gas
(8,879)

Domestic supply(13,997)
Loss
(1110)

Uncommercial
energy(10,495)
Electricity Oil
(535) product
(1027)
Coal(234)

Natural gas(596)

Source: Based on information materials prepared by the Japan Electric Power Information Center Inc.

3) Enhancement and rationalization of the use of energy


The energy policy is established by the Energy Planning Division of the Ministry of Energy. This policy was
established in the 1990s, and was updated in 2011. In this new energy policy, Effective Use of Petroleum and
Natural Gas and Private Enterprises Participation in the Energy Filed were set forth in place of Active
Development of Hydropower, Which is Domestic Resources, which used to be set forth in the past. Petroleum
and natural gas are limited resources. These resources are intended to be effectively allocated to domestic
demands (electric power and industries) and to export, through which foreign currencies are earned.

19

4) Electric power demand prediction, and electric power development plans


The electric power consumption in Myanmar is extremely low. The consumption per capita is approximately
1/70 of that in Japan, or about 1/20 of that in Thailand. The electrification rate is as low as 28%.

Table 1-3 Electric power situations in Myanmar and other various countries
ITEM
Peak Demand
[GW]
Electricity Sales (a)
[TWh/year]
Population (b)
[Million]
Electricity Sales per Capita (a)/(b)
[MWh/year/capita]
Electrification Ratio
[%]

Myanmar

Japan

Thailand

Indonesia

Philippines

Jordan

Zambia
(FY2005)

156

26

29

11

6.3

851.6

162.7

174

59.2

14.3

8.1

62

127

67

244

97

13

0.1

6.7

2.3

0.7

0.6

2.3

0.6

28

100

99

73

81

100

26

Source: Data prepared by the Study team

High economic growth is expected to take place in the future. Also, electric power demand is presumed to
significantly increase. Electric power demand predictions are carried out not only by the Ministry of Electric
Power, but also by international organizations such as the ADB, the World Bank, and the JICA. Estimations are
made using indices such as economic growth rates (GDP), populations, and electrification rates. Recently, demand
predictions are performed using JICAs Electric Power Master Plan. The results of these predictions are shown
below together with the results of the prediction made by the Ministry of Electric Power. In Case High, the peak
electric power will be 14,500 MW in 2030. This value is about seven times as high as the current amount.

20

Figure 1-5 Electric power demand in Myanmar

Power Demand [MW]

25000
19217

20000

14542

15000

MOEP
9100

10000

High Case
Low Case

5000
1666

0
2010

2015

2020

2025

2030

2035

Year

Source: JICA Electric Power Master Plan Study: Draft Version

For the purpose of meeting this power demand, an electric power source of 28,500 MW will be required in
2030. That is, it follows that an electric power source of 25,000 MW will be newly developed. In terms of the
electric power source make-up, not only hydropower electric power source, but also coal, gas, and renewable
energy electric power sources are intended to be developed in conformity with the government energy policy. In
JICAs Electric Power Master Plan investigation, a proposal is made of the optimum electric power source
make-up in which consideration is given to the following matters: diversification of electric power sources;
electric power source development costs; and electric power supply costs. It is concluded that the optimum
coal-fired electric power source is 5,000 MW, which is equivalent to 20% of all electric power sources.

Figure 1-6 Electric power source make-up in Myanmar

Installed capacity :28,551MW


Renewable

Installed capacity :3,614MW


Gas
714.9
MW

Hydro
2,780
MW

Gas
2,484
MW

2,000
MW

Coal
120
MW

Hydro
19,037
MW

2013

Source: JICA Electric Power Master Plan Study: Draft Version


21

Coal
5,030
MW

5) Electric power transmission systems


The electric power transmission systems in Myanmar consist of 230 kV, 132 kV, and 66 kV systems, and are
subject to the jurisdiction of the Myanma Electric Power Enterprise (MEPE). The numbers of facilities, and the
facilities capacities as of the end of 2013, are as shown in Table1-4*.
The 230 kV system, which is the trunk system, is formed of two routes extending from the central part to
the southern part of this country. The facility capacity for supplying electric power generated by hydropower
plants in the northern part to demand areas in the southern part is insufficient. Therefore, a 500 kV power
transmission lines is newly planned.
.Mawlamyine is located in the southern part. At present, connection is established from the Thaton Electric
Power Substation to the Mawlamyine Electric Power Substation by means of one 230 kV power transmission line.
A second line is being additionally routed. This additional routing work is scheduled to be completed by 2015.

Table1-4 Electric power transmission facilities and electrical energy transformation facilities that are subject
to the jurisdiction of the MEPE (as of the end of 2013)
Item
Number of electric power
transmission lines
Electric power transmission
line distance (km)
Number of electric power
substations
Electric power substation
capacity (kVA)

230 kV

132 kV

66 kV

Total

43

35

138

216

3,047

2,109

3,616

8,772

30

25

130

185

3,760

1,323

1,975

7,058

Source: MEPE

22

Figure1-7 Chart of electric power transmission systems in Myanmar

Existing power system ant planning up to 2020


(Mawlamyine and vicinity inc. Yangon area)

Source: Data provided by the Ministry of Electric Power


The system operation in this country is carried out by the Load Dispatch Center (LDC), which controls
supply and demand adjustments of all systems, the Generation Control Center (GCC), which has jurisdiction
over hydropower plants and coal-fired power plants, and the National Control Center NCC), which reports the
system operation status to the Ministry of Electricity Power, and has LDC and GCC backup functions.

Figure 1-8 System operation work setup


Backup

NCC

GCC

Request for electric


power generation
Operating instructions for
relevant units

Electric power substation


operating instructions

Backup

LDC
Power plant operating
instructions

Systems for electric power transmission and electrical


energy transformation (230 kV 132 kV)
Gas-fired power plants and diesel oil-fired power plants

Source: Data prepared by the Study team

23

6) Electric power distribution systems


The electric power distribution systems in Myanmar are subject to the jurisdiction of the Yangon City
Electricity Supply Board (YESB) in the case of the Yangon district, and the Electric Supply Enterprise (ESE) in
the case of other districts. Electric power is received at 66 kV or 33 kV from the Myanma Electric Power
Enterprise (MEPE), which handles higher-ranking systems. Electric power thus received is supplied to consumers
at 11 kV, 6.6 kV, or 0.4 kV. Furthermore, the ESE has also jurisdiction over electric power generation by means of
diesel power generators and small hydropower generators.

Figure1-9 Relationship chart for electric power enterprises

(
Myanma
Electric Power MEPE)
Enterprise
Myanmar Electric Power Enterprise

(66kV,33kV)

Electric
Supply Enterprise

(ESE)

Yangon
City Electricity

(YESB)Supply Board

Electric Supply Enterprise

Yangon City Electricity Supply Board

(11kV,6.6kV,0.4kV)

Consumer

Source: Data prepared by the Study team


The suburbs of Mawlamyine in Mon State are subject to the jurisdiction of the Mon State Engineering Office of
the ESE. The electric power distribution facilities in the possession of Mon State and the ESE are as shown in the
table below. Electrification rates in Mon State are 71% in urban areas and 51% in provincial areas. These rates are
higher than those in the entire region under the jurisdiction of the ESE, which are 53% in urban areas and 32% in
provincial areas.
In districts under the jurisdiction of the ESE, when it is necessary to newly install electric power distribution
facilities to meet new demands, there are cases where consumers receive electric power in such a way that
consumers bear the cost of new facilities and subsequently transfer these facilities to the ESE. For this reason,
there is a high possibility that power plant constructors have to bear the costs of electric power distribution
facilities that serves to receive the electric power required to construct power plants and perform trial runs.

24

Table1-5 Electric power distribution facilities under the jurisdiction of the ESE
Item
Electric power distribution
line distance (km)
Number of electric power
substations
Electric power substation
capacity (MVA)

66 kV
33 kV
11 kV
Mon State
19
238
644
Entire region
3,144
6,011
12,373
covered by ESE
Mon State
4
32
617
Entire region
141
717
13,292
covered by ESE
Mon State
37
62
118
Entire region
1,470
2,275
3,034
covered by ESE
Source: Data issued by ESE (July 2013)

6.6 kV
11

400 V
628

263

14,010

11

312

1.33

164

In the electric power distribution systems in Myanmar, there are frequent occurrences of power outages due to
failures caused by deterioration of electric power distribution facilities, and due to insufficient supply from
higher-ranking systems. Furthermore, the overall length of low voltage lines is so long that instances of electric
power distribution losses and voltage drops are on the increase. The ADB, the World Bank, and the JICA have
declared their intentions to provide support for these issues.

7) Electric power tariffs


MoEP raised the electricity tariffs in April 2014 for the purpose of improving the income and expense balance, in
which chronic deficits continued. Such a Tariff rise was implemented for the first time in about two years after
January 2012. At the beginning, the YESB announced a tariff rise on October 28, 2013. The tariff rise was
scheduled for November 1, 2013. However, due to citizens protests, the parliament passed a motion for review,
with the result that the tariff rise was temporarily frozen. Subsequently, another motion was passed in the
parliament, resulting in the tariff rise taking effect on April 1, 2014.
The Table 1-6 of electricity tariff before April 2014 and those in and after April 2014 are shown below. The
tariffs for ordinary households were raised to a maximum of 140%. The tariffs for industries were raised to a
maximum of 200%. The tariffs were not raised for streetlight contracts or for foreign currency-based
(dollar-based) contracts applied to foreigners to foreign enterprises.

25

Table1-6 Comparison of electricity Tariffs before the tariff rise and those thereafter

Household

Type

General Purpose
Domestic Power
Small Power
Industrial

Industry

Other

Bulk
Street Lighting
Temporary Lightning
Foreign users

Electricity
Tariff (/kwh)
kWh
2014331
201441
Until 31st March 2014
From
1st April 2014
1kWh 100kWh
35Kyat
35Kyat
101kWh 200kWh
40Kyat
201kWh
50Kyat
1kWh 500kWh
75kyat
75Kyat
5000kWh 10000kWh
100kyat
10001kWh 50000kWh
125kyat
50001kWh 200000kWh
150kyat
200001kWh 300000kWh
125kyat
300001kWh
100kyat
35Kyat
35Kyat
35Kyat
35Kyat
75Kyat
75Kyat
0.12USD
0.12USD

Source: Data prepared by the Study team

26

Chapter 2 Study Methodologies


(1) Description of study
A series of study work was carried out on the basis of the following items: the energy policy of Myanmar;
energy in this country and in that area in Mon State which is the project site; those publications related to the
electric power situation which are released to the public; information and data that are collected from, or obtained
by interviewing relevant members of, the Ministry of Electric Power, which is the counterpart; and the results of
studies made by visiting the site, and the particulars of the information obtained thereby.
Studies were made of the following particulars, and studies were made of facilities, fund-raising, and
implementation of plans. Subsequently, evaluations were made of the basic plans and business prospects for the
coal-fired power plant and for the coal storage and supply base.

1) Matters related to the policies, courses of actions, and laws of the county
a) Matters related to the policies and laws related to coal in Myanmar
b) The energy policy, electric power development plans, electric transmission plans, electricity rates, etc.

2) Study of fuel supply


a) Reserves, prices, properties, etc. of coal inside and outside Myanmar

3) Study of the places of the coal-fired power plant and the coal storage and supply base
a) Locations of the ultra-supercritical coal-fired power plant and the coal storage and supply base (areas of the
sites, geographical features, weather, hydrological features, ownership, surrounding environment [Distances
from electric power consumption places, connection with electric power transmission lines, industrial water],
etc.)
b) Coal storage and supply base: Harbor (Depth, weather, ship traffic volume, etc)
c) Power plant: Calculation of rough estimates of operating costs such as for the investigation of the harbor
where water intake openings, water discharge outlets, and piers are to be installed

4) Evaluation of impacts on environmental aspects, social aspects, and consideration-related aspects


a) Outlines of environment-related laws and regulations in Myanmar
b) Those impacts on environmental aspects and social aspects which are associated with construction and
operation regarding this project
c) Environmental improvement effects associated with the implementation of this project (analytical
techniques)
d) Effective use of coal ash and desulfurized by-product calcium sulfate in the cement industry etc.

27

5) Financial and economic analyses


a) Financial analysis and economic analysis

6) Possibility of participation of Japanese enterprises


a) Status of investment in Myanmar from foreign countries
b) Investment-related laws, and IPP-related legal systems and tax systems, in Myanmar
c) Investment environment for Japanese enterprises

(2) Study team


1) Study team
Table 2-1 Study team
Role

Name

Project manager

Keiji Morino

Supervision of investigation

Narichika Kobayashi

3
4
5
6

Ryu Zushida

Economic and financial analyses


Legal system and investment
environment

Shinji Hosono
Shinichiro Kobayashi
Takamichi Ozaki
Eiji Kurihara

Management in general

Naoto Kawabe

On-site support (Yangon)

Munehisa Ito

On-site support (Naypyidaw)

Keiichi Kagami

10

Supervision of technology

Kimitsugu Kozasa

11

Electric power development


Yoshitaka Saito

planning
12

Mitsui & Co., Ltd.

Electric power transmission


planning

Kazunori Ohara

Chubu Electric Power


Co., Inc.

13

Power system planning

Yoshihide Takeyama

14

Thermal power plant planning

Shunichiro Yasuda

15

Environmental and social Impact

Kensuke Fukushima

16

analysis

Myanmar Koei International

17

Marine civil engineering planning

Penta-Ocean Construction Co., Ltd.)

Source: Data prepared by the Study team

28

2) Counterparts
Figure2-1 Organization of MoEP
Minister

Deputy Minister

Deputy Minister

Department of Department of
Hydropower
Hydropower
Implementation
Planning
(DHPI)
(DHPP)

Hydropower
Generation
Enterprise
(HPGE)

Department
of Electricity
Power
(DEP)

Myanma
Electric Power
Enterprise
(MEPE)

Yangon City
Electricity
Supply Board
(YESB)

Electric
Supply
Enterprise
(ESE)

Source: Data prepared by the Study team

Table 2-2 Counterparts who were met


Affiliation

Official position

Ministry of Electric Power


Department of Hydro Power Planning
Ministry of Electric Power
1

Ministry of Electric Power


Department of Hydro Power Planning
Ministry of Electric Power
Department of Hydro Power Planning
Ministry of Electric Power
Department of Hydropower Planning
Ministry of Electric Power

Electricity Supply Enterprise


Ministry of Electric Power
MEPE
Ministry of Electric Power
Department of Electric Power
Ministry of Electric Power

Department of Hydro Power Planning


Ministry of Mine

Deputy Director General

U Aye San

Deputy Minister

Maw Thar Htwe

Director

U Aung Ko Ko

Deputy Director

U Tint Lwin Oo

Deputy Director General

U Aye San

Managing Director

Myint Aung

Managing Director

Htein Lwin

Deputy Director General

Mi Mi Khaing

Director

Aung Ko Ko

Deputy Director general

U Kyaw Din

Director

Dr. Myint Soe

Source: Data prepared by the Study team

29

Name

(3) Study schedule


Table 2-3 Study schedule

Aug

Sep

2014
Oct

2015
Nov

Dec

Jan

Feb

Domestic study)
Law and regurations study
Fuel Supply Planning study
Facility Planning study
Fund planning study
Environmental Impact accessment
Plan study
Economical study
Report
Site study
1st
Disscussion
2nd
Site study
3rd
Interim report
Final
Final Report

Source: Data prepared by the Study team

Oct. 5, 2014
(Sun)
Oct 6, 2014
(Mon)
Oct 7, 2014 (Tue)
Oct 8, 2014
(Wed)
Oct 9, 2014 (Thu)
Oct 10, 2014
(Fri)
Oct 11, 2014
(Sat)

Table2-4 First site study


Activities
Travel Narita Yangon
Internal meeting
Meeting with subcontractors for local works
Meeting with the Japanese Embassy
Meeting with JICA/Myanmar Office
Meeting with JICA Expert in the Ministry of Transportation
Internal meeting and work
Travel: Yangon Naypyidaw
Internal meeting and work
Meeting with the Deputy Minister of the Ministry of Electric Power and the Director
of the Department of Electric Power Planning
Internal meeting and work
Travel: Naypyidaw Yangon
Yangon Narita
Travel: Yangon Narita
Source: Data prepared by the Study team

30

Table 2-5 Second site study


Activities
Nov 9, 2014
(Sun)
Nov 10, 2014
(Mon)

Nov 12, 2014


(Wed)
Nov 13, 2014
(Thu)

Travel: Narita Yangon


Travel: YangonMawlamyine
Visit to potential project sites
Visit to potential project sites
Visit to potential project sites
Internal meeting and work
Travel: Yangon (Narita)
Travel: (Yangon)Narita
Source: Data prepared by the Study team

Table2-6 Third site study


Activities
Nov 24, 2014
(Mon)
Nov 25, 2014
(Tue)
Nov 26, 2014
(Wed)
Nov 27, 2014
(Thu)
Nov 28, 2014
(Fri)
Nov 29,
2014(Sat)

Travel: Narita Yangon


Travel: Yangon Naypyidaw
Meeting with the Department of Hydropower Planning of the Ministry of Electric
Power
Internal meeting and work
Presentation at a seminar held by the HIDA
Meeting with the Ministry of Mine
Internal meeting and work
Internal meeting and work
Travel: Naypyidaw Yangon
Meeting with the Japanese Embassy in Yangon
Travel: Yangon Narita
Travel: Narita Chubu
Source: Data prepared by the Study team

Table2-6 Fourth site study


Activities
Jan 26, 2015
(Mon)
Jan 27, 2015
(Tue)
Jan 28, 2015
(Wed)
Jan 29, 2015
(Thu)
Jan 30, 2015 (Fri)

Travel: Narita Yangon


Travel: YangonNaypyidaw
Meeting with the Ministry of Electric Power
Meeting with the Ministry of Electric Power
Travel: Naypyidaw Yangon
Meeting with the Japanese Embassy in Yangon
Meeting with JICA/Myanmar Office
Travel: Yangon (Narita)
Travel: (Yangon)Narita
Source: Data prepared by the Study team

31

Chapter 3 Justification, Objectives and Technical


Feasibility of the Project
(1) Project background
As shown in Chapter 1, it is estimated that in 2030, the electric power demand in Myanmar will be seven times
as high, compared to the present. In order to meet this increase in the electric power demand and to stably supply
electric power, it is necessary that prompt development of power plants. On the basis of the experience gained in
Japan regarding the oil crisis, it is necessary that not depending only on one type of fuel, development of power
plants shall be done using various types of fuel, such as not only gas-fired power generators, coal-fired power
generators, and hydropower generators, but also generators using renewable energy like wind power and solar
power.
But supply capability of each fuel sources and the places where hydro power can be developed are regulated.
Considering this aspect, it is also important that low cost constitution of power generating facilities.
The details of the above are shown below.
Figure 3-1 Prediction of the gas demand in Myanmar

Source: JICA, Electric Power Master Plan in Myanmar, 2014

Figure 3-1 shows the predicted values of the following items in Myanmar: the amount of gas demanded; and
the amount of gas that can be supplied. The amount of gas demanded means the amount of gas required to operate
the 2,484 MW gas-fired power plants that was assumed for the electric power source. The pink line indicates the
amount of gas that can be supplied in Myanmar. It is estimated that in 2030, the amount of gas demanded will be
three times as high as the amount of gas that can be supplied in Myanmar. Therefore, it will be necessary to cover
the shortage by import. Ordinary import of liquefied natural gas (LNG), and import of natural gas through
pipelines from neighboring countries, are conceivable. In this regard, development of these pipelines requires cost
and time.

32

Figure 3-2 Amounts of coal required for coal-fired power generation in Myanmar

Source: JICA, Electric Power Master Plan in Myanmar, 2014


Figure 3-2 shows the amounts of coal demanded with the power generation demand taken into account and the
amounts of coal that can be produced in Myanmar. In 2030, it will be necessary to import coal that is about five
times as much as the amount that can be produced in Myanmar.
Figure3-3 Plans for the development of hydropower plants

Source: JICA, Electric Power Master Plan in Myanmar, 2014

33

Figure 3-3 shows plans for the development of hydropower plants. Development of large-scale hydropower
plants involves the following problems, among others: Long development periods are required (10 years or
more). Depending on development places, environmental impacts, social impacts, etc. are high (such as
submergence of a wide range of land, and relocation of residents). Depending on locations, it is difficult to
establish connection with electric power transmission lines. Furthermore, there is a problem in that power
generation capacities vary depending on season. In dry seasons, power generation output power is 70% of that in
rainy seasons.

Power generation cost cet/kwh

Figure3-4 Comparison of thermal power generation costs (Classified by fuel type)

CO2 countermeasure cost


Managerial and repair cost
Construction cost
Fuel cost

Coal

Gas

Oil

Sources: In-house information materials of Chubu Electric Power Co., Inc. and information materials of the
Federation of Electric Power Companies of Japan

Figure 3-4shows power generation costs as classified by fuel type. Fuel prices are subject to large variations
and are subject to various estimation methods. Generally speaking, it can be said that coal-fired power generation
is most inexpensive on an overall basis.

34

Figure 3-5 Changes in generated electric power as classified by fuel type

Source: In-house information material of Chubu Electric Power Co., Inc.

Figure3-5 shows generated electric power amounts in the past and at present in Japan as classified by fuel type.
Up to the 1970s, electric power supply in Japan depended primarily on hydropower generation and coal-fired
power generation. In the 1970s, oil shocks were experienced twice. Since then, efforts have been made to
diversify fuel types. In specific terms, development of nuclear power plants, and thermal power plants fired by
liquefied natural gas (LNG) or coal, has been pushed forward. Currently, as shown in Figure 3-5, the breakdown
of the power generation facility fleet is such that no specific fuel type is depended upon.

Figure 3-6 Changes in generated power amounts, as classified by fuel type, which occurred after the Great East
Japan Earthquake, compared to the corresponding amounts before this earthquake

Source: In-house information material of Chubu Electric Power Co., Inc.


35

Figure3-6 shows quite recent generated power amounts as classified by fuel type. In Japan, the Great East Japan
Earthquake was experienced in March 2011. At the Fukushima No. 1 Nuclear Power Plant, which was damaged
by the earthquake and the resulting tsunami, there occurred a serious accident in which nuclear reactors failed to
be cooled. At present, safety improvement measures are being taken in nuclear power plants in Japan. All nuclear
reactors are stopped.
After the earthquake, the following measures were taken, among others: LNG thermal power generation
amounts were increased by urgently increasing LNG imports; aged oil-fired power plants were rehabilitated. As a
result, power generation operations have been carried out without causing great obstacle to electric power supply.
On the basis of the above, promotion of the diversification of fuel is very important in terms of the security of
electric power supply.

Figure 3-7 Power generation amounts, as classified by fuel type, with respect to daily load duration curves

Source: In-house information material of Chubu Electric Power Co., Inc.

Figure 3-7 shows changes in daily power generation amounts, as classified by fuel type, in a state when nuclear
power plants are operable.
The operating arrangement is such that nuclear power and coal-fired power, for which fuel costs are low, are
used as base electric power sources, and that electric power is generated at full output power at all times.
Adjustment of power generation amounts commensurate with demands is carried out at power plants using gas
turbines, which excel in load adjustment speeds (generation power amount adjustment speeds). On the basis of the
above, it is necessary in terms of supply and demand adjustment that coal-fired power and gas-fired power be
developed in such a way as to strike an appropriate balance.

So far, it was explained that diversification of fuel is important. That is, an explanation was given that it is
important to carry out development in such a way as to strike an appropriate balance among gas-fired, oil-fired,
and hydropower generation. The contents of the explanation made so far made are summarized below:

It is expected that in Myanmar, the electric power demand will rapidly increase by 2030.

Coal-fired power is the most inexpensive electric power source.


36

In Japan, oil crises were experienced in which shortage of oil supply, and efforts have been made to
diversify fuel. Diversification of fuel is important in terms of security and of supply and demand
adjustment.

Development of coal-fired power plants is an important means for resolving the energy issue in Myanmar.

37

(2) Basic conditions of the project


1) Assumption of fuel to be used (design coal)
In Myanmar, there is a coal mine called Kalewa Coal Mine, where sub-bituminous coal whose properties permit
the coal to be used to generate electric power, can be mined. However, in most of other coal mines,
sub-bituminous coal with poor properties, and lignite, are mined. The properties of these coal types are low
calorific values, high water contents, high sulfur contents, and low crushability. In order to use the
above-mentioned coal types as power generation fuel, increased facility costs are entailed. Therefore, the
aforementioned coal types are unsuitable as power generation fuel. Furthermore, Kalewa Coal Mine alone cannot
cover all of the coal-fired power plants to be developed in Myanmar from now on.
Figure3-8 Places holding coal deposits underground in Myanmar

Source: Data based on DGSE information materials


38

Table3-1 Properties of coal in Myanmar


Kalewa

Rashio

Tigyit

Eastern Shan

6,500

3,450 - 5,400

5,000

3,000 - 6,000

Sulfur content (%)

0.52 - 0.78

0,39 - 1.04

0.46 - 0.96

0.4 - 1.17

Crushability (HGI)

34 - 42

20 - 27

20 - 27

Ash content (%)

4.4 - 5.8

2.3 - 8.1

8 - 12

2 - 16

9.7
Sub-bituminous
coal

8.6 - 24.0

18.51

40

Lignite

Lignite

Lignite

Calorific value (kcal/kg)

Water content (%)


Coal type

Estimated reserves
214
29
20
150
(in millions of tons)
Source: Data prepared by the Study team on the basis of DGSE information materials

On the basis of the above, it is assumed that in this project, bituminous coal will be used imported from
Australia and Indonesia, which are neighboring countries of Myanmar. Also, the facilities will be designed in such
a way that the use of sub-bituminous coal in Myanmar. And that blending system of two types of coal such as
sub-bituminous coal and bituminous coal shall be considered.

1) Generating capacity: Big scale and reliable plant shall be required;

Net Out Put; 600 MW


Gross Out Put; 660 MW

2) The calorific value will be as follows:

Higher Heating Value (HHV) : Approximately 24,000 kJ/kg

3) Assumption of the power generation efficiency


The power plant generation efficiency will be similar to that of an ultra-supercritical coal-fired power plant
which is operated in Japan on a base load operation basis, which has a large number of operating track records,
and which has high reliability. The value of the power generation end efficiency will be as follows:
Power generation efficiency: 42% (HHV)

4) Assumption of the annual load factor


The annual load factor will be assumed similarly to the case in item (2) 2) above. The value of the annual load
factorwill be as follows:
Annual use rate: 80%

5) Assumption of the availability


The availability will be assumed similarly to the case in item (2) 2) above. The value of the availability will be
as follows:
Availability: 84%
39

6) Operation method
As regards the operation method, operations as a base load plant will be assumed.

7) Amounts of fuel (coal) used


The following values of the amounts of fuel used were calculated under the above-mentioned conditions: the
annual value, the monthly average value, the daily average value, and the value under the rated load.

Table3-2 Assumed amounts of coal used


Unit
Annual value
Monthly average value
Daily average
Value under rated load

Amount of coal used

ton/year
ton/month
ton/day
ton/h

Source: Data prepared by the Study team

40

1,500,000
120,000
4,000
204

(3) Outline of the plan for the project


1) Outlines of sites
a) Selection criteria and selection results
From the viewpoints listed below, the following items will be selected: land for the construction of a coal-fired
power plant with a power generation output of 600 MW, and for the construction of a coal storage yard; and
hydrological states for the construction of coal receiving facilities.

Hydrological features (Water depths, tide levels, tidal currents, and wind speeds)

Terrains

Use status

Presence or absence of dwelling houses, schools, etc.

Legal system-based restrictions on the use of land and water areas

Distances from power transmission line

Securing of industrial water

Access road

Distances from pagodas

b) Project area
It was decided that the project area be that portion of the coastline which extends to the south by approximately
30 km from Kyaikami located approximately 90 km southwest from Mawlamyine, the largest city in Mon State.

Figure 3-9

Source: Data prepared by the Study team


41

Mawlamyine is connected by 230 kV electric power transmission lines to Yangon and to the trunk systems all
over Myanmar. Furthermore, the area faces the Sea of Andaman, and is suitable as a base of marine transportation
of imported coal. Limestone is taken out in the suburbs. Therefore, the area is suitable also for the installation of
limestone-calcium-sulfate type desulfurization equipment.
Figure3-10 Places holding limestone deposits
underground in Myanmar

Figure3-11 Schematic of electric power transmission


systems in the suburbs of Mawlamyine

Existing power system ant planning up to 2020


(Mawlamyine and vicinity inc. Yangon area)

Source: DGSE information materials.

Source: Data provided by the Ministry of Electric


Power

Figure3-12 Mawlamyine Electric Power Substation

Source: Photograph taken by the Study team

During the on-site exploration, confirmations were made of the hydrological states of the sea area and the
positions of schools, dwelling houses, pagodas etc., and selection was made of the land required to construct the
power plant.

42

Figure3-13 School, dwelling house

Source: Photograph taken by the Study team

Figure3-14 Pagodas

Source: Photograph taken by the Study team

Figure3-15 Study of candidate places

Source: Photograph taken by the Study team

43

Figure3-16

Study of a candidate place

Source: Photograph taken by the Study team

44

(4) Plant Layout


1) Future installation of an additional power plant
The layout was arranged in such a way that the spaces for coal handling system, ( coal unloading system,
coal storage equipment, coal conveying equipment), unit equipment, flue gas environmental treatment system,
waste water treatment system, and maintenance areas are secured so that in the future, a similar 600 MW class
coal-fired power USC plant can be additionally set up. Furthermore, the layout was also arranged in such a way
that account was taken of future additional installation of comprehensive wastewater treatment equipment etc.
2) Water depth
A plan was prepared in such a way that coal ships will be anchored at a place where the water depth is 15 m
or so and which is approximately 1.5 km offshore. Coal ships were assumed to be 80,000 DWT class
oceangoing vessels of approximately 12 m full draft. Moreover, by building a breakwater, the risk of cases
where it is impossible to generate power, due to reasons such as the inability to carry out cargo handling during
rough weather during monsoon season, is intended to be reduced.
3) Recycling of water intake and water discharge
The warm wastewater flow rate is assumed to be 28.5 m3/s or less per unit. The seawater temperature
deference between intake water and discharge water shall be designed 7 or less. Furthermore, water
intake openings and water discharge outlets were arranged in such a way that warm wastewater from water
discharge outlets will not flow into water intake openings.
4) Direct convey line from coal jetty to boiler shall be considered
The layout was arranged in such a way that after unloaded, coal can be sent directly to boiler from the jetty..

5) Coal blending
Coal blending equipment (equipment whereby two types of coal can be blended at coal bending rates within
the range from 10 90%) was installed at the outlet of the coal storage yard so that bituminous coal could be
blended with sub-bituminous coal etc.
6) Coal ash and gypsum shipping equipment (Jetpack vehicle transportation, ship transportation)
A plan was prepared in which limestone and gypsum would be subjected to marine transportation on 2,000
DWT ships (marine transportation to foreign countries was also assumed). Furthermore, facilities were
configured in such a way that it would also be possible to carry out delivery by means of jetpack vehicles.
7) Water to be used
The layout was arranged in such a way that plant water receiving equipment and pretreatment equipment
would be installed at an entrance to the premises of the power plant, and that the piping length would be the
shorts. At present, no industrial water facilities are developed in neighboring places of the project site.
Therefore, it is assumed that water will be taken from rivers, well.or instration of RO system.

45

Figure 3-17 View of the layout

Source: Data prepared by the Study team


46

(5) Power generation facilities


1) Design policy for the power plant
(a) Design policy
It was decided that the power plant comprise one 600 MW unit, and that the major design conditions be as
shown in there table below.

Table3-3 Design conditions for the New Power Plant


No.
1
2
3
4
5
6
7
8
9
a
b
c
d
e
f
g
10

Item

Unit

Rated output power (Net value)


MW
Number of units
Unit
Electric power generation efficiency (Higher Heating
%
Value HHV )
Load factor/Availability
%
Annual operating hours
h/ y
Annual Gross Generation Output
GWh/y
Auxiliary power consumption rate
%
Annual Net Generation Output
GWh/y
Fuel consumption
Design standard Heating value (Gross as received)
kJ/kg
- Fuel consumption (Load factor = 100%)
t/h
(Maximum value per hour)
- Fuel consumption (Load factor = 100%)
t/d
(Maximum value per day)
- Fuel consumption (Load factor = 80%)
t/month
(Monthly average)
- Fuel consumption (Load factor = 80%)
t/year
(Annual average)
- Coal storage yard capacity) (Number of days)
days
- Coal storage yard capacity) (tons)
ton
Ash discarding place capacity (Number of years)
Years
Source: Data prepared by the Study team

Numerical
value
600
1
42
80/84
7,358
3,532
5.5
3,338
24,000
204
4,896
120,000
1,500,000
45
200,000
5

(b) Steam conditions


As regards the steam conditions to be applied to the power plant, it was decided that at the turbine inlet,
the main steam temperature be 600C and the reheated steam temperature be 600OC. At present, this
temperature level is in the top level.

Table3-4 Power plant steam conditions


NO
1
2

Item
Pressure
Temperature
Pressure

Value
24.5 MPa (g)
600 C
4.38 MPa(g)

Main steam (at the high pressure


steam turbine inlet)
Reheated
steam
(at
the
Intermediate
pressure
steam
Temperature
600 C
turbine inlet)
Source: Data prepared by the Study team

47

Remarks

(c) Design coal


It was decided that the properties of coal be as shown below. Design was carried out on this basis.
Table 3-5 Design coal properties
Item

Numerical value

Higher heating value of constant humidity coal

24,000 kJ/kg

Total S content (on a dry basis)

1.0%

N content (on a dry basis)

1.8%

Ash content (on a dry basis)

20%

Hygroscopic moisture (Surface moisture)

7%

Source: Data prepared by the Study team


2) Main specifications of power generation equipment
In this paragraph, description is given of the main equipment (boilers, turbine generators), and of the
recommended main specifications.
Figure3-19 Main system schematics

Source: Data prepared by the Study team


(a) Boiler

Fuel

: Imported coal (from Australia and Indonesia,)

Auxiliary fuel

:Light oil

Stem conditions

: USC (600/600C)

Boiler type

: Ultra-supercritical once-through boiler where pulverized coal is burned


exclusively

Maximum steam flow rate : 1,930 t/h

Main equipment

: Two boiler circulation pumps, two water separators, six mills (one mill
being a spare), two forced draft fans, two primary air fans, two induced
fans, and two, boost up fans.
48

Figure 3-20 Schematic of boiler

Source: Data prepared by the Study team


Figure 3-21 Schematic of coal pulverizing equipment

Figure 3-22

Source: Data prepared by the Study team

49

Coal pulverizing equipment

(b) Turbine

Steam conditions

: USC (600/600C)

Turbine type

: Tandem compound, single reheat condensing turbine

Main valves

: Four Main steam stop valves, four steam control valves, two reheated
steam stop valves, and two intercepting valves

Water supply pumps

: Steam turbine-driven boiler water feed pumps (Two 50% pumps) and
electromotor-driven boiler water feed pumps (One 25% pumps)

Figure3-23 General view of the steam turbine


(in the course of assembly)

Figure3- 24

Low pressure turbine

Source: Data prepared by the Study team


Figure 3-25

General view of the turbine generator unit

Source: Data prepared by the Study team


(c) Generator

Type

: Rotating field magnet type

Cooling method

: Hydrogen direct cooling (for rotors), and water direct cooling (for stators)

Capacity

: 700 MVA (rating)

Power factor

: 0.9 (The details pertain to the time of the implementation of FS.)

Frequency

: 50 Hz

Excitation method

: Thyristor excitation method

Treatment of sealed oil

: Vacuum treatment method

50

(6) Environmental treatment equipment and coal handling system


In power plants, it is important to install appropriate environmental treatment equipment and carry out suitable
operation and maintenance management. Described below are environmental measures taken in one of the latest
large-sized coal-fired power plants in Japan

Figure 3-26 Schematic of coal-fired power plant

Source: In-house information material of Chubu Electric Power Co., Inc.

Figure 3-26 shows an outline of the whole coal-fired power plant.


Ash, sulfur oxides (SOx), and nitrogen oxides (NOx) are included in exhaust gas generated due to the
combustion of coal. Pieces of equipment for removing these pollutants are installed between the boiler and the
stack.
Furthermore, various types of wastewater are generated in coal-fired power plants. These types include the
following, among others: wastewater from boilers and turbines, wastewater from desulfurization equipment for
removing sulfur oxides, miscellaneous wastewater from offices etc., wastewater from facilities for treating
and transporting ash, wastewater from coal storage yards and wastewater containing oil. These types of
wastewater have different properties, and therefore, should be separately treated appropriately.

51

1) Flue gas treatment system (Prevention of air pollution)

Figure 3-27

Power plant in the 1950s

Present-day coal-fired power plant (Hekinan Thermal Power Plant)

In Japan, progress was made in the introduction


of

environmental treatment equipment such as denitration


equipment,

desulfurization

equipment,

and

dust

precipitators ever since the 1970s, during which


pollution became a serious issue.
Changes in NOx and SOx emissions per kW
Source: In-house information material of
Chubu Electric Power Co., Inc.

The pictures on upper side of Figure 3-27 shows comparison


of coal-fired power plant in the 1950s with that at

present, and visually shows that smoke discharge decreased due to the introduction of environmental treatment
equipment. In Japan, the public air pollution became a serious social problem from the 1960s to the 1970s. For
this reason, ever since the 1970s, various flue gas treatment equipment has been developed and introduced. The
graph on lower side of Figure 3-27 shows changes in emissions of NOx and SOx per kW. Due to the development
and introduction of flue gas treatment equipment, the emissions of air pollutants were drastically reduced.

52

Figure 3-28 Comparison of amounts of air pollutants discharged

NOx
SOx

0.16

USA
(2005)

Canada
(2005)

UK

France

(2005)

(2005)

Germany
(2005)

Italy
(2005)

0.07

Japan Hekinan

Hekinan

(2007)

Source: Data prepared by the Study team by using information materials


of the Federation of Electric Power Companies of Japan

Figure 3-28 shows amounts of SOx and NOx discharged per kWh in coal-fired power plants in various
countries. As compared to other countries in the world, the amounts of the above-mentioned substances
discharged from coal-fired power plants in Japan are extremely low. Furthermore, in Japan, the amount of the
aforementioned substances discharged from the Hekinan Thermal Power Plant of Chubu Electric Co., Inc. is
furthermore lower.
Figure 3-29 shows an outline of flue gas treatment facilities in a coal-fired power plant.

Figure3-29 Outline of flue gas treatment facilities

Source: In-house information material of Chubu Electric Power Co., Inc.


53

Figure3-30

Flue Gas treatment facilities in the Hekinan Thermal Power Plant

Source: In-house information material of Chubu Electric Power Co., Inc.

Combustion gas from the boiler firstly passes through the denitration equipment, which removes nitrogen
oxides (NOx) in a high temperature state. Subsequently, this gas passes through the air preheater and through the
gas and gas heater heat recovery device, where the temperature is reduced. Then the above-mentioned gas passes
through the dry electrostatic precipitator, which serves to remove particles of soot.. Subsequently, this gas passes
through the induced draft fan, and is sent to the desulfurization equipment, which serves to remove sulfur oxides
(SOx).
Downstream of this equipment, the above-mentioned gas passes through the wet electrostatic precipitator,
which serves to remove particles of soot once again. Subsequently, the gas temperature in the gas and gas heater
reheating device is made to the temperature of flue gas high. Then this gas passes through the gas pressure boost
up fan, and is released from the stack.
The wet electrostatic precipitator is installed in the Hekinan Thermal Power Plant, where the regulations of flue
gas emission are very strict. Therefore, this equipment is not generally installed.
Figure 3-31 shows the process where air pollutants in exhaust gas are removed in each facilities of flue gas
treatment system.
Figure3-31 The process where air pollutants in exhaust gas are removed

Source: In-house information material of Chubu Electric Power Co., Inc.


2) Emission standards of exhaust gas
Figure 3-32 shows the emission standards in the Pollution Control Agreements concluded by the Hekinan
Thermal Power Plant with the relevant local autonomous bodies, the emission standards specified in the Air
54

Pollution Control Law in Japan, and the emission standards for air pollutants (NO, SOx, and soot dust) contained
in the exhaust gas produced in coal-fired power plant in the case of the World Bank and the IFC (International
Finance Corporation).

Table 3-6 Comparison of criteria for discharge to the atmosphere

mg/Nm3

Source: Data prepared by the Study team

In the criteria of the World Bank and the IFC, areas are divided into places where air pollution is serious
(degraded airsheds) and other places (non-degraded airsheds).
In Japan, the criteria specified in the Air Pollution Control Law are formulated.
In the Pollution Control Agreements concluded by the Hekinan Thermal Power Plant with the pertinent local
autonomous bodies (Aichi Prefecture and Hekinan City), criteria involving values stricter than those specified in
the Air Pollution Control Law are prescribed. In Japan, factories are concentrated in places such as the areas
around Tokyo Bay, around Ise Bay, and around the Inland Sea. In these areas, it is demanded that particularly
strict criteria be specified with regard to power plants, where large amounts of exhaust gas is discharged.
In Myanmar, the criteria to be complied with will be specified in the course of activities such as studies of
development of domestic laws and evaluations of environmental impacts.
In cease where power plants are to be constructed using loans from banks, it is a general practice to apply the
criteria of the IFC. Applicable criteria differ according to places where power plants are constructed. The criteria
of the IFC's NDA will be applied in places where the atmosphere is clean. In places where air pollution has
progressed, the DA criteria will be applied.
In Myanmar, the Environment Law was enacted in 2012. It is expected that in FY 2014, the criteria for the
atmosphere, wastewater, soil, noise, etc. will be submitted to the parliament and enacted. It is expected that
criteria specific to Myanmar will be formulated by referring to the criteria of the ADB, EU, and IFC.

Here, the IFC standard, which is widely used worldwide, will be borne in mind. On this basis, necessary
environmental measures equipment is described below.
55

3) Flue gas denitration equipment (Selective catalytic reduction [SCR] type)

Figure3-32: Schematic of flue gas denitration equipment

Source: In-house information material of Chubu Electric Power Co., Inc.

Figure 3-32 shows selective catalytic reduction (SCR) type denitration equipment.
In Japan, the criteria for nitrogen oxides (NOx) discharged from large-scale thermal power plants are strict.
Therefore, the selective catalytic reduction type is generally introduced as denitration equipment. This equipment
is arranged in such a way that ammonia is injected into high temperature exhaust gas, thereby being made to react
with nitrogen and water, with the result that nitrogen oxides are reduced. A catalyst serves to accelerate this
reaction. By means of this equipment, 80 to 90% of nitrogen oxides (NOx) can be removed. As regards nitrogen
oxides (NOx ), in countries and regions where the discharge criteria are lenient, denitration equipment is normally
not installed. Catalysts are expensive. Therefore, it is necessary to decide the necessity or non-necessity of
denitration equipment by taking account of discharge criteria that are applied at the stage of detailed studies.
The NOx discharge criteria in the case where DA area is applied pertaining to the IFC criteria in Myanmar, turn
out to be 200 mg/Nm3 (NO, PPm equivalent: 160 ppm). Therefore, denitration equipment is required. In cases
where NDA is applied pertaining to the IFC criteria, the NOx discharge criteria turn out to be 510 mg/Nm3 (NO,
PPm equivalent: 409 ppm). Therefore, denitration equipment is not required in the case of a boiler in which low
NOx fuel is taken into account. Depending on coal type, there is a possibility that the IFC and DA criteria can be
achieved. However, if in-furnace Nox reduction action is intensified with the aim of reducing the NOx
concentration at the boiler outlet, there is a fear that sulfuration corrosion will occur on the furnace wall
evaporation tube. Therefore, this practice is not desirable from the viewpoint of securing reliability for a long
period of time.

Next, a combustion method for suppressing the generation of nitrogen oxides (NOx) is shown below:

56

Figure 3-33

Low NOx combustion method

Source: In-house information material of Chubu Electric Power Co., Inc.

Nitrogen oxides (NOx) that are generated by carrying out rapid combustion at high temperature, are called
thermal NOx. For the purpose of preventing the generation of thermal NOx, the following measures are taken so
that rapid combustion will be prevented from occurring at high temperature in the boiler.

Exhaust gas mixture combustion method:


An arrangement where burned gas is made to circulate again in the boiler furnace, and whereby rapid
combustion is suppressed by reducing the amount of oxygen.

Two-stage combustion method:


An arrangement whereby in places where burners exist, required air is not supplied in full amount, but
combustion air is supplied in two separate stages.

Low NOx burners:


An arrangement where in the burner portions, exhaust gas is mixed in, in addition to combustion air.

57

4) Electrostatic precipitator (ESP)

Figure 3-34 Schematic of electrostatic dust precipitator

Source: In-house information material of Chubu Electric Power Co., Inc.

Figure3-34 shows a dry electrostatic precipitator. This equipment consists of discharging electrodes (linear
articles), which discharge electrons, and dust collecting electrodes (plates), to which dust is made to stick. If the
discharging electrodes are charged with negative electricity and if the dust collecting electrodes are charged with
positive electricity, then electrons are released from the discharging electrodes, with the result that the ash
(particle) in the gas is charged with negative charges. Due to the above, the ash is attracted to the dust collecting
electrodes and stick to these electrodes. On a periodic basis, the ash that stuck to the dust collecting electrodes is
made to drop due to vibrations, and is recovered. The above-mentioned vibrations are generated, for example, by
means of a device whereby the plates constituting the dust collecting electrodes are tapped with hammers. By
means of this electrostatic precipitator, 99% or more of the ash (particle) in the exhaust gas is removed.
It is necessary to decide the required performance by carrying out detailed design at the stage when items such
as the coal to be used and the applicable criteria for discharge to the atmosphere are decided.

58

5) Flue gas desulfurization equipment (FGD)

Figure 3-35 Schematic of flue gas desulfurization equipment

Source: In-house information material of Chubu Electric Power Co., Inc.

Figure3-35 shows flue gas desulfurization (FGD) equipment based on the wet gypsum-limestone method.
Sulfur oxides (SO2) react with lime (CaCO3), oxygen, and water, and turns into gypsum (calcium sulfate) and
carbon dioxide (CO2). Flue gas desulfurization equipment based on the wet gypsum-limestone method is the fruit
of the use of this principle. It is so arranged that limestone crushed into a powdery state is mixed with water,
resulting in the generation of an absorber, and that this absorber is sprayed into exhaust gas. This equipment is
capable of removing 90 to 95% of the sulfur dioxides in the exhaust gas.
In recent coal-fired power plants in Japan, the general practice is to use flue gas desulfurization equipment
based on the wet gypsum-limestone method method. There are a single-tower structure where the soot dust
concentration at the flue gas desulfurization equipment inlet is reduced as much as possible and where the
dustproof cooling tower is eliminated (in the figure above), and a structure type in which a cooling tower aimed at
removing soot dust and cooling gas is installed upstream of the absorption tower.
A type called the low low-temperature dust precipitation system is adopted in the latest flue gas treatment
system . In the case of single-tower type flue gas desulfurization equipment, it is necessary to reduce the soot dust
concentration at the desulfurization inlet. Therefore, it is necessary to enhance the performance of the dry
electrostatic precipitator located upstream. In order to improve the dust precipitation performance, it is necessary
to reduce the gas temperature. Therefore, a low low-temperature dust precipitation system is adopted in which gas
- gas heater heat recovery machine is installed upstream of an electrostatic precipitator and in which the gas
temperature is reduced to 90OC or so. The heat recovered by a heat recovery device is used to raise the exhaust gas
temperature at the stack inlet.(gas - gas heater, gas reheater). The purpose of the above is to raise the temperature
of the gas released to the atmosphere, thereby improving atmospheric diffusion (the effective stack height is
increased).
In the event that the criteria of the IFC and the NDA (850 mg/Nm3. SO2 equivalent: 785 ppm) are applied in
Myanmar, it is considered that it may be possible to omit the flue gas desulfurization equipment in cases where
59

coal with a low sulfur content is used.


However, in this project, it is expected that various types of coal are purchased in the case of imported coal.
Also, the discharge criterias are unclear. Due to the above, studies will be promoted on the assumption that flue
gas desulfurization equipment will be installed.
Meanwhile, in foreign countries, the following flue gas desulfurization types are used, among others: a type
based on the dry limestone-calcium-sulfate method; and a type based on the seawater method. As to the issue of
which is the optimum type, it is necessary to make a decision at the project implementation stage by taking
account on matters such as discharge criteria and the procurability of limestone.

6) Stacks (heights and discharge temperatures)

Figure 3-36 Schematic of a Stack


Stack heights are an impotent factor
when calculating SOx, NOx, and
particulate

diffusion

during

environmental impact studies (EIS).


The design values of Stack heights,
gas

flow

velocities,

and

gas

temperatures are established in such a


way that maximum ground level
concentrations, which are the results
of

the

diffusion

calculation

in

environmental impact studies, will


meet the environmental criteria.
Source: In-house information material of Chubu Electric Power Co., Inc

Figure 3-36 shows the 200 m high centralized stack in the Hekinan Thermal Power Plant. Stack heights are
deeply related to the atmospheric diffusion of exhaust gas. In the evaluation of environmental impacts, the
effective heights of Stacks are calculated from the heights of planned Stacks, gas flow velocities, and gas
temperatures.
Diffusion simulation is carried out on the assumption that exhaust gas diffusion occurs at the heights equal to
the effective stack heights calculated. Through simulations, calculation is made of the maximum ground level
concentrations of sulfur oxides (SOx), nitrogen oxides (NOx), and particle. In the course of the evaluation of
environmental impacts, it is verified that the maximum ground level concentrations meet the environmental air
standards.

7) Reductions in greenhouse effect gas (CO2) emission


In order to reduce carbon dioxide (CO2) emission, it is indispensable to introduce high efficiency power
generation facilities. For this purpose, it is necessary to introduce power generation facilities using
ultra-supercritical (USC) boilers, which have high pressures and high temperatures.
60

Terms related to steam conditions include subcritical (SC) pressure, supercritical (SC) pressure, and
ultra-supercritical (USC) pressure.
The items in Table3-7 shows rough definitions. Relevant defining values differ from manufacturer to
manufacturer. On this basis, rough defining values are shown in Figure 12. Relationships between steam
conditions and efficiencies are noted below. Figure 12 shows that the higher the pressures and temperatures under
steam conditions, the higher the power generation efficiencies.

Figure 3-7 Steam conditions and thermal efficiencies

Source: JICA, Clean Coal Technology in Indonesia, 2012

Subcritical (SubC) pressure conditions


Main steam pressure, reheated steam turbine inlet pressure < 22.1 MPa, Temperature 566C

Supercritical (SC) pressure conditions


Main steam pressure, reheated steam turbine inlet pressure 22.1 MPa, Temperature 566C

Ultra-supercritical (USC) pressure conditions


Main steam pressure, reheated steam turbine inlet pressure 22.1 MPa, Temperature 566C
Figure 3-37 shows comparisons between the subcritical (SubC) conditions and the ultra-supercritical (USC)

pressure conditions. Given below are differences in construction costs and CO2 emissions between the subcritical
(SubC) conditions and the ultra-supercritical (USC) conditions.

61

Figure 3-37

Comparisons between the subcritical pressure conditions and


the ultra-supercritical pressure conditions

Source: JICA, Electric Power Master Plan in Myanmar, 2014

Construction costs become higher under the USC conditions. This is because it is necessary to use materials
capable of withstanding high temperatures. Meanwhile, under the USC conditions, efficiencies become higher.
Therefore, under the USC conditions, fuel consumption and CO2 emissions become lower than under the
subcritical conditions. The notion that the adoption of the ultra-supercritical (USC) conditions is advantageous
from the viewpoint of CO2 reduction and running costs is generally the case.

62

Figure 3-38 shows CO2 emissions in various countries. CO2 emissions from China and the United States are
very high. Meanwhile, CO2 emissions from Myanmar is so low as to be approximately 1/1,000 of CO2 emissions
in China,

Figure 3-38

CO2 emissions in the world originating from energy (2011)

CO2 emission in the world (Energy consumption base)

Others

South Africa

China

Australia
Brazil
Indonesia
Mexico

31.3billion ton

Saudi Arabia
Iran
Canada
South Korea

Japan

America
Russia

EU
India

27

countries
German
UK y
France

Italy

Source: Data cited from the website of the Ministry of the Environment

Table 3-8 CO2 emissions in 2011 (Numbers are in millions of t-CO2.)


Country

Emissions

China

7,999.6

United States

5,287.2

Japan

1,186.0

Myanmar

8.3

Source: Data prepared by the Study team on the basis of information


provided on the website of the Ministry of the Environment

63

Figure 3-39 and Table3-9 show CO2 emissions per capita in 2011 originating from energy. Emissions per capita
in Myanmar are approximately 1/100 of those in the United States.

Figure3-39 CO2 emissions per capita originating from energy as classified by country (2011)
CO2 emission per capita in the world (2011)

Average of the world


Qatar

Qatar

UAE
Australia
America
Saudi Arabia
Canada
South Korea
Russia
Japan
Germany
South Africa
England
Iran

Italy
Qatar
China
France
Qatar
Mexico
Qatar
Brazil
Qatar
Indonesia
Qatar
Qatar
India
Nigeria
Qatar
Qatar

Source: Data cited from the website of the Ministry of the Environment

Table3-9

CO2 emissions per capita in 2011 (Numbers are in millions of t-CO2.)


Country name

CO2 emissions per capita

China

5.92

United States

16.94

Japan

9.28

Myanmar

0.17

Source: Data prepared by the Study team on the basis of information


provided on the website of the Ministry of the Environment

64

Figure 3-40 shows changes in CO2 emissions originating from energy in major countries. Emissions undergo
significant increases in China, where emissions are the highest in the world. It is considered that in China,
emissions will increase in the future as well.

Figure 3-40 Changes in CO2 emissions originating from energy, as classified by major country

China
America
EU 27
India
Russia
Japan
German
Canada
England
Brazil
Italy
France
Spain

Source: Data cited from the website of the Ministry of the Environment

Although the amount of CO2 emissions in Myanmar is rather low compared to the other countries at
present, it is predicted the CO2 emissions will be increased according to the economic development in the
future. It is important to reduce the CO2 emissions in the world including Myanmar by introducing Clean
Coal Technology(CCT) from Japan.

65

7) Wastewater treatment facilities

Figure 3-41 Schematic of wastewater treatment facilities

Source: In-house information material of Chubu Electric Power Co., Inc.

Figure 3-41 shows wastewater treatment facilities in a coal-fired power plant. In these facilities, various types
of wastewater are generated. The properties of wastewater differ from type to type. Therefore, it is necessary to
carry out appropriate treatment depending on individual types of wastewater.

Human sewage from buildings: BOD and COD should be removed.

Desulfurization wastewater from desulfurization equipment:


Fluorine, metals, nitrogen, and COD should be removed

Start-up wastewater from the plant (wastewater containing chemicals):


Hydrazine and COD should be removed, and the wastewater thus treated should be reused.

Treatment of unsteady wastewater:


That type of cleaning wastewater etc, for relevant devices which comprise nitrogen contents should be
neutralized. The nitrogen contents should be flocculated and precipitated. The wastewater thus treated
should be reused.

Treatment of wastewater containing waste liquid:


That type of wastewater from water treatment equipment which does not comprise nitrogen contents
should be subjected to flocculation and precipitation, with the result that the wastewater thus treated
should be reused.
66

Those types of wastewater from oil tanks or various devices which contain oil:
Oil contents should be removed.

Surplus water in ash discarding places: SS should be removed, and pH values should be adjusted.

Rainwater in coal storage yards:


This rainwater should be used for purposes such as sprinkling water onto coal piles.

Figure 3-42shows an outline of the wastewater treatment system in the Hekinan Thermal Power Plant.
In power plants in Japan, various types of treatment are carried out to meet the wastewater criteria. With regard
to the structures of wastewater treatment facilities, various methods are introduced, such as the control of pH
values, removal of very small substances (SS: Suspended Solid), living organism treatment by using bacteria, and
treatment for removing nitrogen and phosphorus. Furthermore, with the aim of reducing the amount of water,
actions are taken to reuse treated wastewater. The configurations of treatment devices differ from plant to plant.
Therefore, detailed explanations of individual devices are omitted in this document.

Figure3-42 Wastewater systems in the Hekinan Thermal Power Plant

Source: In-house information material of Chubu Electric Power Co., Inc.

67

Table3-10 Wastewater criteria in the Hekinan Thermal Power Plant

Source: Data prepared by the study team on the basis of


the Wastewater Criteria of the Hekinan Thermal Power Plant

Table3-10 shows the wastewater criteria specified in the Pollution Control Agreements concluded by the
Hekinan Thermal Power Plant with the relevant local autonomous bodies. With regard to wastewater also,
coal-fired power plants are required to establish strict criteria similarly to the case of exhaust gas.

9) Sound insulation and vibration control measures


Next, noise and vibration prevention measures are shown below. Figure3-43 shows the sound insulation and
vibration control measures. In the Hekinan Thermal Power Plant, large-sized machines such as turbines, boilers,
transformers, and large-sized fans are installed inside of buildings, resulting in reduced noise. Insulation members
for absorbing and reducing sound are used in building walls.

Figure 3-43

68

Source: Data prepared by the study team


Table3-11

Vibration and noise criteria in the Hekinan Thermal Power Plant

Source: Data prepared by the study team


In the graph in Table 3-11, regulation values for vibrations in the Hekinan Thermal Power Plant are shown in
the upper column, and regulation values for noise in this power plant is shown in the lower column. The Hekinan
Thermal Power Plant is located in an area consisting of industrial zones and agricultural zones. The numbers of
residences in neighboring sites are low. Under these circumstances, agreements containing these strict criteria
were concluded with the relevant local autonomous bodies.
10) Coal scatter prevention measures
The coal scatter prevention equipment, which is a portion of the coal facilities, is shown below.
Figure 3-44 Wind shielding fence for preventing coal
Figure3-45 Coal scatter prevention by sprinkling
scatter
water onto a coal pile

69

Figure 3-46 Unloader

Figure3-47 Belt conveyor enclosed with a coal scatter


prevention cover

Source: Data prepared by the study team

Around the coal yard, a wind shielding fence for reducing wind speed is installed for the purpose of preventing
dust scatter. The shielding fence is designed in such a way that the fence height is higher than those of the coal
piles. Water is sprayed to the coal piles, the conveyor connection portions, the unloader, and the excavation
protons of the reclaimer, in an effort to prevent dust scatter. Dust scatter prevention measures are taken by means
of the following, among others; Covers are installed in the vertical elevator portion of the unloader and on the
conveyor.

11) Harbor facilities


a) Assumption of ships
General specifications of oceangoing ships used for the import of coal are shown in the Figure below. The full
load draft is 13 15 m. Therefore, it is necessary that the port of landing have a water depth of 16 m or more. As
shown in Figure3-48, in order to secure a water depth of 16 m or more in neighboring areas of this project site, it
becomes necessary for a jetty to protrude into the sea area, leading to increased construction cost.
In this project, it is assumed that wide-width, shallow-draft dedicated ships will be used for maritime
transportation of coal, thereby importing coal from Indonesia and Australia. Studies are made under the following
conditions.

Deadweight capacity: 80,000 DWT

Cargo handling time: 2 to 3 days/ship

Cargo handling frequency: 1 to 2 times/month

In the Hekinan Thermal Power Plant, the water depth near the pier is 14 m. Therefore, general large-sized
oceangoing ships cannot land. However, maritime transportation and landing of coal is carried out by means of
wide-width, shallow-draft dedicated ships.

70

Table 3-12 Typical coal ship specifications


Ship type

Deadweight capacity tonnage

Draft

(DWT)
Kamsarmax

82,000-ton type

14.5 m or so

Panamax (Pmax)

70,000-ton type

14.3 4 m or so

Handymax/Supramax/Ultramax

50,000-ton 64,000-ton type

Approximately 13 m

Source: Data prepared by the study team


Figure 3-48 Water depths in neighboring areas of Kyaikami

Source: Data prepared by the study team

Table3-13 Outline of a wide-width, shallow-draft dedicated ship


1

Deadweight capacity tonnage (DWT)

88,495

90,685

91,860

91,765

Load weight at a draft of 11.80 m

86,548

86,400

87,800

81,067

11.89

12.05

12.11

12.87

18.7

18.7

18.7

19.3

55,130

55,300

55,295

52,964

Full load draft (summertime)


Mold depth
Gross tonnage

Source: Data prepared by the study team

71

Figure3-49 External appearance view of wide-width, shallow-draft dedicated ship

Source: Data prepared by the study team

b) Pier facilities (Length of the pier)


Data which are based on the global wave numeric value prediction model GPV (GWM), and which cover a
period of 6 years from 2008 to 2013, were consolidated. Subsequently, wave heights, wave directions, and cycle
appearance frequencies around the candidate place for the thermal power plant were analyzed. As a consequence,
the properties of waves and wing conditions are confirmed.

(a) Target places


Four places, A to D, which are located around the candidate place, and in which GPD data can be obtained, are
taken as target places,
Shown below are GPV data extraction places.

72

Figure3-50 Points at which items of GPV data were extracted

A : N1600
E9730
B : N1530
E9730
C : N1530
E9700
D : N1600
E9700

Source: Data prepared by the study team


(b) Summary of the wave height incidence
The following table summarizes the wave height incidences at different points.

Table 3-14 Wave height incidences at different points


Incidence (%)

Wave height
(m)

Point A

Point B

Point C

Point D

0.00 - 1.00

61.6

59.0

58.0

60.3

1.00 - 2.00

32.1

32.0

32.3

33.1

2.00 - 3.00

5.6

7.9

8.4

5.9

3.00 - 4.00

0.8

1.1

1.2

0.8

0.1

0.1

4.00 -

Source: Data prepared by the study team

Significant differences in the incidence between points were not observed, with the incidence of wave heights
of 1.0 m or less being approximately 60% at all points.
To increase the availability factor of the coal unloading berth, the arrangement of breakwaters is considered.
Assuming that the rough wave height ratio is 0.5 in consideration of the shielding effect produced by the
breakwaters, the incidence of wave heights of 1.0 m or less is estimated at 90% or more.
Table 3-15 shows the estimated values of incidences of wave heights after the installation of breakwaters.

73

Table 3-15 Incidence of wave heights after the installation of breakwaters


Incidence (%)

Wave height
(m)

Point A

Point B

Point C

Point D

0.00 - 1.00

93.6

90.9

90.3

93.3

1.00 - 2.00

6.4

9.0

9.6

6.7

0.1

0.1

2.00 - 3.00
3.00 - 4.00

Source: Data prepared by the study team

(c) Summary of incidences of wave heights


The following figured show the scatter tables with a range of wave height and wave direction bins at each point
(wave rose). At every point, the frequency of the southwest wind is high with high wave heights. For this reason,
the off-shore breakwaters for this project will be designed in an arrangement that will prevent the impact of the
southwest wind.
Figure3-51. Wave Rose at point A

Figure3-52. Wave Rose at point B

60%

60%

40

40

20

20

20

40

60

20

01m

40

60

12m

23m

3m

01m

12m

23m

3m

Annual Wave Rose

Annual Wave Rose

Figure3-53. Wave Rose at point C

Fig3-54 Wave Rose at point D

60%

60%

40

40

20

20

20

40

60

20

01m

12m

40

60

23m

3m

01m

Annual Wave Rose

12m

23m

Annual Wave Rose

Source: Data prepared by the study team


74

3m

(d) Study of the port layout


Using the availability factor of the coal unloading berth calculated from the GPV data for the vicinity of the
candidate site as an index, the layout of the port auxiliary facilities of the thermal power station was studied.
(e) Conditions under which the study is made
Table 3-16 shows the conditions under which the study is made.
In the study, target ships, the depth of water of berth, and the berth length are given conditions, and the tide
level is that of the port of Yangon given in Material 1192 of the Port and Airport Research Institute: the on-site
survey of the damage due to the 2008 storm surge in the port of Yangon. The design wave height is defined
according to the wave height assumed to occur at a point with a depth of water of 17.0 m at which a breakwater is
to be installed.
Table 3-16 Conditions under which the study is made
Item

Value

Target ship

80,000 DWT

Depth of water of berth

h = 15.0m

Length of coal unloading berth

L = 350m
H.W.L. = 5.80m
L.W.L. = 0.70m

Tide level
Design wave height

H1/3 = 6.0m

Source: Data prepared by the study team

The study this time is based on calculations made by means of charts and given data, with no on-site data that
has been acquired through measurement. For this reason, accurate depths of water, conditions of soil, and
conditions of weather and oceanographic phenomena are not considered in the present study.
The study has been conducted under the following assumptions also:

All equipment and materials can be procured locally;

A yard and access to it can be secured;

A port of evacuation is nearby; and

Authorization and licensing are not considered.

(f) Selection of a layout


Three typical varieties of berths for unloading coal, a dredged anchorage type, an off-shore extending
breakwater type, and an off-shore extending berth plus off-shore breakwater type, were studied to select one of
them.

75

Figure3-55. Dredged anchorage


type

Figure3-56 Off-shore extending


breakwater type

Figure3-57 Off-shore extended berth


plus off-shore breakwater type

Source: Data prepared by the study team

a) Dredged anchorage type


Breakwater

Constructed as far as the point at which the water is deep, the breakwater protects sea routes near the
port entrance and the anchorage from the waves of the open sea and prevents the sea routes near the port
entrance and the anchorage from being buried in drift sand.
Dredging of mooring facilities and anchorages

The area of sea in front is dredged to establish sea routes and anchorages. Soil and sand from dredging
is used to prepare land in the rear or reclaim land from the sea.

From the breakwater (a sand control hedge) used also as a passage, a berth is constructed to prepare
places for ships to come alongside the berth.
Maintenance

To secure the depth of water below sea routes and anchorages, maintenance dredging is conducted
periodically.
Sedimentation due to drift sand and erosion occur at the base of the breakwater (a groin).

b) Off-shore extending breakwater type


Breakwater

Constructed as far as a point at which the water is deep, the breakwater protects places for ships to come
alongside the berth from the waves of the open sea.

Mooring facilities

From the breakwater used also as a passage, a berth is constructed to prepare places for ships to come
alongside it.
Maintenance

Sedimentation due to drift sand and erosion occur at the base of the breakwater.

c) Off-shore extended berth plus off-shore breakwater type


Breakwater

An off-shore breakwater (a detached breakwater) is constructed to protect places at which ships come
alongside the berth.
76

Mooring facilities

The berth is constructed as far as a point at which the water is deep to provide places at which ships
come alongside the berth.
Maintenance

With the approach trestle constructed with piles and hence not stopping the flow, no coastal deformation
due to drift sand occurs.

In this analysis, distance from the coast and (c) is fixed and subjected to construction cost comparisons for each
type. If a dredged anchorage type is selected, the two bridges are required, off-shore extended berth plus off-shore
breakwater type, in order to avoid the effects of waves, as compared with other types, and require long breakwater
from the fact that it is, off-shore extending breakwater type it can be seen that less construction cost compared to
other types.
Therefore, in this project, construction cost is preliminary estimated based on off-shore extending breakwater
type, using the chart in Mawlamyine suburbs area, distance from the coast line of up to a depth of (a) that can
dock coal carrier and assuming the distance required breakwater.
Figure3-58.

Assuming type

Source: Data prepared by the study team


In the next step of the feasibility study, it is recommended that more detailed surveys of the specific area for the
potential projects site be performed in terms of:
-

Depth of sea water due to the availability of old chart only at present

Area for the Project along the coast line due to the view of rocky area and limited hinterland at some area

77

(g) Outline design of port facilities (a. Off-shore extended berth plus breakwater type)

A) Off-shore breakwater (standard cross-sectional view)


According to the chart, the off-shore breakwater is located at a position at which the depth of water is 17m. It will be completed in a 2,150-m-long riprap sloping
breakwater.
Figure3-59 shows the standard cross-sectional view of an off-shore breakwater.

Figure3-59 Standard cross-sectional view of an off-shore breakwater

Upper
concrete

Sea side
d)

po
tra

Harbor side
Co

nc
ret

ea

e
tT

n
Co

te
cre

or
arm

nit

n
sto

rm
or

mo
r

t)

r
mo
Ar

Ar

32

un

it

sto

ne

(2

Foundation rubble 100 500kg

Source: Data prepared by the study team

78

(1

6t

(1

t)

Te
tra

po

d)

B) Approach trestle (Standard cross-sectional view)


Figure3-60 shows the standard cross-sectional view of the 3,500-m-long approach trestle.

Figure 3-60 Standard cross-sectional view of the approach trestle


(vertical pile trestle; average depth of water: 7.0 m)

Source: Data prepared by the study team

C) Coal unloading berth (Standard cross-sectional view)


The coal unloading berth shall be built in a vertical pile berth structure with a length of 350 m at a depth of
water of 15.0 m.
Figure 3-60 shows the standard cross-sectional view of the coal unloading berth.

Figure 3-60 Standard cross-sectional view of the coal unloading berth


(vertical pile trestle; average depth of water: 15.0 m)

Source: Data prepared by the study team

79

The items of data that will be needed to carry out detailed studies are shown below:
Boring data (soil conditions)
Sounding data (depth of water)
Weather and marine conditions data (tide, wave, and flow regime)
Market survey (prices of materials, etc.)
Target ships
Port facilities and installations (unloader specifications)
Availability factor required for the operation of facilities (calmness inside the port)
c) Other facilities required (tugboats, guard ships, oil fences, etc.)
In the coal unloading facilities, tugboats should be provided for coal transportation ships to turn round safely in
the anchorage. For safe navigation in the waters, guard ships to guide coal transportation ships should be provided
also. Oil fences are installed as a countermeasure against leakage that could occur at the time of unloading coal or
light oil, auxiliary fuel.

12) Coal unloading, storage, and transportation facilities (Coal Handling System)
(a) Conveyor systems
Coal transportation conveyors are roughly classified into a receiving system from the coal unloading berth to
the coal storage yard, a delivery system from the coal storage yard to the coal blending system, and a coal
feeding system from the coal blending system to the boiler coal banker.
In consideration of the kind of coal or of the storage period, a recycling system is provided, as required, by
which piles of coal are heaped up over again to prevent coal from heating. In addition, some plants assume an
addition of a direct feed system that feeds coal from a coal ship directly to the boiler.
Figure 3-62 shows a diagram of the coal unloading and transportation system at the time of the construction of
units 1 to 3 at the Hekinan Thermal Power Station, Chubu Electric Power Co., Inc.

Receiving system: The system running from the coal unloading berth to the coal storage yard.

Delivery system: The system from the coal storage yard to the coal blending system

Coal feed system: The system from the coal blending system to the boiler coal banker

Recycling system: The system by which heaps of coal are piled up over again in the coal storage yard

Direct feed system: The system to transport coal from coal transporting ships directly to the boiler (a system
that is used when accumulation and delivery inside the coal storage yard cannot be performed.)

80

Figure3-62

Conveyor systems

Source: Chubu Electric Power in-house material

The coal storage capacity of the Hekinan Thermal Power Station is designed to store an amount of coal of
680,000 tons that the power station equipped with three units of 700 MW each consumes for the duration of about
45 days. The total area of the coal storage yard is 460,000 m2, with the area of the coal storing portion being about
150,000 m2. The area required for a coal storage yard is determined in consideration of the heating value of the
coal used, the efficiencies of the power generating units, and the number of days of storage required, and other
factors. In this project, facilities are planned that can store an amount of coal of about 200,000 tons for 45 days on
the assumption that the coal equivalent to that used in the Hekinan Thermal Power Station is imported. It is
accordingly estimated that an area corresponding to one occupied by approximately two piles in the coal storage
yard of the Hekinan Thermal Power Station is needed.
A pile in the coal storage yard of the Hekinan Thermal Power Station is 47 m in width, 13 m in stowage height,
and about 550 m in the length of a stowed pile. On the basis of this example, the configuration and dimensions of
the coal unloading and transportation system in this project are assumed as shown in Figure3-59.

81

Figure3-63A plan for a coal unloading and transportation system


The cost is the lowest.
Coal mixing
building

Berth
Case 1

Approx. 500 m

With only one S/R, coal cannot be


Granulating
sent if itbuilding
fails.
Stack/reclaimer
(S/R)

Boiler
Cost: medium
Coal mixing
building

Berth

Coal can be sent if an S/R fails.


Case 2

Granulating
building
Approx. 250 m
Boiler
Approx. 350 450 m
Cost: large
Coal mixing
building

Berth

(1)

Case 3

A future
Granulating
building

one unit can


be

Approx. 500 m
Boiler
Approx. 600 700 m

addition of

accommodat
ed.

Source: Data prepared by the study team

Case 1 shows the lowest-cost system. With only one stack reclaimer (S/R), coal cannot be sent if it fails. In
addition, since the stack reclaimer is used for stacking onto a pile when coal is unloaded from a coal transportation
ship, a common stack reclaimer cannot send coal to the boiler. Stack reclaimers with a function of allowing a
given proportion of coal to flow downstream during stacking are available; it is desirable to adopt stack reclaimers
with the bypass function. Furthermore, with the yard conveyor also being in a single-line configuration in this
case, doubling the conveyor line in the coal transporting and delivery system to secure redundancy does not
enable coal transportation should the yard conveyor fail.
Case 2 is a plan to provide two stack reclaimers and two yard conveyors to secure the same amount of coal
storage as in Case 1 and the redundancy alike, with the reliability increasing.
Case 3 proposes a coal storage pile whose length is the same as that proposed in Case 1, doubling the amount of
82

coal storage. When the addition of units in the future is considered, this plan is preferable.
In advancing the project actually, Case 1 will be adopted to minimize the expenses when constructing one unit,
and as units are added, consideration will be given to the securing of the site and to the layout so that piles can be
added as in Case 3. Or when the plan for an addition of units in near future is decided definitely at the time of
constructing the first unit, it may be desirable to proceed with the construction according to the plan shown in
Case 3 from the beginning. This will require more expenses than Case 2 will do; with the equipment configuration
not differing from that in Case 2, therefore, the expenses will not increase substantially.

(b) Unloader
Figure3-64 shows a bucket elevator type unloader installed in the Hekinan Thermal Power Station. The bucket
elevator section of the unloader is enclosed with a cover to prevent dust particles from flying. Figure 3-65 shows a
bridge-shaped crane unloader (a glove bucket-type unloader).

Figure 3-64 Unloader (elevator-type)

Source: Chubu Electric Power in-house material

Figure3-65 Unloader (glove bucket-type)

SourceCited from the website of Hitachi Plant Mechanics Co., Ltd.

83

(c) Stacker reclaimer


Figure 3-66

Stacker reclaimer

Source: Internal reference of Chubu Electric Power

(d) Reclaimer
Figure3-67

Reclaimer

Source: Internal reference of Chubu Electric Power

(e) Stacker
Figure 3-68

Stacker

Source: Internal reference of Chubu Electric Power


84

In this project, usage of stackreclaimer was mentioned. It is recommended that stackreclaimer has a function of
by-pass system to enable to feed coal directly to the boiler from the berth.

(f) Coal blending system and coal screen


Figure 3-69 Full drawing of coal blending system and coal screen

Source: Internal reference of Chubu Electric Power

Coal blending portion (on right-side above):


for taking out 2 types of coal from hoppers and blend them on the belt conveyer
Coal screen portion (on left-side above):
for sorting out coal pieces of large sizes by applying vibrations and send them to a crusher

(g) Winds-intercepting fence


Fence made up of bent steel plates with punched-out holes (bent perforated plates) for reducing winds blowing
in a coal storage yard.

85

Figure 3-70 Winds-intercepting fence

Source: Internal reference of Chubu Electric Power


(h) Water sprinkler fire extinguisher
At Hekinan Thermal Power Station, water sprinkler fire extinguishers are installed in such a way that every part
of a coal pile can be sprinkled with more than 10 liters/min of water, which is the standard for installing fire
extinguishers stipulated in the Fire Protection Low.
Figure 3-71 Water sprinkler fire extinguisher

Source: Internal reference of Chubu Electric Power

86

13) Ash disposal facility


Figure 3-72 Ash disposal facility

Source: Internal reference of Chubu Electric Power

Coal-fired power plant produces a vast amount of ashes as a result of burning coal. Ashes here refer to powdery
fly ash captured by an electrical dust precipitator or the like, clinker ash produced by ash melted in high-burning
temperatures within a boiler, pyrite discharged from a mill for crushing coal pieces as a foreign substance and so
on.
Furthermore, a desulfurization device produces gypsum as a byproduct. To collect such materials efficiently,
appropriate designed handling system should be considered.
Shown in Figure3-72 is the ash handling system for units No. 4 & 5 in Hekinan Thermal Power Station.
The system is equipped with a subsystem for sorting ash based on its granularity (system for quality control of
coal ash). Small granular ash is recycled as a high valuable substance. As for transport of ash, the system is ready
for both land transport (using tank trucks) and sea transport. At units 4 & 5 in Hekinan Thermal Power Station
shown in the figure, all ashes are reused effectively. As for gypsum, the handling system for it is ready for both
land transport and sea transport as well.

14) Effective utilization of byproducts produced at coal-fired power plant


A coal-fired power plant produces a variety of byproducts such as gypsum, fly ash, clinker ash and so on. At
Hekinan Thermal Power Station, all byproducts are recycled using these respectively as a raw material for cement
and the like, a material for land reclamation and a material for sale as valuable. The thermal power station is
equipped with a device shown in Figure 3-75 for sorting out high-quality fly ash. Since there is a cement factory
in a nearby area in Mawlamyine, there is a favorable environment for the planned power plant to recycle the
87

byproduct.
When constructing a power plant, a survey should be carried out to identify effective ways of utilizing its
byproducts and carry out required equipment design for it based on this survey.

Figure3-73 Byproducts of coal-fired power generation

Source: Internal reference of Chubu Electric Power

Figure3-74

Status of effective utilization of byproducts at Hekinan Thermal Power Station


Sell
99
(10%)
Reclaim,
104
(11%)
,
48
(5%)

Clinker
90
(9%)
Annual amount of
by-product in 2013
[Thousand Ton]

Export
122,
(13%)

Fly ash
870
(91%)

Recycle
for cement
material,
583
(61%)

Source: Internal reference of Chubu Electric Power

<Fly ash (valuable ash>


This substance has superior properties as a mixing ingredient for cement such as 1. fine granularity, 2. light
weight and 3. enhancing effect on materials strength. Fly ash compliant with JIS* standards are used in the
88

following ways:
Table3-17 Example of effective use of fly ash
Concrete production field

Concrete for dams, secondary products (blocks, etc.)

Civil engineering field

Spraying material for tunnel walls, filler for asphalt, etc.

Building construction field

Material for exterior walls, floors, etc.

Others

Mixing ingredient for plastic

* JIS: Japanese Industrial Standard


Source: Data prepared by the study team

<Clinker ash>
This porous substance has superior properties as a material for improving soil quality such as 1. light weight, 2.
water retention capability, 3. high permeability and is used in the following ways:

Table3-18 Example of effective use of clinker ash


Civil engineering field

Material for lower layers of roadbed, anti-freeze material, land


improvement material, light-weight filler, etc.

Agriculture field

Farm field improvement material, raw material for culture soil,


fertilizer, lawn curing material

Others

Wastewater purifying material, etc.


Source: Data prepared by the study team

89

Figure 3-75 System for quality control of coal ash

Source: Internal reference of Chubu Electric Power

90

(7) Power transmission and substation facilities


When an access to existing power grids is considered, Mawlamyine 230 kV substation exists as the one closest
to the planned power plant. This substations system voltage is 230 kV class level. Therefore, access to a power
grid through this substation and impacts of the planned power plant on the 230 kV power grid were reviewed.

a) Existing power grid plan


According to the current 5-year plan of the Myanma Electric Power Enterprise (MEPE), Mon State, in which
Mawlamyine is located, is slated for enhancement of 66 kV power grids, but there is no immediate plan for
enhancing trunk power grids for 500 kV and 230 kV.

Table3-19
State/region

Five-year plan for transmission and substation enhancement


Transmission line [mile]

Substation [MVA]

500kV

230kV

132kV

66kV

500kV

230kV

132kV

66kV

Mon

91

100

Kayin

80

39

200

10

Tanintharyi

142

200

20

Bago

167

366

1000

Yangon

135

900

Source: Ministry of Electric Power

According to the power transmission line expansion plan up to fiscal 2015 of MoEP, installation of 230 kV
transmission lines between Tathon and Mawlamyine is planned. If this plan is realized, the power grid connections
between Yangon, the load center in Myanmar and Mawlamyine, an entry point to the Indochina peninsula will be
strengthened with the 230 kV transmission lines.
Other than this plan, development of a group of hydropower plants in neighboring regions to Mon State is
planned. Contingent on this plan, access to the existing power grid via Tathon Substation from the hydropower
plants is planned (see Figure3-76).

Substation
(start point)
Tathon

Table 3-20 Power transmission line expansion plan


Substation
Voltage Conductor
(end point)
Mawlamyine
230
Single
Source: Ministry of Electric Power (2014)

91

Distance
Miles(km)
50 (80.5)

Figure 3-76 Power grid development plan


Existing power system ant planning up to 2020
(Mawlamyine and vicinity inc. Yangon area)

Source: Ministry of Electric Power (2014)

b) Access to power grid


Two sets of 230 kV power transmission lines should newly be installed from MEPEs Mawlamyine substation
in the vicinity of the project site to connect up with the planned power station.

92

Figure 3-77
(Wire type: 605MCM (Duck) 2 conductors)
Two 230kV transmission lines to
be newly installed

Tathon, etc.

Mawlamyine Substation
230kV
Two 230 kW power outlets to be newly
installed
230kV

740MVA
Main transformer

Start-up
transformer
6.6kV

To
distribution
board

Project site

Source: Compiled by survey delegation

c) Power grid analysis


Mawlamyine, the capital city of Mon State, is located 150 km away, in straight line distance, toward the east
from Yangon. There lies, however, a bay between the two, and these two cities are separated by 300 km of an
overland route distance (with the routes forming the two sides of an equilateral triangle geographically). The city
is at the root of the Indochina peninsula and in the front line for extending power trunk lines toward the southern
part of Myanmar.
Therefore, based on the power grid development plan shown in Figure 3-76, the following were established as
the conditions for reviewing access to the existing power grid from the planned power plant.

Supplying of high-quality electric power to Mon State and its neighboring states/regions, specifically to
Tanintharyi and Kayin

Supplying of power to Yangon Region, a huge center of power consumption, and to Bago State en route to
Yangon for the transmission of power

93

Figure 3-78 Schematic diagram of power supply from planned power plant

Bago

Tanintharyi
Source: Compiled by survey delegation
Detailed analysis
i) Forecasted peak power demand
Growth rates of power demand for the respective regions included in the power grid analysis here are as shown
below:
Table3-21 Region-wise power demand growth rates forecasted by MEPE
Forecasted growth rate of power demand

Growth rate of power demand

[%]

in 2012 [%]

State/region
2015

2020

2025

2030

GDP

Mon

38

11

11

11

9.3

1.0

Kayin

56

11

10.6

1.2

Tanintharyi

20

8.8

1.3

Bago

12

11

11

11

10.3

1.1

Yangon

15

15

15

15

9.5

1.2

Source: Reference of Myanma Electric Power Enterprise


Based on these figures, forecasted peak power demand for the respective regions/states is calculated as follows:
Table 3-22 Forecasted power demand by region (peak power)
Peak power [MW]
Region/state

2012

Forecast
2020

2030

Mon

45

116

418

Kayin

13

70

165

Tanintharyi

52

101

290

Bago

131

180

646

Yangon

742

2,800

8,209

1,874

5,020

14,542

Nationwide

Source: Compiled by survey delegation


94

ii) Identification of power grid to be analyzed


Power grid to be analyzed and preconditions of analysis concerning power demand and supply were as
described below.
Power grid
The 230 kV power grid interval between the Kamarnat substation, which would be connected to the planned
power plant and the Mawlamyine substation through which the power plants to be analyzed access the power grid
was subjected to a detailed analysis. Since a 500 kV line is planned to be interconnected with the grid at the
Kamarnat substation as shown in Figure 3-72, Therefore, the area further than the Kamarnat substation in the
Yangon region was not cared in this analysis in consideration with assumption of strong stability.
Demand
The forecasted power demand by region (peak power) shown in Table 3-22 was distributed to the key 230 kV
substations described above. In the analysis, the forecasted peak power figures for 2020 (closest to the earliest
implementation timing for the planned power plant subject to analysis) based on the conditions for reviewing
access to the existing power grid from the planned power plant above.
Supply (capability)
The following conditions were set to check the capabilities of the power generation plants subjected to the
analysis.

Exclusion of hydropower stations in Hyatkyi and Beelin shown in Figure3-75 (in consideration of lead
time for the development of a hydropower station, these were excluded).

Suspended operation of the existing gas-fired thermal power plant in Tathon for ciritical scene in the
analysis

Full and constant output operation for the power generation plants subjected to the analysis, which is
supplemented by the power generated solely at the planned power station

95

Forecasted peak power figures for the power grid subjected to the analysis and those at the respective key 230
kV substations are shown in Figure 3-79.

Figure 3-79

Analyzed power grid and forecasted peak demand figures

Kamarnat

Sittaung

40
Hatkyi
5

1360MW

Tathon

Beelin

Tathon
98

51MW

Potential

280MW
Mawlamyine
Mawlamyaine

13

600MW

Myeik
Myeik

46
91

Kawkareik

Source: Compiled by survey delegation

Elements of 230 kV transmission wires and voltage adjustment range at 230 kV are as follows:

Table3-23
Wire type

Amperage

2Duck 605 MCM (single)

1,124

Heat capacity

Heat capacity [MW]

[MWA]

(PF-0.85)

447

380

Source: Compiled by survey delegation

Electricity class for


analysis
230 kV

Table3-24
Voltage adjustment range for
analysis
5% (11.5 kV)

Current operational voltage


adjustment range
12% (28 kV)

Source: Compiled by survey delegation

iii) Result
Analysis results are shown in Figure 3-80. It is assumed for the analysis that an additional transmission line is
installed over the interval between the Mawlamyine substation and the Tathon substation to supply electricity
generated at the planned power plant. By using a reactive power regulator additionally to reduce reactive power
96

losses created when transmitting electricity over long-distance wires, it is possible to supply electricity to the
Myeik substation, which is a hub to supply power to the southern part of the Indochina peninsula and to the
Kamaranat substation, which controls supply of electricity to the Bago and Yangon regions.
Voltages are all within the adjustment range except for the 216 kV (94%) result for the bus line in the Kamarnat
substation. Here, the voltage at this substation can be considered to be affected by the reduction of the part of the
analyzed power grid further than the planned power station. It is expected that the voltage result in a more detailed
analysis will be within the adjustment range.

Figure3-80

Analysis result (for forecasted power grid in 2020)

Source: Compiled by survey delegation

97

(8) Others
Facilities for coexistence with local communities

Figure 3-81

Facilities for coexistence with local communities

Source: Internal reference of Chubu Electric Power

Shown in Figure 3-81 are facilities built by Hekinan Thermal Power Station for coexistence with local
communities. These are part of our initiatives for gaining understanding of local residents by providing
information on coal-fired thermal power plants to them at these facilities.

Flower garden in a park open to local residents (top right)

Public relations hall in front and flower garden and wild bird park in back (top left)

Fishing park constructed around a water discharge channel and water discharge area (open to local residents)
(bottom)

98

Figure 3-82

Example of public road and facility construction

Source: Internal reference of Chubu Electric Power

Construction of a power plant brings a lot of benefits to local governments and communities:

Increased tax revenues

Implementation of public roads and facilities

Increased numbers of restaurants and lodging facilities

Increase employment opportunities

To facilitate the construction and operation of a power plant, it is important to coexist with local communities
along with keeping up proper operation and maintenance of it by establishing appropriate environmental standards
and installing appropriate equipment.

99

Chapter 4 Evaluation of Environmental and Social Impacts


(1) Analysis of the environmental and social conditions at present
1) Analysis of Present Condition

a) Natural Condition
a. Topography and Geographical Features
Mon State is situated on the mouth of Sittaung River. It is surrounded by Bago Division in the North, Kayin
State in the East, Thailand and Tanintharyi Division in the South and the Andaman Sea and Gulf of Martaban in
the West. Thanbyuzayat Township is located between north latitudes 1558'N and 16 20'N and 9715' E and 97
30'E. Thanbyuzayat Township has an area of 823.62 km (318 square miles) and it stretches from Wagaru Creek in
the north and Htinyu Creek in the south.
Thanbyuzayat Township is located around 30 m (100 ft) in average above sea level according to information
from Thanbyuzayat General Administration Department (GAD) in 2014. Geographically, Thanbyuzayat Township
extends north to south along the foothill of Taungngyo Range in the east and coastal region in the west.
Taungngyo Range lies about 2 miles from Thanbyuzayat town and it has an elevation range of 100 m to 650 m.
Mawlamyine University research thesis about salt industry of Thanbyuzayat Township in 19951 cited that the
eastern hilly region, Taungngyo area occupies about 40% of the township area. The flat plains occupy 60% of the
entire township area and lie between Taungngyo Range and the Andaman Sea in the west. Apart from Taungngyo
Range, there exists hills in the north and major hills are Sin-Taung (287 m), Yesat-Taung (213 m), Dola-Taung
(186 m), Kayinthaung-Taung (145 m), Meinbala-Taung (113 m) and Mankasu-Taung (107 m) respectively. Other
hillocks are Wagaru-Taung, Kanyin-Taung, Ingyin-Taung, Sundaw-Taung and Yathae-Taung. The western coastal
plain of the southern part of the Township is usually below 30 m above sea level, except for the outcrop of
Thabutaw-Taung of which height is 108 m.
The eastern part of the township lies on a steep slope area covered with forests. Between these hill slopes and
sea coast, there are stretches of agricultural lands for fruits, rubber and paddy cultivations. According to the
available information1, crop lands occupy near the coastal areas below 3 m above sea level and rubber plantations
occupy between 30 m and 150 m above sea level.

b) Geology and Soil


1. Geology
According to the Geology Map of Myanmar in Thanbyuzayat Township (), a wide expanse of paddy field is
composed of Holocene Alluvium (Q) and Pleistocene Older Alluvium & Gravel (Q). These alluviums include
1

Source: Salt Industry of Thanbyuzayat Township, Thesis report, Cho Cho Mya,1995, University of Mawlamyine

100

fertile materials deposited by running water. The Taungnyo Range consists of old hard rocks, Unnumbered
Granites (g), Carboniferous Taungnyo Series, and Paleozoic Mergui Series (P z-). Beaches and swamps are
found at the coastal line. In such area the old hard rocks, Unnumbered Granites (g) are found near Kaikkami
Town.
Figure 4-1 Geology Map of Thanbyuzayat Township

Source: Agricultural Geography of Thanbyuzayat Township, Universities Research Journal 2012, Vol. 5, No. 9
2. Soil
According to FAO classification, main soil in Thanbyuzayat Township is categorized as Gleysol ().
Figure 4-2 Geographical Distribution of 10 Dominant Soil Types in Myanmar

Source: FAO/NRL from Harmonized World Soil Database (HWSD) FAO


Agricultural Geography of Thanbyuzayat Township provides more detail soil classification of Thanbyuzayat
Township ().There are six main soil types in Thanbyuzayat Township:
1. Alluvial Soils (Fluvisol),
2. Gley & Gley Swampy Soils (Gleysol),
3. Yellow Brown Forest Soils (Xanthic Ferralsol),
101

4. Red Brown Forest Soils (Rhodic Ferrosol),


5. Beach Sands (Arenosol) and
6. Swamp Soils(Gley-Gleysol).
Fluvisols are found in the Wakharu Creek plain in the north-western part of the township. They dominate in
Hnitkai,Padangan, Kyonkadat, Taunghpalu and Wagru village tracts. They have the texture of silty and clay loam
and are suitable for paddy cultivation. Gleysols usually contain large amount of salts which dominate near the
flood plains of small creeks with occasional tidal floods and are found from Set Se Village Tract in the North to
Anin Village Tract to the South. Xanthic Ferrasol and Rhodic Ferrasol dominate widely on the mountain slope in
the eastern part of the township and are used for tree crops and fruit gardens. According to the land use
classification, they are classified as rubber land of good productivity and occupy about 40 percent of the total area
of the township. Arenosol and Gley-Gleysol are limited at the coastal areas and not important for agriculture.
Figure 4-3 Soil Map of Thanbyuzayat Township

Source: Agricultural Geography of Thanbyuzayat Township -Universities Research Journal 2012, Vol. 5, No. 9

3. Hydrology
In the northern part of Mon State, Sittaung River flows into the Gulf of Mottama (Martaban). Thanlwin River
which is one of the major river in Myanmar also passes through the state and flows into the Gulf of Mottama.
Most of other rivers and creeks which flow through the state flow into the Gulf of Mottama. Thanbyuzayat
Township is one of the area in the state that has many creeks flowing from east to west. Most of the creeks start
from the easterly Thaungnyo hill, and flow into the sea in westerly direction. The most important creek is the
Wakharu Creek which forms part of the border with Mudon Township and flows into the sea near north of
Kyaikkami. Other creeks are Karupi Creek (23 km) Waekalaung Creek (8 km), Kotlay Creek, Htinyu Creek, Anin
Creek (19 km), and Thabyae Creek (21 km). These creeks are useful for transportation and salt pans are found
along the creeks1. Major rivers and creeks which flow in Thanbyuzayat Township is described in .
1

Source: Salt Industry of Thanbyuzayat Township, Thesis report, Cho Cho Mya,1995, University of Mawlamyine

102

There is not much information about ground water for the Thanbyuzayat Township. Domestic water sources in
general rural areas in Mon States are natural streams, groundwater, springs and/or the rain-fed ponds.
Figure 4-4 Major Rivers in Thanbyuzayat Township

Source: Modified map based on Township map from Thanbyuzayat GAD

4. Meteorology
Thanbuyzayat Township receives tropical monsoon climate, with warm temperature and large amount of rainfall.
There is no meteorological station existing in Thanbuyzayat Township, thus meteorological data of Mawlamyine
Township, which is located about 40 mile north of Thanbuyzayat Township are presented in . Mean temperature
ranges from approximately 22 oC to 32 oC throughout the year, with relative humidity of approximately 77%.
Average annual rainfall during 2001 to 2010 is 5,161 mm but there are certain fluctuations in the rainfall year by
year. According to the meteorological data from Thanbyuzayat GAD, in 2013 annual rainfall amount was 5,845
mm. In the Thanbyuzayat region, the coldest temperature observed in January 2013 was 16.8C. In April and May,
highest monthly mean temperature was found, of which value was 35C.

103

Table 4-1 Meteorological Information of Mawlamyine Township

Item

2001-2010

1981-2010 Average*

Annual Rainfall (mm)


Mean Maximum
Temperature (C)
Mean Minimum
Temperature (C)
Mean Relative
Humidity (%)

Average**

2010**

2013***

4,995

5,161

3,084

5,845

31.5

32.2

33.3

33.56

22.3

22.6

23.2

20.13

77.2

76.8

Source: * Universities Research Journal 2012, Vol. 5, No. 9


**Statistical Yearbook 2011 and
***Basic regional information, Thanbyuzayat Township GAD, 2014
and indicate the mean climatic factors based on 20 year records from 1981 to 2010. The lowest monthly mean
temperature is observed in January, of which value was24.3C. The hottest months were April and May. The
monthly mean temperatures of these months were 29.9C and 28.2C respectively. Main rainy season was from
May to September, with peak rain days in June, July, August and September. The mean monthly rainfalls during
these months were 969 mm, 1,165 mm, 1,219 mm, and 673 mm respectively. The amount of rainfall during the
hottest months, April and May, was 58 mm and 641 mm, respectively.
Figure4-5 Month-wise Temperature in Mawlamyine (Average of 1981 to 2010)

TEMPERATURE (C)

40
Minimum
Temp

35
30
25
20
15
10
JAN

FEB MAR APR MAY JUN

JUL AUG SEP

OCT NOV DEC

Source: Modified from Agricultural Geography of Thanbyuzayat Township, Universities Research Journal 2012, Vol.5,
No.9

104

Figure 4-6 Month-wise Rainfall and Rainy Days in Mawlamyine (Average of 1981 to 2010)

30

1200
1000

25

Precipitation
Rainy

20

Rainy Days

Precipitation (mm)

1400

800

15

600

10

400
200

0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Source: Modified from Agricultural Geography of Thanbyuzayat Township, Universities Research Journal 2012, Vol.5,
No.9

5. Natural Disasters
Myanmar is vulnerable to a wide range of hazards, including floods, cyclones, earthquakes, landslides and
tsunamis. The frequency for medium to large-scale natural disasters to occur every couple of years is high,
according to historical data. For the Southeast Myanmar, flooding has affected a large area including in Mon
States.
Major natural disasters from 2008 to 2012 are summarized in .

Table 4-2 Major Natural Disasters in Myanmar

Major Natural
Disaster

Event

May 2008 (Cyclone Nargis): Cyclone Nargis left some 140,000 people dead and missing
in the Ayeyarwady Delta region. An estimated 2.4 million people lost their homes and
livelihoods.
June 2010 (Floods in northern Rakhine State): The floods killed 68 people and affected
June 2010
29,000 families. Over 800 houses were completely destroyed
October 2010 (Cyclone Giri): At least 45 people were killed, 100,000 people became
homeless and some 260,000 people were affected. Over 20,300 houses, 17,500 acres of
October 2010
agricultural land and nearly 50,000 acres of aquaculture ponds were damaged by the
Cyclone Giri.
March 2011 (6.8 Earthquake in Shan State): Over 18,000 people were affected. At least 74
March 2011
people were killed and 125 injured. Over 3,000 people became homeless.
October 2011 (Floods in Magway Region): Nearly 30,000 people were affected to varying
October 2011
degree. Over 3,500 houses and some 5,400 acres of croplands were destroyed.
August 2012 (Floods across Myanmar): The floods in different states and regions
displaced some 86,000 people and affected over 287,000 people. Ayeyarwady Region was
August 2012
the worst affected with some 48,000 people displaced. Over 136,000 acres of farmland,
houses, roads and bridges were damaged.
November 2012 (6.8 Earthquake in northern Myanmar): At least 16 people were killed and
November 2012
52 injured, with over 400 houses, 65 schools and some 100 religious building damaged.
Source: Myanmar Natural Disaster 2012, OCHA (Office for the Coordination of Humanitarian Affairs)
May 2008

Detail information for natural disasters in Thanbyuzayat Township was not available but describes major
disasters occurred in the township during FY2013.
105

Table 4-3

No

Major Disasters Recorded in Thanbyuzayat Township (FY2013)

Name of Disaster

Occurred Date

Died/ Lost

Damaged

Loss of Value

People List

Building

(Kyats

Numbers

Million)

Kyaikkami Town (gale)

23.8.2013

55 Household

6,648,000

Pa Nga Village (fire)

21.1.2014

4 Household

1,657,500

Source: Thanbyuzayat Township, GAD


6. Oceanography
In Mawlamyine area, tide stations are located in Kyaikkami and Mawlamyine town. Tidal information recorded
in these two locations for 2010 are described in . Average difference between high tide and low tide is
approximately 4.5 m per year for Kyaikkami and 3 m per year for Mawlamyin station respectively.
Figure 4-7

Average monthly tide level at Kyaikkami (KKM) and Mawlamyine (MLM) in 2010

6
Tide level (m)

5
4
3
2
1
0
-1

Jan

Feb

Mar

Apr

May Jun

High tide (KKM)


High tide (MML)

Jul

Aug

Sep

Oct

Nov

Dec

Low tide (KKM)


Low tide (MML)

Source: Mawlamyine Port Authority

7. Forest Areas and Protected Areas


a. Forest Areas
Total land area of Mon State is 4,748 square mile (12,297 km2) and 901.88 square mile (2,336 km2) is designated
as Forest Area by the definition in the Forest Law. Among the forest area in the State, 832.32 square mile (2,154
km2) is Reserved Forest and Protected Public Forest, and 69.56 square mile (181 km2) is Protected Area as shown
in .

106

Table 4-4

Forest Area Status in Mon State


Forest Area (square mile)

Total Land Area


Area

Year

Reserved Forest and

Protected Area

Protected Public Forest Area

System

(square mile)

Total

2006-2007

261,228

61,354.52

10,275.52

71,630.04

2007-2008

261,228

62,489.38

10,275.52

72,764.9

2008-2009

261,228

62,801.89

10,275.52

73,077.41

2009-2010

261,228

63,048.86

10,275.53

73,324.39

20010-2011

261,228

62,748.95

14,631.17

77,380.12

Union

100

24

5.6

29.6

2006-2007

4,748

838.23

69.56

907.79

2007-2008

4,748

838.23

69.56

907.79

Mon

2008-2009

4,748

837.85

69.56

907.41

State

2009-2010

4,748

837.84

69.56

907.4

20010-2011

4,748

832.32

69.56

901.88

17.5

1.5

100

19

Source: Statistical Yearbook 2011

In Thanbyuzayat Township, there is one Reserved Forest namely Htinyu Reserved Forest which is located above
the Htinyu creek. It was established in 1920 with total area of 1,741 acres (705 ha) as shown in . According to the
report of Thabyuzayat Township Forest Department2, reserved forest area in township are converted into rubber
plantation based on 30-year concession agreed between the Forest Department and developers in 1995. Land use
inside the Htinyu Reserved Forest is rubber plantation area with about 1,580 acres (639 ha), paddy cultivation area
with about 13 acres (5 ha), the area for religious purpose with 4 acres (2 ha), and other purpose area with 144
acres (58 ha). Based on information collected up to the end of November 2014, there seems to be no Reserved
Forest and Protected Public Forest existing in the vicinity of the Project candidate sites.

Report on Forestry related information and work done 2014 October

107

Figure 4-8

Reserved Forest in Thanbyuzayat Township

Source: Modified map based on Township map from Thanbyuzayat GAD

b. Protected Areas
According to Forest Department, 43 protected areas exist in Myanmar. Thirty-five sites were designated from
1918 to 2010. Eight additional sites proposed from 1997 to 2008 are still under examination. The 35 designated
protected areas cover approximately 42,000 km of land, representing 6.2% of the total country area. In case of
establishment of eight additional protected areas, proposed from 2001 to 2008, the area would increase 7,400 km
(1.1%), and the total area would be 49,500 km,representing 7.3% of the total land area. Two protected areas were
notified in the Mon State. Their descriptions are provided in . No protected areas are designated in Thanbyuzayat
Township.

108

Table 4-5 Descriptions of Protected Areas Status in Mon State


Name of Wildlife

Outline

Sanctuary

- Established year 1942 (Re-notified in 2002 Notification No. 23/2002(15-3-2002)


- Area: 23.93 km2(9.24 sq. mile)
KelathaWildlife

- Major forest types: Evergreen forest, Hill forest

Sanctuary

- Key Fauna: Samber, Barking deer, Wildboar, Avifauna


- Objectives: To conserve rare wildlife and associated habitats
- Protected status: Managed by BilinTownship Forest Department
- Established year: 2001 (Protected Area; Notification No. 37/2001(6-7-2001))
- Area:156.23km2(60.32sq. mile)
- Major forest types: Evergreen forest, Hill forest

Kyaikhtiyoe

- Key Fauna: Goral, Gaur, Sambar, Barking deer, Macque

Wildlife

- Objectives: To maintain green environment of the Kyaikhtiyoe pagoda, alegendary

Sanctuary

and national heritage of Myanmar and To conserve rare wildlife and associated
habitats.
- Protected status: Managed by Park Warden Office, Nature and Wildlife

Conservation Division, Forest Department


Source: Letter from Planning and Statistics Department, Ministry of Environmental Conservation and Forestry
dated on April 23, 2013

c. Flora, Fauna and Biodiversity


Mawlamyine District 10-Year Forest Management Plan prepared by the Forest Department describes major
species of flora and fauna identified in the district. This information, as shown in and , can be used as a
reference for possible fauna and flora species which may exist in the Project candidate sites . Total of 85 tree
species 10 bamboo species, 2 grass species and 7 rattan species were recorded in Mawlamyine District. According
to categories in IUCN Red List, 1 of critically endangered (CR) species, 2 of endangered (EN) species and 1 of
vulnerable (VU) species were found in the flora list of Mawlamyine District. As major terrestrial flora species in
Mawlamyine District, 7 of mammals, 11 of bird species and 26 of bird species were recorded as shown in Table
4-7. Protected animals in Mawlamyine District are listed in . All of the protected animals listed are categorized by
IUCN Red List, of which classification are 7 of endangered species, 3 of vulnerable species and 1 of nearly
threatened species.

109

Table 4-6 Major Flora Species in Mawlamyine District

No

Scientific Name

Local Name

Family Name

IUCN
List

Plants
1.
2.

Tectona grandis
Dipterocarpus turbinatus/
Dipterocarpus alatus

Kyun

Lamiaceae

Ka-nyin

Dipterocarpaceae

NE
CR /
EN

3.

Pentace burmanica

Ka-shit

Malvaceae

NE

4.

Erythrina suberosa

Ka-thit

Fabaceae

NE

5.

Albizia lebbek

Kok-ko

Fabaceae

NE

6.

Salmalia anceps

Kok-he

Malvaceae

NE

7.

Xylocarpus moluccensis

Kya-na

Meliaceae

LC

8.

Taxotrophis zeylanica

Kyant-sa

Meliaceae

LC

9.

Schleichera oleosa

Gyo

Sapindaceae

NE

10.

Hevea brasiliensis

Euphorbiaceae

NE

11.

Vitex pubescens

Kyetyo

Lamiaceae

NE

12.

Barringtonia acutangula

Kyi

Lecythidaceae

NE

13.

Premna pyramidata

Lamiaceae

NE

14.

Hymenodictyon excelsum

Khu-than

Rubiaceae

NE

15.

Garuga pinnata

Chin-yok

Burseraceae

NE

16.

Spondias mangifera

Gwe

Anacardiaceae

NE

17.

Albizia procera

Sit

Fabaceae

NE

18.

Dillenia pentagyna

Zin-Byun

Dilleniaceae

NE

19.

Ficus glaberrima

Nyaung

Moraceae

NE

20.

Euphorbia neriifolia

Ta-zaung

Euphorbiaceae

NE

21.

Excoecaria agallocha

Kayaw (Tayaw)

Euphorbiaceae

LC

22.

Madhuca longifolia

Ta-laing-gaung

Sapotaceae

NE

23.

Pterospermum acerifolium

Taung-phet-wun

Malvaceae

NE

24.

Decaspermum paniculatum

Taung-thabye

Myrtaceae

NE

25.

Swintonia floribunda

Taung-thayet

Anacardiaceae

NE

26.

Ficus glabella

Taung-tha-phan

Moraceae

NE

27.

Diospyros burmanica

Te

Ebenaceae

NE

28.

Terminalia tomentosa

Tauk-kyan

Combretaceae

NE

29.

Vitex glabrata

Tauk-sha

Lamiaceae

NE

30.

Mitragyna parvifolia

Hthein

Rubiaceae

NE

31.

Bombax insigne

Didu

Malvaceae

NE

Rubber
(Kyetpaung)

Kyun-nalin
(Kyun-bo)

110

Remark

No

Scientific Name

Local Name

Family Name

IUCN
List

32.

Durio zibethinus

Du-yin

Malvaceae

NE

33.

Kydia calycina

Dwa-bok

Malvaceae

NE

34.

Eriolaena candollei

Dwa-ni

Malvaceae

NE

35.

Pterospermum semisagittatum

Na-gye

Malvaceae

NE

36.

Lannea coromandelica

Na-be

Anacardiaceae

NE

37.

Flacourtia cataphracta

Na-ywe

Salicaceae

NE

38.

Adina cordifolia

Hnaw

Rubiaceae

NE

39.

Heritiera

fomes

/Heritiera

littoralis/ Heritiera burmensis

EN
Pinle-kanazo

Malvaceae

/LC
NE

40.

Casuarina equisetifolia

Pinle-kabwe

Casuarinaceae

NE

41.

Xylocarpus gangeticus

Pinle-on

Miliaceae

LC

42.

Palaquium polyanthum

Peinne-bo

Sapotaceae

NE

43.

Xylia xylocarpa

Pyin-ka-do

Fabaceae

NE

44.

Lagerstroemia speciose

Pyin-ma

Lythraceae

NE

45.

Holoptelea integrifolia

Myauk-seik

Ulmaceae

NE

46.

Vitex peduncularis

Pet-lezin

Lamiaceae

NE

47.

Heterophragma adenophylla

Phet-than

Bignoniaceae

NE

48.

Berrya cordifolia

Petwun

Malvaceae

NE

49.

Terminalia chebula

Phan-ga

Combretaceae

NE

50.

Rhizophora mucronata

Byu-chidauk

Rhizophoraceae

LC

51.

Bruguiera conjugate

Byu-u-talon

Rhizophoraceae

NE

52.

Mitragyna rotundifolia

Bin-ga

Rubiaceae

NE

53.

Careya arborea

Bambwe

Lecythidaceae

NE

54.

Dalbergia ovate

Madama

Leguminosae

LC

55.

Acrocarpus fraxinifolius

Mayanin

Fabaceae

NE

56.

Markhamia stipulata

Ma-hlwa

Bignoniaceae

NE

57.

Anthocephalus cadamba

Ma-u-let-tan-she

Rubiaceae

NE

58.

Garcinia mangostana

Min-gut

Clusiaceae

NE

59.

Lophopetalum wallichii

Mone-daing

Celastraceae

NE

60.

Microcos nervosa

Mya-ya

Malvaceae

NE

61.

Homalium tomentosum

Myauk-chaw

Salicaceae

NE

62.

Duabanga grandiflora

Myauk-ngo

Lythraceae

NE

63.

Dalbergia kerrii

Yin-zat

Leguminosae

NE

64.

Anogeissus acuminate

Yone

Combretaceae

NE

65.

Bombax ceiba

Lat-pan

Malvaceae

NE

111

Remark

No

Scientific Name

Local Name

Family Name

IUCN

66.

Terminalia pyrifolia

Lein

Combretaceae

NE

67.

Lagerstroemia tomentosa

Leza

Lythraceae

NE

68.

Firmiana colorata

Wet-shaw

Malvaceae

NE

69.

Stereospermum personatum

Malvaceae

NE

70.

Eugenia mangifolia

Tha-bye

Fabaceae

NE

71.

Albizia lucidior

Than-that

Fabaceae

NE

Thaw-ka

Fabaceae

NE

72.

Saraca

indica

/Saraca

lobbiana

Thakut-pho
(Than-de)

73.

Croton oblongifolius

Thetyin-gyi

Euphorbiaceae

NE

74.

Hopea griffithii

Thin-gan

Dipterocarpaceae

VU

75.

Millettia pendula

Thin-win

Fabaceae

NE

76.

Sideroxylon burmanicum

Thit-cho

Sapotaceae

NE

77.

Terminalia belerica

Thit-seint

Combretaceae

NE

78.

Sandoricum koetjape

Thit-to

Meliaceae

NE

79.

Millettia brandisiana

Thit-pagan

Fabaceae

NE

80.

Dalbergia kurzii

Thit-pok

Leguminosae

LC

81.

Dipterocarpus tuberculatus

In

Dipterocarpaceae

LC

82.

Shorea siamensis

In-gyin

Dipterocarpaceae

LC

83.

Diospyros ehretioides

Auk-chin-sa

Ebenaceae

NE

84.

Streblus asper

Ok-hne

Moraceae

NE

85.

Litsea monopetala

On-don

Lauraceae

NE

Bamboo
1.

Bambusa bambos

Kyakat-wa

Poaceae

NE

2.

Bambusa polymorpha

Kyathaung-wa

Poaceae

NE

3.

Cephalostachyum pergracile

Tin-wa

Poaceae

NE

4.

Dendrocalamus strictus

Hmyin-wa

Poaceae

NE

5.

Oxytenanthera albociliata

Wa-gok

Poaceae

NE

6.

Dendrocalamus brandisii

Wa- new

Poaceae

NE

7.

Dendrocalamus membranaceus

Wa-phyu

Poaceae

NE

8.

Dendrocalamus brandisii

Wa-bo

Poaceae

NE

9.

Dendrocalamus hamiltonii

Wabo-myet-sangye

Poaceae

NE

Thaik-wa

Poaceae

NE

10. Bambusa tulda


Grass
1.

Saccharum spontaneum

Kaing

Poaceae

LC

2.

Imperata cylindrical

Thekke

Poaceae

NE

112

Remark

List

No

Scientific Name

Local Name

IUCN

Family Name

List

Remark

Rattan
1.

Calamus viminalis

Kyein-kha

Arecaceae

NE

2.

Calamus guruba

Kyein-ni

Arecaceae

NE

3.

Calamus floribundus

Ye-kyein

Arecaceae

NE

4.

Calamus latifolius

Yamata-kyein

Arecaceae

NE

5.

Zalacca beccarii

Yingan-kyein

Arecaceae

NE

6.

Calamus helferianus

Kyein-phyu-klay

Arecaceae

NE

7.

Calamus longisetus
Kabaung- kyein
Arecaceae
NE
Note 1: ICUN Red List categories are as follows: CR: Critically Endangered, EN: Endangered, VU:
Vulnerable, NT: Nearly Threaten Species, NE: Not Evaluated; DD: Data Deficient; LC: Least Concern;
Note 2: Some species have only local name information and scientific names may not be always correct.
Source: Forest Department Mawlamyine District Management Plan 2005-2009

Table 4-7 Major Terrestrial Fauna Species in Mawlamyine District


No

Scientific Name

Local Name

Common Name

Family Name

IUCN
List

Mammals
1.

Elephas maximus

Sin

Asian Elephant

Elephantdae

EN

2.

Hoolock hoolock

Myauk-hlwe-kyaw

Hoolock Gibbon

Hylobatidae

EN

3.

Sus scrofa

Taw-wat

Wild boar

Suidae

LC

4.

Viverra spp

Taw- kyaung

Wild cat

Viverridae

5.

Cuon spp

Taw-kwe

Wild dog

Canidae

6.

Muntiacus muntjak

Ji

Barking deer

Cervidae

LC

7.

Axis porcinus

Da-yae

Hog Deer

Cervidae

EN

1.

Porphyrio porphyria

Mae-nyo

Purple coot

Rallidae

LC

2.

Hylobates hoolock

Si-Sali

Hoolock Gibbon

Hylobatidae

EN

3.

Egretta garzetta

Byine

Little Egret

Ardeidae

LC

4.

Turnix suscitator spp

Ngone

Barred Buttonquail

Turnicidae

NE

5.

Streptopelia xanthocycla

Joe

Columbidae

LC

6.

Francolinus pintadeanus

Khar

Burmeese francolin

Phasianidae

LC

7.

Threskiornis spp

Ka-yu-sote

Black-headed Ibis

Threskiornithidae

8.

Caprimulgus asiaticus

Bote

Indian nightjar

Caprimulgidae

LC

9.

Caprimulgus macrurus

Bote

large-tailed nightjar

Caprimulgidae

LC

10. Phalacrocorax carbo

Tin-kyi-myo

Great cormorant

Phalacrocoracidae

11. Pavo muticus

U-Dawn

Green Peafowl

Phasianidae

Birds

Burmese
Collared-dove

113

EN

Note 1: ICUN Red List categories are as follows: CR: Critically Endangered, EN: Endangered, VU: Vulnerable, NT:
Nearly Threaten Species, NE: Not Evaluated; DD: Data Deficient; LC: Least Concern;
Note 2: Some species have only local name information and scientific names may not be always correct.

Source: Forest Department Mawlamyine District Management Plan 2005-2009

Table 4-8 Protected Animals in Mawlamyine District


No

Scientific Name

Local Name

Common Name

Family Name

IUCN List

Totally Protected Animals


1.

Rhinoceros sondaicus

Kyant

Javan rhinoceros

Rhinocerotidae

NE

2.

Pavo muticus

U-Dawn

Green peafowl

Phasianidae

EN

Protected Animals
1.

Elephas maximus

Sin

Asian elephant

Elephantdae

EN

2.

Bos gaurus

Pyaung

Gaur

Bovidae

VU

Seasonal Protected Animals


3.

Axis porcinus

Da-yae

Hog deer

Cervidae

EN

4.

Cervus unicolor

Sat

Sambar

Cervidae

VU

Other Animals
1.

Panthera tigris

Kyar

Tiger

Felidae

EN

2.

Panthera pardus

Kya-thit

Leopard

Felidae

NT

3.

Helarctos malayanus

Wat-wun

Sun bear

Ursidae

VU

Note: ICUN Red List categories are as follows: CR: Critically Endangered, EN: Endangered, VU: Vulnerable, NT:
Nearly Threaten Species, NE: Not Evaluated; DD: Data Deficient; LC: Least Concern;

Source: Forest Department Mawlamyine District Management Plan 2005-2009

For fish species in the Mawlamyine District, Department of Fisheries under the Ministry of Livestock, Fisheries
and Rural Development, has a list of major fish species existing in the district. The list is shown in .
Table 4-9 Fish Species in Mawlamyine District
No

Scientific Name

Local Name

Common Name

Family Name

IUCN
List

Fishes
1.

Lates calcarifer

Ka-katit

Giant seabass

Latidae

NE

2.

Arius thalassinus

Nga-yaung

Giant catfish

Ariidae

NE

3.

Arius venosus

Nga-yaung

Veined catfish

Ariidae

NE

4.

Arius dussumieri

Nga-yaung

Blacktip sea catfish

Ariidae

LC

5.

Arius maculatus

Nga-yaung

Spotted catfish

Ariidae

NE

6.

Arius platystomus

Nga-yaung

Ariidae

LC

7.

Osteogeneiosus militaris

Nga-yaung

Ariidae

NE

8.

Pampus chinensis

Nga-mote-phyu

Stromateidae

NE

Flatmouth

sea

catfish
Soldier catfish

114

Chinese

silver

No

Scientific Name

Local Name

Common Name

IUCN

Family Name

List

pomfret
9.

Nga-mote-phyu

Silver pomfret

Stromateidae

NE

10. Lobotes surinamensis

Pinle-nga-pyayma

Tripletail

Lobotidae

NE

11. Scomberomorus guttatus

Nga- kwin-shat

Scombridae

DD

12. Cynoglossus microlepis

Nga-kway-sha

Tongue sole

Cynoglossidae

LC

Nga-kway-sha

Large scale flounder

Bothidae

NE

Nga-kway-sha

Ocellated flounder

Bothidae

NE

15. Pseudorhombus javanicus

Nga-kway-sha

Javan flounder

Bothidae

NE

16. Pseudorhombus arsius

Nga-kway-sha

Largetooth flounder

Bothidae

NE

17. Tenualosa ilisha

Nga-tha-lauk

Hilsa shad

Clupeidae

LC

18. Harpodon nehereus

Nga-hnat

Bomby duck

Synodontidae

NE

19. Polynemus indicus

Kaku-yan

Indian tassel fish

Polynemidae

NE

20. Trichiurus muticus

Nga-da-gon

Small head hair tail

Trichiuridae

NE

21. Trichiurus lepturus

Nga-da-gon

Large head hair tail

Trichiuridae

NE

22. Trichiurus armatus

Nga-da-gon

Savalani hair tail

Trichiuridae

NE

23. Trichiurus cristatus

Nga-da-gon

Crested hair tail

Trichiuridae

NE

24. Congresox talabonoides

Nga-shwe

Indian pike conger

Muraenesocidae

NE

25. Congresox talabon

Nga-shwe

Yellow pike conger

Muraenesocidae

NE

26. Congresox bagio

Nga-shwe

Muraenesocidae

NE

13.

14.

Pampus argenteus

Engyroprosopon
grandisquamis
Pseudorhombus
dupliciocellatus

Indo-pacific Spanish
mackerel

Common

pike

conger

Note 1: ICUN Red List categories are as follows: CR: Critically Endangered, EN: Endangered, VU: Vulnerable, NT:
Nearly Threaten Species, NE: Not Evaluated; DD: Data Deficient; LC: Least Concern;
Note 2: There are only local name information and scientific names may not be always correct.

Source: Department of Fisheries


Based on species information indicated in the above, threaten and nearly threaten species according to ICUN
Red List categories, are summarized in . These species will be taken into consideration in case that further and
detail environmental baseline survey will be conducted.
Table 4-10 Threaten and Nearly Threaten Species
No.

Scientific Name

Common Name

Local Name

Family

IUCN Red
List Status

Remark

Threaten Species (CR: Critically Endangered, EN: Endangered, VU: Vulnerable)


1. Dipterocarpus turbinatus

Ka-nyin

Dipterocarpaceae

CR

Plant

2. Dipterocarpus alatus

Ka-nyin

Dipterocarpaceae

EN

Plant

115

No.

Scientific Name

Common Name

Local Name

Family

IUCN Red
List Status

Remark

3. Heritiera fomes

Pinle-kanazo

Malvaceae

EN

Plant

4. Hopea odorata

Thin-gan

Dipterocarpaceae

VU

Plant

5. Elephas maximus

Sin

Elephantdae

EN

Mammal

6. Hoolock hoolock

Myauk-hlwe-kyaw Hoolock Gibbon

Hylobatidae

EN

Mammal

7. Cuon alpinus

Taw-kwe

Wild dog

Canidae

EN

Mammal

8. Axis porcinus

Da-yae

Hog deer

Cervidae

EN

Mammal

9. Panthera tigris

Kyar

Tiger

Felidae

EN

Mammal

10. Hylobates hoolock

Si-Sali

Hoolock Gibbon

Hylobatidae

EN

Bird

11. Pavo muticus

U-Dawn

Green peafowl

Phasianidae

EN

Bird

12. Viverra megaspila

Taw- kyaung

Wild cat

Viverridae

VU

Mammal

13. Bos gaurus

Pyaung

Gaur

Bovidae

VU

Mammal

14. Helarctos malayanus

Wat-wun

Sun dear

Ursidae

VU

Mammal

Kya-thit

Leopard

Felidae

NT

Mammal

Asian elephant

Nearly Threaten Species (NT)


-

Panthera pardus

Note: ICUN Red List categories are as follows: CR: Critically Endangered, EN: Endangered, VU: Vulnerable, NT: Nearly
Threaten Species, NE: Not Evaluated; DD: Data Deficient; LC: Least Concern;

Source: Forest Department Mawlamyine District Management Plan 2005-2009

c) Social Environment
1. Introduction
The Project candidate sites are located in the northwestern area of Thanbyuzayat Township in Mon State. Mon
State consists of Thaton District and Mawlamyine District, having four townships and six townships as shown in .
Thanbyuzayat Township is located in Mawlamyine District. Thanbyuzayat Township shares borders with Kyarinn
Seikgyi Township in the east, Ye Township in the south, Bay of Mottama in the west and Mudon Township in the
north.
Thanbyuzayat Township was named because a rest house with white zinc roofing (white zinc means Thanbyu
and rest house means Zayat in Myanmar). The house had been constructed in 1874, and it became a Township
Administrative Office in 19643. According to the Notices of the Department of Home Affairs dated on 10 June,
1964, Kyaikkami Township was renamed to Thanbyuzayat Township and Kyaikkami District to Mawlamyine
District as well. Thanbyuzayat Township has an area of 823.62 km (318 square miles) and it stretches from
Wagaru Creek in the north and Htinyu Creek in the south.

Source: Thanbyuzayat Township GAD 2014 (October)

116

Figure 4-9 District Map of Mon State

Source: Myanmar Information Management Unit (MIMU) 2013 (March)

2. Administration
Thanbyuzayat Township is comprised of 15 wards and 26 village tracts, having a total of 69 villages.
Administrative breakdown of Thanbyuzayat Township is summarized in and village tract locations and their
boundaries are described in .
Table 4-11 Administrative Breakdown of Thanbyuzayat Township
Township

Type of

Town

Ward

Village

Area
Thanbyuzayat

Urban

Rural

Village

Tract
Thanbyuzayat

11

Kyaikkami

26

69

15

26

69

Total

Source: Thanbyuzayat Township GAD 2014 (October)

117

3. Township Departmental Offices and Staff


According to the township GAD, there are 39 governmental offices in Thanbyuzayat Township. As of October
2014, 66 management staffs (officers) are appointed out of 80 sanctioned (83 % filled), whereas 1,626 of staffs are
appointed out of 2,043 sanctioned (80 % filled). Thanbyuzayat Township GAD Office is located in Kyaung Pine
Ward.
Figure 4-10 Village Tract Map of Thanbyuzayat Township

Source: Modified Map of Thanbyuzayat Township Information and Communication Department

4. Population and Demography


According to Thanbyuzayat Township GAD, the total population of the Township was 155,032 in October 2014
as shown in . On the other hand, the provisional result of the 2014 Myanmar Census, conducted from 29th March
to 10th April 2014, showed that the township population was 170,480. The results infer that the actual population
of the township may be higher than the number recorded by the GAD. However, details needed to be confirmed
after the final result of the 2014 Myanmar Census is announced.

118

Table 4-12 Total Population of Thanbyuzayat Township


Subject

Over (18) Years 2013

Under (18) Years (2013

Male

Female

Total

Male

Urban

16,126

18,679

34,805

8,797

Rural

33,167

34,788

67,905

49,293

53,467

102,710

Total

Female

Total

Total

Male

Female

Total

8,509

17,306

24,923

27,188

52,111

17,620

17,399

35,016

50,787

52,187

102,921

26,417

25,908

52,322

75,710

79,375

155,032

Source: Thanbyuzayat Township GAD 2014 (October)


According to Thanbyuzayat Township GAD data, the population of Thanzyuzayat Township was 150,586 and
151,553 persons in 2012 and 2013 respectively. The ratio of population increase had been 0.6% from 2012 to
2013, whereas the ratio was 2.3% from 2013 to 2014.
5. Ethnicity and Religion
Majority of ethnic groups in Thanbyuzayat Township are Mon and Burma, these two groups exceeding 90% of
total population in the township. Kayin, Rakhine, Kachin and Shan national races also live in the township.
shows the breakdown of ethnicity in Thanbyuzayat Township.

Table 4-13 Total Number of Ethnicity in Thanbyuzayat Township


Kachin

Kaya

Kayi

n
-

Chin

Mon

Burma

Rakhine

Shan

Others

Total
Population

7,532

322

78,957

62,475

3,228

27

2,005

152,549

Source: Thanbyuzayat Township GAD 2014 (April)

Since Mon and Burma races are dominant groups, the majority of people are Buddhists (89 %) in the township.
shows the breakdown of religion in Thanbyuzayat Township.

Table 4-14 Religion of Thanbyuzayat Township Residents


Buddhism

Christian

Hindu

Islamic

Nat

Others

Total
Population

134,605

5,811

4,807

6,070

260

151,553

Source: Thanbyuzayat Township GAD 2014 (April)

According to township GAD, there are 322 Buddhism related buildings within the township as shown in . Names
and locations of nine major pagodas and four major monasteries are described in .
Table 4-15 Buddhism Religious Buildings in Thanbyuzayat Township
Pagoda

Monastery

Convent School

Grand Total

85

201

36

322

Source: Thanbyuzayat Township GAD 2014


119

Table 4-16 Major Pagodas and Monasteries in Thanbyuzayat Township


No

Buildings and Places

Description

Location

Kyaikkami Yae Le Pagoda

Pagoda

Kyaikkami

Thandar Dagon Pagoda

Pagoda

Setse Village

Ingyin Taung Pagoda

Pagoda

Aung Tharyar Ward

San Taw Taung Pagoda

Pagoda

Wae Kali Village

Kyaik Ne Yae Le Pagoda

Pagoda

An Khae Village

Kyaiksaw Yae Le Pagoda

Pagoda

Setse Village

Koe Thein Koe Than Pagoda

Pagoda

War Kha Yu Village

Kyaik Win Dat Pagoda

Pagoda

Hantharwaddy Ward

Ma Shi Kha Na Pagoda

Pagoda

Sakhangyi Village

10

Myodawoo

Monasteries

Aung Thar Yar Ward

11

Parama Aryone

Monasteries

Setse Village

12

Mya Thein

Monasteries

Kyar Kan Ward

13

Kyaikami Yae Le

Monasteries

Kyaikkami

Source: Thanbyuzayat Township GAD 2014

For other religions, numbers of religious monuments and buildings in the township is summarized in . Since
Buddhists accounted for about 90% of the total population, number of religious monuments other than Buddhism
is small in Thanbyuzayat Township.

Table 4-17 Others Religious Monument Buildings


Christian Church
Islam
Hindu Temple
Urban
Rural
Urban
Rural
Urban
Rural
2

Source: Thanbyuzayat Township GAD 2014 (April)

6. Land Use
According to land use plans of Thanbyuzayat Township for FY2014, provided by the township Settlement and
Land Records Department (SLRD), there is 203,315 acres (822,79. ha) of land in the township and nearly half of
its lands are used as an agriculture/ cultivated land. In the agricultural / cultivated land, garden land is the
dominating land use, and 34% of total township area is occupied by the garden land.

describes breakdown of

township land use in FY2014.


No
1

Table 4-18 Land Use of Thanbyuzayat Township in 2014-2015


Type of Land
Area (Acre)
Ratio (Against Total
Land)
Net Sown Area
95,709
47.07 %
(a) Paddy Land
25,897
12.74 %
(b) Garden Land (Rubber and Others)
69,315
34.09 %
120

No

Type of Land

Area (Acre)

Ratio (Against Total


Land)
0.24 %
0.02 %
0.86 %
52.04 %
0.0005 %
3.56 %
0.30 %
0.81 %
0.01 %
4.12 %
0.06 %
0.04 %
0.47 %
0.61 %

(c) Thatch Land (Nipa Palm)


497
Omitted Land (Paddy Land)
52
Reserved Forest Land
1,741
Other Wood Land
Cultivable Waste Land
Non-agricultural Land
105,813
(a) Mine Land
1
(b) Pastures
7,232
(c) Railway Land
605
(d) Road Land
1,641
(e) Dam and Reservoirs Land
19
(f) River and Creek Land
8,379
(g) Ponds and Lakes Land
121
(h) Industrial Land
90
(i) Residents Land (Urban)
955
(j) Villages Land
1,250
(l) Cemetery and Religious Buildings
10,586
Land
5.21 %
(m) Others Land
74,934
36.86 %
Total Area (Township)
203,315
100 %
Source: Thanbyuzayat Township Settlement and Land Records Department (SLRD) 2014

2
3
4
5
6

7. Industry
a. Agriculture and Forestry
According to Township GAD, rubber is the most cultivated as well as harvested cash crops in Thanbyuzayat
Township as shown in . The rubber plantations exceed 80% of total cultivated area of long-term crops.

Table 4-19 Long-term Cash Crops in Thanbyuzayat Township


Name of Crop

Cultivated Area

Harvested Area

Unit Yield

Production

(Acre)

(Acre)

(Baskets/ Acre?)

(Basket)

Rubber

60,605

50,106

708.98

35,524,528

Pepper

2,235

2,089

88.85

185,820

41

41

16.40

664

730

705

4,236.38

686,880

Coconut

1,600

1,435

5,420

7,779,135

Fruit Trees

7,935

6,411

73,164

60,797

Sugarcane (consumed)
Betel

Total

10,470.51

44,177,027

Source: Thanbyuzayat Township GAD 2014 (April)


According JICA study4, the rubber plantations started in Mon State around 100 years ago. Due to the high price

Source: the report of JICA Study Team -Preparatory Survey for the integrated regional development for ethnic
minorities in the south-east Myanmar

121

of rubber materials and products in the past few decades, rubber plantation area increased rapidly. In Mon States,
the rubber plantations account for approximately 14.9% of the total land area and it has the largest ration of rubber
plantation area as compared with the union level (0.7%).

In case of crops for staple foods, monsoon paddy is the most cultivated and produced crops in Thanbyuzayat
Township as shown in . The monsoon paddy occupied about 99% of total agricultural cultivated area.

Crops

Paddy
Sesame
Sunflower
Black
gram
(Bean)
Green gram

Table 4-20 Major Agricultural Crops in Thanbyuzayat Township


Season
2012-2013
Cultivated
Harvested
Unit Yield
(Acre)
(Acre)
(Basket / Acre?)
Summer
77
Rainy
37,731
37,731
66.29
Rainy
47
Winter
193
193
6.53
8
1
Rainy
Winter

Red gram
Sugarcane (Sugar)

15
40
40
40
Source: Thanbyuzayat Township GAD 2014

Production
(Basket)
2,501,214
1,260
-

16.50

660

In case for forest products, hardwoods including teak, iron wood and others were exported to India and
Europe during the colonial period5. Currently, major forest products produced in the Thanbyuzayat Township
are summarized in . 1,550 cubic ton of timber is produced as firewood, and the one tenth volume of firewood
is produced as charcoal wood.

Table 4-21 Major Forestry Products in Thanbyuzayat Township


No

Type of Products

Unit

Production Amount

Firewood

Cubic Ton

1,550

Charcoal

Cubic Ton

147

Bamboo

Piece

194,000

Thatch

No

136,000

Bark of wood

Viss

7,660

Source: Thanbyuzayat Township GAD 2014


b. Fishery
According to the State Office of Department of Fisheries, majority of fishing activities are conducted inshore
with more number of fishing boats registered and having higher total annual production. Current status of fishery

Source: The report of JICA Study Team -Preparatory Survey for the integrated regional development for ethnic
minorities in the south-east Myanmar

122

in Mon State is shown in .

Table 4-22 Fishery Status in Mon State


In shore license
Township

Annual

No. of Inshore

Production

fishing boat
Thanbyuzayat

Off shore license

Total Tax (kyat)

(ton)
376

60,135

No. of

Annual

Offshore

Production

vessel

(ton)

3,619,550

76

Total Tax
(kyat)

4,339

5,634,000

Source: Mon state Department of Fishery 2014

Detail data for the Thanbyuzayat Township was not available, but fishery industry seems to be dominated by
small-scale in-shore fishing. Inland (freshwater) fishery activities seem to be less significant in comparison with
inshore fishing. Aquaculture production status of Thanbyuzayat Township is described in . However production
amount from aquaculture was not available.

Table 4-23 Aquaculture Ponds of Fish and Prawn Production


Year

Fish
Number of Pond

Prawn
Acre

Number of Pond

Acre

2010-2011

24

109.74

45

123.66

2011-2012

24

109.74

45

Source: Thanbyuzayat Township GAD 2014 (April)

c. Other Industries
Other industries are not described in Thanbyuzayat Township Fact issued by Thanbyuzayat Township GAD. The
recent Gross Domestic Product value of the Township is summarized in . Production sector serves more than
60 % of total GDP value.

Table 4-24 Gross Domestic Products (GDP) of Thanbyuzayat Township


No

Subject

Production Value

2012-2013

2013-2014

2013 (until the end of December)

GDP

Target Value

Value

Implementati

Increased

(million Kyat)

(million Kyat)

(million

on

(%)

Kyat)

(%)

100,215.4

106,596.3

73,608.3

69.1

0.2

Services

39,065.7

44,121.4

37,480.4

84.9

21.2

Trading Value

29,216.3

31,783.8

24,180.9

76.1

0.5

GDP and Service

168,497.4

182,501.5

135,269.6

74.1

5.3

Value
Source: Thanbyuzayat Township GAD 2014 (April)
123

d. Social Infrastructure and Service


8. Power/ Electricity
Power supply is from the national grid in Thanbyuzayat Township. The total power demand is about 4,000 KVA.
Household electrification rate is about 40% in the Thanbyuzayat Township urban areas. Types and quantities of
transformers installed and their distribution amount in the township is described in .
Table 4-25 Existing Transformers and Distribution Amount
No Type of Transformer Quantity Total Distribution (KVA)
1
50 KVA
7
280
2
100 KVA
12
960
3
150KVA
14
1,792
4
200KVA
8
1,280
5
250KVA
5
1,000
6
315KVA
16
4,032
7
750KVA
1
600
Total
63
9,944
Source: Thanbyuzayat Township GAD 2014

9. Water Supply
The present principal water sources for the domestic water use in urban areas vary in natural streams,
groundwater, springs, rain-fed ponds and artifical reservoirs. In most areas, the water is taken from these water
sources and distributed through pipes but without any purification facilities. The urban water supply sources in
Mon States in 2013 are summarized in .

Table 4-26 Water Sources for Major Townships in Mon State


Township

Water Source

Presence of Public
Water Supply

Natural Stream

Ground-

System

(River/Creak)

water

Kyaikto

Bilin

Thaton

Paung

Mawlamyine

Chaungzon

Rain-fed

Dam

Pond

Reservoir

O
O
O

O
O

Kyaikmaraw
Mudon

Spring

O
O

Thanbyuzayat

Ye

Source: The report of JICA Study Team -Preparatory Survey for the integrated regional development for ethnic
minorities in the south-east Myanmar

124

According to Township Irrigation Department, under the Ministry of Agriculture and Irrigation, water supply for
Thanbyuzayat Township is mainly from individual dug wells and tube wells. Water shortages are experienced
during summer season. Small scale water supply is also available by private suppliers with trucks. There is no
dam in Thanbyuzayat Township.
Existing water reservoirs and canals in Thanbyuzayat Township for irrigation purposes are summarized in . 40%
of area against proposed area is not available as irrigation water.

No

1
2

3
4

Table 4-27 Irrigation Embankment and Canal in Thanbyuzayat Township


Name of
Proposed
Actual
Different
Explanation for different Area
Embankment,
Command
Area
Area (Acre)
Canal
Area(Acre)
(Acre)
Ah
Ninn 364
163
201
Original Enbankment is situated near
Embankment
sea water creek.
Ah Ninn Thabyay 565
240
325
Soil is acidity.
Chaung
Embankment
Ah Zinn Canal
880
472
408
Extending the Ward, Village and
others land.
Taung Pu Lu 935
668
267
(No information.)
Canal
Source: Thanbyuzayat Township Irrigation Department 2014

11. Transportation
Major roads within the township and connecting outside of the township are summarized in . There is no airport
and no harbor (except for small jetties) in Thanbyuzayat Township. The main rail road is Mawlamyine- Ye rail
road, which is about 143 km (89 miles) long as listed in . The major road in the township is Mawlamyine- Ye road
which is 156 km (97 miles) long in total and runs north to south of the Township.

Table 4-28 Major Inter/Intra Roads in Thanbyuzayat Township


Type of Road

Road Name

Distance
(Mile/ Phalon)

Union Main Road

Townships connected Roads

Thanbyuzayat Ye

27/0

Thanbyuzayat Kyaikkami

15/0

Thanbyuzayat Setse

5/0

Thanbyuzayat - Phayar Thone Su

59

Thanbyuzayat Mawlamyine

40 / 0

Thanbyuzayat- Ye

57

Thanbyuzayat Mudon

22

Thanbyuzayat _ Phayar Thone Su

Town, Rural, Village connected

Thanbyuzayat _ Kyaikkami

15 /2

roads

Thanbyuzayat _ Setse

15 / 0

Mawlamyine- Ye Rail Road

Thanbyuzayat _ Wae Kali

1 /1

Thanbyuzayat- Ye

54
125

Type of Road

Road Name

Distance
(Mile/ Phalon)

Thanbyuzayat- Mawlamyine

35/2

Thanbyuzayat Mudon

19/6

Source: Thanbyuzayat Towship GAD 2014

According to Township GAD, there are 13 major bridges in Thanbyuzayat Township. There is only one bridge
that is over 180 feet in Ka Yote Pi Village.. The number of bridges in Thanbyuzayat Township is shown in .

Table 4-29 Number of Bridges in Thanbyuzayat Township


Total Bridges

Total Bridges

Total Bridges

Total Bridges

(Over 180')

(From 100' to 179' )

(From 50' to 100')

(Under 50')

Source: Thanbyuzayat Towship GAD 2014


Alignments of major road and railways in the township is shown in .
Figure 4-11 Road/ Railway Network diagram of Thanbyuzayat Township

Source: Thanbyuzayat Township Information and Communication Department


126

Total

13

12. Communication
Communication facilities of Thanbyuzayat Township are indicated in . Internet user is equal to about 10% of the
total township population.
Post

Fax

Table 4-30 Communication Facilities of Thanbyuzayat Township


Fixed Phone
IP
Star Cordless
Mobile Phone
(Satellite)
938
17,654
Source: Thanbyuzayat Township GAD 2014

Number
of
Internet User
15,425

13. Public Health


According to Township GAD, Thanbyuzayat Township has 5 doctors, 12 nurses and 6 health assistants, of which
ratios against the total township population are 1:35,921, 1:14,967, and 1:29,934, respectively. The number of
medical facility of Thanbyuzayat Township is indicated in .

Table 4-31 Medical Facility of Thanbyuzayat Township


Township

Governmental Hospital

Thanbyuzayat

Private

Rural Health

Hospital

Centers

Sub Health Centers


22

Source: Thanbyuzayat Township GAD 2014

Status of common diseases in Thanbyuzayat Township is indicated in . The number of HIV/AIDS patients
identified was 94 and 16 in 2012 and 2013, respectively. Two patients died from HIV/AIDS in 2012 to 2013.
Table 4-32 Common Disease of Thanbyuzayat Township
Malaria

Diarrhea

Tuberculosis

Dysentery

Enlarged Liver

Infected

Died

Infected

Died

Infected

Died

Infected

Died

Infected

Died

494

2,183

138

487

144

Source: Thanbyuzayat Township GAD Year 2014

The key health index of the township is described in .


Reproduction Rate
0.06

Table 4-33 Health Index (In Thousand)


Birth Rate
Maternal
Infant Mortality
Mortality Rate
Rate
15.96
1.05
0.07
Source: Thanbyuzayat Township GAD 2014

Abortion Rate
0.197

14. Education
According to Township GAD, there is no university, college and science school in Thanbyuzayat Township.
Educational facility of Thanbyuzayat Township is indicated in .

127

Table 4-34 Numbers of Schools, Teachers, Students in Thanbyuzayat Township


Schools

Teachers

Students

High

Middle

Primary

Pre

High

Middle

Primary

Pre

Total

High

Middle

Primary

Pre

Total

109

42

360

94

551

76

1,081

8,700

2,330

17,508

905

20,743

Source: Thanbyuzayat Township GAD 2014


Orphans or poor people have been supported by Monastery education. There are 36 convent schools that support
education too. Overall literacy rate is 98.27 % in Thanbyuzayat Township.

a. Livelihood
According to Township GAD, odd-job (approximately 70,000 persons) is the major sources of income for the
township, followed by others (may include unemployed and approximately 28,000 persons), trading
(approximately 23,000 persons), and agriculture (approximately 18,500 persons). The breakdown of types of
workers in Thanbyuzayat Township is indicated in . Annual average individual income was 637, 572 kyats / year
and 814,944 kyats / year for FY2011 and FY 2012, respectively. Number of unemployment was 27,269, and
Jobless rate was 18.00% in FY2012.
Table 4-35 Types of Workers in Thanbyuzayat Township
Year

Government

Services

Agriculture

Staff

Livestock

Trading

Industry

Odd-job

Others

Total

Farming

2013

1,693

5,739

18,426

2,159

22,852

3,254

69,660

27,770

151,553

2014

1,704

5,777

18,567

2,173

23,002

3,275

70,118

27,953

152,549

Source: Thanbyuzayat Township GAD 2014


b. Cultural Heritage
According to Thanbyuzayat Township GAD, 12 historical buildings and places are recognized as shown in .
Names and locations of these major sites are described in .
No
1
2
3
4
5
6
7
8
9
10
11
12

Table 4-36 Historical Buildings and Places


Buildings and Places
Description
Myanmar-Thai Railway Museum (Death Railway Museum (relics)
Museum)
Dana Thahara War Cemetery
Cemetery
Japan Pagoda
Pagoda
Hot Spring
Natural spring
Rest-house (100 years)
Building
Kyaikkami Yae Le Pagoda
Pagoda
Kyaik Ne Yae Le Pagoda and Beach
Pagoda, Beach
Kyaiksaw Yae Le Pagoda
Pagoda
Sin Pone Cave
Natural Cave
Kyat Thon Island Light House
Building
War Kha Yu Ancient City
Relics
Main Balra Taung
Mountatin
Source: Thanbyuzayat Township GAD 2014

128

Location
Thanbyuzayat
Thanbyuzayat
Wae Yet Ywar Village
Wae Ka Li Village Tract
Thanbyuzayat
Kyaikkami
An Khae Village
Set Se Village
Kyaikkami
Set Se Village Tract?
War Kha YuVillage Tract
Wea Ka War Village

Figure 4-12

Cultural Heritage Map of Thanbyuzayat Township

Source: Modified Map from Thanbyuzayat Township Information and Communication Department

c) Conditions of Project Candidate Sites and Surrounding Area


1. Outline
The Project candidate sites are located along the northwest coast of Thanbyuzayat Township. The sites are more
likely to be included in following 4 village Tracts ().

Mya Mar Lar

Sin Taung

Kayin Taung

Set Se

Therefore, information and data for these four village tracts (Project Village Tracts) are presented hereunder as
long as such were available. In addition to these four village tracts, Project candidate sites may fall into either
Kyon Ka Yoke, Wea Ka War, or Pa Nga Village Tract. Further conformation and collection of information will be
required when the Project site is selected from these three village tracts.

129

Figure 4-13 Village Tract Map of Three Village Tracts from Thanbyuzayat Township

Source: Modified Map of Thanbyuzayat Township GAD 2014 (October)

a. Population
The populations of the Project Village Tracts are indicated in . There are in total of 2,819 households and 15,598
persons in the Project Village Tracts.

Ward/
Village
Tract
Mya
Mar
Lar

Sin
Taung

Kayin
Taung

Table 4-37 Populations of Project Village Tracts from Thanbyuzayat Township


Village House Household
Under (18) years
Over (18) years
Total Population
Male Female Total
M
F
Total
M
F
Total
(M)
(F)
Mya
292
292
346
291
637
521
584
1,105
867
875
1,742
Mar Lar
Total
292
292
346
291
637
521
584
1,105
867
875
1,742
Sin
Taung
Taung
Wine
Ka Dat
Htauk
Total
Kayin
Taung

79

81

107

112

219

147

156

303

254

268

522

21

23

30

34

64

31

40

71

61

74

135

279

284

342

354

696

453

488

941

795

842

1,637

379
580

388
630

479
643

500
677

979
1,320

631
1,025

684
1,078

1,315
2,103

1,110
1,668

1,842
1,755

2,294
3,423

130

Ah Nan
San
Total
Set Se Set Se
Sanngyi
Hlar Ka
Hmai
Yathay
Taung
Total
Grand Total

160

223

188

223

411

340

346

686

528

569

1,097

740
849
82
95

853
850
62
84

698
53
68

900
674
89
64

1,731
1,372
142
132

1,365
1,389
137
183

1,424
1,514
142
178

2,789
2,903
279
361

2,196
2,087
190
251

2,324
2,188
231
242

4,520
4,275
421
493

319

290

246

267

513

670

670

1,340

916

937

1,853

1,286 1,065 1,094 2,159 2,379 2,504


4,883
2,819 2,721 2,785 5,506 4,896 5,196 10,092
Source: Thanbyuzayat Township GAD 2014 (October)

3,444
7,617

3,598
7,981

7,042
15,598

1,345
2,759

b. Land Use (updating)


For village tract level land use, GAD offices (township level and respective village tract administrators offices)
and township Settlement and Land Records Department (SLRD) office have different statistical records of
different years. Information of SLRD for 2013 is described in

and that of GAD for 2014 is described in . It is

difficult to generalize information of different sources. However, there is a tendency that more than half of village
tract area is occupied by agricultural land in all of the Project Village Tracts.

Table 4-38 Type of Land Use of Project Village Tracts in Thanbyuzayat Township 1

227
30

4,542
3,148

12

4,781
3,178

535

2,130

174

2,839

10
24

602
1,394

2,494
12,314

186

3,096
13,894

77
74

50
68

64

810

136
2,362

42
257

297
1,225

Pond /Lake

10
43

19
118

2,422
2,309

3,875
3,543

8,656
6,721

15

392

487

736

2,512

5,351

24

32
477

2,028
2,652

100
5,567

2,635
12,565

5,731
26,459

Village
Land
Cemetery
and
Religious
Land

River and
Stream

Road

Pasture
land

1,297
922

Total

5
3

Mine land

Total

Dani Land

Non Cultivated land (Acre)


Other land

Kayin
Taung
Sin Taung
Mya Mar
Lar
(including
Kyaikkami
)
Setse
Total

No. of
Kwin

Garden and
Rubber

Village
Tract

Farm land

Cultivated Area (Acre)

Grand
Total

Source: Thanbyuzayat Township Settlement and Land Records Department (SLRD) 2013
Table 4-39 Type of Land Use of Project Village Tracts in Thanbyuzayat Township 2
Village Tract
Net
Pasture Mine
Road
River Factory Village Cemetery Other Total
Agricultural Land
Land
and
land
Land
and
Land (acre)
Land
Stream
Religious
Land
Mya Mar Lar
2,808
7
1
29
804
10
123
362
518 4,662
Source: Village Tract GAD 2014

Breakdown of registered agricultural land use for 2014 in the Project Village Tracts are summarized in . There
are certain fluctuations of agricultural land area from 2013, but it can be concluded that majority of agricultural
lands are occupied by the rubber plantation if the Project Village Tracts.

131

Table 4-40 Breakdown Registered Agricultural Land Use of Project Village Tracts in Thanbyuzayat Township
Number of
Registered
Farmers

Village Tract

Kwin
No

Mya Mar Lar

530

Kayin Taung

1,085

Sin Taung

779

Setse

10

862

Total

23

3,256

Rubber
land
(acre)

Garden
Land
(acre)

635

765

734

44

2,178

237

3,398

40

3,679

Paddy Land
(acre)

35.81
472
1,379.81

Thatch
Land
(acre)

Total Area
(acre)

2,400.82

724.95

3,161.58

1,945

105

2,525

1,603.95

48

8,508.82

11,543.58

Source: Thanbyuzayat Township SLRD 2014


In principle, agricultural lands in Myanmar are registered by SLRD and grouped in a block called Kwin. Each
parcel of agricultural land having different users (famers) are numbered by what is locally called U-Pine. Not all
of the Project Village Tract, but for Mya Mar Lar and Setse village tracts, kwin-wise list of farmland/rubber
plantation owners, land acreage and their u-pine numbers were obtained. Obtained list is summarized in .

Table 4-41 Kwin-wise Farm Land and Rubber Plantation Information.


Village Tract
Kwin No.
Farm Land
Rubber
Total
Number of
(Acre)
Plantation
(Acre)
Registered Farmers
(Acre)
F
R
Total
F
R
Total
Mya Mar Lar 907
213.43
0.00
213.43
34
0
34
907 (A) (Buddha Gone Kwin)
44.51
25.23
69.74
14
8
22
907 (A) (Buddha Gone Kwin)
281.50
0.00
281.50
136
0
136
908 (Thein Kwin)
256.48
136.22
392.70
118
21
139
909
480.35
268.30
748.65
406
67
473
909(A)
519.65
247.36
767.01
215
65
280
OSS 1
186.98
0.00
186.98
83
0
83
Total
1,982.90
677.11
2,660.01
1,006
161 1,167
Setse
922
56.57
160.82
217.39
13
39
52
923
6.08
397.01
403.09
2
69
71
923(A)
19.80
0.00
19.80
8
0
8
924 (A)
36.24
467.63
503.87
11
79
90
924 (B)
0.00
145.22
145.22
0
36
36
925
248.59
231.03
479.62
75
25
100
926
125.95
27.36
153.31
36
14
50
927(A)
0.00
0.00
0.00
0
0
0
927(B)
96.74
136.13
232.87
35
44
79
Total
589.97
1,565.20
2,155.17
180
306
486
Grand Total
2,572.87
2,242.31
4,815.18
1,186
467 1,653
Source: Thanbyuzayat Township Settlement and Land Records Department (SLRD) 2014

Within the Project Village Tracts, following kwins are located along the coastline and in the further stage of the
Project, a detail survey is required in these kwins for identifying acreage and type of land uses and users which
may be affected by the Project.
-

Kwin Number: 908, 909, 909A, 1219, 1294, OSS-2, OSS-3, 925

Kwin map of the Project Village Tract is described in .


132

Figure 4-14 Kwin Map of the northwest Coast of Thanbyuzayat Township

Source: Modified Map from Thanbyuzayat Township Settlement and Land Records Department (SLRD)

c. Cultural Heritage
The Project Village Tract has 4 of cultural and regional important heritages as shown in . Especially, Kyaikkami
Pagoda is the symbol monument of the area and conserved by Kyaikkami Pagoda Association.

133

Figure 4-15 Cultural Heritage Map of the northwest Coast of Thanbyuzayat Township

Source: Modified Map from Thanbyuzayat Township Information and Communication Department

3. Prediction of Impact in Without Projects Case


In connection to the forecast of the future conditions for without projects case, the following positive and
negative impacts are predicted.
Positive Impacts for without project case:

There will be no land acquisition and involuntary resettlement

Livelihood related to on-shore fishery will maintain the same as now and will not be affected (which does
not always require land acquisition and involuntary resettlement)

On-shore and other transportation means along the coast line will maintain the same.

No impacts on air quality and water quality by the Project

Negative Impacts for without project case:

Insufficient supply of electricity to the region and to the national grid will continue

Speed of economic development in the Thanbyuzayat Township and the Mawlamyine District may be
decreased.

Due to shortage of electricity, improvement of surrounding infrastructure such as public facilities and
local employment maybe hindered.

134

(2) Environmental improvement effects by the Project


a) Air Quality, Water Quality, Noise, and Other Environmental Improvement Effects
Construction of the coal thermal power plant will improve electricity generation capacity of the country and
contribute to increasing demands for the electricity. Furthermore, the coal thermal power plant will enable to
supply more stable and regulated amount of electricity throughout the year in comparison to the hydro power
plant which is currently the dominant source of power generation in Myanmar. These in return, will bring more
economics and industrial developments in the Mawlamyine areas.
Though the coal thermal power plant, by its nature, has certain impacts to air quality and water quality by gas
emission and intake/ discharge of circulated water, appropriate environmental mitigation measures such as
denitrification device desulfurization device, precipitator, and water treatment facility will be introduced to
minimize the environmental impacts. Moreover, introducing ultra super critical boiler and other latest coal power
plant related technologies will also minimize environmental impacts.
Though jetties for the Project are planned mainly for unloading of imported coal, the jetty structure may serve as
breakwater for hinterland/ water and shelter for ships nearby during high tides / abnormal weather conditions.
On the other hand, the Project will mainly improve environmental items such as lifestyle and livelihood as
follows.

Increase supply of electricity to the region for further economic development and livelihood improvement
in the township and the district.

Improve lifestyle of surrounding residents of the Project site by development of surrounding


infrastructure such as access road, and other public facilities.

Contribute to local employment and may improve lifestyle and livelihood of surrounding residents

135

(3) Environmental and social impacts of the Project


a) Examination of Environmental and Social Impacts
In the Study, environmental and social impacts of the Project of coal thermal power plant and its jetty were
evaluated

shows the evaluation results of environmental and social impacts by mainly using Categories and

Items in Checklist 2 Thermal Power Plant attached with JICA Guidelines for Environmental and Social
Considerations (April 2010) as a reference format. In addition to the Checklist 2 Thermal Power Plant, the
Checklist 6 Power Transmission and Distribution Lines, and the Checklist 10 Port and Harbors, were also
referred based on the necessity.
However, the examination made in this Study is preliminary and the factors which would give serious impacts on
environment and social aspects should be fully checked and evaluated in EIA and/or SIA studies by the Project
proponents and/or petitioners.

Table 4-42 Environmental Checklist (Coal Thermal Plant including Jetty and Transmission)

Not Clear

common

(1) EIA and Environmental Permits

1 Permits and Explanation

(a) Have EIA reports been


already prepared in official
process?

None

Small

Major

Environmental
Item

Category

Reference tableJICA s Environmental Checklist (Thermal Power Plant, Port, Transmission & Distribution )
Significance of
Potential
Possible
Confirmation of
Environmental Impacts Environ
Environmental
mental
Main Check Items
Considerations
Issues
(Reasons, Mitigation
and
Measures)
Problems
EIA have not
prepared
yet.
accordance with
Notification
No.50/2014,
Project requires
implementation
EIA.
Ditto.

(b) Have EIA reports been


approved by authorities of the
host country's government?
(c) Have EIA reports been
unconditionally approved? If
conditions are imposed on the
approval of EIA reports, are the
conditions satisfied?
(d) In addition to the above
approvals, have other required
environmental permits been
obtained from the appropriate
regulatory authorities of the
host country's government?

Ditto.

Ditto.

136

been
In
MIC
the
the
of

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems

Common

(2) Explanation to the Local Stakeholders

(a) Have contents of the project


and the potential impacts been
adequately explained to the
Local stakeholders based on
appropriate
procedures,
including
information
disclosure? Is understanding
obtained from the Local
stakeholders?

EIA have not been


prepared yet.
According to draft
EIA procedure, at least
two public
consultation meetings,
first during the
scoping stage and the
second one upon
completion of draft
EIA report, are
required for EIA level
assessment.
Ditto.

Common

(3)
Examinati
on of
Alternativ
es

(b) Have the comment from the


stakeholders (such as local
residents) been reflected to the
project design?
(a) Have alternative plans of the
project been examined with
social
and
environmental
considerations?

Thermal

(1) Air Quality

2 Pollution Control

(a) Do air pollutants, such as


sulfur oxides (SOx), nitrogen
oxides (NOx), and soot and dust
emitted by the power plant
operations comply with the
countrys emission standards?
Is there a possibility that air
pollutants emitted from the
project will cause areas that do
not comply with the countrys
ambient air quality standards?
Are any mitigating measures
taken?

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)

The location of coal


thermal power plant
has
not
been
determined yet.

(b) In the case of coal-fired


power plants, is there a
possibility that fugitive dust
from the coal piles, coal
handling facilities, and dust
from the coal ash disposal sites
will cause air pollution? Are
adequate measures taken to
prevent the air pollution?

137

Air
pollution
by
emission
gas.
No
national
quality
standards
yet

The Project should


plan and design for
compliance
with
environmental
standards set by the
Project.
Impacts on air quality
canbe
little
if
desulfurization system,
denitration
system,
electrostatic
precipitator/
fabric
filters,
and
other
necessary mitigation
measures are properly
installed..
Air
The Project should
pollution plan and design for
by dusts. compliance
with
No
environmental
national
standards set by the
quality
Project.
standards Impacts on dust from
yet
coal yard and ash
disposal site can be
little if coal yard is
planned to be set at
distance
from

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
residential area and
dust prevention fence
will be installed to
minimize spreading of
dust.

Thermal

(2) Water Quality

Port

(1) Air Quality

(a) Do air pollutants, such as


sulfur oxides (SOx), nitrogen
oxides (NOx), and soot and dust
emitted from ships, vehicles and
project equipments comply with
the
country's
emission
standards? Are any mitigating
measures taken?

(a) Do effluents including


thermal effluents from the
power plant comply with the
countrys effluent standards? Is
there a possibility that the
effluents from the project will
cause areas that do not comply
with the countrys ambient
water quality standards or cause
any significant temperature rise
in the receiving waters?

(b) In the case of coal-fired


power plants, do leachates from
the coal piles and coal ash
disposal sites comply with the
countrys effluent standards?

138

Air
pollution
by
exhauste
d gases.
No
national
quality
standards
yet

The Project should


plan and design for
compliance
with
environmental
standards set by the
Project.
To comply with target
level set by the
Project, environmental
management
and
monitoring plan must
be
prepared
and
operated properly.
Changes The Project should
in
plan and design for
aquatic
compliance
with
fauna & environmental
flora,
standards set by the
and
Project.
water
Impacts of thermal
pollution water discharge are
by water expected to be limited.
temperat Temperature
ure
difference
of
increase discharged
water
of
will be set to be less
discharg than 7 and will
ed water. comply with target
No
level based on the
national
results of prediction
quality
by simulation model.
standards
yet
The Project should
plan and design for
Water
compliance
with
pollution
environmental
by the
standards set by the
Project.
Project.
No
Less residents are
national
expected
in
the
quality
surrounding of the
standards
Project site.. Thus no
yet.
significant
serious
impacts by the Project

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems

Port

(2) Water Quality

(c) Are adequate measures


taken to prevent contamination
of
surface
water,
soil,
groundwater, and seawater by
the effluents?

Ditto

(a) Do effluents from the


project facilities comply with
the country's effluent and
environmental standards?

Ditto

(b) Do effluents from the ships


and other project equipments
comply with the country's
effluent and environmental
standards?

Ditto

139

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
are
predicted.
However,
if
any
impact
may
be
predicted by further
studies, as required,
necessary
measures
will be carried out.
Countermeasures to
avoid water pollution
such as waste water
treatment,
slope
protection, and etc.
will be taken.
The Project should
plan and design for
compliance
with
environmental
standards set by the
Project if national
standards are not set
yet
by
the
commencement of the
Project..
No significant serious
impacts by the Project
are
predicted.
However,
if
any
impact
may
be
predicted by further
studies, as required,
necessary
measures
will be carried out.
The Project should
plan and design for
compliance
with
environmental
standards set by the
Project if national
standards are not set
yet
by
the
commencement of the
Project.
No
significant
serious
impacts by the Project
are
predicted.
However,
if
any
impact
may
be
predicted by further
studies, as required,
necessary
measures

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
will be carried out.

(c) Does the project prepare any


measures to prevent leakages of
oils and toxicants?

Ditto

(d) Does the project cause any


alterations in coastal lines and
disappearance/appearance
of
surface water to change water
temperature or quality by
decrease of water exchange or
changes in flow regimes?

Ditto.

(e) Does the project prepare any


measures to prevent polluting
surface, sea or underground
water by the penetration from
reclaimed lands?

Ditto.

Transmission/ Distribution

(2) Water Quality

(a) Is there any possibility that


soil runoff from the bare lands
resulting from earthmoving
activities, such as cutting and
filling will cause water quality
degradation in downstream
water areas? If the water quality
degradation is anticipated, are
adequate measures considered?

Ditto.

140

Pollution mitigation
measures will be
introduced and no
significant
serious
impacts by the Project
are predicted.
Significant
alternations of the
coast lines and change
in water temperature
by jetty construction
and operation are not
expected
in
the
Project.
Significant
land
reclaimation is not
expected
in
the
Project. However, if
any impact may be
predicted by further
studies, as required,
necessary
measures
will be carried out
No significant serious
impacts by the Project
are
predicted.
However,
if
any
impact
may
be
predicted by further
studies, as required,
necessary
measures
will be carried out

None

(a) Are wastes generated from


the ships and other project
facilities properly treated and
disposed of in accordance with
the country's regulations?

Small

Port

(3) Wastes

Thermal

(3) Wastes

(a) Are wastes, (such as waste


oils, and waste chemical
agents),
coal
ash,
and
by-product gypsum from flue
gas desulfurization generated by
the power plant operations
properly treated and disposed of
in
accordance
with
the
countrys regulations?

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Harmful
damages
to
surround
ing
environ
ment and
residents

Harmful
damages
to
surround
ing
environ
ment

(b) Is offshore dumping of


dredged soil properly disposed
in accordance with the country's
regulations?

Potential
Environ
mental
Issues
and
Problems

Ditto.

(c) Does the project prepare any


measures to avoid dumping or
discharge toxicants?

Ditto.

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
Impacts on waste can
be limited because fly
ash and bottom ash
will be recycled as
by-products
and
Furthermore,
other
solid waste will be
disposed
of
on
designated dumping
site. However, if any
impact
may
be
predicted by further
studies, as required,
necessary
measures
will be carried out.
No significant serious
impacts by the Project
are
predicted.
However,
if
any
impact
may
be
predicted by further
studies, as required,
necessary
measures
will be carried out.
No significant serious
impacts by the Project
are
predicted.
However, if dredging
is
required,
appropriate measures
will be carried out.
Ditto.

Thermal/port

(4) Noise and Vibration

(a) Do noise and vibrations


comply with the countrys
standards?

141

Noise
and
vibration
problem
by
vehicles
and
thermal
plant

The Project should


plan and design for
compliance
with
environmental
standards set by the
Project.
Impacts on noise and
vibration are expected
to be limited because
the distance between
source (machineries in
the power generation
facilities)
and
receptors (residences)

None

(a) Does the project site


encompass primeval forests,
tropical
rain
forests,
ecologically valuable habitats
(e.g., coral reefs, mangroves, or
tidal flats)?

Small

(a) Is the project site located in


protected areas designated by
the
countrys
laws
or
international
treaties
and
conventions?
Is
there
a
possibility that the project will
affect the protected areas?

Common

(2) Ecosystem

(a) Are adequate measures


taken to prevent contamination
of sediments by discharges or
dumping of hazardous materials
from the ships and related
facilities?

Common

(1) Protected Areas

(a) Are there any odor sources?


Are adequate odor control
measures taken?

Port

(7) Sediment

Thermal/port

(6) Odor

Thermal/port

(5) Subsidence
3 Natural Environment

(a) In the case of extraction of a


large volume of groundwater, is
there a possibility that the
extraction of groundwater will
cause subsidence?

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

142

Damages
to
structure
s
and
land
usages
by
the
Project

Harmful
effects
by
chemical
s used by
the
Project

Sediment
pollution
by
the
Project

Potential
Environ
mental
Issues
and
Problems

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
Use of ground water is
limited,
thus,
no
significant
serious
impacts by the Project
are
predicted.
However,
if
any
impact
may
be
predicted by further
studies, as required,
necessary
measures
will be carried out.
Impacts on offensive
odor
caused
by
ammonia are expected
to be little because the
amount of ammonium
to
be
used
on
denitration process is
small and will be
handled appropriately.
Impact
on
sedimentation
are
expected to be limited
because
dredging
works which might
affect the surrounding
area are site specific.
However,
if
any
impact
may
be
predicted by further
studies, as required,
necessary
measures
will be carried out.
There is no protected
area in the vicinity of
the project candidate
sites.

Damages
and
destructi
on
to
nature
and
ecology
by
the
Project
Ditto.
There is no large
primeval
forests,
wetland area and tidal
flats in the Project
candidate sites as well
as their surroundings

None

Small

(b) Does the project site


encompass
the
protected
habitats of endangered species
designated by the countrys
laws or international treaties
and conventions?
(c) If significant ecological
impacts are anticipated, are
adequate protection measures
taken to reduce the impacts on
the ecosystem?

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems
Ditto.

Port

(2) Ecosystem

Ditto.

At
district
level
endangered
species
are recorded. Details
need to be confirmed
by the further study
for the Project.
Currently,
no
significant impact is
predicted considering
Myanmar
environmental rules
and regulations. If any
impact
may
be
predicted by further
studies,
alternative
locations
will
be
examined
to
avoid/mitigate
the
predicted impacts.
No significant serious
impacts by the Project
are
predicted.
However,
if
any
impact
may
be
predicted by further
studies, as required,
necessary
measures
will be carried out.
Ditto.

Ditto.

Ditto.

(d) Is there a possibility that the


amount of water (e.g., surface
water, groundwater) used by the
project will adversely affect
aquatic environments, such as
rivers? Are adequate measures
taken to reduce the impacts on
aquatic environments, such as
aquatic organisms?
(e) Is there a possibility that
discharge of thermal effluents,
intake of a large volume of
cooling water or discharge of
leachates will adversely affect
the ecosystem of surrounding
water areas?
(d) Is there a possibility that the
project will adversely affect
aquatic
organisms?
Are
adequate measures taken to
reduce negative impacts on
aquatic organisms?
(e) Is there a possibility that the
project will adversely affect
vegetation or wildlife of coastal
zones? If any negative impacts
are anticipated, are adequate
measures taken to reduce the
impacts on vegetation and
wildlife?

Ditto.

Ditto.

143

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)

Ditto.

Ditto.

None

Small

Transmission/ Distribution

(d) Are adequate measures


taken to prevent disruption of
migration routes and habitat
fragmentation of wildlife and
livestock?

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems
Ditto.

Port

(3) Hydrology

(e) Is there any possibility that


the project will cause the
negative impacts, such as
destruction of forest, poaching,
desertification, reduction in
wetland areas, and disturbance
of
ecosystem
due
to
introduction
of
exotic
(non-native invasive) species
and pests? Are adequate
measures for preventing such
impacts considered?
(f) In cases where the project
site is located in undeveloped
areas, is there any possibility
that the new development will
result in extensive loss of
natural environments?

(a) Do the project facilities


affect adversely flow regimes,
waves, tides, currents of rivers
and etc if the project facilities
are constructed on/by the seas?

Ditto.

Ditto.

144

Alternati
on to
hydrolog
y and
resulting
changes
in tides
and
currents

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
There are no
situations such as
disruption
of
migration
routes,
habitat fragmentation
and traffic accident of
wildlife and livestock
in the Project sites. If
any impact may be
predicted by further
studies,
alternative
route
will
be
examined
to
avoid/mitigate
the
predicted impacts.
There may be some
threats and fears such
as
destruction
of
forests, etc. in the
Project. It is necessary
to be examined by
further study.

There may be some


possibility for loss of
natural environment in
the Project. It is
necessary
to
be
examined by further
study.
Significant
alternations of flows,
waves, tides, currents
by jetty construction
and operation are not
expected
in
the
Project.
If any impact may be
predicted by further
studies,
alternative
route
will
be
examined
to
avoid/mitigate
the
predicted impacts.

None

Transmission/ Distribution

(a) Is there any soft ground on


the route of power transmission
and distribution lines that may
cause
slope
failures
or
landslides?
Are
adequate
measures considered to prevent
slope failures or landslides,
where needed?

Small

Port

(4) Topography and Geology

(a) Does the project require any


large
scale
changes
of
topographic/geographic features
or cause disappearance of the
natural seashore?

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems
Alternati
on and
damages
to
topograp
hy by the
Project.

Ditto.

Thermal

(1) Resettlement

4 Social Environment

(b) Is there any possibility that


civil works, such as cutting and
filling will cause slope failures
or landslides? Are adequate
measures considered to prevent
slope failures or landslides?
(c) Is there a possibility that soil
runoff will result from cut and
fill areas, waste soil disposal
sites, and borrow sites? Are
adequate measures taken to
prevent soil runoff?
(a) Is involuntary resettlement
caused
by
project
implementation? If involuntary
resettlement is caused, are
efforts made to minimize the
impacts
caused
by
the
resettlement?

Ditto.

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
There may be less
possibility
for
alteration
and
damages
to
topography, geology,
and natural seashore
by the Project.
If any impact may be
predicted by further
studies,
alternative
route
will
be
examined
to
avoid/mitigate
the
predicted impacts.
There may be some
possibility
for
alternation
and
damage by the Project.
It is necessary to be
examined by further
study. If required
proper actions such as
slope
protection,
compaction, etc. will
be taken.
Ditto.

Ditto.

Ditto.

145

Involunt
ary
resettlem
ent
by
the
Project.

If land acquisition and


involuntary
resettlement
are
needed, Resettlement
Action Plan (RAP)
will be prepared based
on
international
standards. Fisher-men
who
may
have
impacts by the project
interventions shall be
also covered in RAP.

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)

(b) Is adequate explanation on


compensation and resettlement
assistance given to affected
people prior to resettlement?
(c) Is the resettlement plan,
including compensation with
full
replacement
costs,
restoration of livelihoods and
living standards developed
based on socioeconomic studies
on resettlement?
(d) Are the compensations
going to be paid prior to the
resettlement?
(e) Are the compensation
policies prepared in document?

Ditto

(f) Does the resettlement plan


pay particular attention to
vulnerable groups or people,
including women, children, the
elderly, people below the
poverty line, ethnic minorities,
and indigenous peoples?
(g) Are agreements with the
affected people obtained prior
to resettlement?
(h) Is the organizational
framework
established
to
properly
implement
resettlement? Are the capacity
and
budget
secured
to
implement the plan?
(i) Are any plans developed to
monitor
the
impacts
of
resettlement?
(j) Is the grievance redress
mechanism established?

Ditto

Ditto

Ditto

Ditto

Ditto

Ditto

Ditto

Ditto

Thermal

(2) Living and


Livelihood

(a) Is there a possibility that the


project will adversely affect the
living conditions of inhabitants?
Are
adequate
measures
considered to reduce the
impacts, if necessary?

146

Harmful
effect
and
unemplo
yment
etc.
to
residents
by
the
Project.

Adverse impacts to
people such as noise,
vibration,
air
pollution, etc. should
be
taken
into
consideration.
As
required,
necessary
measures will be
carried out.

(c) Is there a possibility that


large vehicles traffic for
transportation of materials, such
as raw materials and products
will have impacts on traffic in
the surrounding areas, impede
the movement of inhabitants,
and any cause risks to
pedestrians?
(d) Is there a possibility that
diseases, including infectious
diseases, such as HIV, will be
brought due to the immigration
of workers associated with the
project?
Are
adequate
considerations given to public
health, if necessary?

None

Small

(b) Is sufficient infrastructure


(e.g., hospitals, schools, and
roads) available for the project
implementation? If the existing
infrastructure is insufficient, are
any plans
developed
to
construct new infrastructure or
improve
the
existing
infrastructure?

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Harmful
effect to
living
condition
s
of
residents
by
the
Project
and
surround
ing
residents.
Accident
and
traffic
congesti
on by the
Project

Port

(2) Living and


Livelihood

(e) Is there a possibility that the


amount of water used (e.g.,
surface water, groundwater) and
discharge of thermal effluents
by the project will adversely
affect existing water uses and
uses of water areas (especially
fishery)?
(b) Is there a possibility that
changes
in
water
uses
(including
fisheries
and
recreational uses) in the
surrounding areas due to project
will adversely affect the
livelihoods of inhabitants?

147

Potential
Environ
mental
Issues
and
Problems

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
No significant serious
impacts by the Project
are
predicted.
However, as required,
necessary
measures
will be carried out.

Ditto.

Deteriora
tion of
Public
hygiene
by
the
Project

Contermeasures will
be taken by interal
regualtions imposed
by the Project and in
cooperation with the
related aurhorities so
that such situations
will not arisen by the
Projects.
Harmful No significant serious
effect to impacts by the Project
livelihoo are
predicted.
d
of However, as required,
surround necessary
measures
ing
will be carried out.
residents.
Ditto

Loss of fishing ground


by construction of
jetties may occur at
small scale, but no
significant
serious
impacts by the Project
are
predicted.
However, as required,
necessary
measures
will be carried out.

None

Small

(c) Is there a possibility that


port and harbor facilities will
adversely affect the existing
water traffic and road traffic in
the surrounding areas?

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Transmission/ Distribution

(2) Living and Livelihood

Common

(3) Heritage

(c) Is there any possibility that


installation of structures, such
as power line towers will cause
a radio interference? If any
significant radio interference is
anticipated,
are
adequate
measures considered?
(d) Are the compensations for
transmission wires given in
accordance with the domestic
law?
(a) Is there a possibility that the
project will damage the local
archeological,
historical,
cultural, and religious heritage?
Are
adequate
measures
considered to protect these sites
in
accordance
with
the
countrys laws?

Potential
Environ
mental
Issues
and
Problems

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)

Accident
and
traffic
congesti
on by the
Project

No significant impacts
are predicted by the
Project. But it is
necessary
to
be
examined by further
study.
.
Interfere There may be some
nce
to impacts by the Project.
current
It is necessary to be
living
examined by further
study.

Ditto

Ditto.

Common

(4) Landscape

(a) Is there a possibility that the


project will adversely affect the
local landscape? Are necessary
measures taken?

Destructi
on and
damages
by
the
Project

148

In the vicinity of
candidate sites there
are
a
few
archeological,
historical,
cultural,
and religious heritage
sites. Primarily such
locations shall be
avoided upon the
selection of the site. If
any impact may be
predicted by further
studies,
required
countermeasures will
be
examined
to
avoid/mitigate
the
predicted impacts.
Landsca Basically,
no
pe
significant impact is
inhibitio predicted, but shall
n by the confirm whether the
Project
Project inhibit views
to pagoda along the
coast. If any adverse
impacts are predicted
in further study phase,
necessary
countermeasures will
be taken based on the
Myanmar laws and
regulations.

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems

Common

(5) Ethnic Minorities and Indigenous Peoples

Common

(6) Working Conditions

(a) Are considerations given to


reduce impacts on the culture
and
lifestyle
of
ethnic
minorities
and
indigenous
peoples?

Impact
on
the
Ethnic
Minoritie
s
and
Indigeno
us
Peoples
by
the
Project

(b) Are all of the rights of


ethnic
minorities
and
indigenous peoples in relation
to land and resources respected?
(a) Is the project proponent not
violating
any
laws
and
ordinances associated with the
working conditions of the
country which the project
proponent should observe in the
project?

Ditto.

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
Though there are
certain
ethnic
minorities
reside
within the township,
no significant ethnic
issue in and around
the
Project
is
predicted.
If
any
impact
may
be
predicted by further
studies,
required
countermeasures will
be
examined
to
avoid/mitigate
the
predicted impacts.
Ditto.

Corrupti
on
in
occupati
onal
health
and
safety by
the
Project

The
working
conditions will be
protected
by
the
Myanmar laws and
regulations.
As
required, the Project
will prepare internal
regulations
for
occupational
health
and safety referring to
regulations imposed
by
international
organizations
and
other countries
Accident Proper instruction and
at work guidance on safety
by
the consideration will be
Project
given to workers and
other
individuals
involved
in
the
Projects.

(b)
Are
tangible
safety
considerations in place for
individuals involved in the
project, such as the installation
of safety equipment which
prevents industrial accidents,
and management of hazardous
materials?
(c) Are intangible measures
being planned and implemented
for individuals involved in the
project,
such
as
the
establishment of a safety and
health program, and safety
training (including traffic safety
and public health) for workers
etc.?

Ditto.

149

Proper instruction and


guidance about safety
and hygiene will be
given to workers and
other
individuals
involved
in
the
Projects.

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems

Common

(1) Impacts during Construction

5 Others

(d) Are appropriate measures


taken to ensure that security
guards involved in the project
not to violate safety of other
individuals involved, or local
residents?

Safety of
local
residents
inhibitio
n
compani
on by the
Project

(a) Are adequate measures


considered to reduce impacts
during construction (e.g., noise,
vibrations, turbid water, dust,
exhaust gases, and wastes)?

Environ
mental
pollution
and
contamin
ation Noise &
vibration
,
turbidity,
dust,
exhauste
d
gas,
wastes,
etc..

(b) If construction activities


adversely affect the natural
environment (ecosystem), are
adequate measures considered
to reduce the impacts?

Damages
to natural
environ
ment by
the
Construc
tions

(c) If construction activities


adversely affect the social
environment, are adequate
measures considered to reduce

Traffic
congesti
on,
nuisance,
150

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
Proper instruction and
guidance about safety
and hygiene will be
given to workers and
other
individuals
involved
in
the
Projects. Also public
awareness raising to
the general public will
be also implemented.
The following
measures will be
taken:
(1)
Noise &
vibration: Low noise
and vibration
methods and
constructional
vehicles and
equipment.
(2)
Turbid
water: Sediment
basins, etc.
(3)
Exhaust gas:
Less exhaust gas
constructional
vehicles and
equipment.
(4)
Construction
dusts: Spraying
water, etc.
(5)
Wastes:
Spoils, solid wastes,
etc. will be properly
disposed or
reclaimed.
It is considered that
the
construction
activities will not
affect the natural
environment adversely
in the construction
sites, but adequate
measures will be
considered to mitigate
impacts as required.
Adequate
measures
such as detours, etc.
will be taken to
mitigate impacts to

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

Potential
Environ
mental
Issues
and
Problems

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
social environment.

(a) In the case of coal-fired


power plants, are adequate
measures planned to prevent
spontaneous combustion at the
coal piles (e.g., sprinkler
systems)?

Risk of
fire and
explosio
n

common

(3) Monitoring

etc

Thermal

(2) Accident
Prevention
Measures

the impacts?

(a) Does the proponent develop


and implement monitoring
program for the environmental
items that are considered to
have potential impacts?

Proper instruction and


guidance about fire
prevention as well as
proper fire prevention
facilities
will
be
provided
in
the
Projects.
Monitoring should be
executed, based on
environmental plan in
EIA. In case RAP is
prepared, monitoring
should
be
also
executed based on
monitoring
plan
described in RAP.
Ditto.

(b) What are the items, methods


and
frequencies
of
the
monitoring program?

Thermal

Reference to Checklist of Other Sectors

6 Note

(c) Does the proponent establish


an
adequate
monitoring
framework
(organization,
personnel, equipment, and
adequate budget to sustain the
monitoring framework)?
(d)
Are
any
regulatory
requirements pertaining to the
monitoring
report
system
identified, such as the format
and frequency of reports from
the proponent to the regulatory
authorities?
(a) Where necessary, pertinent
items described in the Power
Transmission and Distribution
Lines checklist should also be
checked
(e.g.,
projects
including installation of electric
transmission
lines
and/or
electric distribution facilities).

Ditto.

Ditto.

(b) Where necessary, pertinent


items described in the Ports and
Harbors checklist should also
be checked (e.g., projects
including construction of port
151

Placeme
nt of the
transmiss
ion line
by
the
Project

Incorporated in this
checklist.
Transmission line and
relevant facilities may
be
involved
in
construction of the
coal thermal plant, but
needed
to
be
confirmed at further
study for the Project
Placeme Incorporated in this
nt
of checklist.
jetty
Limited impacts are
facilities predicted
for
by
the construction of jetty

None

Small

Not Clear

Main Check Items


Major

Environmental
Item

Category

Significance of
Possible
Environmental Impacts

and harbor facilities).

Potential
Environ
mental
Issues
and
Problems
Project

Transmission/ Distribution

Construc
tion of
roads for
transmiss
ion line
installati
on

Common

Note on Using Environmental


Checklist

(a) Where necessary, pertinent


items described in the Road
checklist should also be
checked
(e.g.,
projects
including installation of electric
transmission
lines
and/or
electric distribution facilities).

(a) If necessary, the impacts to


transboundary or global issues
should be confirmed (e.g., the
project includes factors that
may cause problems, such as
transboundary waste treatment,
acid rain, destruction of the
ozone layer, and global
warming).

Global
environ
mental
issues by
the
Project

Confirmation of
Environmental
Considerations
(Reasons, Mitigation
Measures)
facilities
for
the
Project,
However,
details needed to be
confirmed at further
study for the Project
Limited impacts are
predicted
for
construction of roads
for transmission line
installation, However,
details needed to be
confirmed at further
study for the Project

No serious global
issues is predicted by
the Project, since
impacts by the exhaust
gases
will
be
minimized as much as
possible
by
introducing
various
energy
saving
measures
by
the
Project.
However,
details needed to be
confirmed at further
study for the Project
Alternati No serious impacts to
on and ground
water
is
damages predicted
by
to
construction of jetty
ground
for the project
water
regimes
by
the
Project

Port

Note on Using Environmental Checklist

(a) Where necessary, impacts

on groundwater hydrology
(groundwater level drawdown
and salinization) that may be
caused
by
alteration
of
topography, such as land
reclamation
and
canal
excavation
should
be
considered, and impacts, such
as land subsidence that may be
caused by groundwater uses
should be considered. If
significant
impacts
are
anticipated, adequate mitigation
measures should be taken.
1). Regarding the term Countrys Standards mentioned in the above table, in the event that
environmental standards in the country where the project is located diverge significantly from
international standards, appropriate environmental considerations are requested to be made. In cases
where local environmental regulations are yet to be established in some areas, considerations should
152

be made based on comparisons with appropriate standards of other countries (including Japan's
experience).
2). Environmental checklist provides general environmental items to be checked. It may be necessary to
add or delete an item taking into account the characteristics of the project and the particular
circumstances of the country and locality in which it is located.
Source: Prepared by Study Team based on JICA s Environmental Checklist

b) Alternatives and Mitigation Measures on Environmental and Social Consideration for the Project
The several alternative locations, possible designs and construction methods for the coal thermal power plant and
the jetty will be examined in further study phase. Also detail land use and socio-economic conditions of potential
project affected people (PAPs) will be verified in further study phase of the Project.
Meanwhile, detailed alternatives have not been studied or specified because basic plan and design of the thermal
power plant and regional development program are not finalized yet. To prepare and finalize those, it is necessary
to collect detailed data and information such as geological/ hydrological / bathymetric conditions of concerned
onshore area through site surveys and measurements.
Therefore, draft mitigation measures, alternative locations and design cannot be studied in details currently. If the
Project has significant influence on natural and social environmental conditions, it is necessary to identify such
impacts, and propose alternative plans for whole or a part of the Project to mitigate the predicted impacts.
At present, technically, no serious adverse impact is predicted by construction and operation of the coal thermal
power plant if appropriate mitigation measures as described in

are adopted and implemented. However, the coal

thermal power has significantly negative impressions within Myanmar. Thus, raising public awareness about the
coal thermal power plant in general may be required to mitigate unnecessary objection and negative campaigns
toward the Project.

153

(4) Outlines of the related laws and regulations for environmental impact
assessment in Myanmar
a) Environmental Laws, Rules and Regulations of the Republic of the Union of Myanmar

1. Environmental Legislation and Institutional System


a. Institutional Setting
As of end of November 2014, Myanmar has 31 ministries in its Union Government. The leading ministries in
charge of environmental and social consideration are the Ministry of Environmental Conservation and Forestry
(MOECAF) and the Ministry of Social Welfare, Relief and Resettlement (MSWRR). Depending on type and
extent of projects, other ministries such as the Ministry of Home Affairs, the Ministry of Agriculture and Irrigation,
the Ministry of Labor, the Ministry of Construction, the Ministry of Industry, and so on will take roles in
environmental and social consideration.

b. Fundamental Laws and Regulations


Major legislations pertinent to natural and social environment areas in Myanmar are categorized as follows and
described hereunder;
-

Laws and regulations related to environmental consideration,

Laws and regulations related to social welfare and occupational health, and

Key laws and regulations for land related right and land acquisition.

c. Laws and Regulations Related to Environmental Consideration


Followings and their amendments/ subordinate documents are key as well as applicable laws and regulations in
respect to Environmental Consideration in current Myanmar. Except for the Environmental Conservation Law
(2012) and its subordinate laws / rules, there are no law determining about the comprehensive environmental
conservation and management in Myanmar. Currently, the following laws and regulations are enacted in
environmental and social consideration field in Myanmar.
-

The Water Power Act 1927 (Burma Act 11, 1927)

The Underground Water Act 1930

Territorial Sea and Maritime Zone Law 1977

Irrigation Laws and Regulations 1982

Law on Aquaculture 1989

Marine Fisheries Law (1990)

Freshwater Fisheries Law (1991)

The Forest law 1992 (8/92)

The Protection of Preservation of Cultural Heritage Region Law 1994


154

The Protection of Wildlife, Wild Plant and Conservation of Natural Area Law 1994

National Environment Policy 1994

Mines Law 1994

The Conservation of Water Resources and River Law 2006

The Environmental Conservation Law 2012

Farmland Law 2012 (Pyidaungsh Hluttaw Law No.11, 2012)

Farmland Rules, 2012 (President Office Notification No 62, 2012)

Vacant, Fallow and Virgin Lands Management Law 2012 (Pyidaungsh Hluttaw Law No.10)

Vacant, Fallow and Virgin Lands Management Rules 2012 (President Office Notification No 1, 2012)

The Environmental Conservation Rules 2014

The EIA Procedure (Draft)

d. Laws and Regulations Related to Social Welfare and Occupational Health


Some of existing laws and regulations determine about social welfare issues and environmental consideration
issues. Major existing and applicable laws for social welfare are listed as follows.
-

Factory Act 1951

The Oil Field (Labor and Welfare ) Act 1951

The Leave and Holiday Act 1951

Public Health Law 1972

Standing Order 2/95 Occupational Health Plan 1995

Settlement of Labor Dispute Law 2012 (5/2012)

Social Welfare Law 2012 (15/2012)

Minimum Wage Law 2013 (7/2013)

e. Key Laws and Regulations for Land Related Right and Land Acquisition
Followings and their amendments/ subordinate documents are key as well as applicable laws and regulations in
respect to land related rights and land acquisition in current Myanmar. Though some laws already have been
repealed, such laws are still partially applicable depending on situations.
-

The (Lower Burma) Land and Revenue Act, 1879 (India Act II, 1876)

The Upper Burma Land and Revenue Regulation, 1889

The Land Acquisition Act, 1894 (India Act 1, 1894)

Land Acquisition Directions

The Lower Burma Town and Village Lands Act 1899 (Burma Act IV, 1898)

Land and Revenue Order (Rule), 1911

Land Acquisition Rules 1932

Land Acquisition Manual 1947

The Land Nationalization Act,1953 (Act No 75, 1953)*

Land Nationalization Rules, 1954*


155

The Law Safeguarding Peasant Rights (Agriculturists Rights Protection Law) 1963 (Union Myanmar
Revolutionary Council Law No. 91, 1963)

Farmland Law 2012 (Pyidaungsh Hluttaw Law No.11, 2012)

Farmland Rules, 2012 (President Office Notification No 62, 2012)

Vacant, Fallow and Virgin Lands Management Law 2012 (Pyidaungsh Hluttaw Law No.10)

Vacant, Fallow and Virgin Lands Management Rules 2012 (President Office Notification No 1, 2012)
*Law itself is already repealed but some of sections are still applied depending on respective situations.

f. Laws and Regulations at State Level


Similar to other regions/states in Myanmar, Mon State follows Union level laws and regulations most of cases.
However, Mon State also enacts is own laws and regulations. Followings are major state level laws in Mon State.

Table 4-43 Major Mon State Level Laws and Regulations

No.
1

Law Name
Mon State Fishery
Law
(11st April 2014)

Mon State Village


Fuel-wood Plantation
Law
(30th
September
2013)

Conservation
of
Cultural
Heritage
Law, Mon State
(8th November 2013)
Systematic
Production
and
Usage of Fertilizer
Law in Mon State
(23rd
December
2014)

Salt
and
Salt
Products Law in
Mon State
(11st April 2014)

General Summarization
(A) The objectives of the law are
(i) To protect the extinct of fish species and to develop fisheries
(ii) To protect damage of freshwater fishery water expanses
(iii) To permit fishery by paying tax to the State
(iv) To manage fisheries by law and taking legal actions.
(B) The law determines about fishery water expanse for coastal water and
freshwater, committees duties, fishery franchise holding persons duties, etc,. )
The conservation of biodiversity of algae and other aquatic creatures in coastal area
is one of committees duties.
A) The objectives of the law are
(i) To develop the State by establishing village fuel-wood plantations in vacant
lands, lands under governments control, and damaged forest lands.
(ii) To increase land use price
(iii) To obtain more fuel-wood due to the systematic fuel-wood consumption
through collective plantation, production and utilization of user groups.
(iv) To protect natural disaster and to conserve natural environment
(v) To utilize the residual parts of fuel-wood such as trunk for other purposes
B)
The law determines about formation of village fuel-wood
plantation, committees duties, foresters duties and Inspections activities, etc.)
The law determines about designation of cultural heritage area, conservation and
protection of cultural heritage area, committees duties, issue of permit for
constructions of hotels, industrial buildings, and research activities in cultural area,
and inspection activities in cultural heritage area, etc.
The main objectives of the law are
(i) To support development of farming sector which is fundamental economy of
country
(ii) To supervise fertilizer enterprise
(iii) To support natural environmental conservation and soil conservation by
utilizing proper fertilizers
(iv) To conduct research and education programs for growers to provide
comprehensive knowledge of fertilizer application
(v) To enhance cultivation of organic products and to provide safe crops to public
The main objectives of the law are
(i) To produce salt and salt products without forest depletion
(ii) To extend the production capacity of salt and salt production area
(iii) To assist in salt and salt products export activities
(iv) To distribute enhanced technologies to salt and salt products entrepreneurs
156

No.
6

Law Name
Recreation Centers,
Zoological
and
Botanical
Garden
Law
(Draft version)

Mon
State
Development Law
(Amended)
(10th April 2013)

Mon
State
Loading/Unloading
Law
(19th
December
2012)

Mon State Excise on


Alcohols/Beer/Spirits
Law
(19th
December
2012)
Mon State Land Tax
Law
(19th
December
2012)
Mon State Fire Risk
and Natural Disasters
Prevention Law
(10th April 2013)

10

11

12

13

Mon State Theatre


Supervision Law
(10th April 2013)
Mon State Private
Water-crafts
Operation Law
(8th November 2013)

General Summarization
The objectives of the law are
(i) To protect natural plants and wild animals by establishing zoological and
botanical gardens
(ii) To protect animals and natural plants and their origin having dangers of
extinction
(iii) To support natural science researches
(iv) To conduct development programs considering environmental conservation
affairs
(v) To cooperate between government organizations, international organizations,
non-government organizations, and individuals for environmental conservation
affairs.
(vi) To provide recreation centers for public
The Law determines about management of development activities (town planning,
water supply, town cleansing, sanitation in rural and downtown area, electricity
supply, establishing of private and development committee markets, environmental
conservation activities, public health caring activities, etc.), management of vehicles
including slow moving vehicles like trishaw, management of ferry boats business,
management of killing animals, finance management, fund raising for development
activities, taxes collection, etc.
The objectives of the law are
(i) To support for improvement of trading and rapid trade flow
(ii) To provide worthy wages to loading and unloading worker for their physical
efforts
(iii)To provide social stability and occupation welfare of loading and unloading
workers
The law determines about permission of loading and unloading enterprise,
systematic supervisions on loading and unloading enterprise under rules and
regulations of this Law, Occupational safety, etc.
The objectives of the law are
(i)
To control the epidemic of alcoholic drinking habit
(ii)
To avoid illegal production and selling in the distribution of alcohols
(iii)
To attain excise on alcohols/beer/spirits for the State
The law determines about farm land to be taxed, rate of land tax, exemption of land
tax, collection of land tax, collection of unpaid land tax by opening as case file, etc.

The objectives of the law are


(i)
To prevent or mitigate the damage/deprivation of cultural heritage, private
and government industries/ enterprises/ services, publics health, life, building and
property, farm lands and animals due to fire risk and natural disasters.
(ii)
To conduct emergency response plans and rescure plans without any time
delay in case of fire risk and natural disasters
(iii)
To implement rehabilitation activities as soon as possible after fire risk
and natural disasters
The law determines about formation of fire risk and natural disasters prevention
committee, implementation of fire risk and natural disasters prevention activities,
rescue and rehabilitation activities, etc.
The law determines about application procedure to get permission for holding
variety concert at theatre, functions and duties of concert organizer, etc.
The law determines about extension of water-crafts lines, construction of jetties,
cooperation between water-crafts owners/businessmen under township committees
guidance to emerge modern transportation system having less impact on natural
environment, registration and designation of water-craft line, fund raising activities,
etc.
157

No.
14

15

Law Name
General Summarization
Mon State Honorary The objectives of the law are
Certificates
and (i)
To develop the State and Nation
Commendations
(ii)
To develop economy and social activities
Awarding Law
(iii)
To honor persons who valiantly participate in the fields of literature,
(31st
September culture, religion, etc.
2013)
Regulation
for No fishing zone is defined for around 300 meter surrounding of Kyaikkami Yee Le
Fishery
around Pagoda and lobster protected area is defined for about 3 km2 (3 km x 1 km)
Pagoda areas
surrounding of Kyaik Saw Yee Le Pagoda area respectively. Source: Department of
Fisheries Thanbyuzayat Township.
Source: Relevant state level laws and regulations

b) Environmental Quality Standards


According to the Environmental Conservation Law, MOECAF will set standards of environmental qualities as
agreed by the Union Government and the Environmental Conservation Committee. Standards to be set by
MOECAF are as follows:
-

Standard quality of water related to the use of inland water available to public places, dams, ponds,
swamps, flooded land, channel, creeks and rivers.

Standard quality of water at coastal regions and delta area

Standard quality of groundwater

Standard quality of air

Standard of noise and vibration

Standard of odor and emission gas

Standard of wastewater

Standard of soil and leachate from solid waste

Other standard environment qualities set by the Union Government

As of the end of November 2014, these standards have not been set yet. Project proponents are required to set
quantitative target levels, independently at this moment.
Currently, MOECAF is in a process for establishment of National Environmental Quality Standards. However,
establishment of comprehensive and practical standards is quite difficult task and it may take certain time. In
consideration of immediate demand for waste water quality, MOECAF is planning to determine Guidelines for
National Environmental Quality Standards, and National Wastewater Quality Standard by end of FY2014.
Though industrial waste water quality has not been stipulated by MOECAF as of November 2014, Ministry of
Industry (MOI) has issued Water and Air Pollution Control Plan on 21st August, 1995. This plan has stipulated
standard values for wastewater effluent from industries before the effluent can be discharged into natural water
environment such as rivers, creeks, lakes and ponds. Currently, these values are often referred to in Myanmar, thus
until establishment of the national environmental standards or guidelines, the target industrial wastewater effluent
from the Project shall not exceeded the values presented in .

158

Table 4-44 Guideline Value of Industrial Wastewater Effluent

No.
1
2

Parameter
Temperature
pH

Color and Odor

4
5

Dissolved solids
SS
BOD (5 days at
20oC)
COD (KMnO4)
Sulphide (as H2S)
Cyandie (as HCN)
Oil and Grease
Tar
Formaldehyde
Phenol and cresols
Free chlorine
Zinc
Chromium
Arsenic
Copper
Mercury
Cadmium
Barium
Selenium
Lead
Nickel
Insecticides
Radioactive
materials

6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26

Unit
o
C

Allowable values
Max 40
5-9
-

mg/L

Max 2000
Max 30

mg/L

Max 20-60

mg/L
mg/L
mg/L
mg/L

Max 60
Max 1
Max 0.2
Max 5
None
Max 1
Max 1
Max 1
Max 5
Max 0.5
Max 0.25
Max 1.0
Max 0.005
Max 0.03
Max 1.0
Max 0.02
Max 0.2
Max 0.2
None

mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L

Remarks

Not objectionable when mixed in receiving


water

Depending on geography of waste


discharging point

None
Source: Ministry of Industry

c) EIA System and Approval Procedure in Myanmar

1. Laws and Regulations regarding EIA


a. Introduction
As of November 2014, detailed legal process for the Environmental Impact Assessment (EIA) has not been
enacted in Myanmar. However, the Ministry of Environmental Conservation and Forestry (MOECAF) has been
preparing series of the EIA Procedure draft which defines detailed legal process related to EIA. The draft EIA
Procedure covers contents such as screening of projects, qualification for conducting EIA/ IEE (Initial
Environmental Examination), preparation of EIA/IEE report, Environmental Management Plan (EMP), public
involvement, approval of EIA/IEE report by MOECAF, , Environmental Compliance Certificate (ECC), and
monitoring process after approval of EIA/IEE report and etc.. Currently, 6th draft of EIA Procedure is under
preparation.
Though the EIA Procedure is still not enacted, currently, majority of new projects in Myanmar are often
requested by the Myanmar Investment Commission (MIC) to submit EIA/ IEE report in accordance with draft
EIA procedures, upon business/ investment applications. This is prevalent in case of foreign investment projects
159

regulated by the Foreign Investment Law 2012 and its subordinate laws/regulations.
Myanmar Investment Commission Notification No. 50/2014 (14 August 2014, modifications of Notification No.
1/2013), Economic Activities Which Require Environmental Impact Assessment, determines 30 sectors which
require EIA prior to business license. In the list, following are types of economic activities which require EIA and
relevant to power generation.
-

No. 4: Hydropower and other heavy electricity generation, construction of electrical power transmission
line

The Foreign Investment Rules 2013 also depicts that environmental social considerations of projects shall refer
to the Environmental Conservation Law.

2) Super Ordinate Laws of draft EIA Procedures


a. Environmental Conservation Law (2012)
Environmental Conservation Law (ECL) in Myanmar was prepared by MOECAF and enacted in 31 March, 2012.
This is the fundamental law for environmental conservation in Myanmar. describes overall composition of ECL.

Table 4-45

Composition of the Environmental Conservation Law

Chapter
1
2
3
4
5
6
7
8
9
10
11
12
13
14

Title and Definition


Objectives
Formation of the Environmental Conservation Committee
Duties and Powers relating to the Environmental Conservation of the
Ministry
Environmental Emergency
Environmental Quality Standards
Environmental Conservation
Management of Urban Environment
Conservation of Natural Resources and Cultural Heritages
Prior Permission
Insurance
Prohibitions
Offences and Penalties
Miscellaneous
Source: Environmental Conservation Law 2012

Sections
1-2
3
4-6
7-8
9
10-12
13-16
17
18-20
21-25
26-27
28-30
31-34
35-42

b. Environmental Conservation Rules (2014)


Environmental Conservation Rules (ECR) is detailed enforcement regulations of the Environmental
Conservation Law and enacted on 5 June, 2014. describes overall composition of ECR.

160

Table 4-46

1
2
3
4
5
6
7
8
9
10
11
12
13
14

Composition of the Environmental Conservation Rules

Chapter
Title and Definition
Adopting Policy Relating to Environmental Conservation
Environmental Conservation
International, Regional and Bi-lateral Cooperation Relating to
Environmental Conservation
Environmental Management Fund
Environmental Emergency
Environmental Quality Standards
Management of Urban Environment
Waste Management
Conservation of Natural Resources and Cultural Heritages
Environment Impact Assessment
Prior Permission
Prohibitions
Miscellaneous
Source: Environmental Conservation Rules 2014

Sections
1-2
3-6
7-26
27-28
29-35
36-37
38-39
40
41-46
47-50
51-61
62-68
69
70-74

ECR stipulates basic policy and concept on EIA application of the development of Projects (Chapter 11);
-

To prepare the environment impact assessment report including EMP and submit to the Ministry (Section
55 (a)), and

To implement and carry out EMP within the time stipulated by the Ministry and submit the performance
situation to the Ministry (Section 55 (b)).

Prior Permission (Chapter 12) is required for categories of business, work-site or factory, workshops which may
cause an impact on the environmental quality (Section 62). Though categories of business and activities which
require the prior permission are yet to be determined as of November 2014, businesses / projects which may cause
hazardous impacts and projects which are required to conduct EIA / IEE seem to be categorized for prior
permission according to the latest draft EIA procedure.
c. Draft EIA Procedures
Though there are still considerable modifications going on by MOECAF for the EIA Procedures as of November
2014, there seems to be not much of significant changes in the overall composition of the EIA Procedures among
the different versions of drafts. describes overall composition of the latest EIA Procedure.
Table 4-47

1
2-1
2-2
3
4
5
6
7
8
Appendix A
Appendix B
Appendix C

Composition of the draft EIA Procedure (November 2014)

Chapter
Title and Definition
Establishment of Environmental Impact Assessment Process
Requirement of Third Parties to Conduct EIA/IEE
Screening
Initial Environmental Examination
Environmental Impact Assessment
Environmental Consideration in Project Approval
Monitoring
Penalties
Project Categorization for Assessment Purposes
IEE/EIA Procedures
Penalties Categorization
Source: Draft EIA Procedures
161

Sections
1-2
3-14
15-22
23-27
28-40
41-73
74-95
96-112
113-120

3) EIA System and Approve Procedure


a. Basic framework of EIA
According to the draft EIA procedure, basic framework to be laid out for EIA in Myanmar is as follows.
-

All projects undertaken in Myanmar by any organizations or individuals having the potential to cause
significant adverse impacts, are required to undertake environmental impact assessment and to obtain an
Environmental Compliance Certificate in accordance with the EIA Procedure. (Article 3, 6th draft)

The EIA Procedure does not address specific matters in relation to resettlement and indigenous people.
Projects involving resettlement or potentially affecting indigenous people shall additionally comply with
separate procedures issued by responsible ministries before issuing separate procedures by MOECAF, and
in the absence of such procedures all such projects shall adhere to international good practice on
involuntary resettlement and indigenous people.(Article 9, 6th draft)

Existing projects or projects under construction before the issuance of the EIA Procedure shall develop an
Environmental Management Plan (EMP) within a time frame prescribed by the Ministry and such EMP
shall be subject to the review and approval of the Ministry. (Article 10, 6th draft)

b. Screening of Projects
According to the draft EIA Procedure, MOECAF will determine project type (scale of environmental
assessment) based on project proposals submitted by project proponents (Article 23, 6th draft, ).

Table 4-48 Types (Scales) of Projects Determined in EIA Procedure


Project Type
Description
EIA Type Project
Project judged by MOECAF as being likely to have
potential for adverse impacts. Pubic consultation process
is obligatory
IEE Type Project
Project judged by MOECAF to have some adverse
impacts, but of lesser degree and/or significance than
those for EIA type projects. Public consultation process is
required based on necessity
Neither EIA nor IEE Project judged by MOECAF not required to undertake any
Type Project
environmental assessment.
Source: Draft EIA Procedures
The draft EIA Procedure also determines project categories which require EIA or IEE (Annex 1 Project
Categorization for Assessment Purposes). Though there are certain changes of project categories among drafts,
the latest draft EIA Procedure is aiming to simplify but to include necessary project categories which require EIA
or IEE.
c. Process of IEE/EIA
The draft EIA Procedure determines processes for IEE, EIA and required actions for on-going projects (when the
EIA Procedure is enacted). Following figure summarize respective processes. The process which is currently
required by MIC is also included in .
162

Figure 4-16 Overall EIA Process in draft EIA Procedures and MIC application

IEE

EIA

On-going Projects

MIC Requirements

Environmental (IEE)
Investigation
(including Public
Consultation Process)

Scoping
(Public Consultation)
Scoping Report

Environmental / Social
Compliance Audit
& Investigation

Submission of
Environmental & Social
Consideration Related
Report

Environmental (EIA)
Investigation

Submission of
Environmental
Management Plan
(EMP)

Preparation &
Submission of IEE
Report
Review and Approval
Process
(Maximum 60days)
(Including IEE Report
Disclosure & Public
Consultation Process)

Issuance of
Environmental
Compliance Certificate
(ECC)

Draft EIA Report


Disclosure and Public
Consultation of draft
EIA Report

MIC 1st Review (PAT)


Comments from
Relevant Ministries and
Reflection of Comments
to the Report
MIC 2nd Review,
Approval of Report

Submission of EIA
Report
Review and Approval
Process
(Maximum 90days)
Issuance of
Environmental
Compliance Certificate
(ECC)

Source: Draft EIA Procedures and MIC related documents

d. Environmental Compliance Certificate


According to the 6th draft EIA Procedure, MOECAF will issue Environmental Compliance Certificate (ECC)
after approving IEE Report or EIA Report, or an EMP.
After the EIA Procedure will be enacted, obtaining ECC will be prerequisite for obtaining permit issued by the
Myanmar Investment Commission, any ministry, or any other competent authority, to proceed implementation
of the Project.

e. Draft EIA/IEE Categorization for Energy Sector Projects


At the latest draft EIA Procedure, 24 types of projects for energy sector are determined for IEE/EIA categories
and details are described in .

163

Table 4-49 Draft EIA/IEE Categorization for Energy Sector Projects


Project
Type of Investment Projects
No.
2 Hydro power project

3 Nuclear power plant


4 Natural gas or biogas power plant or
waste heat power plant
5 Coal power plant
6 Thermal power plant (not included in
No. 4 and 5 categories)
7 Geothermal power plant
8 Construction of combined cycle (Gas
and Thermal) power stations
9 Wind power plant
10 Solar power plant
11 Plant of power generation from waste
materials
12 Construction or distribution of oil and
natural gas pipeline
13 Oil refinery plant or Natural gas plant
(LPG, LNG, Mo Gas, Kerosene,
Diesel, Fuel, Petroleum, )
14 Oil and Natural gas terminals
15 Fuel station (including LPG, CNG)
16 Construction of depot for oil or natural
gas storage

Size of Project which require


IEE
1MW and < 15 MW (or)
reservoir capacity <
20,000,000 m3 (or) reservoir
area < 400 ha
5 MW and 50 MW

15 MW (or) reservoir capacity


20,000,000 m3 (or) reservoir area
400 ha
All sizes
50 MW

1 MW and 10 MW
5 MW and 50 MW

10 MW
50 MW

5 MW and 50 MW

50 MW

5 MW and < 50 MW

50 MW

10 MW and 50 MW
50 MW

50 MW
All projects which IEE
recommends to conduct EIA
All projects which IEE
recommends to conduct EIA
50 km

50MW
> 10 km and < 50 km
-

storage capacity > 10 m3


(10,000 L)
oil storage capacity < 10,000
tons - gas storage capacity <
2,500 tons
< 50 km

17 Installation of Electrical power line <


230 kV
18 Installation of Electrical power line
(Main power line) 230 kV
19 High voltage transformer substation
< 10 ha
20 Oil or natural gas exploration by
All sizes
means of geophysical drilling
21 Onshore oil and gas development
projects
22 Offshore oil and gas development
projects
23 Production of oil -based organic
chemical
24 Natural Gas production industry (LPG
products including Naphtha, gasoline,
kerosene, disel fuel, waxes, lubes or
Methanol)
25 Liquefied Natural Gas production
industry
Source: Draft EIA Procedures

Among the categories indicated in

Size of Project which require EIA

All sizes

All sizes
All projects which IEE
recommends to conduct EIA
oil storage capacity 10,000 tons
- gas storage capacity 2,500
tons
50 km
All sizes
10 ha
All projects which IEE
recommends to conduct EIA
All sizes
All sizes
All sizes
All sizes

All sizes

as well as in other categories in the latest draft EIA procedures, following


164

types of project categorization are more likely applicable for the Project considered in the Study (). Considering
the current plan for the Project, EIA level study is required for the coal power plant. For the jetty component, it
shall be considered as one of subsidiary facilities of the coal power plant and to shall be assed as part of the EIA
level study for the entire coal power plant.

Table 4-50 Possible EIA/IEE Categorization for the Project


Type of Investment Projects
Coal power plant

Size of Project which require IEE


1 MW and 10 MW

Installation of Electrical power line < 230 < 50 km


kV
Installation of Electrical power line (Main
power line) 230 kV
Port construction project (port, jetty and
area < 25 ha
warehouse to load cargos and dock the
passenger ships)
Source: Draft EIA Procedures

Size of Project which require EIA


10 MW
50 km
All sizes
Area 25 ha

4) Other Environmental Guidelines to be Complied


In addition to the environmental laws, rules and regulations of Myanmar, environmental guidelines of donors and
other international organizations may need to be complied, based on further development status, especially
financial source of the Project. Followings are some of representative environmental guidelines need to be
considered.
JICA/ JBIC:

JICAs or JBICs Environmental Guidelines designates that any project and activity which may
give significant impacts on natural and social environments is classified as Category A. The
Category A project should disclose the EIA report and environmental approval certificate.

World Bank: The World Bank instructs to prepare a resettlement action plan in case that the large scale of
involuntary resettlement, of which PAPs are equal to more than 200 people, accompanies with
implementation of the project (Source: WB OP4.12).

5) EIA TOR for further study


A draft Terms of Reference (TOR) for investigation of Environmental Impact Assessment (EIA) of the Project is
prepared for further considerations and summarized in .

165

Table 4-51 Draft TOR for EIA of the Project


Item
Assumptions

Description

(1) EIA Level Study


(2) Duration: at least 9 months and covering both rainy and dry seasons for surveys/
measurements
1 Preparatory (1) Kick-off Meeting with Ministry of Environment Conservation and Forestry (MOECAF:
Work
based on necessity)
(2) Field Pre-Survey
(3) Data Collection by Literature or F/S Report and Field Reconnaissance
2
(1) Reviewing Project Description
Development (2) Confirmation on Latest Legal Documents
of
Basic (3) Setting Environmental Standard to be applied
Framework
for EIA
3 Scoping
(1) Preparation of Scoping Documents and TOR of EIA Investigation
(2) 1st Stakeholder Meeting
(3) Discussion of TOR for EIA Investigation with MOECAF (based on necessity)
4
Investigation
No.
Item
Survey Item
Frequency
Points
(Baseline
1
Meteorology
Wind Speed, Wind Direction, Continuously
1
point
Survey)
Isolation, Radiation budget,
near
Cloud
proposed
project
site
2
Air Quality
NO2, SO2, TSP, CO, PM10
Monthly
from 1
point
October 2013 to (near
February 2014 (1 proposed
point,
near project
proposed project site,)
site)
3
Water
Salinity, Temp., Turbidity, 1m 3 times (15 days 2 points
Temperature
layer each
each)
(1 line)
4
Current/ River Current Flow
3 times (5 days 2 points
Flow
in 2 weeks each) (1 line)
5
Water Quality 1)
Temperature
(water, 1 time each in 2 points
(Natural and atmosphere), 2) water level, 3) dry and rainy
Living
flow rate, 4) odor, 5) color, 6) season
Conditions)
electrical conductivity, 7) pH,
8) BOD5, 9) SS, 10) DO, 11)
total coliform, 12) COD, 13)
total nitrogen, 14) total
phosphorous, 15) total organic
compounds, 16) turbidity, 17)
hardness, 18) nitrates (NO3-N,
NO2-N),
19)
ammonium
nitrogen (NH4-N)
6
Water Quality 20) arsenic (As), 21) mercury 1 time in dry and 2 points
(Toxic
(Hg), 22) lead (Pb), 23) rainy season
Substance)
cadmium (Cd), 24) hexavalant
chromium
(Cr(VI)),
25)
copper (Cu), 26) zinc (Zn), 27)
nickel (Ni), 28) manganese
(Mn), 29) iron (Fe), 30) tin
(Sn), 31) cyanide (CN), 32)
phenol, 33) oil and grease, 34)
sulfide, 35) sulfate, 36)
fluoride
166

Sediment
(River Bed)

Traffic
Volume

9
10
11

Noise
Vibration
Flora
and
Fauna

12

Cultural and
landscape

13

Social*

pH, As, Pb, Cd, Cu, Zn, Mn,


Fe, Cr (VI), Se, Hg, Ni, CN,
F, B
Number of Vehicle for each
type (track, normal vehicle
motor cycle)
Leq (dB)
Lv (dB)
Biological
Environment,
Vegetation
and
Habitat
Mapping,
Aqua-ecosystem
survey
Cultural heritage, religious
facilities, landscape points, etc.

1 time in dry
season

1 points

1 time (weekday)

2 points

1 time (weekday)
1 time (weekday)
2 times (dry and
rainy season)

2 points
2 points
proposed
project
site and
off shore
proposed
project
site
proposed
project
site

1 time

Land use and infrastructure, 1 time


Population,
Living and
livelihood,
working
conditions,
Sanitation and
health etc.
S*In addition, surveys for preparation of RAP are required if there will be significant
involuntarly resettlement by the Project.
5
(1) Prediction of Environmental and Social Impact (Key environmental elements: Air and
Environmental Water Temperature)
Impact
(2) Preparation of draft EIA Report
Assessment
(3) 2nd Stakeholder Meeting
(4) Preparation of EIA Report including EMP
(5) Submission of EIA Report to MOECAF
Source: Study team

(5) Actions to be taken by the related authorities in Myanmar to realize


the Project
a) Summary of the Actions to be Taken
It is recommended that the related authorities and / or the Project proponent will implement the following tasks
and duties promptly to realize the Project:
Project proponents in collaboration with concerned authorities shall conduct followings.

Firstly, basic surveys to determine location of the coal thermal power plant and its jetty including
alternatives will be conducted.

Concurrently to above, a census or social survey to pre-determine users as well as residents of the project
locations (project affected persons: PAPs) will be conducted.

Thereafter, EIA should be conducted to obtain the environmental approvals. As necessary, resettlement
action plan (RAP) with compensation plan and livelihood restoration plan will be prepared. Actions to be
taken are shown below;

Implement basic surveys such as meteorological measurements, soil investigation, air quality
167

survey, water quality survey, river / current flow survey, onshore and offshore fauna / flora survey,
and social survey for collecting fundamental baseline information not only for planning /
designing of the Project but also for assessing the environmental impacts of the Project,

Prepare and finalize TOR for EIA study to start EIA process promptly. As necessary, quantitative
targets for environmental conservation for the Project will be set independently if national
standards are not formulated yet by the commencement of EIA study.

Implement EIA by third party organization hired by the Project proponent to obtain
environmental permission (ECC: Environmental Compliance Certificate or equivalent) from the
government.

If necessary, obtain required environmental approvals other than ECC, such as approvals relating
to usage of on-shore area.

Prepare RAP if it is required land acquisition and involuntary resettlement, , and

Commence land acquisition procedure considering predicted environmental and social impacts.
Then start negotiations on compensation with PAPs who will be affected by the Project such as
famers/residents within the project site and fishermen living around the project site.

It is recommended that the concerned government authorities will conduct followings to facilitate
implementation of coal thermal power plant related project.

MOECAF is expected to finalize the EIA Procedures and the procedure to be enacted. This will
streamline currently vague requirements for EIA.

MOECAF is expected to prepare and indicate draft national environmental quality standards/
guidelines, enabling project proponents to comply such standards for environmental and social
safeguard

Ministry of Electric Power (MOEP) is expected to implement series of public awareness campaign for
coal thermal power plant development and electricity supply/ demand issues for more scientific
understandings toward the coal thermal plant by the general public. MOEP is in the position to
increase coal thermal power plants to meet the demand. However, majority of the general public have
stereotype negative impressions toward the coal thermal power plant due to inappropriate construction
and management of existing coal thermal power plant (Tigyit Power Plant in Shan State).

168

Chapter 5 Financial and Economic Evaluation


(1) Cost estimation of the Project
Based on similar projects being studied by the Study team and also on the past experiences, the preliminary
project cost was estimated.
The total capital expenditure for the Project is estimated approximately 130 billion yen and a rough breakdown
is as follows:

a) Ultra-supercritical pressure coal-fired power plant


The sum including the estimated cost for boiler, turbine, electrical and instrument equipment with cables, water
drainage and treatment, foundation and civil works, surrounding infrastructures, designing fee and others is as
follows:
79 billion yen

b) Harbor facilities
The sum including the estimated cost for approach pier, coal unloading pier and breakwater is as follows:
33 billion yen

c) Coal storage facilities


The sum including the estimated cost for machinery for coal unloading and transport, foundation and civil
works, surrounding area infrastructure, designing fee and others is as follows:
12 billion yen

d) Other expenses
The sum including the estimated expense for dispatching of engineers, credit guarantee, contingencies and
others is as follows:
6 billion yen

(2) Preliminary financial and economic analyses


1) Preconditions for the financial and economic analyses
It is assumed that, for the following reasons, the Project is not one that operates as an IPP project on the basis
of the budget of an isolated project but one that operates under the management of MoEP.
a) It is assumed that the Project is not intended to earn tariff revenues based on the price of power but concerns a
power station operated within the budget of MoEP.

b) Costs associated with the Project that are paid to the outside of MoEP, such as labor costs, are demanded and
approved as an annual budget of MoEP.
169

c) Yen loan (ODA) is provided to the Ministry of Finance and is paid back by the Ministry of Finance; for this
reason, it is mandatory for MoEP to make repayments of the loan to the Ministry of Finance.

2) Basic conditions and assumed conditions for the analysis


a) Duration of the Project
Operating period of the Project is 20 years including the 4 years for construction period.

b) Annual expected operating time


To simplify calculations, an 80% capacity factor (365 days x 24 hours/day x 80%), namely 7,008 hours/year,
is assumed throughout the project period in this analysis.

3) Values associated with the generated output


a) Assumed annual generated output
Assumed annual generated output at average is taken at 600 MW at an outdoor temperature of 30C.
b) Annual degradation rate
With the aim of simplifying calculations, this analysis assumes that the degradation rate is zero.

c) Transmission LossDistribution Loss


With the aim of simplifying calculations, this analysis assumes that the transmission loss and the distribution
loss are zero.

4) Taxation on the project


This analysis assumes that the development and operations of the project are exempted from all taxation by the
Government of Myanmar.

5) FIRR calculation
1.

Costs

Capital expenditures (CAPEX) and operating expenditures (OPEX) needed to operate a power plant are
considered in general. CAPEX as referred to here are made up of costs of engineering, procurement and
construction of the power plant, incidental facilities, consulting services and so on for the Project.

2.

Convenience/Benefit

This amounts to the product of the quantity sold to the consumers by the sales price to the consumers in
Myanmar.
a) Assumed selling tariff to MEPE
Electricity-selling tariff to sold to MEPE by a power generation business operator in Myanmar (in the case in
which the fuel expenses are passed on to MEPE) was USD0.03 0.04/kWh. In this analysis, the unit price of
170

USD0.035/kWh (the mean value), is used.

b) Assumed income
Using the above assumed tariff, the assumed income is calculated as shown below:
(The assumed revenue: 147.168MMUS$) = (Tariff: 0.035USD/kWh) (Output: 600 MW) (7,008 hours)
6) EIRR calculation
a) Preconditions for the assumed economic convenience
1. Costs
CAPEX and OPEX needed to run a power plant are considered. The CAPEX as referred to here are made up
of costs of engineering, procurement and construction of the power plant, incidental facilities, consulting
services and so on for the Project.

2. Convenience/Benefit
Diesel-engine-generator often is used for power generation due to unstable electricity supply in Myanmar.
Therefore, the fuel cost and the maintenance cost for such diesel-engine-generated power can be considered
as the willingness to pay (WIP) of the consumers in calculating EIRR.
The economic convenience of the private diesel-engine-based power generation with a power generating
capacity of 600 MW is calculated from the viewpoint of the following willingness to pay (WIP) of the
consumers.
According to the Project for Electrification of Rural Areas by Means of Flowing-water Micro Hydropower
Generation in the Republic of Union of Myanmar, a report of the Results of Fiscal 2012 Global Warming
Countermeasure Technology Promotion Projects of NEDO, MoEP has installed diesel generators at 645
locations or so throughout the country of Myanmar for the purpose of rural area electrification, with
electricity generated at a cost as high as 50 60 yen/kWh (USD 0.42 0.5/kWh for an exchange rate of 120
yen/USD). Coal-fired power generation that replaces diesel-engine-based power generation using expensive
fuel is assumed in the calculation of EIRR for the Project.
The assumed expenditures for the operation of a diesel generator with an output of 600 MW at a capacity
factor of 80% (365 days 24 hours/day 80%) for 7,008 hours/year are as shown below, provided that the
power generating cost of the diesel generator is set at the midpoint value (55 yen/kWh, namely USD
0.48/kWh).
(WTP: 2578.944MMUS$) = (0.46USD/kWh) (Average Output: 600 MW) (7,008 hours)
8) Operating Expenditures (OPEX)
In this analysis, OPEX can be determined from the three factors, the fuel costs, the fixed costs and the variable
costs, as shown below.
With Myanmar having not imported coal, the price of coal is set by adding the premium expenses for a
long-term contract and the assumed transportation costs from Australia to Myanmar to the average FOB-based
price of Australian coal over the past five years. In addition, it is assumed that this power station with an output
171

of 600 MW consumes approximately 1.5 million tons of coal under the operation at an assumed capacity factor
of 80%.
OPEX calculation has been performed with the fixed and the variable costs assumed to be on the same level as
that of maintenance expenses of coal-fired power stations of similar size in the neighboring countries (USD 35
mil/year).

a) Fuel costs
1) (Fuel costs) = (Coal price) (Average annual coal consumption: 1.5 million tons)
The price of coal is set by adding the premium expenses for a long-term contract and the assumed
transportation costs from Australia to Myanmar to the average FOB-based price of Australian coal over the
past five years (USD 120/ton).

b) Variable and fixed costs


OPEX calculation has been performed with the fixed and the variable costs assumed to be on the same level as
that of maintenance expenses of coal-fired power stations of similar size in the neighboring countries (USD 35
mil/year).

9) Result of the economic and financial analysis (for 20-year operation)

(3) Financial internal rate of return (FIRR)


a) In this analysis, an assumed electricity-selling tariff that is USD 0.035/kWh; and the FIRR was calculated
to be 5%, which turned out to be lower than the hurdle rate used commonly in developing nations, 15%.

172

Project
Year
-4
-3
-2
-1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

O&M cost

Plant cost

Owner's Cost

0
0
0
0
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35

-271
-271
-271
-271

-58
-58
-58
-58

Revenue

147
147
147
147
147
147
147
147
147
147
147
147
147
147
147
147
147
147
147
147
US$ million

(4) Economic internal rate of return (EIRR)


a) The EIRR was calculated to be 58%, fuel conversion from diesel to coal has been found that there is
economic rationality.

173

Project
Year
-4
-3
-2
-1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Coal price
(USD/ton

120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00

Coal
consumption
millon ton

1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5

Fuel cost

O&M cost

Plant cost

Owner's Cost

0
0
0
0
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00
-180.00

0
0
0
0
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35
-35

-271
-271
-271
-271

-58
-58
-58
-58

WTP

2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579
2,579

US$ million

174

Chapter 6 Envisaged Project Schedule


The positioning of this survey was a preliminary feasibility study for a feasibility study that is a precondition
for the construction of a coal-fired thermal power plant, and it was completed in February 2015. The survey was
to be reported to the Japanese Ministry of Economy, Trade and Industry, and also to the Myanmar government
through the Ministry. Thereafter, in order to move the project forward, a memorandum of understanding on the
advancement of the project is expected to be signed between the Myanmar government and the Japanese
government, and the Myanmar government is supposed to request the Japanese government for provision of yen
loans.
After the request is made, a feasibility study of the project will be carried out. JICA is entrusted with the
investigation of the economic, social, financial, technological and environmental aspects of the project and the
operation and maintenance/management regimes of the project implementation entity. Based on the result of this
screening, the Japanese government will decide whether it is appropriate to provide yen loan to the project for
which the request has been made. If the yen loan is approved, its amount, the terms of loan and so on will be
decided.
The Japanese government will notify the loaning country of its decision concerning the yen loan through the
diplomatic route to the loaning country. Thereafter, the two governments will initiate talks for reaching an official
agreement. When an agreement is reached between the two governments, exchange of notes (E/N) detailing the
items of the agreement will be held. Thereafter, JICA will initiate its loan agreement negotiations with the loaning
entity (loaning government, governmental agency, etc.). After a loan agreement (LA) is signed, the project will be
implemented.

The envisaged schedule for the project implementation is as shown below.


1Q

2014
2Q
3Q

4Q

1Q

2015
2Q
3Q

4Q

1Q

2016
2Q
3Q

4Q

1Q

2017
2Q
3Q

4Q

1Q

2018
2Q
3Q

4Q

1Q

2019
2Q
3Q

4Q

1Q

2020
2Q
3Q

4Q

1Q

2021
2Q
3Q

4Q

1Q

2022
2Q
3Q

4Q

Preliminary
Feasibility Study
Yen loan Request from
Myanmar government
Feasibility Study
Review
Exchange of E/N
Exchange of L/A
Construction
COD

The schedule after the completion of the preliminary feasibility study in February 2015 is as follows: informing
the Myanmar government of the content of the study, request to be made by the Myanmar government on the
provision of an yen loan to the Japanese government, selection of project-implementing entity by the Japanese
government after the request is made, signing of a memorandum of understanding on the implementation of the
feasibility study between the implementing entity and MoEP of Myanmar, implementation of the feasibility study
in 2016, review by the Japanese government of the project after the feasibility study is completed, exchange of
notes and signing of a loan agreement with the Myanmar government. After these steps are taken, plant
175

construction is slated to begin in 2018. After 5 years or so of construction period, commencement of commercial
operation of the power plant is planned in 2022.

176

Chapter 7 Implementing organizations


(1) Overview of implementing organizations in Myanmar
In Myanmar, the Ministry of Electric Power (MoEP) has jurisdiction over policies on electricity. MoEP,
established in 1997 as a spin-off from the Ministry of Energy, was split, through reorganizations carried out in
2002 and 2006, into MoEP No. 1 (MoEP 1), which was made responsible mainly for hydropower generation, and
No. 2 (MoEP 2), which was made responsible for gas-fired thermal power generation and power distribution.
These two split ministries were reunified under the newly formed Ministry of Electric Power (see below figure).
As a legacy of the splitting, a deputy minister presides over the organizations of the former MoEP 1 and another
deputy minister over those of the former MoEP 2. The minister of the new MoEP presides over both as union
minister.
. The former MoEP No. 1 has jurisdiction over a coal-fired thermal power plant and Department of Hydro
Power Planning (DHPP) is responsible for the future plan of the projects. The Project is supposed to be financed
by an yen loan by the Japanese Government and the power plant is supposed to be owned and operated by the
Myanmar Government. Therefore, it will be owned and operated by MoEP accordingly.
The Project will use coal as its fuel. However, due to delay in infrastructure development and due specifically to
unfeasibility of the use of brown coal produced in Myanmar in the case of the plant where supercritical or
ultra-supercritical pressure coal-fired power generation is planned, coal to be used for the Project must be
imported from such countries as Indonesia and Australia. Since the Ministry of Mine of Myanmar deals only with
the management of domestically produced coal (production adjustment, management of export, etc.), it has no
jurisdiction over import of coal under the present circumstance. Myanmar has little experience importing coal to
begin with and therefore, in order to proceed with coal-fired power plant with imported coal, MoEP must carry out,
via the Ministry of Commerce, the required procedure for obtaining import permit and so on. The Ministry of
Commerce may require the opinion from the Ministry of Mine when the procedure for obtaining a coal import
permit is being advanced. However, as long as introduction of supercritical or ultra-supercritical pressure
coal-fired boilers, with which domestically produced coal cannot be used, is sought, MoEP has control over the
issue of coal import.
Myanmar Electric Power Enterprise (MEPE) under MoEP will be in charge of power transport, and the Yangon
City Electricity Supply Board (YESB) will be in charge of distributing power in the Yangon region. As for power
distribution in rural regions, the Electricity Supply Enterprise (ESE) will be in charge.

177

(2) Organization/system for project implementation in Myanmar


There is no established organization specifically for implementing the Project in Myanmar yet. However, in
accordance with the below letter from MoEP, it is assumed that MoEP will form a specific organization for the
Project or assign the specific team for the Project in due course.

178

179

(3) Capability of the implementing organizations and countermeasures


There exists in Myanmar only one coal-fired power plant, constructed by Chinese, in Tigyit, and its power
generation efficiency is below 30%. Therefore, there is virtually little know-how accumulated on how to construct,
own and operate a coal-fired power plant. However, since there are hydropower plants constructed, owned and
operated by the MoEP itself, people in Myanmar possess a good knowledge and know-how on how to deal with
residents around the area for a new power plant, how to operate such a plant and so on.
180

Therefore, when it comes to development of coal-fired power plants in Myanmar, know-how on constructing,
owning and operating ultra supercritical coal-fired power plants, operation and maintenance and training of
workers must be provided to the Myanmar Government in cooperation with Japanese utility companies, electric
power companies, with abundant experiences in them with Japanese Government.

Operators of power plants in Myanmar will have an opportunity to be trained at ultra-supercritical coal-fired
power plants and supercritical coal-fired plants in Japan as a potential operator of the plants in order to acquire
know-how on operation and maintenance so that they can operate the planned power plant with Myanmars
personnel only in the future.

181

Chapter 8 Technical Advantages of Japanese Companies


(1) Competitiveness of Japanese companies for the Project
Tigyit Power Plant is the only coal-fired power plant in operation in Myanmar (2 of 60 MW units). The power
generation plant began its operation, supported by the Chinese government, in 2004. However, its operation rate
remain around 30% due, it is said, to various reasons such as problems with equipment. Also, it is said that
environmental pollution by flue gasses emitted from the plant due to problems with equipment in the exhaust gas
system has become an issue.
Under these circumstances, high hopes are placed on a high-efficiency and environment-friendly coal-fired
power station based on advanced technologies of Japanese manufacturers. The integrated approach with the
Japanese government and private companies to combines the export of experienced operating know-how of
Japanese utility companies, the capability of project development and finance arrangement of Japanese trading
houses, and ODA, financial assistance and technical support by the Government of Japan will contribute to the
enhancement of more business opportunities for the related industries for Japanese companies and also to the
facilitation of appropriate economic development in Myanmar.
For an ultra supercritical pressure power plant, major equipment such as the boiler, a steam turbine, and a
generator are expected to be manufactured in Japan or by Japanese companies. Furthermore, technical assistance
in operation and maintenance of the coal-fired power station after its commissioning for well managed operation
at high efficiency can be provided to the power plant in Myanmar by Japanese utility companies and the
technological transfer can also be expected for a long run perspective.
In the case of ultra-supercritical coal-firing power plants, major supplier for main equipment (including civil
engineering and construction work) such as boilers, steam turbines and power generators would be will constitute
a Japanese portion (including made-in-Japan portion or Japanese-made portion that are produced making use of
overseas hubs of Japanese companies).
Also, in order to maintain high-efficiency operation of the coal-fired power plant in Myanmar, a technical
service agreement (TSA) to provide technical support for its operation and repair after the plant has begun its
operation and a long term service agreement (LTSA) to have manufactures guarantee their products against
technical risks such as check and maintenance of important parts and troubleshooting measures may be signed so
that expansion of exports from Japan can be expected not only during the construction period, but also while the
plant is being operated.

(2) Expected Japanese contents


Major equipment with technical advantages by potential major Japanese suppliers are listed below.

Name of main equipment

Manufacture, etc.
182

Boiler

Mitsubishi Hitachi Power Systems, Ltd.


IHI Corporation

Steam turbine

Mitsubishi Hitachi Power Systems, Ltd.


Toshiba Corporation

Generator

Mitsubishi Hitachi Power Systems, Ltd.


Toshiba Corporation
Fuji Electric Co., Ltd.

Computer (control system)

Toshiba Corporation
Mitsubishi Electric Corporation
Hitachi Ltd.
ABB Bailey Japan Ltd.

(3) Promotion of the Japanese Contents


It is suggested that the governmental support for the infrastructure projects in a developing countries with
relatively higher country risks be much meaningful for private sector companies to some extent, especially in
terms of financial support such as yen loan as a menu of ODA.
Among the various financial support menu by the Japanese government, STEP (Special Terms for Economic
Partnership) can be beneficial for both countries, Japan and also Myanmar in this case of the Project. With STEP,
Myanmar will be able to enjoy the highly advanced state-of-art technology by Japanese companies and also
possible technological transfer. Japanese companies will be able to enjoy more opportunities to contribute the
Project for mainly supply of goods and services.

183

Chapter 9 Expected fund source for the Project


(1) Direction of the fund sourcing by the Myanmar Government for the
Project
In Myanmar, power plants are constructed and operated with its own fund or grant aid from foreign countries,
or they are constructed and operated by private-sector power companies with an Independent Power Producer
(IPP) scheme. Meanwhile, no plants have recently been constructed with soft loan nor concessional loan from
foreign countries. Since Myanmar has gone through the debt-relief for the soft loans from foreign countries
including Japan, in general, it does not actively seek soft loans for a project.
Power shortage is seen at a moment already and rapid growth of the future demand is expected in Myanmar.
Meanwhile, it is difficult to develop a new gas-fired power plant since there is not much surplus of domestic
natural gas and also it applies to a new hydro power plant due to the environmental issues and other reasons.

In

order to fill the gap between demand and supply of power production capacity in Myanmar, development of a new
coal-fired power plant with a large capacity is inevitable.
Many new power plants are recently being developed with IPP scheme in Myanmar, however these projects are
relatively small size since power plant projects with large capacity find the financial difficulty to be developed
under IPP scheme with project finance due to the following issues:
1.

Laws and regulations to structure project financing and to protect the project sponsors and lenders are yet
to be implemented;

2. Government guarantee may not be secured; and


3.

Expected internal rate of return of the project may not be high enough for private companies due to a heavy
burden for capital expenditures for the related infrastructures.

It is suggested that environmentally friendly and highly efficient ultra super critical coal-fired power plant with
clean coal technology be to be introduced in Myanmar to reduce the environmental burden and to contribute to the
increase of power supply capacity as well.

It is also suggested that the soft loan from the Japanese Government

be applicable to this kind of project with the clean coal technology as the Japanese companies have a strong
competitiveness in the technology.
High officials from MoEP expressed its understanding, to some extent, of the need for the soft loans to
construct power plants during the hearing session by the study team.

(2) Surroundings for fund sourcing


Although grant aid has been provided to power generation sector in Myanmar, no institution has recently
offered a loan to it. Private-sector power companies that are advancing development in Myanmar do not resort to
structuring of project financing. Instead, they use their own funds to advance construction of power plants.
Meanwhile, in the bidding for Myingyan gas-fired IPP power plant project, IFCs consultant team got involved in
184

it, which secured, albeit its small scale, MoEPs guarantee concerning its selling of power. Since this case has a
possibility of being capable of structuring project financing for a large-scale power generation for the first time, it
must be watched carefully. However, it is generally believed that it takes some more times to structure project
financing for large-scale power generation in Myanmar.

(3) Expected fund source for the Project including yen loan
Since this project concerns a large-scale coal-fired power plant, while conditions for structuring project
financing is unimplemented and development based on it is not likely, ODA of yen loan by the Japanese
Government is considered to be made use of.
MoEP expressed its concern for the construction management and operation of the coal-fired power plant due to
the lack of experience and know-how and its intention to request for the technical support for such issues,
however, MoEP was convinced that they would be capable enough to manage the construction and operate the
power plant as well if such technical support is also provided.
And MoEP recognized the benefit of the application of yen loan to the Project and understand that MoEP is the
one to promote the development of the Project based on the basic understandings toward the yen loan.

Therefore,

it is advisable that the application of yen loan is possibly an efficient solution depending on the bilateral
arrangement between the related ministries of the both government of Myanmar and Japan.

185

Chapter 10 Action plans for the request for yen loans


(1) Directions of the yen loan application to the Project
Shown below is a schematic diagram of organizations involved in securing ODA yen loans for Myanmar.

After the result of this survey is reported to the Myanmar government, it will request the Japanese government
for an ODA yen loan. After the request is received by the Japanese government, the governments will sign a
memorandum of understanding for carrying out a feasibility study for cooperation based on the request for the
ODA yen loan. Afterwards, MoEP will sign MOU with Japanese companies selected by the Japanese government
for carrying out a project feasibility survey.

(2) Actions to be taken for the yen loan application


In order to make a request for an ODA yen loan, public knowledge of clean coal technology must be prevailed
in Myanmar. In Myanmar, due to activities of NGO, inefficient operations of the existing coal-fired power plant
and its adverse impacts on peoples environments owing to unimplemented waste treatment for the environment,
people has a strong, and sometimes incorrect, impression of coal-fired power plants as a power source imposing
heavy burdens to the environment. In the course of development of the Project, it is necessary to implement public
relations initiatives to explain that it is possible to achieve coal-fired power generation that does not burden the
environment by introducing the proper countermeasures such as desulfurization equipment and NOx removal
equipment to reduce hazardous substances such as CO2, sulfur oxides and nitrogen oxides produced by burning of
coal. It is also necessary to form common recognition among the people of the Myanmar government that is
favorable to loaning cooperation by letting the importance of such cooperation be known thoroughly to the
economic development of Myanmar.

(3) Related issues for the yen loan application


After this survey is completed, it is suggested that public relations using TV commercials to raise the level of
recognition of clean coal within Myanmar, briefing on clean coal to NGO and the press, holding of lectures to
government personnel on clean coal and so on be carried out. It is also suggested that government personnel be
briefed on favorable benefits of infrastructure development with ODA yen loan on the growth of the nation as a
precursor activity for requesting it.
186

Potrebbero piacerti anche